Lockhart Power Company; Notice Soliciting Scoping Comments, 68815-68816 [E9-30810]
Download as PDF
pwalker on DSK8KYBLC1PROD with NOTICES
Federal Register / Vol. 74, No. 248 / Tuesday, December 29, 2009 / Notices
two new caisson structures; and an
increase in the certificated storage
capacity, all as more fully set forth in
the application which is on file with the
Commission and open for public
inspection. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits,
in the docket number field to access the
document. For assistance, call (866)
208–3676 or TTY, (202) 502–8659.
Any questions concerning this
application should be directed to Jim
Goetz, MoBay Storage Hub, LLC, 5847
San Felipe, Suite 3050, Houston, Texas
77057, (713) 961–3204 (phone) or (713)
961–2676 (fax).
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
Federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
VerDate Nov<24>2008
19:02 Dec 28, 2009
Jkt 220001
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
Protests and interventions may be
filed electronically via the Internet in
lieu of paper; see, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Comment Date: January 12, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–30813 Filed 12–28–09; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
68815
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2621–009]
Lockhart Power Company; Notice
Soliciting Scoping Comments
December 18, 2009.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: P–2621–009.
c. Date filed: November 16, 2009.
d. Applicant: Lockhart Power
Company.
e. Name of Project: Pacolet
Hydroelectric Project.
f. Location: The proposed project is
located on the Pacolet River, near the
Town of Pacolet, Spartanburg County,
South Carolina. The project does not
occupy federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Bryan D. Stone,
P.O. Box 10, 420 River Street, Lockhart,
SC 29364; Telephone (864) 545–2211.
i. FERC Contact: Lee Emery,
Telephone (202) 502–8379, or by e-mail
at lee.emery@ferc.gov.
j. Deadline for filing scoping
comments: January 19, 2010.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp), under the ‘‘eFiling’’
link. For a simpler method of submitting
text only comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. All
filings with the Commission must
include project name and number (i.e.,
Pacolet Project No. 2621–009) and bear
the heading ‘‘Comments on Scoping
Document 1.’’
k. This application is not ready for
environmental analysis at this time.
l. The proposed Pacolet Project would
consist of two developments; one that is
an existing, licensed development (the
Lower Pacolet development) and a new
development (Upper Pacolet
E:\FR\FM\29DEN1.SGM
29DEN1
pwalker on DSK8KYBLC1PROD with NOTICES
68816
Federal Register / Vol. 74, No. 248 / Tuesday, December 29, 2009 / Notices
development). The project would have
an annual generation of 8,092,000
kilowatt-hours. The proposed project
would consist of the facilities described
below.
The Upper Pacolet development
would consist of: (1) An existing 315foot-long by 18-foot-high concrete and
rubble masonry dam, with the addition
of 3-foot-high flashboards; (2) an
existing 30-acre reservoir, with a
useable storage capacity of 90 acre-feet
at elevation 519.0 feet North American
Vertical Datum 1988 (NAVD 88); (3)
new vertical slide intake gates with rack
and pinion operators, sluice gates, and
trashracks having a 1.375-inch clear bar
spacing with a single trash rake cleaning
mechanism; (4) a new 24-foot-wide by
40-foot-long concrete powerhouse that
would contain a vertical Kaplan turbine
with an estimated generating capacity of
1.1 megawatts (MW); (5) a proposed
200-foot-long, 34.5 kilovolt (kV)
transmission line; (6) a proposed
switchyard; and (7) appurtenant
facilities.
The Lower Pacolet development (all
existing facilities) would consist of: (1)
A 347-foot-long by 24-foot-high concrete
and rubble masonry dam, with 4-foothigh flashboards; (2) three sand gates;
(3) an 11-acre reservoir, with a useable
storage capacity of 44-acre feet at an
elevation of 492.0 feet NAVD 88; (4) an
intake structure equipped with
trashracks, having a 1.375-inch clear bar
spacing and a trash rake; (5) a 100-footlong by 10-foot-diameter penstock; (6) a
67-foot-long by 32-foot-wide concrete
powerhouse, integral with the dam,
containing two vertical turbines, each
generating 400 kilowatts (kW); (7) a
tailrace with a 340-foot-long curved
training wall; (8) a 250-foot-long, 34.5kV transmission line; and (9)
appurtenant facilities.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov, using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits,
in the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is available for
inspection and reproduction at the
address in Item H above.
n. You may register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Scoping Process
The Commission staff intends to
prepare a single Environmental
VerDate Nov<24>2008
19:02 Dec 28, 2009
Jkt 220001
Assessment (EA) for the Pacolet
Hydroelectric Project, in accordance
with the National Environmental Policy
Act. The EA will consider both sitespecific and cumulative environmental
impacts and reasonable alternatives to
the proposed action.
Commission staff does not propose to
conduct any on-site scoping meetings at
this time. Instead, we are soliciting
comments, recommendations, and
information, on the Scoping Document
(SD) issued on December 18, 2009.
Copies of the SD outlining the subject
areas to be addressed in the EA were
distributed to the parties on the
Commission’s mailing list and the
applicant’s distribution list. Copies of
the SD may be viewed on the Web at
https://www.ferc.gov, using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits,
in the docket number field to access the
document. For assistance, call 1–866–
208–3676 or, for TTY, (202) 502–8659.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–30810 Filed 12–28–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings # 1
December 22, 2009.
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC10–20–000.
Applicants: Locust Ridge Wind Farm,
LLC, Fortis Energy Marketing & Trading
GP.
Description: Supplemental Filing of
Fortis Energy Marketing & Trading GP
and Locust Ridge Wind Farm, LLC.
Filed Date: 12/18/2009.
Accession Number: 20091218–5208.
Comment Date: 5 p.m. Eastern Time
on Monday, December 28, 2009.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER97–2846–017;
ER99–2311–014.
Applicants: Carolina Power & Light
Company; Florida Power Corporation.
Description: Notice of Change in
Status for Florida Power Corporation.
Filed Date: 12/18/2009.
Accession Number: 20091218–5104.
Comment Date: 5 p.m. Eastern Time
on Friday, January 8, 2010.
Docket Numbers: ER99–2341–014;
ER06–1334–008; ER07–277–006.
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
Applicants: Invenergy Cannon Falls
LLC, Spindle Hill Energy LLC, Hardee
Power Partners Limited.
Description: Supplemental
Information for Notification of Change
in Fact Filing of Hardee Power Partners
Limited, Spindle Hill Energy LLC and
Invenergy Cannon Falls, LLC.
Filed Date: 12/22/2009.
Accession Number: 20091222–5124.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 12, 2010.
Docket Numbers: ER07–277–007.
Applicants: Invenergy Cannon Falls
LLC.
Description: Supplemental
Information for Triennial Report Filing
of Invenergy Cannon Falls LLC.
Filed Date: 12/22/2009.
Accession Number: 20091222–5121.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 12, 2010.
Docket Numbers: ER08–237–006.
Applicants: Forward Energy LLC.
Description: Supplemental
Information for Triennial Report Filing
of Forward Energy LLC.
Filed Date: 12/22/2009.
Accession Number: 20091222–5127.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 12, 2010.
Docket Numbers: ER09–1719–001.
Applicants: Midwest Independent
Transmission System.
Description: Midwest Independent
Transmission System Operator, Inc
submits a compliance filing.
Filed Date: 12/17/2009.
Accession Number: 20091218–0206.
Comment Date: 5 p.m. Eastern Time
on Thursday, January 7, 2010.
Docket Numbers: ER10–444–000.
Applicants: Carolina Power & Light
Company.
Description: Carolina Power & Light
Co. submits a revised Power Supply and
Coordination Agreement.
Filed Date: 12/17/2009.
Accession Number: 20091218–0210.
Comment Date: 5 p.m. Eastern Time
on Thursday, January 7, 2010.
Docket Numbers: ER10–445–000.
Applicants: Oncor Electric Delivery
Company LLC.
Description: Oncor Electric Delivery
Co, LLC’s submits First Revised Sheet
No. 37 et al to FERC Electric Tariff,
Twelfth Revised Volume No. 1.
Filed Date: 12/17/2009.
Accession Number: 20091218–0209
Comment Date: 5 p.m. Eastern Time
on Thursday, January 7, 2010.
Docket Numbers: ER10–446–000.
Applicants: Oncor Electric Delivery
Company LLC.
Description: Oncor Electric Delivery
Co, LLC’s submits a First Revised Sheet
E:\FR\FM\29DEN1.SGM
29DEN1
Agencies
[Federal Register Volume 74, Number 248 (Tuesday, December 29, 2009)]
[Notices]
[Pages 68815-68816]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-30810]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2621-009]
Lockhart Power Company; Notice Soliciting Scoping Comments
December 18, 2009.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: P-2621-009.
c. Date filed: November 16, 2009.
d. Applicant: Lockhart Power Company.
e. Name of Project: Pacolet Hydroelectric Project.
f. Location: The proposed project is located on the Pacolet River,
near the Town of Pacolet, Spartanburg County, South Carolina. The
project does not occupy federal lands.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Bryan D. Stone, P.O. Box 10, 420 River
Street, Lockhart, SC 29364; Telephone (864) 545-2211.
i. FERC Contact: Lee Emery, Telephone (202) 502-8379, or by e-mail
at lee.emery@ferc.gov.
j. Deadline for filing scoping comments: January 19, 2010.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site (https://www.ferc.gov/docs-filing/ferconline.asp), under the
``eFiling'' link. For a simpler method of submitting text only
comments, click on ``Quick Comment.'' For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov; call toll-free at
(866) 208-3676; or, for TTY, contact (202) 502-8659. Although the
Commission strongly encourages electronic filing, documents may also be
paper-filed. To paper-file, mail an original and eight copies to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. All filings with the
Commission must include project name and number (i.e., Pacolet Project
No. 2621-009) and bear the heading ``Comments on Scoping Document 1.''
k. This application is not ready for environmental analysis at this
time.
l. The proposed Pacolet Project would consist of two developments;
one that is an existing, licensed development (the Lower Pacolet
development) and a new development (Upper Pacolet
[[Page 68816]]
development). The project would have an annual generation of 8,092,000
kilowatt-hours. The proposed project would consist of the facilities
described below.
The Upper Pacolet development would consist of: (1) An existing
315-foot-long by 18-foot-high concrete and rubble masonry dam, with the
addition of 3-foot-high flashboards; (2) an existing 30-acre reservoir,
with a useable storage capacity of 90 acre-feet at elevation 519.0 feet
North American Vertical Datum 1988 (NAVD 88); (3) new vertical slide
intake gates with rack and pinion operators, sluice gates, and
trashracks having a 1.375-inch clear bar spacing with a single trash
rake cleaning mechanism; (4) a new 24-foot-wide by 40-foot-long
concrete powerhouse that would contain a vertical Kaplan turbine with
an estimated generating capacity of 1.1 megawatts (MW); (5) a proposed
200-foot-long, 34.5 kilovolt (kV) transmission line; (6) a proposed
switchyard; and (7) appurtenant facilities.
The Lower Pacolet development (all existing facilities) would
consist of: (1) A 347-foot-long by 24-foot-high concrete and rubble
masonry dam, with 4-foot-high flashboards; (2) three sand gates; (3) an
11-acre reservoir, with a useable storage capacity of 44-acre feet at
an elevation of 492.0 feet NAVD 88; (4) an intake structure equipped
with trashracks, having a 1.375-inch clear bar spacing and a trash
rake; (5) a 100-foot-long by 10-foot-diameter penstock; (6) a 67-foot-
long by 32-foot-wide concrete powerhouse, integral with the dam,
containing two vertical turbines, each generating 400 kilowatts (kW);
(7) a tailrace with a 340-foot-long curved training wall; (8) a 250-
foot-long, 34.5-kV transmission line; and (9) appurtenant facilities.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov, using the ``eLibrary''
link. Enter the docket number, excluding the last three digits, in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is available for inspection and
reproduction at the address in Item H above.
n. You may register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
o. Scoping Process
The Commission staff intends to prepare a single Environmental
Assessment (EA) for the Pacolet Hydroelectric Project, in accordance
with the National Environmental Policy Act. The EA will consider both
site-specific and cumulative environmental impacts and reasonable
alternatives to the proposed action.
Commission staff does not propose to conduct any on-site scoping
meetings at this time. Instead, we are soliciting comments,
recommendations, and information, on the Scoping Document (SD) issued
on December 18, 2009.
Copies of the SD outlining the subject areas to be addressed in the
EA were distributed to the parties on the Commission's mailing list and
the applicant's distribution list. Copies of the SD may be viewed on
the Web at https://www.ferc.gov, using the ``eLibrary'' link. Enter the
docket number, excluding the last three digits, in the docket number
field to access the document. For assistance, call 1-866-208-3676 or,
for TTY, (202) 502-8659.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-30810 Filed 12-28-09; 8:45 am]