Intent To Prepare a Draft Environmental Impact Statement (DEIS) for the State of Alaska's Proposed Alaska Stand Alone Pipeline (ASAP) Natural Gas Transportation Pipeline, 63736-63737 [E9-28865]
Download as PDF
63736
Federal Register / Vol. 74, No. 232 / Friday, December 4, 2009 / Notices
DEPARTMENT OF DEFENSE
Department of the Army, Corps of
Engineers
Intent To Prepare a Draft
Environmental Impact Statement
(DEIS) for the State of Alaska’s
Proposed Alaska Stand Alone Pipeline
(ASAP) Natural Gas Transportation
Pipeline
AGENCY:
U.S. Army Corps of Engineers,
DoD.
mstockstill on DSKH9S0YB1PROD with NOTICES
ACTION:
Notice of Intent.
SUMMARY: The Alaska District, U.S.
Army Corps of Engineers (Corps)
intends to prepare a Draft
Environmental Impact Statement (DEIS)
to identify and analyze the potential
impacts associated with the
construction of the proposed Alaska
Stand Alone Pipeline (ASAP) natural
gas transportation pipeline. The Corps is
the lead federal agency and the Bureau
of Land Management (BLM), National
Park Service (NPS) and Environmental
Protection Agency (EPA) are
participating as cooperating agencies in
the DEIS development process. The
Environmental Impact Statement (EIS)
will be used as a basis for the Corps
permit decision and to ensure
compliance with the National
Environmental Policy Act (NEPA). The
Corps will be evaluating a permit
application for work under Section 10 of
the Rivers and Harbors Act and Section
404 of the Clean Water Act. Because
ASAP would require decisions and
actions by other federal agencies (such
as right-of-way grants and other
permits), this DEIS will also fulfill the
NEPA responsibilities of those federal
agencies.
FOR FURTHER INFORMATION CONTACT:
Questions about the proposed action
and the DEIS can be answered by: Ms.
Serena Sweet, Regulatory Division,
telephone: (907) 753–2819, toll free in
AK: (800) 478–2712, fax: (907) 753–
5567, e-mail:
serena.e.sweet@usace.army.mil, or mail:
U.S. Army Corps of Engineers, CEPOA–
RD, Post Office Box 6898, Elmendorf
AFB, Alaska 99506–0898. Additional
information may be obtained at https://
www.asapeis.com.
SUPPLEMENTARY INFORMATION:
1. The permit applicant, the State of
Alaska, is proposing to construct a 24inch diameter, high-pressure pipeline
from Alaska’s North Slope to Cook Inlet
to transport North Slope natural gas to
in-state Alaska markets. The pipeline
would be located entirely within the
State of Alaska. Gas off-take would be
provided for the Fairbanks Area and in
VerDate Nov<24>2008
17:26 Dec 03, 2009
Jkt 220001
other locations along the route. The
Alaska Stand Alone Pipeline project
includes a Gas Conditioning Plant on
the North Slope prior to the pipeline
inlet, compressor stations along the
pipeline, and natural gas liquid (NGL)
extraction facilities to produce utilitygrade natural gas. The gas reserves in
the Prudhoe Bay field are some of the
largest on the North Slope and represent
the most likely sources of gas for the
pipeline system.
2. Alternatives: Two routing options
are being considered to bring the gas
from the North Slope to Alaska
consumers. These two options follow
routings from Prudhoe Bay to Cook Inlet
via the Parks Highway and the
Richardson Highway. Both route
options share the same starting point at
Prudhoe Bay and ending point (at Mile
Post 55 of the Beluga Pipeline) as well
as a common routing from Prudhoe Bay
to the Livengood area. In addition, two
spur line options and two pre-build
options, using a proposed AlaskaCanada Gasline as the transport to the
takeoff points will be included in this
analysis.
a. Stand Alone Alternative Routes:
i. Parks Highway Stand Alone—from
Prudhoe Bay to Livengood, then to Cook
Inlet generally following the Parks
Highway; includes service to Fairbanks.
ii. Richardson Highway Stand
Alone—from Prudhoe Bay to Livengood,
to Fairbanks, then generally following
the Trans Alaska Pipeline alignment to
Delta Junction, to north of Glennallen
via the Richardson Highway, then to
Cook Inlet via the Glenn Highway;
includes service to Glennallen.
b. Spur Alternative Routes:
i. Parks Highway Spur—from
Fairbanks to Cook Inlet generally
following the Parks Highway.
ii. Richardson Highway Spur—from
Delta Junction to north of Glennallen via
the Richardson Highway, then to Cook
Inlet via the Glenn Highway; includes
service to Glennallen.
c. Pre-Build Alternative Routes:
i. Parks Highway Pre-Build—from
Cook Inlet to Fairbanks generally
following the Parks Highway.
ii. Richardson Highway Pre-Build—
from Cook Inlet via the Glenn Highway
to north of Glennallen then to Delta
Junction via the Richardson Highway,
then generally following the Trans
Alaska Pipeline alignment to Fairbanks
(with a smaller diameter pipeline).
d. Gas Source Alternatives:
i. Prudhoe Bay Gas Source: Natural
gas from the Prudhoe Bay gas fields
would require treatment at a gas
treatment plant that would likely be
located at Prudhoe Bay. From Prudhoe
Bay the gas pipeline would generally
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
follow the existing Trans Alaska
Pipeline System (TAPS) corridor across
the North Slope and enter the Brooks
Range near Galbraith Lake.
ii. Gubik Gas Source: The Gubik Gas
Field is located 19 miles east of Umiat
and approximately 70 miles west of
TAPS Pump Station #2. The pipeline
from the Gubik Field would parallel a
proposed road alignment to the east,
crossing the Anaktuvuk River, and
proceeding southeast to the Itkillik
River. The route would then parallel the
Itkillik River to the east side of Itigaknit
Mountain then south to connect with
the TAPS Corridor near Toolik Lake.
The exact location of the Gubik
production facilities has not been
selected. The length of the Gubik
Pipeline route to the TAPS corridor is
estimated to be about 90 miles.
3. Scoping Process: The scoping
period will begin on December 7, 2009,
and end on February 5, 2010.
a. The Corps invites full public
participation to promote open
communication on the issues
surrounding the proposal. All federal,
state, Tribal, local agencies, and other
persons or organizations that have an
interest are urged to participate in the
NEPA scoping process. Scoping
meetings will be held to receive public
input on the proposed purpose and
need of the project, to identify
significant issues and to discuss
proposed alternatives. The scoping
process will help to further explain the
purpose and need plus the alternatives
to be reviewed in the DEIS.
b. The scoping meetings are
tentatively planned for the dates and
locations listed at https://
www.asapeis.com (please consult
website for any changes and additional
information including the scoping
summary). The Corps expects to hold
scoping meetings in Anchorage, Barrow,
Delta Junction, Fairbanks, Glennallen,
McKinley Park, Nenana, and Wasilla.
4. The lands along the proposed
pipeline corridor and one or more of its
alternatives are owned by numerous
entities; including, federal and state
governments, the State of Alaska, and
private land holders. These federal land
managers include the BLM, NPS and the
Department of Defense. Private
landholders include Native
corporations, Native allottees, and land
owned by other private individuals.
5. The DEIS will analyze the potential
social, economic, and environmental
impacts to the affected areas. The
following major issues will be analyzed
in depth in the DEIS: the natural gas
delivery system construction and
operation and its affect upon the
surrounding communities; essential fish
E:\FR\FM\04DEN1.SGM
04DEN1
Federal Register / Vol. 74, No. 232 / Friday, December 4, 2009 / Notices
habitat; threatened and endangered
species including critical habitat;
cultural resources; socioeconomics; and
secondary and cumulative impacts.
6. It is anticipated that the DEIS will
be available August 2010 for public
review.
Dated: November 23, 2009.
Serena E. Sweet,
Project Manager, Alaska District, U.S. Army
Corps of Engineers.
[FR Doc. E9–28865 Filed 12–3–09; 8:45 am]
BILLING CODE 3720–58–P
DEPARTMENT OF DEFENSE
Department of the Army, Corps of
Engineers
Intent To Prepare a Draft
Environmental Impact Statement
(DEIS) for the Proposed Point
Thomson Project To Develop the
Thomson Sand Reservoir by
Extracting Gas Condensate and Oil for
the Purpose of Commercial Production
as Proposed by the Exxon Mobil
Corporation (ExxonMobil)
AGENCY:
U.S. Army Corps of Engineers,
DoD.
mstockstill on DSKH9S0YB1PROD with NOTICES
ACTION:
Notice of Intent.
SUMMARY: The Alaska District, U.S.
Army Corps of Engineers (Corps)
intends to prepare a Draft
Environmental Impact Statement (DEIS)
to identify and analyze the potential
impacts associated with the
development of the Thomson Sand
Reservoir, including construction and
operation of the proposed project. The
Corps will be evaluating a permit
application for work under Section 10 of
the Rivers and Harbors Act and Section
404 of the Clean Water Act. The
Environmental Impact Statement (EIS)
will be used as a basis for the permit
decision and to ensure compliance with
the National Environmental Policy Act.
FOR FURTHER INFORMATION CONTACT:
Questions about the proposed action
and the DEIS can be answered by: Ms.
Julie McKim, Regulatory Division,
telephone: (907) 753–2773, toll free in
AK: (800) 478–2712, Fax: (907) 753–
5567, e-mail:
julie.w.mckim@usace.army.mil, mail:
U.S. Army Corps of Engineers, CEPOA–
RD, Post Office Box 6898, Elmendorf
AFB, Alaska 99506–0898. Additional
information may be obtained at https://
www.pointthomsonprojecteis.com.
SUPPLEMENTARY INFORMATION:
1. Background Information: The
Environmental Protection Agency (EPA)
previously issued a notice of intent to
prepare a DEIS on April 19, 2002 for a
VerDate Nov<24>2008
17:26 Dec 03, 2009
Jkt 220001
similar proposal to develop oil and gas
reserves in or near the Point Thomson
Unit, potentially including designation
of ocean dredged material disposal
site(s). The EPA was the lead Federal
Agency because the proposed project
would have required authorization
under Section 102 of the Marine
Protection, Research, and Sanctuaries
Act (MPRSA), with the Corps as a
Cooperating Agency. Per the applicant’s
request, the agreement to pursue the EIS
was terminated between the EPA and
the applicant, Exxon Mobil Corporation
(ExxonMobil). In October 2009,
ExxonMobil submitted a new proposed
project that would not be subject to
Section 102 of the MPRSA but would
require authorization from the Corps
under Section 10 of the Rivers Harbors
Act of 1899 and Section 404 of the
Clean Water Act. Therefore, the Corps
has been designated the lead Federal
agency for the revised proposed project.
2. The permit applicant, ExxonMobil,
is proposing to develop the Thomson
Sand Reservoir located approximately
60 miles east of Deadhorse on the
Beaufort Sea coast, in the State of
Alaska. A minimum of five wells would
be drilled from three pads: a Central
Pad, and East and West Pads located to
access the eastern and western extent of
the reservoir. The applicant would
produce gas from the reservoir to
recover liquid condensate from natural
gas and re-inject the residual gas back
into the reservoir, conserving it for
future use. Hydrocarbon liquid
condenses from the produced natural
gas when pressure and temperature are
lowered below original reservoir
conditions during production at surface
processing facilities. ExxonMobil
proposes to develop offshore portions of
the reservoir using long reach
directional drilling techniques from the
onshore pads. The produced
hydrocarbon liquids (condensate and
oil) would be shipped through a new
22-mile long, elevated pipeline from
Point Thomson to the existing Badami
Development. This pipeline would then
tie into the existing Badami common
carrier pipeline, which connects with
the existing common carrier oil sales
pipeline system to the Trans-Alaska
Pipeline System Pump Station No. 1.
The Central Pad would also include
infrastructure to support operations and
drilling, such as temporary construction
and permanent camps; offices,
warehouses, and shops; electric power
generating and distribution facilities;
diesel fuel, water, and chemical storage;
treatment systems for drinking water
and wastewater; a grind and inject
module; waste management facilities;
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
63737
and communications facilities. Other
project facilities, in addition to the
drilling pads, would include a gravel
airstrip, a bulkhead and dolphins, infield gravel roads, ice roads, in-field
pipelines, and a gravel mine. Dredging
may be required at the bulkhead.
3. Alternatives: Reasonable
alternatives will be identified and
evaluated throughout the Scoping and
EIS process.
4. Scoping: The scoping period will
begin on January 11, 2010 and end on
February 25, 2010.
a. The Corps invites full public
participation to promote open
communication on the issues
surrounding the proposal. All Federal,
State, Tribal, local agencies, and other
persons or organizations that have an
interest are urged to participate in the
NEPA scoping process. Meetings will be
held to receive public input on the
proposed purpose and need of the
project, to identify significant issues and
to discuss proposed alternatives. The
scoping process will help to further
explain the purpose and need plus the
alternatives to be reviewed in the DEIS.
b. The DEIS will analyze the potential
social, economic, physical, and
biological impacts to the affected areas.
The following major issues will be
analyzed in depth in the DEIS:
threatened and endangered species
including critical habitat; hydrology and
wetlands; fish and wildlife; the
construction and operation of the
facilities and their effect upon the
surrounding communities; cultural
resources; socioeconomics; alternatives;
secondary and cumulative impacts.
c. The Corps will serve as the lead
Federal agency in the preparation of the
DEIS. The Environmental Protection
Agency, United States Fish and Wildlife
Service, and State of Alaska Department
of Natural Resources are participating as
cooperating agencies.
5. The Corps expects to hold scoping
meetings in Anchorage, Barrow,
Fairbanks, Kaktovik, and Nuiqsut.
Further information about these
meetings will be published locally, on
the project Web site https://
www.pointthomsonprojecteis.com, or
can be obtained by contacting the Corps
as described above. A description of the
proposed project will be posted on the
project Web site prior to these meetings
to help the public focus their scoping
comments.
6. It is anticipated that the DEIS will
be available November 2010 for public
review.
Dated: November 23, 2009.
E:\FR\FM\04DEN1.SGM
04DEN1
Agencies
[Federal Register Volume 74, Number 232 (Friday, December 4, 2009)]
[Notices]
[Pages 63736-63737]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-28865]
[[Page 63736]]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army, Corps of Engineers
Intent To Prepare a Draft Environmental Impact Statement (DEIS)
for the State of Alaska's Proposed Alaska Stand Alone Pipeline (ASAP)
Natural Gas Transportation Pipeline
AGENCY: U.S. Army Corps of Engineers, DoD.
ACTION: Notice of Intent.
-----------------------------------------------------------------------
SUMMARY: The Alaska District, U.S. Army Corps of Engineers (Corps)
intends to prepare a Draft Environmental Impact Statement (DEIS) to
identify and analyze the potential impacts associated with the
construction of the proposed Alaska Stand Alone Pipeline (ASAP) natural
gas transportation pipeline. The Corps is the lead federal agency and
the Bureau of Land Management (BLM), National Park Service (NPS) and
Environmental Protection Agency (EPA) are participating as cooperating
agencies in the DEIS development process. The Environmental Impact
Statement (EIS) will be used as a basis for the Corps permit decision
and to ensure compliance with the National Environmental Policy Act
(NEPA). The Corps will be evaluating a permit application for work
under Section 10 of the Rivers and Harbors Act and Section 404 of the
Clean Water Act. Because ASAP would require decisions and actions by
other federal agencies (such as right-of-way grants and other permits),
this DEIS will also fulfill the NEPA responsibilities of those federal
agencies.
FOR FURTHER INFORMATION CONTACT: Questions about the proposed action
and the DEIS can be answered by: Ms. Serena Sweet, Regulatory Division,
telephone: (907) 753-2819, toll free in AK: (800) 478-2712, fax: (907)
753-5567, e-mail: serena.e.sweet@usace.army.mil, or mail: U.S. Army
Corps of Engineers, CEPOA-RD, Post Office Box 6898, Elmendorf AFB,
Alaska 99506-0898. Additional information may be obtained at https://www.asapeis.com.
SUPPLEMENTARY INFORMATION:
1. The permit applicant, the State of Alaska, is proposing to
construct a 24-inch diameter, high-pressure pipeline from Alaska's
North Slope to Cook Inlet to transport North Slope natural gas to in-
state Alaska markets. The pipeline would be located entirely within the
State of Alaska. Gas off-take would be provided for the Fairbanks Area
and in other locations along the route. The Alaska Stand Alone Pipeline
project includes a Gas Conditioning Plant on the North Slope prior to
the pipeline inlet, compressor stations along the pipeline, and natural
gas liquid (NGL) extraction facilities to produce utility-grade natural
gas. The gas reserves in the Prudhoe Bay field are some of the largest
on the North Slope and represent the most likely sources of gas for the
pipeline system.
2. Alternatives: Two routing options are being considered to bring
the gas from the North Slope to Alaska consumers. These two options
follow routings from Prudhoe Bay to Cook Inlet via the Parks Highway
and the Richardson Highway. Both route options share the same starting
point at Prudhoe Bay and ending point (at Mile Post 55 of the Beluga
Pipeline) as well as a common routing from Prudhoe Bay to the Livengood
area. In addition, two spur line options and two pre-build options,
using a proposed Alaska-Canada Gasline as the transport to the takeoff
points will be included in this analysis.
a. Stand Alone Alternative Routes:
i. Parks Highway Stand Alone--from Prudhoe Bay to Livengood, then
to Cook Inlet generally following the Parks Highway; includes service
to Fairbanks.
ii. Richardson Highway Stand Alone--from Prudhoe Bay to Livengood,
to Fairbanks, then generally following the Trans Alaska Pipeline
alignment to Delta Junction, to north of Glennallen via the Richardson
Highway, then to Cook Inlet via the Glenn Highway; includes service to
Glennallen.
b. Spur Alternative Routes:
i. Parks Highway Spur--from Fairbanks to Cook Inlet generally
following the Parks Highway.
ii. Richardson Highway Spur--from Delta Junction to north of
Glennallen via the Richardson Highway, then to Cook Inlet via the Glenn
Highway; includes service to Glennallen.
c. Pre-Build Alternative Routes:
i. Parks Highway Pre-Build--from Cook Inlet to Fairbanks generally
following the Parks Highway.
ii. Richardson Highway Pre-Build--from Cook Inlet via the Glenn
Highway to north of Glennallen then to Delta Junction via the
Richardson Highway, then generally following the Trans Alaska Pipeline
alignment to Fairbanks (with a smaller diameter pipeline).
d. Gas Source Alternatives:
i. Prudhoe Bay Gas Source: Natural gas from the Prudhoe Bay gas
fields would require treatment at a gas treatment plant that would
likely be located at Prudhoe Bay. From Prudhoe Bay the gas pipeline
would generally follow the existing Trans Alaska Pipeline System (TAPS)
corridor across the North Slope and enter the Brooks Range near
Galbraith Lake.
ii. Gubik Gas Source: The Gubik Gas Field is located 19 miles east
of Umiat and approximately 70 miles west of TAPS Pump Station
2. The pipeline from the Gubik Field would parallel a proposed
road alignment to the east, crossing the Anaktuvuk River, and
proceeding southeast to the Itkillik River. The route would then
parallel the Itkillik River to the east side of Itigaknit Mountain then
south to connect with the TAPS Corridor near Toolik Lake. The exact
location of the Gubik production facilities has not been selected. The
length of the Gubik Pipeline route to the TAPS corridor is estimated to
be about 90 miles.
3. Scoping Process: The scoping period will begin on December 7,
2009, and end on February 5, 2010.
a. The Corps invites full public participation to promote open
communication on the issues surrounding the proposal. All federal,
state, Tribal, local agencies, and other persons or organizations that
have an interest are urged to participate in the NEPA scoping process.
Scoping meetings will be held to receive public input on the proposed
purpose and need of the project, to identify significant issues and to
discuss proposed alternatives. The scoping process will help to further
explain the purpose and need plus the alternatives to be reviewed in
the DEIS.
b. The scoping meetings are tentatively planned for the dates and
locations listed at https://www.asapeis.com (please consult website for
any changes and additional information including the scoping summary).
The Corps expects to hold scoping meetings in Anchorage, Barrow, Delta
Junction, Fairbanks, Glennallen, McKinley Park, Nenana, and Wasilla.
4. The lands along the proposed pipeline corridor and one or more
of its alternatives are owned by numerous entities; including, federal
and state governments, the State of Alaska, and private land holders.
These federal land managers include the BLM, NPS and the Department of
Defense. Private landholders include Native corporations, Native
allottees, and land owned by other private individuals.
5. The DEIS will analyze the potential social, economic, and
environmental impacts to the affected areas. The following major issues
will be analyzed in depth in the DEIS: the natural gas delivery system
construction and operation and its affect upon the surrounding
communities; essential fish
[[Page 63737]]
habitat; threatened and endangered species including critical habitat;
cultural resources; socioeconomics; and secondary and cumulative
impacts.
6. It is anticipated that the DEIS will be available August 2010
for public review.
Dated: November 23, 2009.
Serena E. Sweet,
Project Manager, Alaska District, U.S. Army Corps of Engineers.
[FR Doc. E9-28865 Filed 12-3-09; 8:45 am]
BILLING CODE 3720-58-P