Southern Star Central Gas Pipeline, Inc.; Notice of Intent To Prepare an Environmental Assessment for the Proposed Elk City Storage Expansion Project and Request for Comments on Environmental Issues, 61145-61146 [E9-28012]
Download as PDF
Federal Register / Vol. 74, No. 224 / Monday, November 23, 2009 / Notices
operation of the Commission’s
regulations at 18 CFR 366.7(a).
Kimberly D. Bose,
Secretary.
[FR Doc. E9–28013 Filed 11–20–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP10–2–000]
Southern Star Central Gas Pipeline,
Inc.; Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Elk City Storage Expansion
Project and Request for Comments on
Environmental Issues
November 16, 2009.
jlentini on DSKJ8SOYB1PROD with NOTICES
The Federal Energy Regulatory
Commission (FERC or Commission) is
in the process of preparing an
environmental assessment (EA) on the
environmental impacts of the Elk City
Storage Expansion Project (Project)
proposed by Southern Star Central Gas
Pipeline, Inc. (Southern Star). Southern
Star has proposed to construct and
operate a new natural gas compressor
station in Montgomery County, Kansas,
and amend the current operational plan
for the existing natural gas storage field.
The Notice of Intent (NOI) explains
the scoping process that will be used to
gather input from the public and
interested agencies on the Project. Your
input will help determine which issues
will be evaluated in the EA. Please note
that the scoping period for this Project
will close on December 14, 2009.
Comments on the Project may be
submitted in written form or
electronically, as described below. This
NOI is being sent to Federal, State, and
local government agencies; elected
officials; affected landowners;
environmental and public interest
groups; Indian tribes and regional
Native American organizations;
commentors and other interested
parties; and local libraries and
newspapers. We 1 encourage
government representatives to notify
their constituents of this proposed
Project and encourage them to comment
on their areas of concern.
Summary of the Proposed Project
Southern Star proposes to construct a
compressor station adjacent to an
existing Southern Star dehydration
plant and install two 450-foot, 30-inch
1 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects
(OEP).
VerDate Nov<24>2008
16:37 Nov 20, 2009
Jkt 220001
diameter pipelines connecting the
proposed compressor station with the
existing dehydration plant. The
compressor station will be
approximately 5.5 acres and the
pipeline construction corridor will be
100-foot-wide. A new pond will be
constructed south of the compressor
station to replace the existing pond that
will be filled during construction of the
compressor station.
A location map depicting the
proposed facilities is attached to this
NOI as Appendix 1 .2
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping’’. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, the Commission staff
requests public comments on the scope
of the issues to address in the EA. All
comments received are considered
during the preparation of the EA. State
and local government representatives
are encouraged to notify their
constituents of this proposed action and
encourage them to comment on their
areas of concern.
In the EA we will discuss impacts that
could occur as results of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils.
• Water resources.
• Aquatic resources Vegetation and
wildlife.
• Threatened and endangered
species.
• Land use, recreation, and visual
resources.
• Cultural resources.
• Socioeconomics.
• Air quality and noise.
• Reliability and safety.
• Cumulative impacts.
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
2 The appendices referenced in this notice are not
printed in the Federal Register, but they are being
provided to all those who receive this notice in the
mail. Copies of the NOI can be obtained from the
Commission’s Web site at the ‘‘eLibrary’’ link,
Commission’s Public Reference Room, or by calling
(202) 502–8371. For instructions on connecting to
eLibrary, refer to the end of this notice.
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
61145
avoid impacts on the various resource
areas.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to federal, state,
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the Public Participation
section.
Currently Identified Environmental
Issues
We have already identified issues that
we think deserve attention based on our
previous experience with similar
projects in the region. This preliminary
list of issues, which is presented below,
may be revised based on your comments
and our continuing analyses specific to
the Project.
• Potential noise and vibration
impacts from compressor station.
• Air quality impacts from the
compressor station.
• Wetland and waterbody impacts.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the Project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your written comments are timely and
properly recorded, please send in your
comments so that they will be received
in Washington, DC on or before
December 14, 2009.
Comments on the proposed Project
can be submitted to the FERC in written
form. For your convenience, there are
three methods which you can use to
submit your written comments to the
Commission. In all instances please
reference the Project docket number
(CP10–2–000) with your submission.
The three methods are:
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located at
https://www.ferc.gov under the link
called ‘‘Documents and Filings’’. A
Quick Comment is an easy method for
E:\FR\FM\23NON1.SGM
23NON1
61146
Federal Register / Vol. 74, No. 224 / Monday, November 23, 2009 / Notices
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the ‘‘eFiling’’
feature that is listed under the
‘‘Documents and Filings’’ link. eFiling
involves preparing your submission in
the same manner as you would if filing
on paper, and then saving the file on
your computer’s hard drive. You will
attach that file to your submission. New
eFiling users must first create an
account by clicking on the links called
‘‘Sign up’’ or ‘‘eRegister’’. You will be
asked to select the type of filing you are
making. A comment on a particular
project is considered a ‘‘Comment on a
Filing’’; or
(3) You may file your comments with
the Commission via mail by sending an
original and two copies of your letter to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Room 1A, Washington,
DC 20426.
Label one copy of the comments for
the attention of Gas Branch 3, PJ–11.3.
jlentini on DSKJ8SOYB1PROD with NOTICES
Environmental Mailing List
An effort is being made to send this
notice to all individuals, organizations,
and government entities interested in
and/or potentially affected by the
proposed project. This includes all
landowners whose property may be
used temporarily for project purposes,
who have existing easements from the
pipeline, or who own homes within
distances defined in the Commission’s
regulations of certain aboveground
facilities. By this notice we are also
asking governmental agencies,
especially those in Appendix 2, to
express their interest in becoming
cooperating agencies for the preparation
of the EA.
If you do not want to send comments
at this time but still want to remain on
our mailing list, please return the
Information Request (Appendix 3). If
you do not return the Information
Request, you will be taken off the
mailing list.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the Internet at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits, in the Docket Number
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at 1–866–208–3676, or for TTY, contact
VerDate Nov<24>2008
16:37 Nov 20, 2009
Jkt 220001
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on December 1, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–28012 Filed 11–20–09; 8:45 am]
Kimberly D. Bose,
Secretary.
[FR Doc. E9–28014 Filed 11–20–09; 8:45 am]
BILLING CODE 6717–01–P
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
ENVIRONMENTAL PROTECTION
AGENCY
Federal Energy Regulatory
Commission
[EPA–HQ–OECA–2009–0401; FRL–8983–9]
[Docket Nos. ER10–253–000; EL10–14–000]
Primary Power, LLC; Notice of Filing
November 16, 2009.
Take notice that on November 10,
2009, Primary Power, LLC, pursuant to
sections 205 and 209 of the Federal
Power Act and Order No. 679, filed a
Petition for Declaratory Order
requesting Incentive Rate Treatment,
Acceptance of Rate of Return and
Certain Related Determinations for the
Grid Plus Transmission System.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
Agency Information Collection
Activities; Submission to OMB for
Review and Approval; Comment
Request; NESHAP for Miscellaneous
Organic Chemical Manufacturing
(Renewal), EPA ICR Number 1969.04,
OMB Control Number 2060–0533
AGENCY: Environmental Protection
Agency (EPA).
ACTION: Notice.
SUMMARY: In compliance with the
Paperwork Reduction Act (44 U.S.C.
3501 et seq.), this document announces
that an Information Collection Request
(ICR) has been forwarded to the Office
of Management and Budget (OMB) for
review and approval. This is a request
to renew an existing approved
collection. The ICR, which is abstracted
below, describes the nature of the
collection and the estimated burden and
cost.
DATES: Additional comments may be
submitted on or before December 23,
2009.
ADDRESSES: Submit your comments,
referencing docket ID number EPA–HQ–
OECA–2009–0401, to (1) EPA online
using www.regulations.gov (our
preferred method), or by e-mail to
docket.oeca@epa.gov, or by mail to: EPA
Docket Center (EPA/DC), Environmental
Protection Agency, Enforcement and
Compliance Docket and Information
E:\FR\FM\23NON1.SGM
23NON1
Agencies
[Federal Register Volume 74, Number 224 (Monday, November 23, 2009)]
[Notices]
[Pages 61145-61146]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-28012]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP10-2-000]
Southern Star Central Gas Pipeline, Inc.; Notice of Intent To
Prepare an Environmental Assessment for the Proposed Elk City Storage
Expansion Project and Request for Comments on Environmental Issues
November 16, 2009.
The Federal Energy Regulatory Commission (FERC or Commission) is in
the process of preparing an environmental assessment (EA) on the
environmental impacts of the Elk City Storage Expansion Project
(Project) proposed by Southern Star Central Gas Pipeline, Inc.
(Southern Star). Southern Star has proposed to construct and operate a
new natural gas compressor station in Montgomery County, Kansas, and
amend the current operational plan for the existing natural gas storage
field.
The Notice of Intent (NOI) explains the scoping process that will
be used to gather input from the public and interested agencies on the
Project. Your input will help determine which issues will be evaluated
in the EA. Please note that the scoping period for this Project will
close on December 14, 2009.
Comments on the Project may be submitted in written form or
electronically, as described below. This NOI is being sent to Federal,
State, and local government agencies; elected officials; affected
landowners; environmental and public interest groups; Indian tribes and
regional Native American organizations; commentors and other interested
parties; and local libraries and newspapers. We \1\ encourage
government representatives to notify their constituents of this
proposed Project and encourage them to comment on their areas of
concern.
---------------------------------------------------------------------------
\1\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
Summary of the Proposed Project
Southern Star proposes to construct a compressor station adjacent
to an existing Southern Star dehydration plant and install two 450-
foot, 30-inch diameter pipelines connecting the proposed compressor
station with the existing dehydration plant. The compressor station
will be approximately 5.5 acres and the pipeline construction corridor
will be 100-foot-wide. A new pond will be constructed south of the
compressor station to replace the existing pond that will be filled
during construction of the compressor station.
A location map depicting the proposed facilities is attached to
this NOI as Appendix 1 .\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice are not printed in
the Federal Register, but they are being provided to all those who
receive this notice in the mail. Copies of the NOI can be obtained
from the Commission's Web site at the ``eLibrary'' link,
Commission's Public Reference Room, or by calling (202) 502-8371.
For instructions on connecting to eLibrary, refer to the end of this
notice.
---------------------------------------------------------------------------
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
to discover and address concerns the public may have about proposals.
This process is referred to as ``scoping''. The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this Notice of Intent, the Commission staff
requests public comments on the scope of the issues to address in the
EA. All comments received are considered during the preparation of the
EA. State and local government representatives are encouraged to notify
their constituents of this proposed action and encourage them to
comment on their areas of concern.
In the EA we will discuss impacts that could occur as results of
the construction and operation of the proposed project under these
general headings:
Geology and soils.
Water resources.
Aquatic resources Vegetation and wildlife.
Threatened and endangered species.
Land use, recreation, and visual resources.
Cultural resources.
Socioeconomics.
Air quality and noise.
Reliability and safety.
Cumulative impacts.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to federal, state, and local agencies, public
interest groups, interested individuals, affected landowners,
newspapers, libraries, and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission.
To ensure your comments are considered, please carefully follow the
instructions in the Public Participation section.
Currently Identified Environmental Issues
We have already identified issues that we think deserve attention
based on our previous experience with similar projects in the region.
This preliminary list of issues, which is presented below, may be
revised based on your comments and our continuing analyses specific to
the Project.
Potential noise and vibration impacts from compressor
station.
Air quality impacts from the compressor station.
Wetland and waterbody impacts.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the Project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
written comments are timely and properly recorded, please send in your
comments so that they will be received in Washington, DC on or before
December 14, 2009.
Comments on the proposed Project can be submitted to the FERC in
written form. For your convenience, there are three methods which you
can use to submit your written comments to the Commission. In all
instances please reference the Project docket number (CP10-2-000) with
your submission. The three methods are:
(1) You may file your comments electronically by using the Quick
Comment feature, which is located at https://www.ferc.gov under the link
called ``Documents and Filings''. A Quick Comment is an easy method for
[[Page 61146]]
interested persons to submit text-only comments on a project;
(2) You may file your comments electronically by using the
``eFiling'' feature that is listed under the ``Documents and Filings''
link. eFiling involves preparing your submission in the same manner as
you would if filing on paper, and then saving the file on your
computer's hard drive. You will attach that file to your submission.
New eFiling users must first create an account by clicking on the links
called ``Sign up'' or ``eRegister''. You will be asked to select the
type of filing you are making. A comment on a particular project is
considered a ``Comment on a Filing''; or
(3) You may file your comments with the Commission via mail by
sending an original and two copies of your letter to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas Branch 3,
PJ-11.3.
Environmental Mailing List
An effort is being made to send this notice to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project. This includes all landowners whose
property may be used temporarily for project purposes, who have
existing easements from the pipeline, or who own homes within distances
defined in the Commission's regulations of certain aboveground
facilities. By this notice we are also asking governmental agencies,
especially those in Appendix 2, to express their interest in becoming
cooperating agencies for the preparation of the EA.
If you do not want to send comments at this time but still want to
remain on our mailing list, please return the Information Request
(Appendix 3). If you do not return the Information Request, you will be
taken off the mailing list.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
Internet at https://www.ferc.gov using the ``eLibrary'' link. Click on
the eLibrary link, click on ``General Search'' and enter the docket
number, excluding the last three digits, in the Docket Number field. Be
sure you have selected an appropriate date range. For assistance,
please contact FERC Online Support at FercOnlineSupport@ferc.gov or
toll free at 1-866-208-3676, or for TTY, contact (202) 502-8659. The
eLibrary link also provides access to the texts of formal documents
issued by the Commission, such as orders, notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-28012 Filed 11-20-09; 8:45 am]
BILLING CODE 6717-01-P