Federal Acquisition Regulation; Submission for OMB Review; Schedules for Construction Contracts, 58630 [E9-27248]
Download as PDF
58630
Federal Register / Vol. 74, No. 218 / Friday, November 13, 2009 / Notices
requirement regarding an existing OMB
clearance.
FOR FURTHER INFORMATION CONTACT:
Suzanne Neurauter, Procurement
Analyst, Contract Policy Branch, GSA
(202) 219–0310 or e-mail
Suzanne.neurauter@gsa.gov.
SUPPLEMENTARY INFORMATION:
A. Purpose
Federal Acquisition Regulation (FAR)
52.203–7, Anti-Kickback Procedures,
requires that all contractors have in
place and follow reasonable procedures
designed to prevent and detect in its
own operations and direct business
relationships, violations of section 3 of
the Anti-Kickback Act of 1986 (41
U.S.C. 51–58). Whenever prime
contractors or subcontractors have
reasonable grounds to believe that a
violation of section 3 of the Act may
have occurred, they are required to
report the possible violation in writing
to the contracting agency or the
Department of Justice. The information
is used to determine if any violations of
section 3 of the Act have occurred.
B. Annual Reporting Burden
Respondents: 100.
Responses per Respondent: 1.
Annual Responses: 100.
Hours per Response: 1.
Total Burden Hours: 100.
Obtaining Copies of Proposals:
Requesters may obtain a copy of the
information collection documents from
the General Services Administration,
Regulatory Secretariat (MVPR), 1800 F
Street, NW., Room 4041, Washington,
DC 20405, telephone (202) 501–4755.
Please cite OMB Control No. 9000–0091,
Anti-Kickback Procedures, in all
correspondence.
Dated: November 5, 2009.
Al Matera,
Director, Acquisition Policy Division.
[FR Doc. E9–27249 Filed 11–12–09; 8:45 am]
BILLING CODE 6820–EP–P
DEPARTMENT OF DEFENSE
GENERAL SERVICES
ADMINISTRATION
NATIONAL AERONAUTICS AND
SPACE ADMINISTRATION
A. Purpose
srobinson on DSKHWCL6B1PROD with NOTICES
[OMB Control No. 9000–0058]
Federal Acquisition Regulation;
Submission for OMB Review;
Schedules for Construction Contracts
AGENCY: Department of Defense (DOD),
General Services Administration (GSA),
and National Aeronautics and Space
Administration (NASA).
ACTION: Notice of reinstatement request
for an information collection
VerDate Nov<24>2008
17:07 Nov 12, 2009
Jkt 220001
SUMMARY: Under the provisions of the
Paperwork Reduction Act of 1995 (44
U.S.C. Chapter 35), the Federal
Acquisition Regulation (FAR)
Secretariat will be submitting to the
Office of Management and Budget
(OMB) a request to review and approve
a reinstatement of a previously
approved information collection
requirement concerning schedules for
construction contracts. A request for
public comments was published in the
Federal Register at 74 FR 30092, on
June 24, 2009.
Public comments are particularly
invited on: Whether this collection of
information is necessary for the proper
performance of functions of the FAR,
and whether it will have practical
utility; whether our estimate of the
public burden of this collection of
information is accurate, and based on
valid assumptions and methodology;
ways to enhance the quality, utility, and
clarity of the information to be
collected; and ways in which we can
minimize the burden of the collection of
information on those who are to
respond, through the use of appropriate
technological collection techniques or
other forms of information technology.
DATES: Submit comments on or before
December 14, 2009.
ADDRESSES: Submit comments regarding
this burden estimate or any other aspect
of this collection of information,
including suggestions for reducing this
burden to: FAR Desk Officer, OMB,
Room 10102, NEOB, Washington, DC
20503, and a copy to the General
Services Administration, Regulatory
Secretariat (MVPR), 1800 F Street, NW.,
Room 4041, Washington, DC 20405.
Please cite OMB Control No. 9000–0058,
Schedules for Construction Contracts, in
all correspondence.
FOR FURTHER INFORMATION CONTACT:
Ernest Woodson, Procurement Analyst,
Contract Policy Branch, (202) 501–3775
or e-mail ernest.woodson@gsa.gov.
SUPPLEMENTARY INFORMATION:
In accordance with FAR the
Contractor shall, within five days after
work commences on the contract or
another period of time determined by
the Contracting Officer, prepare and
submit to the Contracting Officer for
approval three copies of a practicable
schedule showing the order in which
the Contractor proposes to perform the
work, and the dates on which the
Contractor contemplates starting and
completing the several salient features
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
of the work (including acquiring
materials, plants, and equipment). The
schedule shall be in the form of a
progress chart of suitable scale to
indicate appropriately the percentage of
work scheduled for completion by any
given date during the period. If the
Contractor fails to submit a schedule
within the time prescribes, the
Contracting Officer may withhold
approval of progress payments until the
Contractor submits the required
schedule.
B. Annual Reporting Burden
Respondents: 2,600.
Responses per Respondent: 2.
Annual Responses: 5,200.
Hours per Response: 1.
Total Burden Hours: 5,200.
Obtaining Copies of Proposals:
Requesters may obtain a copy of the
information collection documents from
the General Services Administration,
Regulatory Secretariat (MVPR), 1800 F
Street, NW., Room 4041, Washington,
DC 20405, telephone (202) 501–4755.
Please cite OMB Control No. 9000–0058,
Schedules for Construction Contracts, in
all correspondence.
Dated: November 5, 2009.
Al Matera,
Director, Acquisition Policy Division.
[FR Doc. E9–27248 Filed 11–12–09; 8:45 am]
BILLING CODE 6820–EP–P
GENERAL SERVICES
ADMINISTRATION
[OMB Control No. 3090–0121]
General Services Administration
Acquisition Regulation; Information
Collection; Industrial Funding Fee and
Sales Reporting
AGENCY: Office of the Acquisition
Policy, GSA.
ACTION: Notice of request for
reinstatement of an information
collection requirement for an existing
OMB clearance.
SUMMARY: Under the provisions of the
Paperwork Reduction Act of 1995 (44
U.S.C. Chapter 35), the General Services
Administration will be submitting to the
Office of Management and Budget
(OMB) a request to review and approve
a reinstatement of a previously
approved information collection
requirement regarding industrial
funding fee and sales reporting.
Public comments are particularly
invited on: Whether this collection of
information is necessary and whether it
will have practical utility; whether our
estimate of the public burden of this
E:\FR\FM\13NON1.SGM
13NON1
Agencies
[Federal Register Volume 74, Number 218 (Friday, November 13, 2009)]
[Notices]
[Page 58630]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-27248]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
GENERAL SERVICES ADMINISTRATION
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
[OMB Control No. 9000-0058]
Federal Acquisition Regulation; Submission for OMB Review;
Schedules for Construction Contracts
AGENCY: Department of Defense (DOD), General Services Administration
(GSA), and National Aeronautics and Space Administration (NASA).
ACTION: Notice of reinstatement request for an information collection
requirement regarding an existing OMB clearance.
-----------------------------------------------------------------------
SUMMARY: Under the provisions of the Paperwork Reduction Act of 1995
(44 U.S.C. Chapter 35), the Federal Acquisition Regulation (FAR)
Secretariat will be submitting to the Office of Management and Budget
(OMB) a request to review and approve a reinstatement of a previously
approved information collection requirement concerning schedules for
construction contracts. A request for public comments was published in
the Federal Register at 74 FR 30092, on June 24, 2009.
Public comments are particularly invited on: Whether this
collection of information is necessary for the proper performance of
functions of the FAR, and whether it will have practical utility;
whether our estimate of the public burden of this collection of
information is accurate, and based on valid assumptions and
methodology; ways to enhance the quality, utility, and clarity of the
information to be collected; and ways in which we can minimize the
burden of the collection of information on those who are to respond,
through the use of appropriate technological collection techniques or
other forms of information technology.
DATES: Submit comments on or before December 14, 2009.
ADDRESSES: Submit comments regarding this burden estimate or any other
aspect of this collection of information, including suggestions for
reducing this burden to: FAR Desk Officer, OMB, Room 10102, NEOB,
Washington, DC 20503, and a copy to the General Services
Administration, Regulatory Secretariat (MVPR), 1800 F Street, NW., Room
4041, Washington, DC 20405. Please cite OMB Control No. 9000-0058,
Schedules for Construction Contracts, in all correspondence.
FOR FURTHER INFORMATION CONTACT: Ernest Woodson, Procurement Analyst,
Contract Policy Branch, (202) 501-3775 or e-mail
ernest.woodson@gsa.gov.
SUPPLEMENTARY INFORMATION:
A. Purpose
In accordance with FAR the Contractor shall, within five days after
work commences on the contract or another period of time determined by
the Contracting Officer, prepare and submit to the Contracting Officer
for approval three copies of a practicable schedule showing the order
in which the Contractor proposes to perform the work, and the dates on
which the Contractor contemplates starting and completing the several
salient features of the work (including acquiring materials, plants,
and equipment). The schedule shall be in the form of a progress chart
of suitable scale to indicate appropriately the percentage of work
scheduled for completion by any given date during the period. If the
Contractor fails to submit a schedule within the time prescribes, the
Contracting Officer may withhold approval of progress payments until
the Contractor submits the required schedule.
B. Annual Reporting Burden
Respondents: 2,600.
Responses per Respondent: 2.
Annual Responses: 5,200.
Hours per Response: 1.
Total Burden Hours: 5,200.
Obtaining Copies of Proposals: Requesters may obtain a copy of the
information collection documents from the General Services
Administration, Regulatory Secretariat (MVPR), 1800 F Street, NW., Room
4041, Washington, DC 20405, telephone (202) 501-4755. Please cite OMB
Control No. 9000-0058, Schedules for Construction Contracts, in all
correspondence.
Dated: November 5, 2009.
Al Matera,
Director, Acquisition Policy Division.
[FR Doc. E9-27248 Filed 11-12-09; 8:45 am]
BILLING CODE 6820-EP-P