City of Seattle, WA; Notice of Designation of Commission Staff as Non-Decisional, 57669 [E9-26886]
Download as PDF
Federal Register / Vol. 74, No. 215 / Monday, November 9, 2009 / Notices
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on November 19, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–26888 Filed 11–6–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL10–8–000]
Town of Edinburg, Indiana,
Complainant, v. Indiana Michigan
Power Agency, Respondent; Notice of
Complaint
mstockstill on DSKH9S0YB1PROD with NOTICES
November 2, 2009.
Take notice that on October 29, 2009,
pursuant to sections 206 and 211A of
the Federal Power Act, 16 U.S.C. 824e,
and 824j–i, and Rule 206 of the
Commission’s regulations, 18 CFR
385.206, the Town of Edinburgh,
(Complainant), filed a formal complaint
against the Indiana Municipal Power
Agency (Respondent) alleging that the
Respondent is in violation of section
211A of the Federal Power Act for
failure to charge Complainant a
comparable transmission rate and
resulting discriminatory overcharges
against Complainant of at least $1.98
million for the period 2003 through
2009.
The Complainant certifies that copies
of the complaint were served on the
contacts for the Respondent as listed on
the Commission’s list of Corporate
Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
VerDate Nov<24>2008
16:52 Nov 06, 2009
Jkt 220001
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on November 18, 2009.
57669
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2144–038—Washington]
City of Seattle, WA; Notice of
Designation of Commission Staff as
Non-Decisional
November 2, 2009.
DEPARTMENT OF ENERGY
Commission staff member James
Hastreiter (Office of Energy Projects,
503–552–2760;
james.hastreiter@ferc.gov) is hereby
designated as ‘‘non-decisional’’ staff and
assigned to participate in settlement
discussions and provide guidance on
the Commission’s policies and
authorities for the Boundary
Hydroelectric Project in the abovereferenced proceeding.
As ‘‘non-decisional’’ staff, Mr.
Hastreiter will not participate in an
advisory capacity in the Commission’s
review of any offer of settlement or
settlement agreement, or deliberations
concerning the disposition of the
relicense application in the abovereferenced proceeding.
Different Commission ‘‘advisory staff’’
will be assigned to review any offer of
settlement or settlement agreement, and
to process the relicense application,
including providing advice to the
Commission with respect to the
agreement and the application. Nondecisional staff and advisory staff are
prohibited from communicating with
one another concerning the merits of the
settlement and the relicense application.
Federal Energy Regulatory
Commission
Kimberly D. Bose,
Secretary.
[FR Doc. E9–26886 Filed 11–6–09; 8:45 am]
Kimberly D. Bose,
Secretary.
[FR Doc. E9–26887 Filed 11–6–09; 8:45 am]
BILLING CODE 6717–01–P
BILLING CODE 6717–01–P
[Docket No. AD09–11–000]
Natural Gas Infrastructure and
Opportunities for Improved Efficiency;
Notice of Conference Postponement
November 2, 2009.
Take notice that the public conference
referenced in the above docket and
initially noticed on September 21, 2009
will be postponed until January. Once
the conference is rescheduled, a
subsequent scheduling notice will be
issued.
For more information about the
conference or any questions, please
contact Pamela Romano at (202) 502–
6854 (pamela.romano@ferc.gov).
Kimberly D. Bose,
Secretary.
[FR Doc. E9–26889 Filed 11–6–09; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER10–90–000]
Lonestar Energy Partners LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
October 30, 2009.
This is a supplemental notice in the
above-referenced proceeding of Lonestar
Energy Partners LLC’s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
E:\FR\FM\09NON1.SGM
09NON1
Agencies
[Federal Register Volume 74, Number 215 (Monday, November 9, 2009)]
[Notices]
[Page 57669]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-26886]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2144-038--Washington]
City of Seattle, WA; Notice of Designation of Commission Staff as
Non-Decisional
November 2, 2009.
Commission staff member James Hastreiter (Office of Energy
Projects, 503-552-2760; james.hastreiter@ferc.gov) is hereby designated
as ``non-decisional'' staff and assigned to participate in settlement
discussions and provide guidance on the Commission's policies and
authorities for the Boundary Hydroelectric Project in the above-
referenced proceeding.
As ``non-decisional'' staff, Mr. Hastreiter will not participate in
an advisory capacity in the Commission's review of any offer of
settlement or settlement agreement, or deliberations concerning the
disposition of the relicense application in the above-referenced
proceeding.
Different Commission ``advisory staff'' will be assigned to review
any offer of settlement or settlement agreement, and to process the
relicense application, including providing advice to the Commission
with respect to the agreement and the application. Non-decisional staff
and advisory staff are prohibited from communicating with one another
concerning the merits of the settlement and the relicense application.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-26886 Filed 11-6-09; 8:45 am]