Pacific Gas and Electric Company; Notice of Authorization for Continued Project Operation, 57163-57164 [E9-26471]
Download as PDF
mstockstill on DSKH9S0YB1PROD with NOTICES
Federal Register / Vol. 74, No. 212 / Wednesday, November 4, 2009 / Notices
also serve a copy of the document on
that resource agency.
k. This application has been accepted,
but is not ready for environmental
analysis at this time.
l. Project Description: The existing
project consists of: (1) A concrete arch
dam with a crest elevation of 2,004 feet
NGVD (North American Vertical
Datum), a structural height of 340 feet,
a thickness ranging from 8 feet at the
crest to 32 feet at the base, and a crest
length of 508 feet, with a total length,
including the spillways, of 740 feet; (2)
two 50-feet-wide spillways fitted with
45-feet-high radial gates, one on each
abutment, which have a combined
maximum capacity of 108,000 cubic feet
per second (cfs) at a forebay water
surface elevation of 1994 feet NGVD; (3)
seven 21-foot-high by 17-foot-wide, lowlevel vertical fixed-wheel sluice gates
that provide an additional discharge
capacity of 252,000 cfs, for a total
discharge capacity at the dam of 360,000
cfs; (4) a 17.5-mile-long, 1,794-acre
reservoir at a normal full pool elevation
of 1,994 feet NGVD with 87,913 acrefeet of gross storage; (5) power intake
facilities excavated on the left abutment
area consisting of an approximately 300foot-wide by 800-foot-long forebay, a
trash rack structure across the entrance
to the forebay, and the portal face with
six 30-foot-wide by 34-foot-high
horseshoe-shaped tunnels extending to
intake gate chambers; (6) six 315-feetlong penstocks lead from each of the
intake gates to one of the six turbinegenerator units in the power plant; (7)
an underground power plant comprised
of a 76-feet wide by 172-feet-high by
477-feet-long machine hall; (8) two
204,506-horsepower (hp) Francis
turbines, with 158.4-megawatt (MW)
generators, two 204,506-hp Francis
turbines, with 161.5–MW generators,
and two 259,823-hp Francis turbines,
with 200–MW generators for a total
authorized generating capacity of 1,003
MW; (9) six draft tubes that discharge
water into the tailrace immediately
below the dam; (10) six horseshoeshaped transformer bays; (11) six
individual three-phase, 230-kilovolt
(kV) transmission lines up the vertical
face of the left abutment of the dam to
six pairs of transmission towers on top
of the abutment; and (12) appurtenant
equipment. The applicant proposes to
install new high efficiency turbines in
Units 55 and 56, concurrently with
planned generator rewinds and step-up
transformer replacements.
m. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
VerDate Nov<24>2008
16:29 Nov 03, 2009
Jkt 220001
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item (h) above.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate
action to take, the Commission will
consider all protests filed, but only
those who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any protests or motions to
intervene must be received on or before
the specified comment date for the
particular application.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’ or
‘‘MOTION TO INTERVENE;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
Agencies may obtain copies of the
application directly from the applicant.
A copy of any protest or motion to
intervene must be served upon each
representative of the applicant specified
in the particular application.
o. Procedural Schedule: See tendering
notice issued on October 8, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–26474 Filed 11–3–09; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
57163
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 803–087 ]
Pacific Gas and Electric Company;
Notice of Authorization for Continued
Project Operation
October 28, 2009.
On October 2, 2007, Pacific Gas and
Electric Company, licensee for the
DeSabla-Centerville Hydroelectric
Project, filed an Application for a New
License pursuant to the Federal Power
Act (FPA) and the Commission’s
regulations thereunder. The DeSablaCenterville Hydroelectric Project is
located on the Butte Creek and West
Branch Feather River, in Butte County,
CA.
The license for Project No. 803 was
issued for a period ending October 11,
2009. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 803 is
issued to the Pacific Gas and Electric
Company for a period effective October
12, 2009 through October 11, 2010, or
until the issuance of a new license for
the project or other disposition under
the FPA, whichever comes first. If
issuance of a new license (or other
disposition) does not take place on or
before October 11, 2010, notice is
hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
E:\FR\FM\04NON1.SGM
04NON1
57164
Federal Register / Vol. 74, No. 212 / Wednesday, November 4, 2009 / Notices
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise. If the
project is not subject to section 15 of the
FPA, notice is hereby given that the
Pacific Gas and Electric Company is
authorized to continue operation of the
DeSabla-Centerville Hydroelectric
Project, until such time as the
Commission acts on its application for
a subsequent license.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–26471 Filed 11–3–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
BILLING CODE 6717–01–P
[Project No. 2179–042]
Merced Irrigation District;Notice of
Dispute Resolution Panel Meeting and
Technical Conference
mstockstill on DSKH9S0YB1PROD with NOTICES
October 28, 2009.
On October 16, 2009, Commission
staff, in response to the filing of notices
of study dispute by the U.S. Department
of Interior (Fish and Wildlife Service),
U.S. Department of Commerce (National
Marine Fisheries Service), and
California State Water Resources
Control Board on October 5, 2009,
convened a single three-person Dispute
Resolution Panels pursuant to 18 CFR
5.14(d).
The Panel will hold a technical
conference at the time and place noted
below. The session will address study
disputes regarding 16 separate studies
that focus on water and aquatic resource
related issues. The disputes primarily
address the Commission’s
determination on the geographic scope
of the proposed project’s direct,
indirect, and cumulative effects and the
level of study being required for
assessing project related effects on
anadromous salmonids and their
habitats. The focus of the technical
session is for the disputing agencies,
applicants, and Commission to provide
the Panel with additional information
necessary to evaluate the disputed
studies. All local, state, and federal
agencies, Indian tribes, and other
interested parties are invited to attend
the meeting as observers. The Panel may
also request information or clarification
on written submissions as necessary to
understand the matters in dispute. The
Panel will limit all input that it receives
to the specific studies or information in
dispute and will focus on the
applicability of such studies or
16:29 Nov 03, 2009
Technical Conference
Date: Tuesday, November 17, 2009.
Time: 8:30 a.m.–5 p.m. (PST).
Place: John E. Moss Federal Building,
First Floor (Stanford Room), 650 Capitol
Mall, First Floor, Sacramento, CA
95814–4708.
Phone: 916–930–3600.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–26475 Filed 11–3–09; 8:45 am]
Federal Energy Regulatory
Commission
VerDate Nov<24>2008
information to the study criteria
stipulated in 18 CFR 5.9(b). If the
number of participants wishing to speak
creates time constraints, the Panel may,
at their discretion, limit the speaking
time for each participant.
If you have any questions, please
contact Aaron Liberty at (202) 502–
6862.
Jkt 220001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP10–8–000]
Tennessee Gas Pipeline Company;
Notice of Request Under Blanket
Authorization
October 28, 2009.
Take notice that on October 22, 2009,
Tennessee Gas Pipeline Company
(Tennessee), 1001 Louisiana Street,
Houston, Texas 77002, filed in Docket
No. CP10–8–000, an application
pursuant to Sections 157.205 and
157.216 of the Commission’s
Regulations under the Natural Gas Act
(NGA) as amended, to abandon by sale
certain natural gas pipeline laterals and
appurtenant facilities located in Harris
and Montgomery Counties, Texas, to
Alamo Pipeline, L.L.C. (Alamo), under
Tennessee’s blanket certificate issued in
Docket No. CP82–413–000,1 all as more
fully set forth in the application which
is on file with the Commission and open
to the public for inspection.
Tennessee states that it proposes to
abandon in place and by sale to Alamo
15.33 miles of 6-inch diameter pipeline
lateral (Line No. 21A–100),2 0.36 miles
of 3-inch diameter pipeline lateral (Line
No. 21A–300),3 two receipt taps, and six
delivery taps, as well as equipment and
associated appurtenances thereto.
Tennessee also states that Alamo would
continue to operate the facilities
following the closing of the purchase
1 20
FERC ¶ 62,409 (1982).
2 8 FPC 276 (1949).
3 6 FERC ¶ 62,073 (1979) and 9 FERC ¶ 61,248
(1979).
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
and sales transaction. Tennessee further
states that Alamo, an intrastate pipeline
that is subject to the jurisdiction of the
Texas Railroad Commission, would
continue to operate the facilities in
natural gas service. Tennessee states
that following the abandonment and
sale of the subject facilities to Alamo,
the laterals would be disconnected from
Tennessee’s mainlines (Line Nos. 100–
1 and 100–3). Tennessee estimates that
it would cost approximately
$14,220,000 to construct similar
facilities today.
Any questions concerning this
application may be directed to Susan T.
Halbach, Senior Counsel, Tennessee Gas
Pipeline Company, 1001 Louisiana
Street, Houston, Texas 77002, via
telephone at (713) 420–5751, or
facsimile (713) 420–1601 or Debbie
Kalisek, Analyst, Certificates &
Regulatory Compliance via telephone at
(713) 420–3292 or facsimile (713) 420–
1605.
This filing is available for review at
the Commission or may be viewed on
the Commission’s Web site at https://
www.ferc.gov, using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
filed to access the document. For
assistance, please contact FERC Online
Support at FERC
OnlineSupport@ferc.gov or call toll-free
at (866) 206–3676, or, for TTY, contact
(202) 502–8659. Comments, protests and
interventions may be filed electronically
via the Internet in lieu of paper. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link. The
Commission strongly encourages
intervenors to file electronically.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to Section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to Section 7 of
the NGA.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–26472 Filed 11–3–09; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\04NON1.SGM
04NON1
Agencies
[Federal Register Volume 74, Number 212 (Wednesday, November 4, 2009)]
[Notices]
[Pages 57163-57164]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-26471]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 803-087 ]
Pacific Gas and Electric Company; Notice of Authorization for
Continued Project Operation
October 28, 2009.
On October 2, 2007, Pacific Gas and Electric Company, licensee for
the DeSabla-Centerville Hydroelectric Project, filed an Application for
a New License pursuant to the Federal Power Act (FPA) and the
Commission's regulations thereunder. The DeSabla-Centerville
Hydroelectric Project is located on the Butte Creek and West Branch
Feather River, in Butte County, CA.
The license for Project No. 803 was issued for a period ending
October 11, 2009. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 803 is issued to
the Pacific Gas and Electric Company for a period effective October 12,
2009 through October 11, 2010, or until the issuance of a new license
for the project or other disposition under the FPA, whichever comes
first. If issuance of a new license (or other disposition) does not
take place on or before October 11, 2010, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1)
of the FPA is renewed
[[Page 57164]]
automatically without further order or notice by the Commission, unless
the Commission orders otherwise. If the project is not subject to
section 15 of the FPA, notice is hereby given that the Pacific Gas and
Electric Company is authorized to continue operation of the DeSabla-
Centerville Hydroelectric Project, until such time as the Commission
acts on its application for a subsequent license.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-26471 Filed 11-3-09; 8:45 am]
BILLING CODE 6717-01-P