Download as PDF 54982 Federal Register / Vol. 74, No. 205 / Monday, October 26, 2009 / Notices Conservation, 1424 9th Ave., P.O. Box 201601, Helena, MT 59620–1601; phone: (406) 444–6646. FERC Contact: Dianne Rodman, (202) 502–6077. Competing Application: This application competes with Project No. 13360–000 filed January 29, 2009. The May 8, 2009 notice for Project No. 13360–000 established a July 7, 2009 deadline for filing competing applications and notices of intent to file a competing application. MDNRC’s notice of intent to file a competing application was timely filed on June 3, 2009, and its competing application was timely filed on July 31, 2009. Deadline for filing comments and motions to intervene: 60 days from the issuance of this notice. Comments and motions to intervene may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https://www.ferc.gov/docs-filing/ ferconline.asp) under the ‘‘eFiling’’ link. For a simpler method of submitting text only comments, click on ‘‘Quick Comment.’’ For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY, contact (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and eight copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P–13562) in the docket number field to access the document. For assistance, contact FERC Online Support. Kimberly D. Bose, Secretary. [FR Doc. E9–25620 Filed 10–23–09; 8:45 am] mstockstill on DSKH9S0YB1PROD with NOTICES BILLING CODE 6717–01–P VerDate Nov<24>2008 15:19 Oct 23, 2009 Jkt 220001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13556–000] Montana Department of Natural Resources and Conservation; Notice of Competing Preliminary Permit Application Accepted for Filing and Soliciting Comments and Motions To Intervene October 19, 2009. On July 16, 2009, the Montana Department of Natural Resources and Conservation (MDNRC) filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Tongue River Power Project, which would be located at the existing Tongue River Reservoir Dam on the Tongue River, in Big Horn County, Montana. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would use the existing 93-foot-high, 1,824-foot-long earthen dam with spillway, and the existing 765-foot-long, 16-foot-diameter horseshoe-shaped auxiliary outlet conduit. MDNRC proposes to construct and install: (1) A new 8-foot-diameter, 765-foot-long steel liner in the existing auxiliary outlet conduit; (2) a new 8foot-diameter, 400-foot-long steel penstock extending to a bifurcation; (3) a new 8-foot-diameter, 60-foot-long steel penstock extending from the bifurcation to the powerhouse; (4) a new 8-footdiameter, 60-foot-long steel conduit extending from the bifurcation to an energy dissipation structure for excess flows and bypass during turbine outages; (5) a new powerhouse containing two generating units with a combined installed capacity of 3,000 kilowatts, discharging flows into the Tongue River; (6) a new substation next to the powerhouse; (7) a new 25kilovolt, 0.75-mile-long transmission line; (8) a new switchyard at the interconnection point with the local grid; and (9) appurtenant facilities. The proposed project would have an average annual generation of 11.5 gigawatthours. Applicant Contact: Kevin Smith, State Water Projects Bureau, Montana Department of Natural Resources and Conservation, 1424 9th Ave., P.O. Box PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 201601, Helena, MT 59620–1601; phone: (406) 444–6646. FERC Contact: Dianne Rodman, (202) 502–6077. Competing Application: This application competes with Project No. 13372–000 filed February 12, 2009. The April 23, 2009 notice for Project No. 13372–000 established a June 22, 2009 deadline for filing competing applications and notices of intent to file a competing application. MDNRC’s notice of intent to file a competing application was timely filed on June 2, 2009, and its competing application was timely filed on July 16, 2009. Deadline for filing comments and motions to intervene: 60 days from the issuance of this notice. Comments and motions to intervene may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https://www.ferc.gov/docs-filing/ ferconline.asp) under the ‘‘eFiling’’ link. For a simpler method of submitting text only comments, click on ‘‘Quick Comment.’’ For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY, contact (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and eight copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13556) in the docket number field to access the document. For assistance, contact FERC Online Support. Kimberly D. Bose, Secretary. [FR Doc. E9–25619 Filed 10–23–09; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\26OCN1.SGM 26OCN1

Agencies

[Federal Register Volume 74, Number 205 (Monday, October 26, 2009)]
[Notices]
[Page 54982]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-25619]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13556-000]


Montana Department of Natural Resources and Conservation; Notice 
of Competing Preliminary Permit Application Accepted for Filing and 
Soliciting Comments and Motions To Intervene

October 19, 2009.
    On July 16, 2009, the Montana Department of Natural Resources and 
Conservation (MDNRC) filed an application for a preliminary permit, 
pursuant to section 4(f) of the Federal Power Act, proposing to study 
the feasibility of the Tongue River Power Project, which would be 
located at the existing Tongue River Reservoir Dam on the Tongue River, 
in Big Horn County, Montana. The sole purpose of a preliminary permit, 
if issued, is to grant the permit holder priority to file a license 
application during the permit term. A preliminary permit does not 
authorize the permit holder to perform any land disturbing activities 
or otherwise enter upon lands or waters owned by others without the 
owners' express permission.
    The proposed project would use the existing 93-foot-high, 1,824-
foot-long earthen dam with spillway, and the existing 765-foot-long, 
16-foot-diameter horseshoe-shaped auxiliary outlet conduit. MDNRC 
proposes to construct and install: (1) A new 8-foot-diameter, 765-foot-
long steel liner in the existing auxiliary outlet conduit; (2) a new 8-
foot-diameter, 400-foot-long steel penstock extending to a bifurcation; 
(3) a new 8-foot-diameter, 60-foot-long steel penstock extending from 
the bifurcation to the powerhouse; (4) a new 8-foot-diameter, 60-foot-
long steel conduit extending from the bifurcation to an energy 
dissipation structure for excess flows and bypass during turbine 
outages; (5) a new powerhouse containing two generating units with a 
combined installed capacity of 3,000 kilowatts, discharging flows into 
the Tongue River; (6) a new substation next to the powerhouse; (7) a 
new 25-kilovolt, 0.75-mile-long transmission line; (8) a new switchyard 
at the interconnection point with the local grid; and (9) appurtenant 
facilities. The proposed project would have an average annual 
generation of 11.5 gigawatt-hours.
    Applicant Contact: Kevin Smith, State Water Projects Bureau, 
Montana Department of Natural Resources and Conservation, 1424 9th 
Ave., P.O. Box 201601, Helena, MT 59620-1601; phone: (406) 444-6646.
    FERC Contact: Dianne Rodman, (202) 502-6077.
    Competing Application: This application competes with Project No. 
13372-000 filed February 12, 2009. The April 23, 2009 notice for 
Project No. 13372-000 established a June 22, 2009 deadline for filing 
competing applications and notices of intent to file a competing 
application. MDNRC's notice of intent to file a competing application 
was timely filed on June 2, 2009, and its competing application was 
timely filed on July 16, 2009.
    Deadline for filing comments and motions to intervene: 60 days from 
the issuance of this notice. Comments and motions to intervene may be 
filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) 
and the instructions on the Commission's Web site (https://www.ferc.gov/docs-filing/ferconline.asp) under the ``eFiling'' link. For a simpler 
method of submitting text only comments, click on ``Quick Comment.'' 
For assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-3676; or, for 
TTY, contact (202) 502-8659. Although the Commission strongly 
encourages electronic filing, documents may also be paper-filed. To 
paper-file, mail an original and eight copies to: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-13556) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

Kimberly D. Bose,
Secretary.
[FR Doc. E9-25619 Filed 10-23-09; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.