EDF Development, Inc., Renewed License No. DPR-63; Constellation Energy Nuclear Group, LLC, Renewed License No. NPF-69; Nine Mile Point Nuclear Station, LLC (Nine Mile Point Nuclear Station Unit Nos. 1 and 2); Order Approving Application Regarding Proposed Corporate Restructuring, 53772-53773 [E9-25165]
Download as PDF
cprice-sewell on DSKGBLS3C1PROD with NOTICES
53772
Federal Register / Vol. 74, No. 201 / Tuesday, October 20, 2009 / Notices
Development under any Support
Agreement.
(c) The Master Demand Notes
described in the supplement to the
application dated July 27, 2009, shall be
effective as of the date of the transfer
and shall be consistent with the
representations contained in the
application. CENG and CCNPP, LLC,
shall take no action to cause CEG and/
or EDF Development, or their successors
and assigns, to void, cancel or
materially modify the Master Demand
Notes without the prior written consent
of the NRC staff.
It is further ordered that, consistent
with 10 CFR 2.1315(b), the license
amendment that makes changes, as
indicated in Enclosure 2 to the cover
letter forwarding this Order, to conform
the license to reflect the subject direct
license transfer is approved. The
amendment shall be issued and made
effective at the time the proposed direct
license transfer is completed.
It is further ordered that CENG shall
inform the Director of the Office of
Nuclear Reactor Regulation, in writing,
of the date of closing of the transfer of
EDF Development’s ownership and
operating interests in CENG at least 1
business day before the closing. Should
the transfer of the license not be
completed within 1 year of this Order’s
date of issuance, this Order shall
become null and void, provided,
however, that upon written application
and for good cause shown, such date
may be extended by Order.
This Order is effective upon issuance.
For further details with respect to this
Order, see the initial application dated
January 22, 2009 (Agencywide
Documents Access and Management
System (ADAMS) Accession No.
ML090290101), as supplemented by
letters dated February 26
(ML090630426), April 8
(ML091000665), June 25
(ML091811094), and July 27, 2009
(ML092150712), and the SE with the
same date as this Order, which are
available for public inspection at the
Commission’s Public Document Room
(PDR), located at One White Flint North,
11555 Rockville Pike, Room O–1 F21
(First Floor), Rockville, Maryland, and
accessible electronically from the
ADAMS Public Electronic Reading
Room on the Internet at the NRC Web
site, https://www.nrc.gov/reading-rm/
adams.html. Persons who do not have
access to ADAMS, or who encounter
problems in accessing the documents
located in ADAMS, should contact the
NRC PDR Reference staff by telephone
at 1–800–397–4209 or 301–415–4737, or
by e-mail at pdr.resource@nrc.gov.
VerDate Nov<24>2008
14:46 Oct 19, 2009
Jkt 220001
Dated at Rockville, Maryland, this 9th day
of October 2009.
For the Nuclear Regulatory Commission.
Bruce S. Mallett,
Deputy Executive Director for Reactor and
Preparedness Programs.
Michael F. Weber,
Director, Office of Nuclear Material Safety.
[FR Doc. E9–25166 Filed 10–19–09; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2009–0193; Docket Nos. 50–220 and
50–410]
EDF Development, Inc., Renewed
License No. DPR–63; Constellation
Energy Nuclear Group, LLC, Renewed
License No. NPF–69; Nine Mile Point
Nuclear Station, LLC (Nine Mile Point
Nuclear Station Unit Nos. 1 and 2);
Order Approving Application
Regarding Proposed Corporate
Restructuring
I
Nine Mile Point Nuclear Station, LLC
(NMPNS, LLC or the licensee) is the
holder of Renewed Facility Operating
License Nos. DPR–63 and NPF–69,
which authorize the possession, use,
and operation of the Nine Mile Point
Nuclear Station, Unit Nos. 1 and 2
(NMP 1 and 2). The facility is located at
the licensee’s site in Oswego, New York.
II
By letter dated January 22, 2009, as
supplemented on February 26, April 8,
June 25, and July 27, 2009 (together, the
application), Constellation Energy
Nuclear Group, LLC (CENG), on behalf
of the licensee and EDF Development,
Inc. (EDF Development) (together, the
applicants), requested that the Nuclear
Regulatory Commission (NRC, the
Commission), pursuant to Title 10 of the
Code of Federal Regulations (10 CFR)
50.80, consent to the indirect license
transfers that would be effected by the
indirect transfer of control of CENG’s
ownership and operating interests in
NMP 1 and 2. The actions being sought
as a result of certain proposed corporate
restructuring actions in connection with
a planned investment by EDF
Development whereby it would acquire
a 49.99% ownership interest in CENG
from Constellation Energy Group, Inc.
(CEG), the current 100% owner of
CENG. EDF Development is a U.S.
corporation organized under the laws of
the State of Delaware and a whollyowned subsidiary of E.D.F. International
S.A., a public limited company
organized under the laws of France,
PO 00000
Frm 00076
Fmt 4703
Sfmt 4703
which is in turn a wholly-owned
´
´
subsidiary of Electricite de France S.A.,
a French limited company.
Following the proposed transaction,
EDF Development will hold a 49.99%
ownership interest in CENG; CEG will
hold a 50.01% ownership interest in
CENG through two new intermediate
parent companies, Constellation
Nuclear, LLC and CE Nuclear, LLC,
formed for non-operational purposes. In
addition, Constellation Nuclear Power
Plants, Inc., which is currently an
intermediate holding company between
CENG and NMPNS, LLC and R.E. Ginna
Nuclear Power Plant, LLC, will convert
to a Delaware limited liability company
and become Constellation Nuclear
Power Plants, LLC, and will exist as an
intermediate holding company between
CENG and NMPNS, LLC, R.E. Ginna
Nuclear Power Plant, LLC, and Calvert
Cliffs Nuclear Power Plant, LLC. No
physical changes to the facilities or
operational changes are being proposed
in the application.
Approval of the transfer of the license
is requested by the applicants pursuant
to 10 CFR 50.80. Notice of the request
for approval and opportunity for a
hearing was published in the Federal
Register on May 6, 2009 (74 FR 21015).
No hearing requests or petitions to
intervene were received. The NRC
received comments from a member of
the public in Seattle, Washington, in an
e-mail dated May 22, 2009. The
comments did not provide any
information additional to that in the
application, nor did they provide any
information contradictory to that
provided in the application.
Pursuant to 10 CFR 50.80, no license,
or any right thereunder, shall be
transferred, directly or indirectly,
through transfer of control of the
license, unless the Commission shall
give its consent in writing. Upon review
of the information in the application
and other information before the
Commission, and relying upon the
representations and agreements
contained in the application, the NRC
staff has determined that the proposed
indirect license transfer of control of the
subject license held by the licensee to
the extent such will result from the
proposed corporate restructuring actions
in connection with the planned
investment by EDF Development
whereby it will acquire a 49.99%
ownership interest in CENG, to the
extent affected by the proposed
transaction as described in the
application, is otherwise consistent with
applicable provisions of law,
regulations, and Orders issued by the
NRC, pursuant thereto, subject to the
conditions set forth below. The NRC
E:\FR\FM\20OCN1.SGM
20OCN1
Federal Register / Vol. 74, No. 201 / Tuesday, October 20, 2009 / Notices
cprice-sewell on DSKGBLS3C1PROD with NOTICES
staff has further found that the
application for the proposed license
amendment complies with the
standards and requirements of the
Atomic Energy Act of 1954, as amended
(the Act), and the Commission’s rules
and regulations set forth in 10 CFR
Chapter I; the facility will operate in
conformity with the application, the
provisions of the Act, and the rules and
regulations of the Commission; there is
reasonable assurance that the activities
authorized by the proposed license
amendment can be conducted without
endangering the health and safety of the
public and that such activities will be
conducted in compliance with the
Commission’s regulations; the issuance
of the proposed license amendment will
not be inimical to the common defense
and security or to the health and safety
of the public; and the issuance of the
proposed amendments will be in
accordance with 10 CFR Part 51 of the
Commission’s regulations and all
applicable requirements have been
satisfied.
The findings set forth above are
supported by the NRC staff’s safety
evaluation (SE) dated the same day as
this Order.
III
Accordingly, pursuant to Sections
161b, 161i, 161o, and 184 of the Act, 42
U.S.C. Sections 2201(b), 2201(i),
2201(o), and 2234; and 10 CFR 50.80, it
is hereby ordered that the application
regarding the indirect license transfers
related to the proposed corporate
restructuring actions in connection with
the planned investment by EDF
Development, as described herein, is
approved, subject to the following
conditions:
(1) The ownership and governance
arrangements as a result of the proposed
transaction, is subject to the following:
(a) The Operating Agreement
included with the application dated
January 22, 2009, may not be modified
in any material respect concerning
decision-making authority over ‘‘safety
issues’’ as defined therein without the
prior written consent of the Director,
Office of Nuclear Reactor Regulation.
(b) At least half the members of
CENG’s Board of Directors must be U.S.
citizens.
(c) The Chief Executive Officer (CEO),
Chief Nuclear Officer (CNO) and
Chairman of the Board of Directors of
CENG must be U.S. citizens. These
individuals shall have the responsibility
and exclusive authority to ensure and
shall ensure that the business and
activities of CENG with respect to the
Calvert Cliffs, Unit Nos. 1 and 2, Calvert
Cliffs ISFSI, Nine Mile Point, Unit Nos.
VerDate Nov<24>2008
14:46 Oct 19, 2009
Jkt 220001
1 and 2, and R.E. Ginna licenses are at
all times conducted in a manner
consistent with the public health and
safety and common defense and security
of the United States.
(d) CENG will establish a Nuclear
Advisory Committee (NAC) composed
of U.S. citizens who are not officers,
directors, or employees of CENG, CEG
or EDF Development. The NAC will
report to and provide transparency to
the NRC and other U.S. governmental
agencies regarding foreign ownership
and control of nuclear operations.
(e) CENG shall cause to be transmitted
to the Director, Office of Nuclear
Reactor Regulation, within 30 days of
knowledge of a filing with the U.S.
Securities and Exchange Commission,
any Schedules 13D or 13G filed
pursuant to the Securities and Exchange
Act of 1934 that disclose beneficial
ownership of any registered classes of
CEG stock.
(2) The financial arrangements
resulting from the proposed transaction,
are subject to the following:
(a) The working capital and cash
pooling arrangements described in
Article IV of the Operating Agreement
included with the application dated
January 22, 2009, and supplement dated
July 27, 2009, shall be effective as of the
date of the transfer and shall be
consistent with the representations
contained in the application. CENG and
NMPNS, LLC shall take no action to
cause CEG and/or EDF Development, or
their successors and assigns, to void,
cancel or materially modify the working
capital and cash pooling arrangements
in the Operating Agreement without the
prior written consent of the NRC staff.
(b) The Support Agreements
described in the supplement to the
application dated February 26, 2009 (up
to $290 million), shall be effective as of
the date of the transfer and shall be
consistent with the representations
contained in the application. CENG and
NMPNS, LLC shall take no action to
cause CEG and/or EDF Development, or
their successors and assigns, to void,
cancel or materially modify the Support
Agreements as submitted without the
prior written consent of the NRC staff,
except, however, the intercompany
credit agreement referenced in the
current licenses for NMP 1 and 2
[condition 2.D(12) for Unit 1 and 2.C(15)
for Unit 2] may be revoked or rescinded
if and when the $290 million support
agreements described in the February
26, 2009, supplement to the application
become effective. CENG shall inform the
Director of the Office of Nuclear Reactor
Regulation, in writing, no later than ten
days after any funds are provided to
CENG or any of the licensees by CEG or
PO 00000
Frm 00077
Fmt 4703
Sfmt 4703
53773
EDF Development under any Support
Agreement.
(c) The Master Demand Notes
described in the supplement to the
application dated July 27, 2009, shall be
effective as of the date of the transfer
and shall be consistent with the
representations contained in the
application. CENG and NMPNS, LLC
shall take no action to cause CEG and/
or EDF Development, or their successors
and assigns, to void, cancel or
materially modify the Master Demand
Notes without the prior written consent
of the NRC staff.
It is further ordered that CENG shall
inform the Director of the Office of
Nuclear Reactor Regulation, in writing,
of the date of closing of the transfer of
EDF Development’s ownership and
operating interests in CENG at least 1
business day before the closing. Should
the transfer of the license not be
completed within 1 year of this Order’s
date of issuance, this Order shall
become null and void, provided,
however, that upon written application
and for good cause shown, such date
may be extended by order.
This Order is effective upon issuance.
For further details with respect to this
Order, see the initial application dated
January 22, 2009 (Agencywide
Documents Access and Management
System (ADAMS) Accession No.
ML090290101), as supplemented by
letters dated February 26
(ML090630426), April 8
(ML091000665), June 25
(ML091811094), and July 27, 2009
(ML092150712), and the SE with the
same date as this Order, which are
available for public inspection at the
Commission’s Public Document Room
(PDR), located at One White Flint North,
11555 Rockville Pike, Room O–1 F21
(First Floor), Rockville, Maryland, and
accessible electronically from the
ADAMS Public Electronic Reading
Room on the Internet at the NRC Web
site, https://www.nrc.gov/reading-rm/
adams.html. Persons who do not have
access to ADAMS, or who encounter
problems in accessing the documents
located in ADAMS, should contact the
NRC PDR Reference staff by telephone
at 1–800–397–4209 or 301–415–4737, or
by e-mail at pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 9th day
of October 2009.
For The Nuclear Regulatory Commission.
Bruce S. Mallett,
Deputy Executive Director for Reactor and
Preparedness Programs.
[FR Doc. E9–25165 Filed 10–19–09; 8:45 am]
BILLING CODE 7590–01–P
E:\FR\FM\20OCN1.SGM
20OCN1
Agencies
[Federal Register Volume 74, Number 201 (Tuesday, October 20, 2009)]
[Notices]
[Pages 53772-53773]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-25165]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2009-0193; Docket Nos. 50-220 and 50-410]
EDF Development, Inc., Renewed License No. DPR-63; Constellation
Energy Nuclear Group, LLC, Renewed License No. NPF-69; Nine Mile Point
Nuclear Station, LLC (Nine Mile Point Nuclear Station Unit Nos. 1 and
2); Order Approving Application Regarding Proposed Corporate
Restructuring
I
Nine Mile Point Nuclear Station, LLC (NMPNS, LLC or the licensee)
is the holder of Renewed Facility Operating License Nos. DPR-63 and
NPF-69, which authorize the possession, use, and operation of the Nine
Mile Point Nuclear Station, Unit Nos. 1 and 2 (NMP 1 and 2). The
facility is located at the licensee's site in Oswego, New York.
II
By letter dated January 22, 2009, as supplemented on February 26,
April 8, June 25, and July 27, 2009 (together, the application),
Constellation Energy Nuclear Group, LLC (CENG), on behalf of the
licensee and EDF Development, Inc. (EDF Development) (together, the
applicants), requested that the Nuclear Regulatory Commission (NRC, the
Commission), pursuant to Title 10 of the Code of Federal Regulations
(10 CFR) 50.80, consent to the indirect license transfers that would be
effected by the indirect transfer of control of CENG's ownership and
operating interests in NMP 1 and 2. The actions being sought as a
result of certain proposed corporate restructuring actions in
connection with a planned investment by EDF Development whereby it
would acquire a 49.99% ownership interest in CENG from Constellation
Energy Group, Inc. (CEG), the current 100% owner of CENG. EDF
Development is a U.S. corporation organized under the laws of the State
of Delaware and a wholly-owned subsidiary of E.D.F. International S.A.,
a public limited company organized under the laws of France, which is
in turn a wholly-owned subsidiary of [Eacute]lectricit[eacute] de
France S.A., a French limited company.
Following the proposed transaction, EDF Development will hold a
49.99% ownership interest in CENG; CEG will hold a 50.01% ownership
interest in CENG through two new intermediate parent companies,
Constellation Nuclear, LLC and CE Nuclear, LLC, formed for non-
operational purposes. In addition, Constellation Nuclear Power Plants,
Inc., which is currently an intermediate holding company between CENG
and NMPNS, LLC and R.E. Ginna Nuclear Power Plant, LLC, will convert to
a Delaware limited liability company and become Constellation Nuclear
Power Plants, LLC, and will exist as an intermediate holding company
between CENG and NMPNS, LLC, R.E. Ginna Nuclear Power Plant, LLC, and
Calvert Cliffs Nuclear Power Plant, LLC. No physical changes to the
facilities or operational changes are being proposed in the
application.
Approval of the transfer of the license is requested by the
applicants pursuant to 10 CFR 50.80. Notice of the request for approval
and opportunity for a hearing was published in the Federal Register on
May 6, 2009 (74 FR 21015). No hearing requests or petitions to
intervene were received. The NRC received comments from a member of the
public in Seattle, Washington, in an e-mail dated May 22, 2009. The
comments did not provide any information additional to that in the
application, nor did they provide any information contradictory to that
provided in the application.
Pursuant to 10 CFR 50.80, no license, or any right thereunder,
shall be transferred, directly or indirectly, through transfer of
control of the license, unless the Commission shall give its consent in
writing. Upon review of the information in the application and other
information before the Commission, and relying upon the representations
and agreements contained in the application, the NRC staff has
determined that the proposed indirect license transfer of control of
the subject license held by the licensee to the extent such will result
from the proposed corporate restructuring actions in connection with
the planned investment by EDF Development whereby it will acquire a
49.99% ownership interest in CENG, to the extent affected by the
proposed transaction as described in the application, is otherwise
consistent with applicable provisions of law, regulations, and Orders
issued by the NRC, pursuant thereto, subject to the conditions set
forth below. The NRC
[[Page 53773]]
staff has further found that the application for the proposed license
amendment complies with the standards and requirements of the Atomic
Energy Act of 1954, as amended (the Act), and the Commission's rules
and regulations set forth in 10 CFR Chapter I; the facility will
operate in conformity with the application, the provisions of the Act,
and the rules and regulations of the Commission; there is reasonable
assurance that the activities authorized by the proposed license
amendment can be conducted without endangering the health and safety of
the public and that such activities will be conducted in compliance
with the Commission's regulations; the issuance of the proposed license
amendment will not be inimical to the common defense and security or to
the health and safety of the public; and the issuance of the proposed
amendments will be in accordance with 10 CFR Part 51 of the
Commission's regulations and all applicable requirements have been
satisfied.
The findings set forth above are supported by the NRC staff's
safety evaluation (SE) dated the same day as this Order.
III
Accordingly, pursuant to Sections 161b, 161i, 161o, and 184 of the
Act, 42 U.S.C. Sections 2201(b), 2201(i), 2201(o), and 2234; and 10 CFR
50.80, it is hereby ordered that the application regarding the indirect
license transfers related to the proposed corporate restructuring
actions in connection with the planned investment by EDF Development,
as described herein, is approved, subject to the following conditions:
(1) The ownership and governance arrangements as a result of the
proposed transaction, is subject to the following:
(a) The Operating Agreement included with the application dated
January 22, 2009, may not be modified in any material respect
concerning decision-making authority over ``safety issues'' as defined
therein without the prior written consent of the Director, Office of
Nuclear Reactor Regulation.
(b) At least half the members of CENG's Board of Directors must be
U.S. citizens.
(c) The Chief Executive Officer (CEO), Chief Nuclear Officer (CNO)
and Chairman of the Board of Directors of CENG must be U.S. citizens.
These individuals shall have the responsibility and exclusive authority
to ensure and shall ensure that the business and activities of CENG
with respect to the Calvert Cliffs, Unit Nos. 1 and 2, Calvert Cliffs
ISFSI, Nine Mile Point, Unit Nos. 1 and 2, and R.E. Ginna licenses are
at all times conducted in a manner consistent with the public health
and safety and common defense and security of the United States.
(d) CENG will establish a Nuclear Advisory Committee (NAC) composed
of U.S. citizens who are not officers, directors, or employees of CENG,
CEG or EDF Development. The NAC will report to and provide transparency
to the NRC and other U.S. governmental agencies regarding foreign
ownership and control of nuclear operations.
(e) CENG shall cause to be transmitted to the Director, Office of
Nuclear Reactor Regulation, within 30 days of knowledge of a filing
with the U.S. Securities and Exchange Commission, any Schedules 13D or
13G filed pursuant to the Securities and Exchange Act of 1934 that
disclose beneficial ownership of any registered classes of CEG stock.
(2) The financial arrangements resulting from the proposed
transaction, are subject to the following:
(a) The working capital and cash pooling arrangements described in
Article IV of the Operating Agreement included with the application
dated January 22, 2009, and supplement dated July 27, 2009, shall be
effective as of the date of the transfer and shall be consistent with
the representations contained in the application. CENG and NMPNS, LLC
shall take no action to cause CEG and/or EDF Development, or their
successors and assigns, to void, cancel or materially modify the
working capital and cash pooling arrangements in the Operating
Agreement without the prior written consent of the NRC staff.
(b) The Support Agreements described in the supplement to the
application dated February 26, 2009 (up to $290 million), shall be
effective as of the date of the transfer and shall be consistent with
the representations contained in the application. CENG and NMPNS, LLC
shall take no action to cause CEG and/or EDF Development, or their
successors and assigns, to void, cancel or materially modify the
Support Agreements as submitted without the prior written consent of
the NRC staff, except, however, the intercompany credit agreement
referenced in the current licenses for NMP 1 and 2 [condition 2.D(12)
for Unit 1 and 2.C(15) for Unit 2] may be revoked or rescinded if and
when the $290 million support agreements described in the February 26,
2009, supplement to the application become effective. CENG shall inform
the Director of the Office of Nuclear Reactor Regulation, in writing,
no later than ten days after any funds are provided to CENG or any of
the licensees by CEG or EDF Development under any Support Agreement.
(c) The Master Demand Notes described in the supplement to the
application dated July 27, 2009, shall be effective as of the date of
the transfer and shall be consistent with the representations contained
in the application. CENG and NMPNS, LLC shall take no action to cause
CEG and/or EDF Development, or their successors and assigns, to void,
cancel or materially modify the Master Demand Notes without the prior
written consent of the NRC staff.
It is further ordered that CENG shall inform the Director of the
Office of Nuclear Reactor Regulation, in writing, of the date of
closing of the transfer of EDF Development's ownership and operating
interests in CENG at least 1 business day before the closing. Should
the transfer of the license not be completed within 1 year of this
Order's date of issuance, this Order shall become null and void,
provided, however, that upon written application and for good cause
shown, such date may be extended by order.
This Order is effective upon issuance.
For further details with respect to this Order, see the initial
application dated January 22, 2009 (Agencywide Documents Access and
Management System (ADAMS) Accession No. ML090290101), as supplemented
by letters dated February 26 (ML090630426), April 8 (ML091000665), June
25 (ML091811094), and July 27, 2009 (ML092150712), and the SE with the
same date as this Order, which are available for public inspection at
the Commission's Public Document Room (PDR), located at One White Flint
North, 11555 Rockville Pike, Room O-1 F21 (First Floor), Rockville,
Maryland, and accessible electronically from the ADAMS Public
Electronic Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to
ADAMS, or who encounter problems in accessing the documents located in
ADAMS, should contact the NRC PDR Reference staff by telephone at 1-
800-397-4209 or 301-415-4737, or by e-mail at pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 9th day of October 2009.
For The Nuclear Regulatory Commission.
Bruce S. Mallett,
Deputy Executive Director for Reactor and Preparedness Programs.
[FR Doc. E9-25165 Filed 10-19-09; 8:45 am]
BILLING CODE 7590-01-P