Dillon Dam Hydroelectric Project; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 50178-50179 [E9-23517]

Download as PDF CPrice-Sewell on DSKGBLS3C1PROD with NOTICES 50178 Federal Register / Vol. 74, No. 188 / Wednesday, September 30, 2009 / Notices section 7(c) of the Natural Gas Act (NGA), and Part 157 of the Commission’s regulations for an order granting a certificate of public convenience to construct and operate the new North Raton Lateral, with appurtenances, in southern Colorado. The project is hereafter referred to as the Raton 2010 Expansion Project. CIG proposes to construct approximately 118 miles of 16-inch diameter pipeline with a total capacity of approximately 130,000 dekatherms per day, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the Web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Specifically, the Raton 2010 Expansion Project consists of (i) approximately 118.6 miles of 16-inch diameter pipeline in Las Animas, Huerfano, Pueblo, and El Paso Counties, Colorado; (ii) new incremental rates related to the cost of service on the new lateral; and (iii) minor modifications to existing compressor and meter stations to allow CIG to transport the additional volumes from the proposed expansion. The Raton 2010 Expansion Project has a design capacity of approximately 130,000 Dth per day subject to long-term firm transportation agreements to move the gas from the Raton Basin to an interconnect with CIG’s mainline in El Paso County, Colorado. The estimated costs of the project are approximately $132 million. Any questions concerning this application may be directed to Richard Derryberry, Director, Regulatory Affairs, Colorado Interstate Gas Company, P.O. Box 1087, Colorado Springs, Colorado 80944, by phone at (719) 520–3788, or by fax at (719) 520–4898. On June 24, 2008 the Commission staff granted CIG’s request to utilize the National Environmental Policy Act (NEPA) Pre-Filling Process and assigned Docket No. PF08–25–000 to staff activities involving the Raton 2010 Expansion Project. Now, as of the filing of CIG’s application on September 10, 2009, the NEPA Pre-Filling Process for this project has ended. From this time forward, CIG’s proceeding will be conducted in Docket No. CP09–464– 000, as noted in the caption of this Notice. Pursuant to Section 157.9 of the Commission’s rules, 18 CFR 157.9, VerDate Nov<24>2008 14:56 Sep 29, 2009 Jkt 217001 within 90 days of this Notice the Commission staff will either: complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all Federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comment Date: October 14, 2009. Kimberly D. Bose, Secretary. [FR Doc. E9–23518 Filed 9–29–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13421–000] Dillon Dam Hydroelectric Project; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications September 23, 2009. On April 2, 2009, Muskingum Valley Hydro (Muskingum) filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of developing the Dillon Dam Hydroelectric Project, to be located on the Licking River in Muskingum County, near Zanesville, Ohio. The proposed project would be located at the U.S. Army Corps of Engineers Dillon Dam consisting of the existing 1,560-acre impoundment with a normal water surface elevation of 735 feet mean sea level. The proposed project would consist of: (1) A new powerhouse to be located on the downstream side of Dillon dam E:\FR\FM\30SEN1.SGM 30SEN1 Federal Register / Vol. 74, No. 188 / Wednesday, September 30, 2009 / Notices below the outlet works; (2) a new 50foot-long, 96-inch penstock; (3) a new turbine generator unit with an installed capacity of 1.59 MW; and (4) a new 300foot-long, 14.7-kV transmission line. The project would have an estimated average annual generation of 9,700 megawatt-hours. Muskingum states that it will investigate various other types of hydroelectric generation at the site including Very Low Head Turbine technology. Applicant Contact: Randall Smith, Muskingum Valley Hydro, 4950 Frazeysburg Road, Zanesville, Ohio 43701 (740) 891–5424. FERC Contact: Patrick Murphy, (202) 502–8755. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket number (P–13421) in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3372. Kimberly D. Bose, Secretary. [FR Doc. E9–23517 Filed 9–29–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY CPrice-Sewell on DSKGBLS3C1PROD with NOTICES Federal Energy Regulatory Commission Combined Notice of Filings #1 September 23, 2009. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER07–509–002. Applicants: California Power Holdings, LLC. VerDate Nov<24>2008 14:56 Sep 29, 2009 Jkt 217001 Description: California Power Holdings, LLC submits revised amendment to market based rate tariff. Filed Date: 09/18/2009. Accession Number: 20090922–0066. Comment Date: 5 p.m. Eastern Time on Friday, October 09, 2009. Docket Numbers: ER09–32–004. Applicants: Barton Windpower LLC. Description: Notice of Non-Material Change in Status of Barton Windpower LLC. Filed Date: 09/23/2009. Accession Number: 20090923–5048. Comment Date: 5 p.m. Eastern Time on Wednesday, October 14, 2009. Docket Numbers: ER09–1479–001. Applicants: Kansas Energy LLC. Description: Kansas Energy LLC submits its amended Petition. Filed Date: 09/21/2009. Accession Number: 20090922–0070. Comment Date: 5 p.m. Eastern Time on Tuesday, October 13, 2009. Docket Numbers: ER09–1643–001. Applicants: E.ON U.S., LLC. Description: Louisville Gas and Electric Co et al. submits Substitute First Revised Sheet 104 et al. to FERC Electric Tariff, Fourth Revised Volume 1. Filed Date: 09/21/2009. Accession Number: 20090922–0036. Comment Date: 5 p.m. Eastern Time on Tuesday, October 13, 2009. Docket Numbers: ER09–1677–001. Applicants: Big Sky Wind, LLC. Description: Big Sky Wind, LLC submits Sub. Original Sheet 3 to its proposed tariff to correct an inadvertent error in the tariff submitted on Sept. 3. Filed Date: 09/21/2009. Accession Number: 20090922–0071. Comment Date: 5 p.m. Eastern Time on Tuesday, October 13, 2009. Docket Numbers: ER09–1711–000. Applicants: California Independent System Operator Corporation. Description: California Independent System Operator Corporation submits an informational filing that is intended to provide notice re the ISO’s revised transmission access charges effective 5/ 1/09. Filed Date: 09/15/2009. Accession Number: 20090916–0092. Comment Date: 5 p.m. Eastern Time on Tuesday, October 06, 2009. Docket Numbers: ER09–1723–000. Applicants: Dry Lake Wind Power, LLC. Description: Application of Dry Lake Wind Power, LLC for order accepting initial tariff, Waiving 60 day prior notice requirement and granting Blanket Approvals etc. Filed Date: 09/22/2009. PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 50179 Accession Number: 20090923–0008. Comment Date: 5 p.m. Eastern Time on Tuesday, October 13, 2009. Docket Numbers: ER09–1724–000. Applicants: Cleco Power LLC. Description: Cleco Power, LLC submits an amendment to the Electric System Interconnection Agreement with Southwestern Electric Power Co. Filed Date: 09/21/2009. Accession Number: 20090922–0037. Comment Date: 5 p.m. Eastern Time on Tuesday, October 13, 2009. Docket Numbers: ER09–1726–000. Applicants: ALLETE, Inc. Description: Allete, Inc submits Schedule 2 to its Open Access Transmission Tariff in order to govern the provision of reactive power and voltage support over certain highvoltage direct-current transmission facilities etc. Filed Date: 09/21/2009. Accession Number: 20090922–0072. Comment Date: 5 p.m. Eastern Time on Tuesday, October 13, 2009. Docket Numbers: ER09–1727–000. Applicants: Midwest Independent Transmission System Operator, Inc.; ALLETE, Inc. Description: Midwest Independent Transmission System Operator, Inc. et al. submits agency agreement and revisions to the Midwest ISO’s open access transmission, energy and operating reserve markets tariff. Filed Date: 09/21/2009. Accession Number: 20090922–0073. Comment Date: 5 p.m. Eastern Time on Tuesday, October 13, 2009. Docket Numbers: ER09–1728–000. Applicants: ALLETE, Inc. Description: Allete, Inc. submits Interconnection and Operating Agreement. Filed Date: 09/21/2009. Accession Number: 20090922–0068. Comment Date: 5 p.m. Eastern Time on Tuesday, October 13, 2009. Docket Numbers: ER09–1732–000. Applicants: Southwest Power Pool, Inc. Description: Southwest Power Pool, Inc. submits Original Service Agreement 1806 to FERC Electric Tariff, Fifth Revised Volume 1. Filed Date: 09/22/2009. Accession Number: 20090923–0007. Comment Date: 5 p.m. Eastern Time on Tuesday, October 13, 2009. Docket Numbers: ER09–1733–000. Applicants: Southwest Power Pool, Inc. Description: Southwest Power Pool, Inc. submits revisions to an executed Meter Agent Services Agreement between Dodwood Energy, LLC as the E:\FR\FM\30SEN1.SGM 30SEN1

Agencies

[Federal Register Volume 74, Number 188 (Wednesday, September 30, 2009)]
[Notices]
[Pages 50178-50179]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-23517]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13421-000]


Dillon Dam Hydroelectric Project; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

September 23, 2009.
    On April 2, 2009, Muskingum Valley Hydro (Muskingum) filed an 
application, pursuant to section 4(f) of the Federal Power Act, 
proposing to study the feasibility of developing the Dillon Dam 
Hydroelectric Project, to be located on the Licking River in Muskingum 
County, near Zanesville, Ohio. The proposed project would be located at 
the U.S. Army Corps of Engineers Dillon Dam consisting of the existing 
1,560-acre impoundment with a normal water surface elevation of 735 
feet mean sea level.
    The proposed project would consist of: (1) A new powerhouse to be 
located on the downstream side of Dillon dam

[[Page 50179]]

below the outlet works; (2) a new 50-foot-long, 96-inch penstock; (3) a 
new turbine generator unit with an installed capacity of 1.59 MW; and 
(4) a new 300-foot-long, 14.7-kV transmission line. The project would 
have an estimated average annual generation of 9,700 megawatt-hours. 
Muskingum states that it will investigate various other types of 
hydroelectric generation at the site including Very Low Head Turbine 
technology.
    Applicant Contact: Randall Smith, Muskingum Valley Hydro, 4950 
Frazeysburg Road, Zanesville, Ohio 43701 (740) 891-5424.
    FERC Contact: Patrick Murphy, (202) 502-8755.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Comments, motions to intervene, notices of intent, and competing 
applications may be filed electronically via the Internet. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original and eight 
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For 
more information on how to submit these types of filings please go to 
the Commission's Web site located at https://www.ferc.gov/filing-comments.asp. More information about this project can be viewed or 
printed on the ``eLibrary'' link of the Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P-
13421) in the docket number field to access the document. For 
assistance, call toll-free 1-866-208-3372.

Kimberly D. Bose,
Secretary.
[FR Doc. E9-23517 Filed 9-29-09; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.