Federal Register / Vol. 74, No. 180 / Friday, September 18, 2009 / Notices
Process for this project has ended. From
this time forward, this proceeding will
be conducted in Docket No. CP09–460–
000, as noted in the caption of this
Notice.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
VerDate Nov<24>2008
15:10 Sep 17, 2009
Jkt 217001
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the eLibrary
link and is available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
Comment Date: October 1, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–22465 Filed 9–17–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13560–000]
Sierra Energy Company; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
September 10, 2009.
On July 23, 2009, and revised on
August 27, 2009, Sierra Energy
Company filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the North Unit
Diversion Dam Project, located on the
Deschutes River in Deschutes County,
Oregon. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would utilize
the existing North Unit Diversion Dam;
and would consist of the following new
facilities: (1) A diversion structure
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
47935
approximately 100-foot-long, 15-footwide, and 6-foot-deep; (2) an 8- to 10foot-diameter, 150-foot-long penstock;
(3) a powerhouse containing two
generating units having an installed
capacity of 1.8 megawatts; (4) a 500foot-long, 21-kilovolt transmission line;
and (5) appurtenant facilities. The
proposed project would have an average
annual generation of 7.2 gigawatt-hours.
Applicant Contact: Bradley Reeves,
Sierra Energy Company, P.O. Box 4313,
Auburn, CA 95604; phone: (530) 367–
4156.
FERC Contact: Gina Krump, (202)
502–6704, gina.krump@ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov/docs-filing/ferconline.asp)
under the ‘‘eFiling’’ link. For a simpler
method of submitting text only
comments, click on ‘‘Quick Comment.’’
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13560) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–22470 Filed 9–17–09; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\18SEN1.SGM
18SEN1
Agencies
[Federal Register Volume 74, Number 180 (Friday, September 18, 2009)]
[Notices]
[Page 47935]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-22470]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13560-000]
Sierra Energy Company; Notice of Preliminary Permit Application
Accepted for Filing and Soliciting Comments, Motions To Intervene, and
Competing Applications
September 10, 2009.
On July 23, 2009, and revised on August 27, 2009, Sierra Energy
Company filed an application for a preliminary permit, pursuant to
section 4(f) of the Federal Power Act, proposing to study the
feasibility of the North Unit Diversion Dam Project, located on the
Deschutes River in Deschutes County, Oregon. The sole purpose of a
preliminary permit, if issued, is to grant the permit holder priority
to file a license application during the permit term. A preliminary
permit does not authorize the permit holder to perform any land
disturbing activities or otherwise enter upon lands or waters owned by
others without the owners' express permission.
The proposed project would utilize the existing North Unit
Diversion Dam; and would consist of the following new facilities: (1) A
diversion structure approximately 100-foot-long, 15-foot-wide, and 6-
foot-deep; (2) an 8- to 10-foot-diameter, 150-foot-long penstock; (3) a
powerhouse containing two generating units having an installed capacity
of 1.8 megawatts; (4) a 500-foot-long, 21-kilovolt transmission line;
and (5) appurtenant facilities. The proposed project would have an
average annual generation of 7.2 gigawatt-hours.
Applicant Contact: Bradley Reeves, Sierra Energy Company, P.O. Box
4313, Auburn, CA 95604; phone: (530) 367-4156.
FERC Contact: Gina Krump, (202) 502-6704, gina.krump@ferc.gov.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Comments, motions to intervene, notices of intent, and competing
applications may be filed electronically via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
(https://www.ferc.gov/docs-filing/ferconline.asp) under the ``eFiling''
link. For a simpler method of submitting text only comments, click on
``Quick Comment.'' For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-3676; or,
for TTY, contact (202) 502-8659. Although the Commission strongly
encourages electronic filing, documents may also be paper-filed. To
paper-file, mail an original and eight copies to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-13560) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-22470 Filed 9-17-09; 8:45 am]