Alabama Power Company; Notice of Availability of Environmental Assessment, 47570 [E9-22234]
Download as PDF
47570
Federal Register / Vol. 74, No. 178 / Wednesday, September 16, 2009 / Notices
River, in Cheshire County, New
Hampshire.
The proposed project would consist
of: (1) The existing 160-foot-long, 16foot-high Ashuelot Park Dam with 2foot-high flashboards; (2) the existing
34-acre reservoir with 120 acre-feet of
storage capacity; (3) a new powerhouse
below the existing outlet works
containing two generating units with a
installed capacity of 240 kilowatts; (4) a
new 150-foot-long tailrace; and (5) an
approximately 500-foot-long
transmission line. The project would
have an estimated average annual
generation of 1,000 megawatts-hours.
Applicant Contact: Mr. John Maclean,
City Manager, 3 Washington Street,
Keene, NH 03431, phone (603) 357–
9804.
FERC Contact: Michael Spencer, (202)
502–6093.
Competing Application: This
application competes with Project No.
13419–000 filed April 2, 2009.
Competing applications had to be filed
on or before July 3, 2009.
Deadline for filing comments, motions
to intervene: 60 days from the issuance
of this notice. Comments, and motions
to intervene may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and eight
copies should be mailed to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. For
more information on how to submit
these types of filings please go to the
Commission’s Web site located at
https://www.ferc.gov/filingcomments.asp.
More information about this project
can be viewed or printed on the
‘‘eLibrary’’ link of Commission’s Web
site at https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13530) in the docket number field to
access the document. For assistance,
call toll-free 1–866–208–3372.
ACTION: Notice of availability of record
of decision (ROD).
SUMMARY: The Bonneville Power
Administration (BPA) has decided to
offer Sagebrush Power Partners, LLC, a
Large Generator Interconnection
Agreement for interconnection of up to
108 megawatts of power into the Federal
Columbia River Transmission System.
The power would be generated from
their proposed Kittitas Valley Wind
Project (Wind Project) in Kittitas
County, Washington. To interconnect
the Wind Project, BPA will construct a
new substation (Bettas Road Substation)
on the Columbia-Covington 230-kilovolt
transmission line about 11 miles
northeast of Ellensburg, Washington.
This decision to interconnect the Wind
Project is consistent with and tiered to
BPA’s Business Plan Environmental
Impact Statement (DOE/EIS–0183, June
1995), and the Business Plan Record of
Decision (BP ROD, August 1995).
ADDRESSES: Copies of this tiered ROD
and the Business Plan EIS may be
obtained by calling BPA’s toll-free
document request line, 1–800–622–
4520. The RODs and EIS are also
available on our Web site, https://
www.efw.bpa.gov.
FOR FURTHER INFORMATION CONTACT:
Richard Yarde, Bonneville Power
Administration—KEC–4, P.O. Box 3621,
Portland, Oregon 97208–3621; toll-free
telephone number 1–800–622–4519; fax
number 503–230–5699; or e-mail
rryarde@bpa.gov.
An environmental assessment (EA) has
been prepared as part of staff’s review
of the proposal. The proposed nonproject use is located on Lewis Smith
Lake in Winston County, Alabama.
In the application, Alabama Power
requests Commission authorization to
permit Silverock Cove, LLC to install 11
cluster docks (with a total of 74 boat
slips), a walking trail, and a community
boat launch within the project
boundary. These structures would serve
the residents of Silverock Cove, a
planned community that is located
adjacent to project lands. The EA
contains Commission staff’s analysis of
the probable environmental impacts of
the proposal and concludes that
approval of the proposal, as modified by
the staff, would not constitute a major
federal action significantly affecting the
quality of the human environment.
The EA is attached to a Commission
order titled ‘‘Order Modifying and
Approving Non-Project Use of Project
Lands and Waters,’’ which was issued
September 8, 2009, and is available for
review and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street, NE., Room
2A, Washington, DC 20426. The EA may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘elibrary’’ link. Enter the docket
number (P–2165) in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3372, or for TTY,
(202) 502–8659.
Issued in Portland, Oregon, on September
4, 2009.
Stephen J. Wright,
Administrator and Chief Executive Officer.
[FR Doc. E9–22284 Filed 9–15–09; 8:45 am]
Kimberly D. Bose,
Secretary.
[FR Doc. E9–22234 Filed 9–15–09; 8:45 am]
BILLING CODE 6450–01–P
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Project Nos. 2165–027]
[Project No. 11291–023–IN]
Alabama Power Company; Notice of
Availability of Environmental
Assessment
Star Mill, Inc.; Notice of Availability of
Environmental Assessment
BILLING CODE 6717–01–P
srobinson on DSKHWCL6B1PROD with NOTICES
Kimberly D. Bose,
Secretary.
[FR Doc. E9–22233 Filed 9–15–09; 8:45 am]
September 9, 2009.
September 9, 2009.
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR Part 380 (Order No.
486, 52 FR 47897), the Office of Energy
Projects has reviewed an application for
non-project use of project lands and
waters at the Warrior River
Hydroelectric Project (FERC No. 2165).
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s regulations, 18 CFR Part
380 (Order No. 486, 52 FR 47879), the
Office of Energy Projects has reviewed
the proposed termination of license by
implied surrender for the Star Milling
and Electric Minor Water Power Project,
located on the Fawn River in La Grange
DEPARTMENT OF ENERGY
Bonneville Power Administration;
Electrical Interconnection of the
Kittitas Valley Wind Project
AGENCY: Bonneville Power
Administration (BPA), Department of
Energy (DOE).
VerDate Nov<24>2008
17:40 Sep 15, 2009
Jkt 217001
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
E:\FR\FM\16SEN1.SGM
16SEN1
Agencies
[Federal Register Volume 74, Number 178 (Wednesday, September 16, 2009)]
[Notices]
[Page 47570]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-22234]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project Nos. 2165-027]
Alabama Power Company; Notice of Availability of Environmental
Assessment
September 9, 2009.
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's (Commission)
regulations, 18 CFR Part 380 (Order No. 486, 52 FR 47897), the Office
of Energy Projects has reviewed an application for non-project use of
project lands and waters at the Warrior River Hydroelectric Project
(FERC No. 2165). An environmental assessment (EA) has been prepared as
part of staff's review of the proposal. The proposed non-project use is
located on Lewis Smith Lake in Winston County, Alabama.
In the application, Alabama Power requests Commission authorization
to permit Silverock Cove, LLC to install 11 cluster docks (with a total
of 74 boat slips), a walking trail, and a community boat launch within
the project boundary. These structures would serve the residents of
Silverock Cove, a planned community that is located adjacent to project
lands. The EA contains Commission staff's analysis of the probable
environmental impacts of the proposal and concludes that approval of
the proposal, as modified by the staff, would not constitute a major
federal action significantly affecting the quality of the human
environment.
The EA is attached to a Commission order titled ``Order Modifying
and Approving Non-Project Use of Project Lands and Waters,'' which was
issued September 8, 2009, and is available for review and reproduction
at the Commission's Public Reference Room, located at 888 First Street,
NE., Room 2A, Washington, DC 20426. The EA may also be viewed on the
Commission's Web site at https://www.ferc.gov using the ``elibrary''
link. Enter the docket number (P-2165) in the docket number field to
access the document. For assistance, contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll-free at 1-866-208-3372, or for TTY,
(202) 502-8659.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-22234 Filed 9-15-09; 8:45 am]
BILLING CODE 6717-01-P