Northern States Power Company, LLC, Monticello Nuclear Generating Plant; Draft Environmental Assessment and Finding of No Significant Impact, 47281-47287 [E9-22127]
Download as PDF
Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices
Commission, Washington, DC 20555–
0001, telephone: (301) 251–7404 or email to Richard.Jervey@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The U.S. Nuclear Regulatory
Commission (NRC) is issuing for public
comment a draft guide in the agency’s
‘‘Regulatory Guide’’ series. This series
was developed to describe and make
available to the public such information
as methods that are acceptable to the
NRC staff for implementing specific
parts of the NRC’s regulations,
techniques that the staff uses in
evaluating specific problems or
postulated accidents, and data that the
staff needs in its review of applications
for permits and licenses.
The draft regulatory guide (DG),
entitled, ‘‘Quality Assurance Program
Requirements for Research and Test
Reactors,’’ is temporarily identified by
its task number, DG–2001, which
should be mentioned in all related
correspondence. DG–2001 is proposed
Revision 1 of Regulatory Guide 2.5,
dated May 1977.
This guide describes a method
acceptable to the staff of the NRC in
complying with the Commission’s
regulations with regard to the overall
quality assurance program requirements
for research and test reactors.
Title 10, Section 50.34(a)(7), of the
Code of Federal Regulations (10 CFR
50.34(a)(7)), requires each applicant for
a construction permit to build a
production or utilization facility to
include, in its preliminary safety
analysis report, a description of the
quality assurance program to be applied
to the design and construction of the
structures, systems, and components of
the facility. Furthermore, 10 CFR
50.34(b)(6)(ii) requires that each
applicant for a license to operate a
facility include, in the final safety
analysis report, a description of the
managerial and administrative controls
to be used to ensure safe operation.
sroberts on DSKD5P82C1PROD with NOTICES
II. Further Information
The NRC staff is soliciting comments
on DG–2001. Comments may be
accompanied by relevant information or
supporting data and should mention
DG–2001 in the subject line. Comments
submitted in writing or in electronic
form will be made available to the
public’ in their entirety through the
NRC’s Agencywide Documents Access
and Management System (ADAMS).
Because your comments will not be
edited to remove any identifying or
contact information, the NRC cautions
you against including any information
VerDate Nov<24>2008
19:12 Sep 14, 2009
Jkt 217001
in your submission that you do not want
to be publicly disclosed.
The NRC requests that any party
soliciting or aggregating comments
received from other persons for
submission to the NRC inform those
persons that the NRC will not edit their
comments to remove any identifying or
contact information, and therefore, they
should not include any information in
their comments that they do not want
publicly disclosed. You may submit
comments by any of the following
methods:
1. Mail comments to: Rulemaking and
Directives Branch, Mail Stop: TWB–05–
B01M, Office of Administration, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001.
2. Federal e-Rulemaking Portal: Go to
https://www.regulations.gov and search
for documents filed under Docket ID
[NRC–2009–0396]. Address questions
about NRC dockets to Carol Gallagher,
301–492–3668; e-mail
Carol.Gallagher@nrc.gov.
3. Fax comments to: Rulemaking and
Directives Branch, Office of
Administration, U.S. Nuclear Regulatory
Commission at (301) 492–3446.
Requests for technical information
about DG–2001 may be directed to the
NRC contact, R.A. Jervey at (301) 251–
7404 or e-mail to
Richard.Jervey@nrc.gov.
Comments would be most helpful if
received by November 13, 2009.
Comments received after that date will
be considered if it is practical to do so,
but the NRC is able to ensure
consideration only for comments
received on or before this date.
Although a time limit is given,
comments and suggestions in
connection with items for inclusion in
guides currently being developed or
improvements in all published guides
are encouraged at any time.
Electronic copies of DG–2001 are
available through the NRC’s public Web
site under Draft Regulatory Guides in
the ‘‘Regulatory Guides’’ collection of
the NRC’s Electronic Reading Room at
https://www.nrc.gov/reading-rm/doccollections/. Electronic copies are also
available in ADAMS (https://
www.nrc.gov/reading-rm/adams.html),
under Accession No. ML091460620.
In addition, regulatory guides are
available for inspection at the NRC’s
Public Document Room (PDR) located at
11555 Rockville Pike, Rockville,
Maryland. The PDR’s mailing address is
USNRC PDR, Washington, DC 20555–
0001. The PDR can also be reached by
telephone at (301) 415–4737 or (800)
397–4205, by fax at (301) 415–3548, and
by e-mail to pdr.resource@nrc.gov.
PO 00000
Frm 00097
Fmt 4703
Sfmt 4703
47281
Regulatory guides are not
copyrighted, and Commission approval
is not required to reproduce them.
Dated at Rockville, Maryland, this 2nd day
of September 2009.
For the Nuclear Regulatory Commission.
Andrea D. Valentin,
Chief, Regulatory Guide Development Branch,
Division of Engineering, Office of Nuclear
Regulatory Research.
[FR Doc. E9–22184 Filed 9–14–09; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–263; NRC–2009–0399]
Northern States Power Company, LLC,
Monticello Nuclear Generating Plant;
Draft Environmental Assessment and
Finding of No Significant Impact
The U.S. Nuclear Regulatory
Commission (NRC) has prepared a draft
Environmental Assessment (EA) as part
of its evaluation of a request by
Northern States Power Company
(NSPM) for a license amendment to
increase the maximum thermal power at
the Monticello Nuclear Generating Plant
(MNGP) from 1,775 megawatts thermal
(MWt) to 2,004 MWt. This represents a
power increase of approximately 13
percent over the current licensed
thermal power. As stated in the NRC
staff’s position paper dated February 8,
1996, on the Boiling-Water Reactor
Extended Power Uprate (EPU) Program,
the NRC staff will prepare an
environmental impact statement if it
believes a power uprate would have a
significant impact on the human
environment. The NRC staff did not
identify any significant impact from the
information provided in the licensee’s
EPU application or during the NRC
staff’s review of other available
information; therefore, the NRC staff is
documenting its environmental review
in this EA. Also, in accordance with the
position paper, the draft EA and Finding
of No Significant Impact are being
published in the Federal Register with
a 30-day public comment period.
Environmental Assessment
Plant Site and Environs
The MNGP site is located in
Monticello, Minnesota, along the
southern bank of the Mississippi River
at River Mile (RM) 900, approximately
30 miles (48 kilometers) northwest of
Minneapolis/St. Paul, and east of
Interstate Highway 94. The 2,150-acre
(870-hectare) site consists of 2 miles (3
kilometers) of frontage on both banks of
the Mississippi River, within portions of
E:\FR\FM\15SEN1.SGM
15SEN1
47282
Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices
sroberts on DSKD5P82C1PROD with NOTICES
Wright and Sherburne Counties. The
plant and its supporting facilities
occupy approximately 50 acres (20
hectares) in Wright County.
MNGP is a single unit boiling water
reactor that has been designed to allow
operation using four water circulating
modes to cool the system, and draws
water from and discharges water to the
Mississippi River. These four water
circulating modes include an open-cycle
(once-through) system, a closed cycle
system using two mechanical draft
cooling towers, a helper cycle system,
and a partial recirculation of the cooling
water. The helper cycle cools water
using both the open cycle to withdraw
water from and discharge the water back
to the Mississippi River, and the cooling
towers to cool water prior to discharge
to the river. The helper cycle is used
when the discharge canal temperature
approaches permit limits and upstream
river temperatures are consistently at or
above 68 °F. MNGP operates in open
cycle or helper cycle approximately 98
percent of the time. In the partial
recirculation mode, 75 percent of the
Mississippi River flow is withdrawn
and the cooling towers are operating. A
portion of the cooled water is
recirculated to the intake and the
remainder is discharged to the river.
The partial recirculation mode is used
when river flow is less than 860 cubicfeet-per-second (cfs) but greater than
240 cfs, and the river temperature is
elevated.
Identification of the Proposed Action
By application dated November 5,
2008, as supplemented on January 29,
2009 (on environmental issues only) the
licensee requested an amendment for
EPU for MNGP to increase the licensed
thermal power level from 1,775 MWt to
2,004 MWt, which is an increase of 13
percent over the current licensed
thermal power and a 20 percent increase
over the original licensed thermal
power. The Atomic Energy Commission
(predecessor of the NRC) issued the
Final Environmental Statement (FES) in
November 1972, for the original license
for MNGP. The NRC previously
approved a 6.3 percent stretch power
uprate in September 1998, increasing
the power output from 1,670 MWt to
1,775 MWt. The NRC EA for that action
resulted in a finding of no significant
impact and was published in the
Federal Register on September 1, 1998
(63 FR 46489). In addition, the NRC
issued a Supplemental Environmental
Impact Statement, NUREG–1437,
Supplement 26 (SEIS–26) in August
2006, associated with renewing the
operating license for MNGP for an
additional 20 years. This proposed
VerDate Nov<24>2008
19:12 Sep 14, 2009
Jkt 217001
amendment for an EPU would result in
an increase in production of electricity
and the amount of waste heat delivered
to the condenser, requiring an increase
to the amount of water withdrawn from
the Mississippi River for cooling
purposes, and a subsequent increase in
the temperature of the water discharged
back to the Mississippi River.
The licensee plans to implement the
proposed EPU in two phases to coincide
with two refueling outages. The first
refueling outage is scheduled for late
2009, with a corresponding increase in
power of approximately 50 MWt to a
total of 1,825 MWt. The second
refueling outage is scheduled for 2011,
and the power level will be increased to
the maximum of 2,004 MWt.
The Need for the Proposed Action
The need for the additional power
generation is based upon NSPM’s 15year Resource Plan that includes a
forecast of an average annual increase of
peak electrical demand of 1.2 percent
through NSPM’s 2008–2022 planning
period. This forecast for increased
energy includes NSPM’s resource
obligations for summer peak net
demand, minimum reserve
requirements, its committed resources,
and other contracted obligations. This
increase in power demand would
partially be met by the increased
amount of power output proposed for
MNGP along with other energy sources.
Environmental Impacts of the Proposed
Action
At the time of issuance of the
operating license for MNGP in 1972, the
NRC staff noted that any activity
authorized by the license would be
encompassed by the overall action
evaluated in the FES for the operation
of MNGP. In addition, the NRC
published the SEIS–26 in 2006, which
evaluated the environmental impacts of
operating MNGP for an additional 20
years, and determined that the
environmental impacts of license
renewal were small. The sections below
summarize the non-radiological and
radiological impacts in the environment
that may result from the proposed
action of the proposed EPU.
Non-Radiological Impacts
Land Use and Aesthetic Impacts
Potential land use and aesthetic
impacts from the proposed EPU include
impacts from plant modifications at
MNGP. While some plant components
would be modified, most plant changes
related to the proposed EPU would
occur within existing structures,
buildings, and fenced equipment yards
PO 00000
Frm 00098
Fmt 4703
Sfmt 4703
housing major components within the
developed part of the site. No new
construction would occur outside of
existing facilities and no expansion of
buildings, roads, parking lots,
equipment storage areas, or
transmission facilities would be
required to support the proposed EPU,
although some transmission and
distribution equipment may be replaced
or modified.
Existing parking lots, road access, laydown areas, offices, workshops,
warehouses, and restrooms would be
used during plant modifications.
Therefore, land use conditions would
not change at MNGP. Also, there would
be no land use changes along
transmission lines (no new lines would
be required for the proposed EPU),
transmission corridors, switch yards, or
substations.
Since land use conditions would not
change at MNGP, and because any land
disturbance would occur within
previously disturbed areas, there would
be little or no impact to aesthetic
resources in the vicinity of MNGP.
Therefore, the NRC staff concludes that
there would be no significant impact
from EPU-related plant modifications on
land use and aesthetic resources in the
vicinity of MNGP.
Air Quality Impacts
During implementation of the EPU at
the MNGP site, some minor and short
duration air quality impacts would
likely occur. Emissions from the
vehicles of workers would be the main
sources of these air quality impacts.
Wright County, where MNGP is located,
is designated as a maintenance area for
carbon monoxide. The NSPM indicated
that an additional 500 temporary
employees would be needed for the
duration of the project. The majority of
the workforce would reside within the
county where MNGP is located. The
screening analysis performed by the
licensee for the proposed Monticello
EPU projects that annual average
vehicular traffic would increase by
approximately 2 percent. The majority
of the EPU-associated activities would
be performed inside existing buildings
and will not cause additional
atmospheric emissions. Therefore, the
NRC staff concludes that there would be
no significant impact on air quality
during and following implementation of
the proposed EPU.
Water Use Impacts
Groundwater
MNGP uses groundwater for
domestic-type water uses and limited
industrial use. Groundwater is obtained
E:\FR\FM\15SEN1.SGM
15SEN1
Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices
sroberts on DSKD5P82C1PROD with NOTICES
from six on-site wells, two of which are
permitted and regulated by the
Minnesota Department of Natural
Resources (MDNR) through the State’s
water appropriation permit program.
These two wells produce 100 gallons
per minute (gpm) each and provide
domestic water to restrooms, showers,
and laundries and industrial use water
to the MNGP reverse osmosis system,
and to pump seals at the plant intake
structure. Four additional small
capacity wells that do not require an
MDNR permit are used to supply
domestic use water to buildings not
connected to the permitted system. The
proposed EPU will not significantly
increase the use of domestic
groundwater, and the volume of
additional groundwater needed for
industrial use is within the limits of the
existing appropriations permit.
Therefore, the NRC staff concludes that
there would be no significant impact on
groundwater resources following
implementation of the proposed EPU.
Surface Water
MNGP uses surface water for plant
condenser cooling, auxiliary water
systems, service water cooling, intake
screen wash, and fire protection. Under
MDNR water appropriation permit
number PA 66–1172–S, MNGP may
withdraw up to 645 cubic feet per
second (cfs) from the Mississippi River.
Surface water consumption under EPU
conditions is expected to be maintained
within permitted limits. The upper limit
of the permit is 8,700 ac-ft per year,
which would not be reached because
the cooling towers are typically
operated in combination with the oncethrough cooling system. As part of its
environmental review for license
renewal, the NRC staff stated in SEIS–
26 that ‘‘the consumptive loss due to
evaporation from the cooling towers
represent 4 percent of the river flow,
which is not considered significant.’’
The increased volume of circulation
water will continue to have an
insignificant effect on the total
consumptive use of surface water at
MNGP. The issue of discharge
temperatures is regulated by the
National Pollutant Discharge
Elimination System (NPDES) permit
discussed in the following section.
Therefore, the NRC staff concludes that
there would be no significant impact on
surface water resources following
implementation of the proposed EPU.
Aquatic Resources Impacts
The potential impacts to aquatic biota
from the proposed action include
impingement, entrainment, and thermal
discharge effects.
VerDate Nov<24>2008
19:12 Sep 14, 2009
Jkt 217001
Since MNGP operates most of the
time in open-cycle mode, an increase in
river water appropriation for the EPU
from the current consumptive rate of
509 cfs to 645 cfs may increase impacts
from entrainment and impingement of
fish and shellfish in their early life
stages. However, in a Section 316(a)
Clean Water Act (CWA) Demonstration
project in 1975, for MNGP that included
an evaluation of plant impacts on
aquatic organisms, the evidence
indicated that operations of MNGP had
not produced appreciable harm to the
aquatic organisms in the Mississippi
River in the vicinity of MNGP. In
addition, in the SEIS–26, the NRC staff
concluded in its assessment of the
relicensing activities of MNGP that
MNGP was in compliance with its
current State of Minnesota NPDES
permit, and in compliance with Section
316(b) of the CWA regarding the use of
best available technology for the
minimization of adverse environmental
impacts from entrainment and
impingement, and further mitigation
measures would not be warranted.
Further, river water appropriation under
EPU operation will not increase beyond
the current maximum MNGP NPDES
Permit limit of 645 cfs. Therefore, the
NRC staff concludes that there would be
no significant adverse impacts from
entrainment or impingement for the
proposed action.
According to the licensee, at the
proposed EPU conditions, the
temperature of the water entering the
discharge canal is expected to increase
by a maximum of 4.5 °F over the current
discharge canal temperature, which
ranges from 66 °F to 95 °F depending
upon the season. This can lead to
changes to the length, width, and
duration of the thermal plume across
the Mississippi River. However, the
licensee states in the application that
when canal discharge temperatures have
approached the limits of the NPDES
permit, MNGP will reduce power in
order to comply with NPDES thermal
discharge requirements. The NRC staff
previously noted in its SEIS–26 and
review of MNGP’s license renewal that,
despite a few periods of non-compliance
with the NPDES permit, there have been
no indications of adverse impacts to the
aquatic biota within the vicinity of the
discharge plume. Therefore, the NRC
staff concludes that there would be no
significant adverse impacts to aquatic
biota from thermal discharges for the
proposed action.
The licensee stated in the application
that an increase of up to 4.5 °F for the
effluent at the discharge canal over the
current temperature would not result in
a significant increase in the production
PO 00000
Frm 00099
Fmt 4703
Sfmt 4703
47283
of harmful thermophilic organisms in
the discharge canal. The maximum
temperature at the discharge canal
would remain within the limits of the
NPDES permit, and this temperature is
also well below the temperature for
maximum growth rate of thermophilic
organisms. The NRC staff determined, in
SEIS–26, that thermophilic organisms
are not likely to occur as a result of
discharges by MNGP into the
Mississippi River. No further mitigation
was necessary according to the NRC
staff. Based upon the information
provided in the application for EPU and
the SEIS–26, the NPDES permit
requirements for water temperature, and
the Section 316(b) requirements of the
CWA, the NRC staff concludes that the
impact of thermophilic microbiological
organisms from the proposed EPU
would not be significant.
Terrestrial Resources Impacts
According to the application and the
previous discussion regarding land use,
the proposed action will not affect any
lands located outside of the inner
security fence at MNGP. Therefore, the
NRC staff concludes that there would be
no significant impacts on terrestrial
biota associated with the proposed
action.
Threatened and Endangered Species
Impacts
Few Federal- or State-listed aquatic
species are known to exist in the four
counties (Wright, Sherburne, Hennepin,
and Anoka counties) in which MNGP
and the related transmission lines are
located, and no Federal- or State-listed
aquatic species have been identified
near MNGP. Similarly, no Federallylisted terrestrial species occur within
the subject four counties. There are six
State-listed species that occur or
potentially occur in the vicinity of
MNGP. However, because no changes
are proposed to terrestrial wildlife
habitat on the MNGP site or its vicinity
from the proposed EPU, the NRC staff
concludes that there would be no
significant impacts to any threatened or
endangered species for the proposed
action.
Historic and Archaeological Resources
Impacts
Historic and archaeological resources
have been identified in the vicinity of
MNGP, but not at MNGP. The licensee
has no plans to construct new facilities
or modify existing access roads, parking
areas, or laydown areas for EPU
operation. The licensee stated that
onsite transmission and distribution
equipment could be replaced or
modified to support EPU activities,
E:\FR\FM\15SEN1.SGM
15SEN1
47284
Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices
however, these activities would be
limited to previously disturbed areas.
Therefore, the NRC staff concludes that
there would be no significant impact
from the proposed EPU on historic and
archaeological resources at MNGP.
Socioeconomic Impacts
Potential socioeconomic impacts from
the proposed EPU include temporary
increases in the size of the workforce at
MNGP and associated increased
demand for public services and housing
in the region. The proposed EPU could
also increase tax payments due to
increased power generation.
Currently, there are approximately
327 full-time workers employed at
MNGP, residing primarily in Wright
County and Sherburne County,
Minnesota. During refueling outages
(approximately every 24 months) the
number of workers at MNGP increases
by as many as 600 workers for 30 to 40
days.
The proposed EPU is expected to
temporarily increase the size of the
workforce at MNGP during two
refueling outages. Approximately 250
additional workers would be needed
during the 2009, refueling outage, and
up to 500 additional workers would be
needed during the 2011, refueling
outage to support EPU-related activities
at MNGP. Once completed, the
proposed EPU would not increase the
size of the MNGP workforce during
future refueling outages.
Most of the EPU plant modification
workers would likely relocate
temporarily to Wright and Sherburne
counties, resulting in short-term
increases in the local population along
with increased demands for public
services and housing. Because plant
modification work would be short-term,
most workers could stay in available
rental homes, apartments, mobile
homes, and camper-trailers. Since
MNGP is located in a high population
area and the number of available
housing units exceeds demand, any
temporary changes in plant employment
would have little or no noticeable effect
on the availability of housing in the
region. Due to the short duration of
plant outages and the availability of
housing, there would be no significant
employment-related housing impacts.
NSPM currently pays annual real
estate taxes to public School District
882, Wright County, and the City of
Monticello. The proposed EPU could
increase property tax payments because
the total amount of tax money paid
would increase as power generation
increases and because the proposed EPU
could increase the assessed market
value of MNGP. Due to the short
duration of EPU-related plant
modification activities, there would be
little or no noticeable effect on tax
revenue streams from the temporary
MNGP workers residing in Wright
County and Sherburne County.
Therefore, the NRC staff concludes that
there would be no significant
socioeconomic impacts from EPUrelated plant modifications and
operations under EPU conditions in the
vicinity of MNGP.
Environmental Justice Impacts
The environmental justice impact
analysis evaluates the potential for
disproportionately high and adverse
human health and environmental effects
on minority and low-income
populations that could result from
activities associated with EPU operation
at MNGP. Such effects may include
ecological, cultural, human health,
economic, or social impacts. Some of
these potential effects have been
identified in resource areas discussed in
this EA. For example, increased demand
for rental housing during plant
modifications for the EPU could
disproportionately affect low-income
populations. Minority and low-income
populations are subsets of the general
public residing around MNGP, and all
are exposed to the same health and
environmental effects generated from
activities at MNGP.
Environmental Justice Impact Analysis
The staff considered the demographic
composition of the area within a 50-mile
radius of MNGP to determine the
location of minority and low-income
populations and whether they may be
affected by the proposed action.
According to U.S. Census Bureau data
for 2000, the largest minority group was
Black or African American (178,000
persons or 6.5 percent), followed by
Asian (132,000 or about 4.8 percent).
Low-Income Populations in the Vicinity
of MNGP were identified as living
below the 1999 Federal poverty
threshold of $17,029 for a family of four.
According to census data, Wright
County and Sherburne County had
higher median household income
averages ($67,391 and $67,634) and
lower percentages (both 5.0 percent) of
individuals living below the poverty
level, respectively.
Potential impacts to minority and
low-income populations would mostly
consist of environmental and
socioeconomic effects (e.g., noise, dust,
traffic, employment, and housing
impacts).
Noise and dust impacts would be
short-term and limited to onsite
activities. Minority and low-income
populations residing along site access
roads could experience increased
commuter vehicle traffic during shift
changes. Increased demand for
inexpensive rental housing during EPUrelated plant modifications could
disproportionately affect low-income
populations, but there are a sufficient
number of rental housing units available
to accommodate the increase of workers
at MNGP during the outages. Due to the
short duration of the EPU-related work
and the availability of rental properties,
impacts to minorities and low-income
populations would be short-term and
limited.
Based on this information and the
analysis of human health and
environmental impacts presented in this
EA, the NRC staff concludes that the
proposed EPU operation would not have
disproportionately high and adverse
human health and environmental effects
on minority and low-income
populations residing in the vicinity of
MNGP.
Non-Radiological Impacts Summary
As discussed above, the proposed
EPU would not result in any significant
non-radiological impacts. The NRC staff
also anticipates that there would be no
significant non-radiological cumulative
impacts related to the proposed EPU.
Table 1 summarizes the nonradiological environmental impacts of
the proposed EPU at MNGP.
sroberts on DSKD5P82C1PROD with NOTICES
TABLE 1—SUMMARY OF NON-RADIOLOGICAL ENVIRONMENTAL IMPACTS
Land Use ............................................................
Air Quality ...........................................................
Water Use ...........................................................
VerDate Nov<24>2008
19:12 Sep 14, 2009
Jkt 217001
No significant impact on land use conditions and aesthetic resources in the vicinity of MNGP.
Temporary short-term air quality impacts from construction activities and vehicle emissions related to travelling of the workforce required to complete EPU modifications; no significant air
quality impacts from such temporary increase in workforce.
Water use changes resulting from the EPU would be relatively minor. No significant impact on
groundwater or surface water resources.
PO 00000
Frm 00100
Fmt 4703
Sfmt 4703
E:\FR\FM\15SEN1.SGM
15SEN1
Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices
47285
TABLE 1—SUMMARY OF NON-RADIOLOGICAL ENVIRONMENTAL IMPACTS—Continued
Aquatic Resources ..............................................
Terrestrial Resources .........................................
Threatened and Endangered Species ................
Historic and Archaeological Resources ..............
Socioeconomics ..................................................
Environmental Justice .........................................
Radiological Impacts
Radioactive Gaseous and Liquid
Effluents, Direct Radiation Shine, and
Solid Waste
Nuclear power plants use waste
treatment systems to collect, process,
recycle, and dispose of gaseous, liquid,
and solid wastes that contain
radioactive material in a safe and
controlled manner within NRC and EPA
radiation safety standards.
sroberts on DSKD5P82C1PROD with NOTICES
Radioactive Gaseous and Liquid
Effluents
During normal power plant operation,
the gaseous effluent treatment system
processes and controls the release of
radioactive gaseous effluents into the
environment.
Implementation of the proposed EPU
would increase the production and
activity of gaseous effluents by
approximately 13 percent, which is in
proportion to the proposed increase in
power level. As reported by the licensee
for the 2001–2006 time period, the
average annual calculated maximum
total body dose to an offsite member of
the general public from gaseous
effluents was 1.62E–02 mrem (1.62E–04
mSv). This dose is well below the 5
mrem (0.05 mSv) dose design objective
in Appendix I to 10 CFR Part 50. Using
the average annual maximum total body
dose (provided by the licensee) to an
offsite member of the general public
from gaseous effluents, and assuming
that the 13-percent EPU will result in a
corresponding increase in dose, the NRC
staff projects that the average annual
calculated maximum total body dose to
an offsite member of the general public
from gaseous effluents would be 1.83E–
02 mrem (1.83E–04 mSv). Thus, the
maximum offsite dose to the member of
the public under the conditions of the
EPU would remain well within the
radiation standards of 10 CFR Part 20
and the design objectives of Appendix
I to 10 CFR Part 50. Therefore, the NRC
staff concludes that the potential
increase in offsite dose due to gaseous
effluent release following
implementation of the EPU would not
be significant.
VerDate Nov<24>2008
19:12 Sep 14, 2009
Jkt 217001
No significant impact to aquatic resources due to impingement and entrainment or thermal discharge.
No significant impact to terrestrial resources.
No significant impact to Federal- or State-listed species.
No significant impact to historic and archaeological resources on site or in the vicinity of
MNGP.
No significant socioeconomic impacts from EPU-related temporary increase in workforce.
No disproportionately high and adverse human health and environmental effects on minority
and low-income populations in the vicinity of MNGP.
MNGP is authorized by the NRC to
release a qualified amount of radioactive
liquid effluent into the environment;
however, by its own policy the licensee
operates the plant as a zero radioactive
liquid release plant. Therefore, there are
no routine periodic releases of liquid
radioactive effluents from the plant.
MNGP’s liquid radioactive waste
management system collects and
processes the liquid waste, and then
either recycles the clean liquid within
the plant or solidifies it for off-site
disposal. The proposed EPU operation
will not change the zero radioactive
release policy at MNGP. No
modifications to the liquid radioactive
waste system would be needed to
handle the increased liquid waste
following implementation of the
proposed EPU.
In the EPU application, the licensee
estimated that the proposed EPU would
slightly increase the volume of
radioactive liquid waste generated from
11,000 gals/day to 11,250 gals/day. This
is a small increase in volume and can
be accommodated by the radioactive
liquid waste system capacity. Although
the licensee strives to operate the plant
as a zero liquid release plant, there were
some radioactive liquid discharges in
2001, 2003, and 2004. As reported by
the licensee for the 2001–2006 time
period, the average annual calculated
maximum total body dose to an offsite
member of the general public from
liquid effluents was 2.72E–06 mrem
(2.72E–08 mSv). This annual dose is
well below the 3 mrem (0.03 mSv) dose
design objective in Appendix I to 10
CFR Part 50. Based on the licensee’s
ability to maintain a near zero liquid
discharge status for several years, and
the resulting dose from the few releases
being well within NRC dose standards,
there is reasonable assurance that the
proposed EPU will not have a
significant impact on future liquid
discharges.
In addition to the dose impact from
gaseous and liquid radioactive effluents,
the licensee evaluated the impact of the
proposed EPU on the direct radiation
(gamma radiation) from plant systems,
liquid storage tanks, the turbine, and
PO 00000
Frm 00101
Fmt 4703
Sfmt 4703
components containing radioactive
materials.
Based on the licensee’s evaluation,
the annual offsite dose to members of
the public from direct radiation under
EPU conditions would be approximately
6 mrem. Thus, the annual cumulative
average calculated maximum total body
dose to an offsite member of the general
public from all sources of radiation from
the facility (i.e., gaseous and liquid
effluents, and direct radiation) following
implementation of the proposed EPU
would be approximately 7 mrem. This
dose is well below the radiation dose
limits and standards in 10 CFR Part 20,
and 40 CFR Part 190. Therefore, the
NRC staff concludes that the potential
increase in offsite radiation dose to
members of the public would not be
significant.
Radioactive Solid Wastes
The radioactive solid waste system
collects, processes, packages, monitors,
and temporarily stores radioactive dry
and wet solid wastes prior to shipment
offsite for disposal. The licensee
reported in its environmental
assessment that MNGP shipped
annually, on average, approximately 706
ft3 of solid radioactive waste consisting
of spent resin, filter sludge, evaporator
bottoms, etc., during the 2001–2006
time period. The licensee projects that
implementation of the proposed EPU
would cause an annual increase of 106
ft3 in the volume of the resins and result
in one additional annual shipment. No
modifications to the solid radioactive
waste system would be needed to
handle the increase in liquid waste
following implementation of the
proposed EPU. The total long-lived
activity contained in the waste is
expected to be bounded by the
percentage of the EPU, and the increase
in the overall volume of waste generated
during operation under EPU conditions
is expected to be minor. Therefore, the
NRC staff concludes that the impact
from the increased volume of solid
radwaste generated under conditions of
the proposed EPU would not be
significant.
E:\FR\FM\15SEN1.SGM
15SEN1
47286
Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices
Spent fuel from MNGP is stored in the
spent fuel pool and the newly
constructed Independent Spent Fuel
Storage Installation (ISFSI). The licensee
estimates that the number of discharged
assemblies would increase from 150
assemblies per cycle to approximately
170 assemblies per cycle following
implementation of the proposed EPU.
The storage capacity of the spent fuel
pool and the ISFSI is sufficient to
accommodate the expected small
increase in discharged fuel assemblies.
Therefore, the NRC staff concludes that
there would be no significant impact
resulting from storage of the additional
fuel assemblies.
Occupational Doses
Implementation of the proposed EPU
would result in the production of more
radioactive material and higher
radiation dose rates in the restricted
areas at MNGP. Occupational exposures
from in-plant radiation primarily occur
during maintenance and refueling
operations. Implementation of the
proposed EPU is not expected to
significantly change the amount of
radiation exposure received by plant
personnel, as the licensee has a
radiation protection program that
monitors radiation levels throughout the
plant to establish work controls,
shielding, and protective equipment
requirements so that worker doses will
remain within the dose limits of 10 CFR
part 20 and as low as is reasonably
achievable. Therefore, the NRC staff
concludes that there would be no
significant increase in the radiation
exposure received by plant personnel
due to implementation of the proposed
EPU.
Postulated Accident Doses
Implementation of the proposed EPU
would increase the core inventory of
radionuclides, which is dependent on
power level. The concentration of the
radionuclides in the reactor coolant may
also increase in proportion to power
level increase; however, this
concentration is limited by the MNGP
Technical Specifications. Therefore, the
reactor coolant concentration of
radionuclides would not be expected to
increase significantly. Some of the
radioactive waste streams and storage
systems evaluated for postulated
accidents may contain slightly higher
quantities of radionuclides. For those
postulated accidents where the source
term has increased, the calculated
potential radiation dose to individuals
at the exclusion area boundary, at the
low population zone, and in the main
control room, as well as in the technical
support center for the loss-of-coolant
accident, remain below the
requirements of 10 CFR 50.67.
The NRC staff is reviewing the
applicant’s analyses to independently
verify the applicant’s calculated doses
under accident conditions. The NRC
staff’s evaluation results will be
contained in the safety evaluation that
will be issued concurrently with the
proposed EPU amendment, if so
approved by the NRC staff. However, for
the purpose of this EA, the NRC staff
concludes that, based on the
information provided by the licensee,
the proposed EPU would not
significantly increase the radiological
consequences of postulated accidents.
Radiological Impacts Summary
As discussed above, the proposed
EPU would not result in any significant
radiological impacts. Because of existing
regulatory requirements regarding limits
to exposure, the NRC staff also
anticipates that there would be no
significant radiological cumulative
impacts related to the proposed EPU, as
the licensee is required to continue to
comply with such regulatory
requirements. Table 2 summarizes the
radiological environmental impacts of
the proposed EPU at MNGP.
TABLE 2—SUMMARY OF RADIOLOGICAL ENVIRONMENTAL IMPACTS
Radioactive Gaseous Effluents ..........................
Offsite Radiation Doses ......................................
Radioactive Liquid Effluents ...............................
Radioactive Solid Wastes ...................................
Occupational Doses ............................................
Postulated Accident Doses .................................
sroberts on DSKD5P82C1PROD with NOTICES
Alternatives to the Proposed Action
As an alternative to the proposed
action, the NRC staff considered denial
of the proposed EPU (i.e., the ‘‘noaction’’ alternative). Denial of the
application would result in no change
in the current environmental impacts.
However, if the EPU were not approved
for MNGP, other agencies and electric
power organizations may be required to
pursue other means, such as fossil fuel
power generation, of providing electric
generation capacity to offset future
demand. Construction and operation of
such a fossil-fueled plant may create
impacts in air quality, land use, and
waste management significantly greater
than those identified for the proposed
EPU at MNGP. Conservation programs
such as demand-side management could
VerDate Nov<24>2008
19:12 Sep 14, 2009
Jkt 217001
Doses from increased gaseous effluents would remain within NRC limits and dose design objectives.
Radiation doses to members of the public would remain small, well below NRC and EPA Federal radiation protection standards.
EPU would not change routine liquid radioactive effluent releases from MNGP; the doses from
discharges, if any, would remain within NRC limits and dose design objectives.
Amount of solid waste generated would increase by approximately 15 percent (i.e., approximately 1 additional truck shipment per year.
Occupational doses would continue to be maintained within regulatory limits.
Calculated doses for postulated design-basis accidents would remain within NRC limits.
possibly replace the proposed EPU’s
additional power output. However, the
regional forecasted future energy
demand calculated by the licensee may
exceed conservation savings and still
require additional generating capacity.
Alternative energy sources such as wind
energy have been incorporated into
NSPM’s regional energy forecast.
Furthermore, the proposed EPU does
not involve environmental impacts that
are significantly different from those
originally identified in the MNGP FES.
Alternative Use of Resources
This action does not involve the use
of any resources not previously
considered in the FES.
PO 00000
Frm 00102
Fmt 4703
Sfmt 4703
Agencies and Persons Consulted
In accordance with its stated policy,
on August 7, 2009, the NRC staff
consulted with the State of Minnesota
official regarding the environmental
impact of the proposed action. The
Minnesota State official had no
comments.
Finding of No Significant Impact
On the basis of the EA, the
Commission concludes that the
proposed action will not have a
significant effect on the quality of the
human environment. Accordingly, the
Commission has determined not to
prepare an environmental impact
statement for the proposed action.
For further details with respect to the
proposed action, see the licensee’s
E:\FR\FM\15SEN1.SGM
15SEN1
Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices
application dated November 5, 2008,
and its supplement dated January 29,
2009 (on environmental issues).
Documents may be examined, and/or
copied for a fee, at the NRC’s Public
Document Room (PDR), located at One
White Flint North, 11555 Rockville Pike
(first floor), Rockville, Maryland 20852.
Publicly available records will be
accessible electronically from the
Agencywide Documents Access and
Management System (ADAMS) Public
Electronic Reading Room on the NRC
Web site, https://www.nrc.gov/readingrm/adams.html. Persons who do not
have access to ADAMS or who
encounter problems in accessing the
documents located in ADAMS should
contact the NRC PDR Reference staff at
1–800–397–4209, or 301–415–4737, or
send an e-mail to pdr.Resource@nrc.gov.
Dated at Rockville, Maryland, this 28th day
of August 2009.
For the Nuclear Regulatory Commission.
Lois James,
Branch Chief, Plant Licensing Branch III–1,
Division of Operating Reactor Licensing,
Office of Nuclear Reactor Regulation.
[FR Doc. E9–22127 Filed 9–14–09; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 70–36; NRC–2009–0278]
Notice Extending the Deadline for
Requesting a Hearing and Correcting
Information Regarding the Procedure
for Requesting a Hearing on a License
Amendment Application Filed by
Westinghouse Electric Company LLC
for the Hematite Decommissioning
Project, Festus, MO
sroberts on DSKD5P82C1PROD with NOTICES
AGENCY: U.S. Nuclear Regulatory
Commission.
ACTION: Notice extending the deadline
for requesting a hearing and correcting
information regarding the procedure for
requesting a hearing.
DATES: Any request for a hearing must
be filed by October 5, 2009.
FOR FURTHER INFORMATION CONTACT: John
J. Hayes, Project Manager, Materials
Decommissioning Branch, Division of
Waste Management and Environmental
Protection, Office of Federal and State
Materials and Environmental
Management Programs, U.S. Nuclear
Regulatory Commission, Two White
Flint North, Mail Stop T8F5, 11545
Rockville Pike, Rockville, Maryland
20852–2738; Telephone: (301) 415–
5928; fax number: (301) 415–5928; email: john.hayes@nrc.gov.
SUPPLEMENTARY INFORMATION:
VerDate Nov<24>2008
19:12 Sep 14, 2009
Jkt 217001
I. Introduction
On July 6, 2009, the U.S. Nuclear
Regulatory Commission (NRC or
Commission) provided notice in the
Federal Register of the opportunity to
request a hearing on Westinghouse
Electric Company LLC’s application for
a license amendment that would allow
it to dispose of NRC-licensed material at
a U.S. Ecology facility near Grand View,
Idaho. The deadline for requesting a
hearing stated in the Federal Register
notice was September 4, 2009.
The NRC is extending the deadline for
requesting a hearing on Westinghouse’s
application until October 5, 2009. The
NRC is also providing corrected
information regarding the procedure for
requesting a hearing. As explained
below, any hearing request must be
served in accordance with the NRC’s EFiling rules in Subpart C of 10 CFR Part
2. Finally, the NRC is providing a
corrected reference number for one
document listed in the July 6, 2009
Federal Notice.
II. Background
By letter dated May 21, 2009, the NRC
received a license amendment
application from Westinghouse Electric
Company LLC (WEC or the licensee),
pertaining to its planned disposal of
NRC-licensed source, byproduct and
special nuclear material. Regarding this
material, WEC seeks approval, pursuant
to 10 CFR 20.2002, of proposed disposal
procedures which are not otherwise
authorized by NRC regulations. WEC
holds NRC License No. SNM–00033,
which authorizes the licensee to
conduct decommissioning activities at
its former fuel cycle facility located in
Festus, Missouri. The amendment
request seeks authorization allowing
WEC to transfer decommissioning waste
to U.S. Ecology Idaho, Inc., a Resource
Conservation and Recovery Act (RCRA)
Subtitle C disposal facility located near
Grand View, Idaho. This facility is
regulated by the Idaho Department of
Environmental Quality, and is not an
NRC-licensed facility. Pursuant to 10
CFR 30.11 and 70.17, WEC’s application
also requested exemptions from the
licensing requirements of 10 CFR 30.3
and 70.3 for the byproduct and special
nuclear material it seeks to transfer.
These exemptions are necessary because
the disposal of byproduct and special
nuclear material must occur at a facility
licensed to possess such material, and
the U.S. Ecology Idaho facility has no
NRC license.
An NRC administrative review,
documented in a letter to Westinghouse
dated June 19, 2009, found the alternate
disposal application acceptable to begin
PO 00000
Frm 00103
Fmt 4703
Sfmt 4703
47287
a technical review. If the NRC approves
the Westinghouse request, the approval
will be documented in an amendment to
NRC License No. SNM–00033. However,
before approving the proposed
amendment, the NRC will need to make
the findings required by the Atomic
Energy Act of 1954, as amended, and
the National Environmental Policy Act.
These findings will be documented,
respectively, in a Safety Evaluation
Report (SER), and in a separate
environmental assessment performed by
the NRC.
III. Opportunity To Request a Hearing
On July 6, 2009, the NRC provided
notice of Westinghouse’s application for
the license amendment described above.
In accordance with the general
requirements in Subpart C of 10 CFR
Part 2, any person whose interest may
be affected by this proceeding and who
desires to participate as a party must file
a written request for a hearing and a
specification of the contentions which
the person seeks to have litigated in the
hearing. Any person filing a hearing
request must do so by October 5, 2009.
As required by 10 CFR 2.309, a
hearing request or petition for leave to
intervene shall set forth with
particularity the interest of the
requestor/petitioner in the proceeding
and how that interest may be affected by
the results of the proceeding. The
request should specifically explain the
reasons why intervention should be
permitted with particular reference to
the following general requirements: (1)
The name, address and telephone
number of the requestor or petitioner;
(2) the nature of the requestor’s/
petitioner’s right under the Act to be
made a party to the proceeding; (3) the
nature and extent of the requestor’s/
petitioner’s property, financial, or other
interest in the proceeding; and (4) the
possible effect of any decision or order
which may be entered in the proceeding
on the requestor’s/petitioner’s interest.
The petition must also identify the
specific contentions that the requestor/
petitioner seeks to have litigated at the
proceeding.
Each contention must consist of a
specific statement of the issue of law or
fact to be raised or controverted. In
addition, the person submitting the
hearing request or petition to intervene
must provide a brief explanation of the
bases for the contention and a concise
statement of the alleged facts or expert
opinion that support the contention and
on which the requester intends to rely
in proving the contention at the hearing.
The requestor must also provide
references to those specific sources and
documents of which the requester is
E:\FR\FM\15SEN1.SGM
15SEN1
Agencies
[Federal Register Volume 74, Number 177 (Tuesday, September 15, 2009)]
[Notices]
[Pages 47281-47287]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-22127]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-263; NRC-2009-0399]
Northern States Power Company, LLC, Monticello Nuclear Generating
Plant; Draft Environmental Assessment and Finding of No Significant
Impact
The U.S. Nuclear Regulatory Commission (NRC) has prepared a draft
Environmental Assessment (EA) as part of its evaluation of a request by
Northern States Power Company (NSPM) for a license amendment to
increase the maximum thermal power at the Monticello Nuclear Generating
Plant (MNGP) from 1,775 megawatts thermal (MWt) to 2,004 MWt. This
represents a power increase of approximately 13 percent over the
current licensed thermal power. As stated in the NRC staff's position
paper dated February 8, 1996, on the Boiling-Water Reactor Extended
Power Uprate (EPU) Program, the NRC staff will prepare an environmental
impact statement if it believes a power uprate would have a significant
impact on the human environment. The NRC staff did not identify any
significant impact from the information provided in the licensee's EPU
application or during the NRC staff's review of other available
information; therefore, the NRC staff is documenting its environmental
review in this EA. Also, in accordance with the position paper, the
draft EA and Finding of No Significant Impact are being published in
the Federal Register with a 30-day public comment period.
Environmental Assessment
Plant Site and Environs
The MNGP site is located in Monticello, Minnesota, along the
southern bank of the Mississippi River at River Mile (RM) 900,
approximately 30 miles (48 kilometers) northwest of Minneapolis/St.
Paul, and east of Interstate Highway 94. The 2,150-acre (870-hectare)
site consists of 2 miles (3 kilometers) of frontage on both banks of
the Mississippi River, within portions of
[[Page 47282]]
Wright and Sherburne Counties. The plant and its supporting facilities
occupy approximately 50 acres (20 hectares) in Wright County.
MNGP is a single unit boiling water reactor that has been designed
to allow operation using four water circulating modes to cool the
system, and draws water from and discharges water to the Mississippi
River. These four water circulating modes include an open-cycle (once-
through) system, a closed cycle system using two mechanical draft
cooling towers, a helper cycle system, and a partial recirculation of
the cooling water. The helper cycle cools water using both the open
cycle to withdraw water from and discharge the water back to the
Mississippi River, and the cooling towers to cool water prior to
discharge to the river. The helper cycle is used when the discharge
canal temperature approaches permit limits and upstream river
temperatures are consistently at or above 68 [deg]F. MNGP operates in
open cycle or helper cycle approximately 98 percent of the time. In the
partial recirculation mode, 75 percent of the Mississippi River flow is
withdrawn and the cooling towers are operating. A portion of the cooled
water is recirculated to the intake and the remainder is discharged to
the river. The partial recirculation mode is used when river flow is
less than 860 cubic-feet-per-second (cfs) but greater than 240 cfs, and
the river temperature is elevated.
Identification of the Proposed Action
By application dated November 5, 2008, as supplemented on January
29, 2009 (on environmental issues only) the licensee requested an
amendment for EPU for MNGP to increase the licensed thermal power level
from 1,775 MWt to 2,004 MWt, which is an increase of 13 percent over
the current licensed thermal power and a 20 percent increase over the
original licensed thermal power. The Atomic Energy Commission
(predecessor of the NRC) issued the Final Environmental Statement (FES)
in November 1972, for the original license for MNGP. The NRC previously
approved a 6.3 percent stretch power uprate in September 1998,
increasing the power output from 1,670 MWt to 1,775 MWt. The NRC EA for
that action resulted in a finding of no significant impact and was
published in the Federal Register on September 1, 1998 (63 FR 46489).
In addition, the NRC issued a Supplemental Environmental Impact
Statement, NUREG-1437, Supplement 26 (SEIS-26) in August 2006,
associated with renewing the operating license for MNGP for an
additional 20 years. This proposed amendment for an EPU would result in
an increase in production of electricity and the amount of waste heat
delivered to the condenser, requiring an increase to the amount of
water withdrawn from the Mississippi River for cooling purposes, and a
subsequent increase in the temperature of the water discharged back to
the Mississippi River.
The licensee plans to implement the proposed EPU in two phases to
coincide with two refueling outages. The first refueling outage is
scheduled for late 2009, with a corresponding increase in power of
approximately 50 MWt to a total of 1,825 MWt. The second refueling
outage is scheduled for 2011, and the power level will be increased to
the maximum of 2,004 MWt.
The Need for the Proposed Action
The need for the additional power generation is based upon NSPM's
15-year Resource Plan that includes a forecast of an average annual
increase of peak electrical demand of 1.2 percent through NSPM's 2008-
2022 planning period. This forecast for increased energy includes
NSPM's resource obligations for summer peak net demand, minimum reserve
requirements, its committed resources, and other contracted
obligations. This increase in power demand would partially be met by
the increased amount of power output proposed for MNGP along with other
energy sources.
Environmental Impacts of the Proposed Action
At the time of issuance of the operating license for MNGP in 1972,
the NRC staff noted that any activity authorized by the license would
be encompassed by the overall action evaluated in the FES for the
operation of MNGP. In addition, the NRC published the SEIS-26 in 2006,
which evaluated the environmental impacts of operating MNGP for an
additional 20 years, and determined that the environmental impacts of
license renewal were small. The sections below summarize the non-
radiological and radiological impacts in the environment that may
result from the proposed action of the proposed EPU.
Non-Radiological Impacts
Land Use and Aesthetic Impacts
Potential land use and aesthetic impacts from the proposed EPU
include impacts from plant modifications at MNGP. While some plant
components would be modified, most plant changes related to the
proposed EPU would occur within existing structures, buildings, and
fenced equipment yards housing major components within the developed
part of the site. No new construction would occur outside of existing
facilities and no expansion of buildings, roads, parking lots,
equipment storage areas, or transmission facilities would be required
to support the proposed EPU, although some transmission and
distribution equipment may be replaced or modified.
Existing parking lots, road access, lay-down areas, offices,
workshops, warehouses, and restrooms would be used during plant
modifications. Therefore, land use conditions would not change at MNGP.
Also, there would be no land use changes along transmission lines (no
new lines would be required for the proposed EPU), transmission
corridors, switch yards, or substations.
Since land use conditions would not change at MNGP, and because any
land disturbance would occur within previously disturbed areas, there
would be little or no impact to aesthetic resources in the vicinity of
MNGP. Therefore, the NRC staff concludes that there would be no
significant impact from EPU-related plant modifications on land use and
aesthetic resources in the vicinity of MNGP.
Air Quality Impacts
During implementation of the EPU at the MNGP site, some minor and
short duration air quality impacts would likely occur. Emissions from
the vehicles of workers would be the main sources of these air quality
impacts. Wright County, where MNGP is located, is designated as a
maintenance area for carbon monoxide. The NSPM indicated that an
additional 500 temporary employees would be needed for the duration of
the project. The majority of the workforce would reside within the
county where MNGP is located. The screening analysis performed by the
licensee for the proposed Monticello EPU projects that annual average
vehicular traffic would increase by approximately 2 percent. The
majority of the EPU-associated activities would be performed inside
existing buildings and will not cause additional atmospheric emissions.
Therefore, the NRC staff concludes that there would be no significant
impact on air quality during and following implementation of the
proposed EPU.
Water Use Impacts
Groundwater
MNGP uses groundwater for domestic-type water uses and limited
industrial use. Groundwater is obtained
[[Page 47283]]
from six on-site wells, two of which are permitted and regulated by the
Minnesota Department of Natural Resources (MDNR) through the State's
water appropriation permit program. These two wells produce 100 gallons
per minute (gpm) each and provide domestic water to restrooms, showers,
and laundries and industrial use water to the MNGP reverse osmosis
system, and to pump seals at the plant intake structure. Four
additional small capacity wells that do not require an MDNR permit are
used to supply domestic use water to buildings not connected to the
permitted system. The proposed EPU will not significantly increase the
use of domestic groundwater, and the volume of additional groundwater
needed for industrial use is within the limits of the existing
appropriations permit. Therefore, the NRC staff concludes that there
would be no significant impact on groundwater resources following
implementation of the proposed EPU.
Surface Water
MNGP uses surface water for plant condenser cooling, auxiliary
water systems, service water cooling, intake screen wash, and fire
protection. Under MDNR water appropriation permit number PA 66-1172-S,
MNGP may withdraw up to 645 cubic feet per second (cfs) from the
Mississippi River. Surface water consumption under EPU conditions is
expected to be maintained within permitted limits. The upper limit of
the permit is 8,700 ac-ft per year, which would not be reached because
the cooling towers are typically operated in combination with the once-
through cooling system. As part of its environmental review for license
renewal, the NRC staff stated in SEIS-26 that ``the consumptive loss
due to evaporation from the cooling towers represent 4 percent of the
river flow, which is not considered significant.'' The increased volume
of circulation water will continue to have an insignificant effect on
the total consumptive use of surface water at MNGP. The issue of
discharge temperatures is regulated by the National Pollutant Discharge
Elimination System (NPDES) permit discussed in the following section.
Therefore, the NRC staff concludes that there would be no significant
impact on surface water resources following implementation of the
proposed EPU.
Aquatic Resources Impacts
The potential impacts to aquatic biota from the proposed action
include impingement, entrainment, and thermal discharge effects.
Since MNGP operates most of the time in open-cycle mode, an
increase in river water appropriation for the EPU from the current
consumptive rate of 509 cfs to 645 cfs may increase impacts from
entrainment and impingement of fish and shellfish in their early life
stages. However, in a Section 316(a) Clean Water Act (CWA)
Demonstration project in 1975, for MNGP that included an evaluation of
plant impacts on aquatic organisms, the evidence indicated that
operations of MNGP had not produced appreciable harm to the aquatic
organisms in the Mississippi River in the vicinity of MNGP. In
addition, in the SEIS-26, the NRC staff concluded in its assessment of
the relicensing activities of MNGP that MNGP was in compliance with its
current State of Minnesota NPDES permit, and in compliance with Section
316(b) of the CWA regarding the use of best available technology for
the minimization of adverse environmental impacts from entrainment and
impingement, and further mitigation measures would not be warranted.
Further, river water appropriation under EPU operation will not
increase beyond the current maximum MNGP NPDES Permit limit of 645 cfs.
Therefore, the NRC staff concludes that there would be no significant
adverse impacts from entrainment or impingement for the proposed
action.
According to the licensee, at the proposed EPU conditions, the
temperature of the water entering the discharge canal is expected to
increase by a maximum of 4.5 [deg]F over the current discharge canal
temperature, which ranges from 66 [deg]F to 95 [deg]F depending upon
the season. This can lead to changes to the length, width, and duration
of the thermal plume across the Mississippi River. However, the
licensee states in the application that when canal discharge
temperatures have approached the limits of the NPDES permit, MNGP will
reduce power in order to comply with NPDES thermal discharge
requirements. The NRC staff previously noted in its SEIS-26 and review
of MNGP's license renewal that, despite a few periods of non-compliance
with the NPDES permit, there have been no indications of adverse
impacts to the aquatic biota within the vicinity of the discharge
plume. Therefore, the NRC staff concludes that there would be no
significant adverse impacts to aquatic biota from thermal discharges
for the proposed action.
The licensee stated in the application that an increase of up to
4.5 [deg]F for the effluent at the discharge canal over the current
temperature would not result in a significant increase in the
production of harmful thermophilic organisms in the discharge canal.
The maximum temperature at the discharge canal would remain within the
limits of the NPDES permit, and this temperature is also well below the
temperature for maximum growth rate of thermophilic organisms. The NRC
staff determined, in SEIS-26, that thermophilic organisms are not
likely to occur as a result of discharges by MNGP into the Mississippi
River. No further mitigation was necessary according to the NRC staff.
Based upon the information provided in the application for EPU and the
SEIS-26, the NPDES permit requirements for water temperature, and the
Section 316(b) requirements of the CWA, the NRC staff concludes that
the impact of thermophilic microbiological organisms from the proposed
EPU would not be significant.
Terrestrial Resources Impacts
According to the application and the previous discussion regarding
land use, the proposed action will not affect any lands located outside
of the inner security fence at MNGP. Therefore, the NRC staff concludes
that there would be no significant impacts on terrestrial biota
associated with the proposed action.
Threatened and Endangered Species Impacts
Few Federal- or State-listed aquatic species are known to exist in
the four counties (Wright, Sherburne, Hennepin, and Anoka counties) in
which MNGP and the related transmission lines are located, and no
Federal- or State-listed aquatic species have been identified near
MNGP. Similarly, no Federally-listed terrestrial species occur within
the subject four counties. There are six State-listed species that
occur or potentially occur in the vicinity of MNGP. However, because no
changes are proposed to terrestrial wildlife habitat on the MNGP site
or its vicinity from the proposed EPU, the NRC staff concludes that
there would be no significant impacts to any threatened or endangered
species for the proposed action.
Historic and Archaeological Resources Impacts
Historic and archaeological resources have been identified in the
vicinity of MNGP, but not at MNGP. The licensee has no plans to
construct new facilities or modify existing access roads, parking
areas, or laydown areas for EPU operation. The licensee stated that
onsite transmission and distribution equipment could be replaced or
modified to support EPU activities,
[[Page 47284]]
however, these activities would be limited to previously disturbed
areas. Therefore, the NRC staff concludes that there would be no
significant impact from the proposed EPU on historic and archaeological
resources at MNGP.
Socioeconomic Impacts
Potential socioeconomic impacts from the proposed EPU include
temporary increases in the size of the workforce at MNGP and associated
increased demand for public services and housing in the region. The
proposed EPU could also increase tax payments due to increased power
generation.
Currently, there are approximately 327 full-time workers employed
at MNGP, residing primarily in Wright County and Sherburne County,
Minnesota. During refueling outages (approximately every 24 months) the
number of workers at MNGP increases by as many as 600 workers for 30 to
40 days.
The proposed EPU is expected to temporarily increase the size of
the workforce at MNGP during two refueling outages. Approximately 250
additional workers would be needed during the 2009, refueling outage,
and up to 500 additional workers would be needed during the 2011,
refueling outage to support EPU-related activities at MNGP. Once
completed, the proposed EPU would not increase the size of the MNGP
workforce during future refueling outages.
Most of the EPU plant modification workers would likely relocate
temporarily to Wright and Sherburne counties, resulting in short-term
increases in the local population along with increased demands for
public services and housing. Because plant modification work would be
short-term, most workers could stay in available rental homes,
apartments, mobile homes, and camper-trailers. Since MNGP is located in
a high population area and the number of available housing units
exceeds demand, any temporary changes in plant employment would have
little or no noticeable effect on the availability of housing in the
region. Due to the short duration of plant outages and the availability
of housing, there would be no significant employment-related housing
impacts.
NSPM currently pays annual real estate taxes to public School
District 882, Wright County, and the City of Monticello. The proposed
EPU could increase property tax payments because the total amount of
tax money paid would increase as power generation increases and because
the proposed EPU could increase the assessed market value of MNGP. Due
to the short duration of EPU-related plant modification activities,
there would be little or no noticeable effect on tax revenue streams
from the temporary MNGP workers residing in Wright County and Sherburne
County. Therefore, the NRC staff concludes that there would be no
significant socioeconomic impacts from EPU-related plant modifications
and operations under EPU conditions in the vicinity of MNGP.
Environmental Justice Impacts
The environmental justice impact analysis evaluates the potential
for disproportionately high and adverse human health and environmental
effects on minority and low-income populations that could result from
activities associated with EPU operation at MNGP. Such effects may
include ecological, cultural, human health, economic, or social
impacts. Some of these potential effects have been identified in
resource areas discussed in this EA. For example, increased demand for
rental housing during plant modifications for the EPU could
disproportionately affect low-income populations. Minority and low-
income populations are subsets of the general public residing around
MNGP, and all are exposed to the same health and environmental effects
generated from activities at MNGP.
Environmental Justice Impact Analysis
The staff considered the demographic composition of the area within
a 50-mile radius of MNGP to determine the location of minority and low-
income populations and whether they may be affected by the proposed
action. According to U.S. Census Bureau data for 2000, the largest
minority group was Black or African American (178,000 persons or 6.5
percent), followed by Asian (132,000 or about 4.8 percent). Low-Income
Populations in the Vicinity of MNGP were identified as living below the
1999 Federal poverty threshold of $17,029 for a family of four.
According to census data, Wright County and Sherburne County had higher
median household income averages ($67,391 and $67,634) and lower
percentages (both 5.0 percent) of individuals living below the poverty
level, respectively.
Potential impacts to minority and low-income populations would
mostly consist of environmental and socioeconomic effects (e.g., noise,
dust, traffic, employment, and housing impacts).
Noise and dust impacts would be short-term and limited to onsite
activities. Minority and low-income populations residing along site
access roads could experience increased commuter vehicle traffic during
shift changes. Increased demand for inexpensive rental housing during
EPU-related plant modifications could disproportionately affect low-
income populations, but there are a sufficient number of rental housing
units available to accommodate the increase of workers at MNGP during
the outages. Due to the short duration of the EPU-related work and the
availability of rental properties, impacts to minorities and low-income
populations would be short-term and limited.
Based on this information and the analysis of human health and
environmental impacts presented in this EA, the NRC staff concludes
that the proposed EPU operation would not have disproportionately high
and adverse human health and environmental effects on minority and low-
income populations residing in the vicinity of MNGP.
Non-Radiological Impacts Summary
As discussed above, the proposed EPU would not result in any
significant non-radiological impacts. The NRC staff also anticipates
that there would be no significant non-radiological cumulative impacts
related to the proposed EPU. Table 1 summarizes the non-radiological
environmental impacts of the proposed EPU at MNGP.
Table 1--Summary of Non-Radiological Environmental Impacts
------------------------------------------------------------------------
------------------------------------------------------------------------
Land Use..................... No significant impact on land use
conditions and aesthetic resources in
the vicinity of MNGP.
Air Quality.................. Temporary short-term air quality impacts
from construction activities and vehicle
emissions related to travelling of the
workforce required to complete EPU
modifications; no significant air
quality impacts from such temporary
increase in workforce.
Water Use.................... Water use changes resulting from the EPU
would be relatively minor. No
significant impact on groundwater or
surface water resources.
[[Page 47285]]
Aquatic Resources............ No significant impact to aquatic
resources due to impingement and
entrainment or thermal discharge.
Terrestrial Resources........ No significant impact to terrestrial
resources.
Threatened and Endangered No significant impact to Federal- or
Species. State-listed species.
Historic and Archaeological No significant impact to historic and
Resources. archaeological resources on site or in
the vicinity of MNGP.
Socioeconomics............... No significant socioeconomic impacts from
EPU-related temporary increase in
workforce.
Environmental Justice........ No disproportionately high and adverse
human health and environmental effects
on minority and low-income populations
in the vicinity of MNGP.
------------------------------------------------------------------------
Radiological Impacts
Radioactive Gaseous and Liquid Effluents, Direct Radiation Shine, and
Solid Waste
Nuclear power plants use waste treatment systems to collect,
process, recycle, and dispose of gaseous, liquid, and solid wastes that
contain radioactive material in a safe and controlled manner within NRC
and EPA radiation safety standards.
Radioactive Gaseous and Liquid Effluents
During normal power plant operation, the gaseous effluent treatment
system processes and controls the release of radioactive gaseous
effluents into the environment.
Implementation of the proposed EPU would increase the production
and activity of gaseous effluents by approximately 13 percent, which is
in proportion to the proposed increase in power level. As reported by
the licensee for the 2001-2006 time period, the average annual
calculated maximum total body dose to an offsite member of the general
public from gaseous effluents was 1.62E-02 mrem (1.62E-04 mSv). This
dose is well below the 5 mrem (0.05 mSv) dose design objective in
Appendix I to 10 CFR Part 50. Using the average annual maximum total
body dose (provided by the licensee) to an offsite member of the
general public from gaseous effluents, and assuming that the 13-percent
EPU will result in a corresponding increase in dose, the NRC staff
projects that the average annual calculated maximum total body dose to
an offsite member of the general public from gaseous effluents would be
1.83E-02 mrem (1.83E-04 mSv). Thus, the maximum offsite dose to the
member of the public under the conditions of the EPU would remain well
within the radiation standards of 10 CFR Part 20 and the design
objectives of Appendix I to 10 CFR Part 50. Therefore, the NRC staff
concludes that the potential increase in offsite dose due to gaseous
effluent release following implementation of the EPU would not be
significant.
MNGP is authorized by the NRC to release a qualified amount of
radioactive liquid effluent into the environment; however, by its own
policy the licensee operates the plant as a zero radioactive liquid
release plant. Therefore, there are no routine periodic releases of
liquid radioactive effluents from the plant. MNGP's liquid radioactive
waste management system collects and processes the liquid waste, and
then either recycles the clean liquid within the plant or solidifies it
for off-site disposal. The proposed EPU operation will not change the
zero radioactive release policy at MNGP. No modifications to the liquid
radioactive waste system would be needed to handle the increased liquid
waste following implementation of the proposed EPU.
In the EPU application, the licensee estimated that the proposed
EPU would slightly increase the volume of radioactive liquid waste
generated from 11,000 gals/day to 11,250 gals/day. This is a small
increase in volume and can be accommodated by the radioactive liquid
waste system capacity. Although the licensee strives to operate the
plant as a zero liquid release plant, there were some radioactive
liquid discharges in 2001, 2003, and 2004. As reported by the licensee
for the 2001-2006 time period, the average annual calculated maximum
total body dose to an offsite member of the general public from liquid
effluents was 2.72E-06 mrem (2.72E-08 mSv). This annual dose is well
below the 3 mrem (0.03 mSv) dose design objective in Appendix I to 10
CFR Part 50. Based on the licensee's ability to maintain a near zero
liquid discharge status for several years, and the resulting dose from
the few releases being well within NRC dose standards, there is
reasonable assurance that the proposed EPU will not have a significant
impact on future liquid discharges.
In addition to the dose impact from gaseous and liquid radioactive
effluents, the licensee evaluated the impact of the proposed EPU on the
direct radiation (gamma radiation) from plant systems, liquid storage
tanks, the turbine, and components containing radioactive materials.
Based on the licensee's evaluation, the annual offsite dose to
members of the public from direct radiation under EPU conditions would
be approximately 6 mrem. Thus, the annual cumulative average calculated
maximum total body dose to an offsite member of the general public from
all sources of radiation from the facility (i.e., gaseous and liquid
effluents, and direct radiation) following implementation of the
proposed EPU would be approximately 7 mrem. This dose is well below the
radiation dose limits and standards in 10 CFR Part 20, and 40 CFR Part
190. Therefore, the NRC staff concludes that the potential increase in
offsite radiation dose to members of the public would not be
significant.
Radioactive Solid Wastes
The radioactive solid waste system collects, processes, packages,
monitors, and temporarily stores radioactive dry and wet solid wastes
prior to shipment offsite for disposal. The licensee reported in its
environmental assessment that MNGP shipped annually, on average,
approximately 706 ft\3\ of solid radioactive waste consisting of spent
resin, filter sludge, evaporator bottoms, etc., during the 2001-2006
time period. The licensee projects that implementation of the proposed
EPU would cause an annual increase of 106 ft\3\ in the volume of the
resins and result in one additional annual shipment. No modifications
to the solid radioactive waste system would be needed to handle the
increase in liquid waste following implementation of the proposed EPU.
The total long-lived activity contained in the waste is expected to be
bounded by the percentage of the EPU, and the increase in the overall
volume of waste generated during operation under EPU conditions is
expected to be minor. Therefore, the NRC staff concludes that the
impact from the increased volume of solid radwaste generated under
conditions of the proposed EPU would not be significant.
[[Page 47286]]
Spent fuel from MNGP is stored in the spent fuel pool and the newly
constructed Independent Spent Fuel Storage Installation (ISFSI). The
licensee estimates that the number of discharged assemblies would
increase from 150 assemblies per cycle to approximately 170 assemblies
per cycle following implementation of the proposed EPU. The storage
capacity of the spent fuel pool and the ISFSI is sufficient to
accommodate the expected small increase in discharged fuel assemblies.
Therefore, the NRC staff concludes that there would be no significant
impact resulting from storage of the additional fuel assemblies.
Occupational Doses
Implementation of the proposed EPU would result in the production
of more radioactive material and higher radiation dose rates in the
restricted areas at MNGP. Occupational exposures from in-plant
radiation primarily occur during maintenance and refueling operations.
Implementation of the proposed EPU is not expected to significantly
change the amount of radiation exposure received by plant personnel, as
the licensee has a radiation protection program that monitors radiation
levels throughout the plant to establish work controls, shielding, and
protective equipment requirements so that worker doses will remain
within the dose limits of 10 CFR part 20 and as low as is reasonably
achievable. Therefore, the NRC staff concludes that there would be no
significant increase in the radiation exposure received by plant
personnel due to implementation of the proposed EPU.
Postulated Accident Doses
Implementation of the proposed EPU would increase the core
inventory of radionuclides, which is dependent on power level. The
concentration of the radionuclides in the reactor coolant may also
increase in proportion to power level increase; however, this
concentration is limited by the MNGP Technical Specifications.
Therefore, the reactor coolant concentration of radionuclides would not
be expected to increase significantly. Some of the radioactive waste
streams and storage systems evaluated for postulated accidents may
contain slightly higher quantities of radionuclides. For those
postulated accidents where the source term has increased, the
calculated potential radiation dose to individuals at the exclusion
area boundary, at the low population zone, and in the main control
room, as well as in the technical support center for the loss-of-
coolant accident, remain below the requirements of 10 CFR 50.67.
The NRC staff is reviewing the applicant's analyses to
independently verify the applicant's calculated doses under accident
conditions. The NRC staff's evaluation results will be contained in the
safety evaluation that will be issued concurrently with the proposed
EPU amendment, if so approved by the NRC staff. However, for the
purpose of this EA, the NRC staff concludes that, based on the
information provided by the licensee, the proposed EPU would not
significantly increase the radiological consequences of postulated
accidents.
Radiological Impacts Summary
As discussed above, the proposed EPU would not result in any
significant radiological impacts. Because of existing regulatory
requirements regarding limits to exposure, the NRC staff also
anticipates that there would be no significant radiological cumulative
impacts related to the proposed EPU, as the licensee is required to
continue to comply with such regulatory requirements. Table 2
summarizes the radiological environmental impacts of the proposed EPU
at MNGP.
Table 2--Summary of Radiological Environmental Impacts
------------------------------------------------------------------------
------------------------------------------------------------------------
Radioactive Gaseous Effluents Doses from increased gaseous effluents
would remain within NRC limits and dose
design objectives.
Offsite Radiation Doses...... Radiation doses to members of the public
would remain small, well below NRC and
EPA Federal radiation protection
standards.
Radioactive Liquid Effluents. EPU would not change routine liquid
radioactive effluent releases from MNGP;
the doses from discharges, if any, would
remain within NRC limits and dose design
objectives.
Radioactive Solid Wastes..... Amount of solid waste generated would
increase by approximately 15 percent
(i.e., approximately 1 additional truck
shipment per year.
Occupational Doses........... Occupational doses would continue to be
maintained within regulatory limits.
Postulated Accident Doses.... Calculated doses for postulated design-
basis accidents would remain within NRC
limits.
------------------------------------------------------------------------
Alternatives to the Proposed Action
As an alternative to the proposed action, the NRC staff considered
denial of the proposed EPU (i.e., the ``no-action'' alternative).
Denial of the application would result in no change in the current
environmental impacts. However, if the EPU were not approved for MNGP,
other agencies and electric power organizations may be required to
pursue other means, such as fossil fuel power generation, of providing
electric generation capacity to offset future demand. Construction and
operation of such a fossil-fueled plant may create impacts in air
quality, land use, and waste management significantly greater than
those identified for the proposed EPU at MNGP. Conservation programs
such as demand-side management could possibly replace the proposed
EPU's additional power output. However, the regional forecasted future
energy demand calculated by the licensee may exceed conservation
savings and still require additional generating capacity. Alternative
energy sources such as wind energy have been incorporated into NSPM's
regional energy forecast.
Furthermore, the proposed EPU does not involve environmental
impacts that are significantly different from those originally
identified in the MNGP FES.
Alternative Use of Resources
This action does not involve the use of any resources not
previously considered in the FES.
Agencies and Persons Consulted
In accordance with its stated policy, on August 7, 2009, the NRC
staff consulted with the State of Minnesota official regarding the
environmental impact of the proposed action. The Minnesota State
official had no comments.
Finding of No Significant Impact
On the basis of the EA, the Commission concludes that the proposed
action will not have a significant effect on the quality of the human
environment. Accordingly, the Commission has determined not to prepare
an environmental impact statement for the proposed action.
For further details with respect to the proposed action, see the
licensee's
[[Page 47287]]
application dated November 5, 2008, and its supplement dated January
29, 2009 (on environmental issues).
Documents may be examined, and/or copied for a fee, at the NRC's
Public Document Room (PDR), located at One White Flint North, 11555
Rockville Pike (first floor), Rockville, Maryland 20852. Publicly
available records will be accessible electronically from the Agencywide
Documents Access and Management System (ADAMS) Public Electronic
Reading Room on the NRC Web site, https://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter
problems in accessing the documents located in ADAMS should contact the
NRC PDR Reference staff at 1-800-397-4209, or 301-415-4737, or send an
e-mail to pdr.Resource@nrc.gov.
Dated at Rockville, Maryland, this 28th day of August 2009.
For the Nuclear Regulatory Commission.
Lois James,
Branch Chief, Plant Licensing Branch III-1, Division of Operating
Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. E9-22127 Filed 9-14-09; 8:45 am]
BILLING CODE 7590-01-P