Lock + TM Hydro Friends Fund XXV, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 47235 [E9-22096]

Download as PDF Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13536–000] Lock + TM Hydro Friends Fund XXV, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications sroberts on DSKD5P82C1PROD with NOTICES September 4, 2009. On July 6, 2009, Lock + TM Hydro Friends Fund XXV, LLC, filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Grim Reaper Hydroelectric Project, to be located on the Fox River, in Outagamie County, Wisconsin. The proposed Grim Reaper Project would be located at the U.S. Army Corps of Engineers Fox River Upper Appleton Dam in Appleton, Wisconsin. The proposed project would consist of: (1) One new underwater frame module containing nine turbines with a total installed capacity of about 4.73 megawatts which would be installed in a new concrete conduit located adjacent to the Corps’ active lock; (2) a new removable lock door; (3) a new switchyard, transformer, and control room which would be located on the west side of the Corps’ Upper Appleton Dam; (4) a new 1500-foot-long, 36.7 kilovolt transmission line, which would deliver power from the turbines to an existing transformer tie-in bus located at the Corps’ lock and dam facilities; and (5) appurtenant facilities. The Grim Reaper Project would have an estimated average annual generation of about 37,278 megawatts-hours, which would be sold to a local utility. Applicant Contact: Mr. Wayne F. Krouse, Managing Partner, Lock+ Hydro Friends Fund XXV, 5090 Richmond Avenue #390, Houston, TX 77056, 877– 556–6566 x709, wayne@hgenergy.com. FERC Contact: John Ramer, (202) 502– 8969. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy VerDate Nov<24>2008 19:12 Sep 14, 2009 Jkt 217001 Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13536) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Kimberly D. Bose, Secretary. [FR Doc. E9–22096 Filed 9–14–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13567–000] City of Guttenberg, IA; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications September 8, 2009. On August 12, 2009, City of Guttenberg, Iowa filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Guttenberg Water Power Project (Guttenberg Project). The Guttenberg Project would be located at the U.S. Army Corps of Engineers’ (Corps) Mississippi River Lock and Dam No. 10, located at River Mile 615.0 on the Mississippi River in Clayton County, Iowa, and Grant County, Wisconsin, adjacent to the City of Guttenberg. The proposed Guttenberg Project would be installed within the existing and unused auxiliary lock adjacent to the 600-foot-long primary, operating lock which is adjacent to the existing 5,747-foot-long Corps Lock & Dam No. 10. The proposed project would consist of: (1) Nine 485-kilowatt generatorturbine units totaling 4.365 megawatts (MW) that would be arrayed within the auxiliary lock on a frame module structure; (2) a new 69-kilovolt transmission line connected to an existing above-ground local distribution system; and (3) appurtenant facilities. The project would have an estimated average annual generation of 27,000 megawatt-hours. Applicant Contact: Mr. Barry Dykhuizen, City Manager, City of PO 00000 Frm 00051 Fmt 4703 Sfmt 4703 47235 Guttenberg, P.O. Box 580, 502 S. 1st St., Guttenberg, IA 52052–0580, (563) 252– 1161 ext. 109. FERC Contact: Patrick Murphy, (202) 502–8755. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13567) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Kimberly D. Bose, Secretary. [FR Doc. E9–22099 Filed 9–14–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13563–000] Juneau Hydropower, Inc.; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications September 4, 2009. On September 3, 2009, Juneau Hydropower, Inc. filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Sweetheart Lake Project located on the Lower Sweetheart Lake and the Sweetheart Creek in Juneau, Alaska. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit E:\FR\FM\15SEN1.SGM 15SEN1

Agencies

[Federal Register Volume 74, Number 177 (Tuesday, September 15, 2009)]
[Notices]
[Page 47235]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-22096]



[[Page 47235]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13536-000]


Lock + TM Hydro Friends Fund XXV, LLC; Notice of Preliminary 
Permit Application Accepted for Filing and Soliciting Comments, Motions 
To Intervene, and Competing Applications

September 4, 2009.
    On July 6, 2009, Lock + TM Hydro Friends Fund XXV, LLC, filed an 
application, pursuant to section 4(f) of the Federal Power Act, 
proposing to study the feasibility of the Grim Reaper Hydroelectric 
Project, to be located on the Fox River, in Outagamie County, 
Wisconsin.
    The proposed Grim Reaper Project would be located at the U.S. Army 
Corps of Engineers Fox River Upper Appleton Dam in Appleton, Wisconsin.
    The proposed project would consist of: (1) One new underwater frame 
module containing nine turbines with a total installed capacity of 
about 4.73 megawatts which would be installed in a new concrete conduit 
located adjacent to the Corps' active lock; (2) a new removable lock 
door; (3) a new switchyard, transformer, and control room which would 
be located on the west side of the Corps' Upper Appleton Dam; (4) a new 
1500-foot-long, 36.7 kilovolt transmission line, which would deliver 
power from the turbines to an existing transformer tie-in bus located 
at the Corps' lock and dam facilities; and (5) appurtenant facilities. 
The Grim Reaper Project would have an estimated average annual 
generation of about 37,278 megawatts-hours, which would be sold to a 
local utility.
    Applicant Contact: Mr. Wayne F. Krouse, Managing Partner, Lock+ 
Hydro Friends Fund XXV, 5090 Richmond Avenue 390, Houston, TX 
77056, 877-556-6566 x709, wayne@hgenergy.com.
    FERC Contact: John Ramer, (202) 502-8969.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Comments, motions to intervene, notices of intent, and competing 
applications may be filed electronically via the Internet. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original and eight 
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For 
more information on how to submit these types of filings please go to 
the Commission's Web site located at https://www.ferc.gov/filing-comments.asp. More information about this project can be viewed or 
printed on the ``eLibrary'' link of Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P-
13536) in the docket number field to access the document. For 
assistance, call toll-free 1-866-208-3372.

Kimberly D. Bose,
Secretary.
[FR Doc. E9-22096 Filed 9-14-09; 8:45 am]
BILLING CODE 6717-01-P