Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 47237-47238 [E9-22092]
Download as PDF
sroberts on DSKD5P82C1PROD with NOTICES
Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices
proposed 4,500-acre-foot reservoir
formed by the South Bight closure dike
and having a surface area of 330 acres;
(3) a proposed inlet structure on the
South Bight closure dike with a
hydraulic capacity of about 9,000 cubic
feet per second (cfs); (4) a proposed 80foot-high, 4,000-foot-long earth-and-rock
fill embankment closure dike across
North Bight; (5) a proposed 4,500-acrefoot reservoir formed by the North Bight
closure dike and having a surface area
of 500 acres; (6) a proposed outlet
structure on North Bight closure dike
with a hydraulic capacity of 8,000 cfs;
(7) a proposed powerhouse with one
generating unit; (8) a proposed 10-milelong, 12.5-kilovolt transmission line
connecting the powerhouse to the
Inland Passage Electric Company’s
electrical system in Hoonah; (9)
proposed construction of about 3 miles
of project access roads; and (10)
appurtenant facilities. The proposed
project would have an installed capacity
of 400 kilowatts and an estimated
average annual generation of about
2,700 megawatt-hours. The proposed
project would occupy about 112 acres of
federal lands managed by the Tongass
National Forest.
Applicant Contact: Mr. Robert S.
Grimm, President, Alaska Power &
Telephone Co., P.O. Box 3222, Port
Townsend, WA 98368; Ph. (360) 385–
1733 ext. 120.
FERC Contact: Nick Jayjack, 202–502–
6073.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s website under the
‘‘e-Filing’’ link. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and eight
copies should be mailed to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. For
more information on how to submit
these types of filings please go to the
Commission’s Web site located at
https://www.ferc.gov/filingcomments.asp. More information about
this project, including a copy of the
application, can be viewed or printed on
the ‘‘eLibrary’’ link of Commission’s
Web site at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket
number (P–13512) in the docket number
field to access the document. For
VerDate Nov<24>2008
19:12 Sep 14, 2009
Jkt 217001
assistance, call toll-free 1–866–208–
3372.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–22094 Filed 9–14–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13468–000]
Champion Ridge Hydro, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
September 8, 2009.
On May 20, 2009, Champion Ridge
Hydro, LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the Champion
Ridge Pumped Storage Hydroelectric
Project, which would be located in
Johnson County, Wyoming. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would use
groundwater and would consist of the
following: (1) A new upper reservoir,
with a surface area of 90 acres, and a
storage capacity of 6,938 acre-feet at a
normal maximum surface elevation of
7,400 feet above mean sea level (msl);
(2) two new earth embankment dams,
210- and 20-foot-high, 4,234- and 690foot-long, respectively; (3) a new lower
reservoir, with a surface area of 180
acres, and storage capacity of 6,552 acrefeet at a normal maximum surface
elevation of 6,000 feet msl; (4) a new
160-foot-high, 2,083-foot-long earth
embankment dam; (5) a new 5,658-footlong by 23-foot-diameter steel penstock
connecting to; (6) a new powerhouse
containing three generating units having
a total installed capacity of 700
megawatts; (7) a new 230-kilovolt, 14.4mile-long transmission line; and (8)
appurtenant facilities. The proposed
project would have an average annual
generation of 2,026.795 gigawatt-hours.
Applicant Contact: Brent Smith,
Symbiotics, LLC, P.O. Box 535, Rigby,
ID 83442; phone: (208) 745–0835.
FERC Contact: Dianne Rodman, (202)
502–6077.
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
47237
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov/docs-filing/ferconline.asp)
under the ‘‘eFiling’’ link. For a simpler
method of submitting text only
comments, click on ‘‘Quick Comment.’’
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13468) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–22093 Filed 9–14–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13467–000]
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
September 4, 2009.
On May 19, 2009, Hydrodynamics,
Inc. filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the Bear Creek
Hydroelectric Project, which would be
located on Bear Creek, in Park County,
Montana. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land disturbing activities or
E:\FR\FM\15SEN1.SGM
15SEN1
sroberts on DSKD5P82C1PROD with NOTICES
47238
Federal Register / Vol. 74, No. 177 / Tuesday, September 15, 2009 / Notices
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist of
the following: (1) A new 8-foot-high,
100-foot-long concrete diversion dam;
(2) a new 7-foot-wide, 30-foot-long
intake extending from the right side of
the dam; (3) a new 36-inch-diameter,
2.3-mile-long steel penstock; (4) a new
powerhouse containing one generating
unit with an installed capacity of 1.5
megawatts; (5) a new tailrace
discharging flows into Bear Creek; (6) a
new substation; (7) a new 69-kilovolt,
1,500-foot-long transmission line; and
(8) appurtenant facilities. The proposed
project would have an average annual
generation of 7.0 gigawatt-hours.
Applicant Contact: Ben Singer,
Project Manager, Hydrodynamics, Inc.,
P.O. Box 1136, Bozeman, MT 59771;
phone: (406) 587–5086.
FERC Contact: Dianne Rodman, (202)
502–6077.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov/docs-filing/ferconline.asp)
under the ‘‘eFiling’’ link. For a simpler
method of submitting text only
comments, click on ‘‘Quick Comment.’’
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13467) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–22092 Filed 9–14–09; 8:45 am]
BILLING CODE 6717–01–P
VerDate Nov<24>2008
20:34 Sep 14, 2009
Jkt 217001
277 to its Seventh Revised Volume No
11 open access transmission tariff.
Federal Energy Regulatory
Filed Date: 09/02/2009.
Commission
Accession Number: 20090903–0119.
Comment Date: 5 p.m. Eastern Time
Combined Notice of Filings No. 1
on Wednesday, September 23, 2009.
Docket Numbers: ER09–1675–000.
September 4, 2009.
Applicants: Florida Power
Take notice that the Commission
Corporation.
received the following electric rate
Description: Florida Power
filings:
Corporation submits First Revised Rate
Docket Numbers: ER09–1281–001.
Schedule FERC No 106 agreement
Applicants: California Independent
between Progress and Seminole Electric
System Operator Corporation.
Cooperative, Inc for supplemental resale
Description: California Independent
service.
System Operator Corporation submits
Filed Date: 09/02/2009.
Attachment A—Distributed Load
Accession Number: 20090903–0118.
Reference Bus Revisions etc.
Comment Date: 5 p.m. Eastern Time
Filed Date: 09/03/2009.
on Wednesday, September 23, 2009.
Accession Number: 20090903–0205.
Docket Numbers: ER09–1676–000.
Comment Date: 5 p.m. Eastern Time
Applicants: Southern Company
on Thursday, September 24, 2009.
Services, Inc.
Docket Numbers: ER09–1577–001.
Description: Southern Company
Applicants: California Independent
Services, Inc submits Revision No 3 to
System Operator Corporation.
Agreement for Network Integration
Description: California Independent
Transmission Service for Alabama
System Operator Corporation submits
Municipal Electric Authority to the
Modification of Amendment No 5 to
Open Access Transmission Tariff of
Rate Schedule No 42.
Southern Companies.
Filed Date: 09/03/2009.
Filed Date: 09/03/2009.
Accession Number: 20090904–0058.
Accession Number: 20090903–0204.
Comment Date: 5 p.m. Eastern Time
Comment Date: 5 p.m. Eastern Time
on Thursday, September 24, 2009.
on Thursday, September 24, 2009.
Docket Numbers: ER09–1578–001.
Docket Numbers: ER09–1677–000.
Applicants: California Independent
Applicants: Big Sky Wind, LLC.
System Operator Corporation.
Description: Big Sky Wind, LLC
Description: California Independent
submits petition for order accepting
System Operator Corporation submits
market based rate tariff and granting
Modification of Amendment No 1 to
waivers and blanket approvals.
Rate Schedule No 61.
Filed Date: 09/03/2009.
Filed Date: 09/03/2009.
Accession Number: 20090904–0060.
Accession Number: 20090904–0059.
Comment Date: 5 p.m. Eastern Time
Comment Date: 5 p.m. Eastern Time
on Thursday, September 24, 2009.
on Thursday, September 24, 2009.
Any person desiring to intervene or to
Docket Numbers: ER09–1606–001.
protest in any of the above proceedings
Applicants: Wisconsin Public Service must file in accordance with Rules 211
Corporation, Interstate Power & Light
and 214 of the Commission’s Rules of
Company.
Practice and Procedure (18 CFR 385.211
Description: Interstate Power and
and 385.214) on or before 5 p.m. Eastern
Light Company et al. submit revisions to time on the specified comment date. It
the Local Balancing Authority Area
is not necessary to separately intervene
Operations Coordination Agreement.
again in a subdocket related to a
Filed Date: 09/03/2009.
compliance filing if you have previously
Accession Number: 20090903–0150.
intervened in the same docket. Protests
Comment Date: 5 p.m. Eastern Time
will be considered by the Commission
on Thursday, September 24, 2009.
in determining the appropriate action to
Docket Numbers: ER09–1641–000.
be taken, but will not serve to make
Applicants: Idaho Power Company.
protestants parties to the proceeding.
Description: Idaho Power Company’s
Anyone filing a motion to intervene or
2009–2010 Annual Informational filing. protest must serve a copy of that
Filed Date: 08/28/2009.
document on the Applicant. In reference
Accession Number: 2009–0828–5128. to filings initiating a new proceeding,
Comment Date: 5 p.m. Eastern Time
interventions or protests submitted on
on Friday, September 18, 2009.
or before the comment deadline need
not be served on persons other than the
Docket Numbers: ER09–1674–000.
Applicant.
Applicants: PacifiCorp.
The Commission encourages
Description: PacifiCorp submits notice
of cancellation for service agreement No electronic submission of protests and
DEPARTMENT OF ENERGY
PO 00000
Frm 00054
Fmt 4703
Sfmt 4703
E:\FR\FM\15SEN1.SGM
15SEN1
Agencies
[Federal Register Volume 74, Number 177 (Tuesday, September 15, 2009)]
[Notices]
[Pages 47237-47238]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-22092]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13467-000]
Notice of Preliminary Permit Application Accepted for Filing and
Soliciting Comments, Motions To Intervene, and Competing Applications
September 4, 2009.
On May 19, 2009, Hydrodynamics, Inc. filed an application for a
preliminary permit, pursuant to section 4(f) of the Federal Power Act,
proposing to study the feasibility of the Bear Creek Hydroelectric
Project, which would be located on Bear Creek, in Park County, Montana.
The sole purpose of a preliminary permit, if issued, is to grant the
permit holder priority to file a license application during the permit
term. A preliminary permit does not authorize the permit holder to
perform any land disturbing activities or
[[Page 47238]]
otherwise enter upon lands or waters owned by others without the
owners' express permission.
The proposed project would consist of the following: (1) A new 8-
foot-high, 100-foot-long concrete diversion dam; (2) a new 7-foot-wide,
30-foot-long intake extending from the right side of the dam; (3) a new
36-inch-diameter, 2.3-mile-long steel penstock; (4) a new powerhouse
containing one generating unit with an installed capacity of 1.5
megawatts; (5) a new tailrace discharging flows into Bear Creek; (6) a
new substation; (7) a new 69-kilovolt, 1,500-foot-long transmission
line; and (8) appurtenant facilities. The proposed project would have
an average annual generation of 7.0 gigawatt-hours.
Applicant Contact: Ben Singer, Project Manager, Hydrodynamics,
Inc., P.O. Box 1136, Bozeman, MT 59771; phone: (406) 587-5086.
FERC Contact: Dianne Rodman, (202) 502-6077.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Comments, motions to intervene, notices of intent, and competing
applications may be filed electronically via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
(https://www.ferc.gov/docs-filing/ferconline.asp) under the ``eFiling''
link. For a simpler method of submitting text only comments, click on
``Quick Comment.'' For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-3676; or,
for TTY, contact (202) 502-8659. Although the Commission strongly
encourages electronic filing, documents may also be paper-filed. To
paper-file, mail an original and eight copies to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-13467) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-22092 Filed 9-14-09; 8:45 am]
BILLING CODE 6717-01-P