City of Morgan City, LA; Notice of Competing Preliminary Permit Application Accepted for Filing and Soliciting Comments and Motions To Intervene, 43693-43694 [E9-20646]

Download as PDF mstockstill on DSKH9S0YB1PROD with NOTICES Federal Register / Vol. 74, No. 165 / Thursday, August 27, 2009 / Notices g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 808(b)(1) and 18 CFR 5.5 of the Commission’s regulations. h. Potential Applicant Contact: Mark Morley, H2O Providers, L.L.C., 20 Boulder Crescent, Second Floor, Colorado Springs, CO 80903; or e-mail at KerryP@morleydevelopment.com. i. FERC Contact: Patti Leppert at (202) 502–6034; or e-mail at patricia.leppert@ferc.gov. j. H2O Providers, L.L.C. reduced the scope of its original project, formally referred to as the Phantom Canyon Pumped Storage Project, to eliminate potential project-related environmental impacts. On July 17, 2009, H2O Providers, L.L.C. filed its request to use the Traditional Licensing Process and provided public notice of its request. In a letter dated August 18, 2009, the Director, Division of Hydropower Licensing, approved H2O Providers, L.L.C.’s request to use the Traditional Licensing Process. k. With this notice, we are initiating informal consultation with: (a) The U.S. Fish and Wildlife Service and NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402; (b) NOAA Fisheries under section 305(b) of the MagnusonStevens Fishery Conservation and Management Act and implementing regulations at 50 CFR 600.920; and (c) the Colorado State Historic Preservation Officer, as required by section 106 of the National Historic Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating H2O Providers, L.L.C. as the Commission’s non-federal representative for carrying out informal consultation, pursuant to section 7 of the Endangered Species Act, section 305 of the Magnuson-Stevens Fishery Conservation and Management Act, and section 106 of the National Historic Preservation Act. m. H2O Providers, L.L.C. filed a PreApplication Document (PAD, including a proposed process plan and schedule) with the Commission, pursuant to 18 CFR 5.5 of the Commission’s regulations. n. A copy of the PAD is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site (https:// www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCONlineSupport@ferc.gov or toll VerDate Nov<24>2008 17:19 Aug 26, 2009 Jkt 217001 43693 free at 1–866–208–3676, or for TTY, (202) 502–8659. A copy is also available for inspection and reproduction at the address in paragraph h. o. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on September 16, 2009. Kimberly D. Bose, Secretary. [FR Doc. E9–20643 Filed 8–26–09; 8:45 am] Kimberly D. Bose, Secretary. [FR Doc. E9–20640 Filed 8–26–09; 8:45 am] BILLING CODE 6717–01–P BILLING CODE 6717–01–P DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission [Docket No. NJ08–6–002] [Project No. 13529–000] Orlando Utilities Commission; Notice of Filing City of Morgan City, LA; Notice of Competing Preliminary Permit Application Accepted for Filing and Soliciting Comments and Motions To Intervene August 19, 2009. Take notice that on August 17, 2009, Orlando Utilities Commission filed Substitute First Revised Sheet 122A for inclusion in Attachment K of its Open Access Transmission Tariff, in compliance with Ordering Paragraph (F) of the Commission’s June 18, 2009 Order, 127 FERC ¶ 61,277 (2009). Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant and all the parties in this proceeding. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. PO 00000 Frm 00030 Fmt 4703 Sfmt 4703 August 20, 2009. On July 6, 2009, the City of Morgan City, Louisiana filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Wax Lake Outlet Project to be located on the Wax Lake Outlet in St. Mary Parish, Louisiana. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of: (1) 25 proposed 200 kilowatt Underwater Electric Kite generating units having a total installed capacity of 5 megawatts; (2) a 1-mile-long, 138 kilovolt transmission line; and (3) appurtenant facilities. The proposed Wax Lake Outlet Project would have an average annual generation of 43.8 gigawatt-hours. Applicant Contact: Genie Bonner, Executive Secretary, 512 First Street, Morgan City, LA 70381, (985) 385–1770. FERC Contact: Kim Carter (202) 502– 6486. Competing Application: This application competes with Project No. 13439–000 filed April 29, 2009. Competing applications must be filed on or before August 24, 2009. Deadline for filing comments, motions to intervene: 60 days from the issuance E:\FR\FM\27AUN1.SGM 27AUN1 43694 Federal Register / Vol. 74, No. 165 / Thursday, August 27, 2009 / Notices of this notice. Comments, motions to intervene, notices of intent and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paper-filed. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket number (P–13529) in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3372. Kimberly D. Bose, Secretary. [FR Doc. E9–20646 Filed 8–26–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL09–66–000] Cross Texas Transmission, LLC; Sharyland Utilities, L.P., E.ON Climate & Renewables North America Inc., Eurus Energy America Corporation, Iberdrola Renewables, Inc., Pattern Renewables LP; Notice of Petition of Declaratory Filing mstockstill on DSKH9S0YB1PROD with NOTICES August 20, 2009. Take notice that on August 7, 2009, Cross Texas LLC, Sharyland Utilities, L.P., E.ON Climate & Renewables North America Inc., Eurus Energy America Corporation, Iberdrola Renewables, Inc., and Pattern Renewables LP, filed an application for petition for declaratory order, requesting the Commission to issue a declaratory order disclaiming jurisdiction over, (1) proposed transmission lines and facilities approved by the Public Utility Commission of Texas that will deliver electric energy to the Electric Reliability Council of Texas grid from two Competitive Renewable Energy Zones (CREZs), Panhandle A and Panhandle B, located solely within the State of Texas in the Texas Panhandle (CREZ Panhandle Transmission Lines); (2) VerDate Nov<24>2008 17:19 Aug 26, 2009 Jkt 217001 transmission service over the CREZ Panhandle Transmission Lines; and (3) sales of energy over the CREZ Panhandle Transmission Lines. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on September 8, 2009. Kimberly D. Bose, Secretary. [FR Doc. E9–20651 Filed 8–26–09; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13559–000] Hydro Power 101, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications August 20, 2009. On July 22, 2009, Hydro Power 101, LLC filed an application, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Tacony Project No. 13559, to be located in the Delaware River in the City of Philadelphia, Philadelphia County, Pennsylvania. The proposed Tacony Project would be located in an area of the Delaware River just upstream of the TaconyPalmyra bridge (State Route 73) and would consist of: (1) Up to 150 20kilowatt (kW) underwater turbine generators with a total capacity of 3,000 kW attached to either pilings in the river bottom, or moored to shore structures; (2) a new 69-kilovolt, 1,200-foot-long transmission line; and (3) appurtenant facilities. The project would have an estimated annual generation between 4,000 and 5,000 megawatt-hours. Applicant Contact: Mr. Jeremy Conner, 3000 Atrium Way, Suite 261, Mt. Laurel, NJ 08054, (856) 273–5761. FERC Contact: Tom Dean, (202) 502– 6041. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘eFiling’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https:// www.ferc.gov/filing-comments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P–13559) in the docket number field to access the E:\FR\FM\27AUN1.SGM 27AUN1

Agencies

[Federal Register Volume 74, Number 165 (Thursday, August 27, 2009)]
[Notices]
[Pages 43693-43694]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-20646]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13529-000]


City of Morgan City, LA; Notice of Competing Preliminary Permit 
Application Accepted for Filing and Soliciting Comments and Motions To 
Intervene

August 20, 2009.
    On July 6, 2009, the City of Morgan City, Louisiana filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act (FPA), proposing to study the feasibility of the Wax 
Lake Outlet Project to be located on the Wax Lake Outlet in St. Mary 
Parish, Louisiana. The sole purpose of a preliminary permit, if issued, 
is to grant the permit holder priority to file a license application 
during the permit term. A preliminary permit does not authorize the 
permit holder to perform any land disturbing activities or otherwise 
enter upon lands or waters owned by others without the owners' express 
permission.
    The proposed project would consist of: (1) 25 proposed 200 kilowatt 
Underwater Electric Kite generating units having a total installed 
capacity of 5 megawatts; (2) a 1-mile-long, 138 kilovolt transmission 
line; and (3) appurtenant facilities. The proposed Wax Lake Outlet 
Project would have an average annual generation of 43.8 gigawatt-hours.
    Applicant Contact: Genie Bonner, Executive Secretary, 512 First 
Street, Morgan City, LA 70381, (985) 385-1770.
    FERC Contact: Kim Carter (202) 502-6486.
    Competing Application: This application competes with Project No. 
13439-000 filed April 29, 2009. Competing applications must be filed on 
or before August 24, 2009.
    Deadline for filing comments, motions to intervene: 60 days from 
the issuance

[[Page 43694]]

of this notice. Comments, motions to intervene, notices of intent and 
competing applications may be filed electronically via the Internet. 
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
Web site under the ``e-Filing'' link. If unable to be filed 
electronically, documents may be paper-filed. To paper-file, an 
original and eight copies should be mailed to: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426. For more information on how to submit these types 
of filings please go to the Commission's Web site located at https://www.ferc.gov/filing-comments.asp. More information about this project, 
including a copy of the application, can be viewed or printed on the 
``eLibrary'' link of the Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P-13529) in the 
docket number field to access the document. For assistance, call toll-
free 1-866-208-3372.

Kimberly D. Bose,
Secretary.
[FR Doc. E9-20646 Filed 8-26-09; 8:45 am]
BILLING CODE 6717-01-P