Clean River Power MR-2, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 41414-41415 [E9-19606]

Download as PDF 41414 Federal Register / Vol. 74, No. 157 / Monday, August 17, 2009 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13409–000] Julian Griggs Dam Water Power Project, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13409) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. E9–19608 Filed 8–14–09; 8:45 am] BILLING CODE P mstockstill on DSKH9S0YB1PROD with NOTICES August 6, 2009. On March 25, 2009, Julian Griggs Dam Water Power Project, LLC filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Julian Griggs Water Power Project, to be located at the City of Columbus’s Julian Griggs dam on the Scioto River in Franklin County, Ohio. The proposed Julian Griggs Project would consist of: (1) The existing 67.5foot-high, 983-foot-long concrete dam; (2) the existing 385-acre reservoir with a 4,322 acre-foot storage capacity; (3) a new 70-foot-long intake structure; (4) two new 70-foot-long, 120-inchdiameter penstocks; (5) a new powerhouse containing two proposed generating units with a total installed capacity of 4.0 megawatts; (6) a new 100-foot-long tailrace; (7) a new switchyard containing a single threephase step-up transformer; and (8) a new 1,100-foot-long, 34.5-kilovolt overhead transmission line. The project would have an estimated average annual generation of 12,000 megawatt-hours. Applicant Contact: Mr. Alan Skelly, 8425 Beechmont Avenue, Cincinnati, OH 45255, phone (513) 375–9242. FERC Contact: Michael Spencer, (202) 502–6093. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on VerDate Nov<24>2008 17:55 Aug 14, 2009 Jkt 217001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13408–000] Clean River Power MR–7, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https:// www.ferc.gov/filing-comments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13408) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. E9–19607 Filed 8–14–09; 8:45 am] BILLING CODE P August 6, 2009. On March 25, 2009, Clean River Power MR–7, LLC filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Philo Lock and Dam Water Power Project, to be located at the State of Ohio’s Philo lock and dam on the Muskingum River in Muskingum County, Ohio. The proposed Philo Lock and Dam Project would consist of: (1) The existing 18.1-foot-high, 730-foot-long concrete dam; (2) the existing 533-acre reservoir with a 3,120 acre-foot storage capacity; (3) a new 150-foot-long, 125foot-wide intake structure; (4) a 125foot-long, 125-foot-wide power canal; (5) a new powerhouse containing five proposed generating units with a total installed capacity of 2.8 megawatts; (6) a new 175-foot-long tailrace; (7) a new switchyard containing a single threephase step-up transformer; and (8) a new 200-foot-long, 34.5-kilovolt overhead transmission line. The project would have an estimated average annual generation of 11,100 megawatt-hours. Applicant Contact: Mr. Alan Skelly, 8425 Beechmont Avenue, Cincinnati, OH 45255, phone (513) 375–9242. FERC Contact: Michael Spencer, (202) 502–6093. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions PO 00000 Frm 00049 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13407–000] Clean River Power MR–2, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications August 6, 2009. On March 25, 2009, Clean River Power MR–2, LLC filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Lowell Lock and Dam Water Power Project, to be located at the State of Ohio’s Lowell lock and dam on the Muskingum River in Washington County, Ohio. The proposed Lowell Lock and Dam Project would consist of: (1) The existing 17.5-foot-high, 840-foot-long concrete dam; (2) the existing 628-acre reservoir with a 4,492 acre-foot storage capacity; (3) a new 180-foot-long, 100foot-wide intake structure; (4) a 150foot-long, 100-foot-wide power canal; (5) a new powerhouse containing three proposed generating units with a total installed capacity of 4.8 megawatts; (6) a new 250-foot-long tailrace; (7) a new switchyard containing a single threephase step-up transformer; and (8) a new 2,000-foot-long, 34.5-kilovolt overhead transmission line. The project would have an estimated average annual generation of 19,300 megawatt-hours. E:\FR\FM\17AUN1.SGM 17AUN1 Federal Register / Vol. 74, No. 157 / Monday, August 17, 2009 / Notices Applicant Contact: Mr. Alan Skelly, 8425 Beechmont Avenue, Cincinnati, OH 45255, phone (513) 375–9242. FERC Contact: Michael Spencer, (202) 502–6093. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https:// www.ferc.gov/filing-comments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P–13407) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. E9–19606 Filed 8–14–09; 8:45 am] BILLING CODE P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13406–000] Clean River Power MR–5, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications mstockstill on DSKH9S0YB1PROD with NOTICES August 6, 2009. On March 25, 2009, Clean River Power MR–5, LLC filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Malta Lock and Dam Water Power Project, to be located at the State of Ohio’s Malta lock and dam on the Muskingum River in Morgan County, Ohio. The proposed Malta Lock and Dam Project would consist of: (1) The existing 15.2-foot-high, 472-foot-long concrete dam; (2) the existing 442-acre reservoir with a 3,000 acre-foot storage VerDate Nov<24>2008 17:55 Aug 14, 2009 Jkt 217001 capacity; (3) a new 150-foot-long, 120foot-wide intake structure; (4) a 200foot-long, 120-foot-wide power canal; (5) a new powerhouse containing three proposed generating units with a total installed capacity of 3.9 megawatts; (6) a new 200-foot-long tailrace; (7) a new switchyard containing a single threephase step-up transformer; and (8) a new 1,200-foot-long, 34.5-kilovolt overhead transmission line. The project would have an estimated average annual generation of 15,800 megawatt-hours. Applicant Contact: Mr. Alan Skelly, 8425 Beechmont Avenue, Cincinnati, OH 45255, phone (513) 375–9242. FERC Contact: Michael Spencer, (202) 502–6093. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https:// www.ferc.gov/filing-comments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13406) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. E9–19605 Filed 8–14–09; 8:45 am] BILLING CODE P PO 00000 Frm 00050 Fmt 4703 Sfmt 4703 41415 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13405–000] Clean River Power MR–1, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications August 6, 2009. On March 25, 2009, Clean River Power MR–1, LLC filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Devola Lock and Dam Water Power Project, to be located at the State of Ohio’s Devola lock and dam on the Muskingum River in Washington County, Ohio. The proposed Devola Lock and Dam Project would consist of: (1) The existing 17.5-foot-high, 587-foot-long concrete dam; (2) the existing 301-acre reservoir with a 3,024 acre-foot storage capacity; (3) a new 175-foot-long, 120foot-wide intake structure; (4) a 120foot-long, 120-foot-wide power canal; (5) a new powerhouse containing three proposed generating units with a total installed capacity of 4.3 megawatts; (6) a new 250-foot-long tailrace; (7) a new switchyard containing a single threephase step-up transformer; and (8) a new 4,000-foot-long, 34.5-kilovolt overhead transmission line. The project would have an estimated average annual generation of 17,300 megawatt-hours. Applicant Contact: Mr. Alan Skelly, 8425 Beechmont Avenue, Cincinnati, OH 45255, phone (513) 375–9242. FERC Contact: Michael Spencer, (202) 502–6093. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on E:\FR\FM\17AUN1.SGM 17AUN1

Agencies

[Federal Register Volume 74, Number 157 (Monday, August 17, 2009)]
[Notices]
[Pages 41414-41415]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-19606]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13407-000]


Clean River Power MR-2, LLC; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

August 6, 2009.
    On March 25, 2009, Clean River Power MR-2, LLC filed an 
application, pursuant to section 4(f) of the Federal Power Act, 
proposing to study the feasibility of the Lowell Lock and Dam Water 
Power Project, to be located at the State of Ohio's Lowell lock and dam 
on the Muskingum River in Washington County, Ohio.
    The proposed Lowell Lock and Dam Project would consist of: (1) The 
existing 17.5-foot-high, 840-foot-long concrete dam; (2) the existing 
628-acre reservoir with a 4,492 acre-foot storage capacity; (3) a new 
180-foot-long, 100-foot-wide intake structure; (4) a 150-foot-long, 
100-foot-wide power canal; (5) a new powerhouse containing three 
proposed generating units with a total installed capacity of 4.8 
megawatts; (6) a new 250-foot-long tailrace; (7) a new switchyard 
containing a single three-phase step-up transformer; and (8) a new 
2,000-foot-long, 34.5-kilovolt overhead transmission line. The project 
would have an estimated average annual generation of 19,300 megawatt-
hours.

[[Page 41415]]

    Applicant Contact: Mr. Alan Skelly, 8425 Beechmont Avenue, 
Cincinnati, OH 45255, phone (513) 375-9242.
    FERC Contact: Michael Spencer, (202) 502-6093.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Comments, motions to intervene, notices of intent, and competing 
applications may be filed electronically via the Internet. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original and eight 
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For 
more information on how to submit these types of filings please go to 
the Commission's Web site located at https://www.ferc.gov/filing-comments.asp. More information about this project can be viewed or 
printed on the ``eLibrary'' link of Commission's Web site at 
http:[sol][sol]www.ferc.gov/docs-filing/elibrary.asp. Enter the docket 
number (P-13407) in the docket number field to access the document. For 
assistance, call toll-free 1-866-208-3372.

Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. E9-19606 Filed 8-14-09; 8:45 am]
BILLING CODE P