Mahoning Creek Hydroelectric Company, LLC; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 40175 [E9-19136]
Download as PDF
40175
Federal Register / Vol. 74, No. 153 / Tuesday, August 11, 2009 / Notices
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the Florida State
Historic Preservation Officer (SHPO), as
required by § 106, National Historic
Preservation Act, and the regulations of
the Advisory Council on Historic
Preservation, 36 CFR, at § 800.4.
q. Procedural schedule: The
application will be processed according
to the following Hydro Licensing
Schedule. Revisions to the schedule will
be made as appropriate.
Issue Deficiency Letter: September 2009.
Issue Acceptance Notice and Letter:
December 2009.
Issue Scoping Document 1 for
comments: January 2010.
Request Additional Information: March
2010.
Issue Scoping Document 2: March 2010.
Notice of application is ready for
environmental analysis: March 2010.
Notice of the availability of the EA: July
2010.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. E9–19137 Filed 8–10–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12555–004]
Mahoning Creek Hydroelectric
Company, LLC; Notice of Application
Tendered for Filing With the
Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
sroberts on DSKD5P82C1PROD with NOTICES
August 4, 2009.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: 12555–004.
c. Date Filed: July 27, 2009.
d. Applicant: Mahoning Creek
Hydroelectric Company, LLC.
VerDate Nov<24>2008
20:51 Aug 10, 2009
Jkt 217001
e. Name of Project: Mahoning Creek
Hydroelectric Project.
f. Location: On Mahoning Creek in
Armstrong County, Pennsylvania. The
proposed project would occupy Federal
land managed by the U.S. Army Corps
of Engineers.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: M. Clifford
Phillips, Vice President, Mahoning
Creek Hydroelectric Company, LLC, 150
North Miller Road, Suite 450 C,
Fairlawn, OH 44333, (330) 869–8451.
i. FERC Contact: Thomas Dean, (202)
502–6041.
j. This application is not ready for
environmental analysis at this time.
k. The proposed Mahoning Creek
Project would use the U.S. Army Corps
of Engineers’ (Corps) Mahoning Creek
dam and would consist of: (1) A new 50foot-high intake structure attached to
the upstream face of the dam, equipped
with removable trashracks, dewatering
bulkhead panels, and a vertical slide
gate; (2) a new lining on the existing
(currently plugged), 108-inch-diameter
conduit through dam monolith 15; (3) a
new 1,090-foot-long, 120-inch-diameter
penstock on the left (south) bank,
bifurcating into two new 110-foot-long,
96-inch-diameter penstocks; (4) a new
powerhouse located approximately 100
feet downstream of an existing stilling
basin weir containing two new Kaplan
turbine/generator units with a total
installed capacity of 6.0 MW; (5) a new
40-foot-wide, 150-foot-long, 10-footdeep tailrace; (6) a new 2.2-mile-long,
25-kilovolt transmission line; (7) a new
100-foot-long bridge to span a small
stream to the entrance of a refurbished
0.5-mile-long access road; and (8)
appurtenant facilities. The project
would have an estimated annual
generation of 20,000 megawatt-hours.
The project would operate using flows
released by the Corps in accordance
with the current dam operation as set by
the Corps.
l. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via e-
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
mail of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following Hydro Licensing
Schedule. The Commission staff
proposes to issue a single
Environmental Assessment (EA) rather
than issuing a draft and final EA. The
schedule allows 30 days for entities to
comment on the EA, and 60 days for
agencies to file modified mandatory
terms and conditions. Staff will take
into consideration all comments and
terms and conditions received on the
EA before final action is taken on the
license application. Revisions to the
schedule may be made as appropriate.
Milestone
Notice of Acceptance and
Ready for Environmental
Analysis.
Filing interventions, comments,
recommendations, preliminary terms and conditions,
and fishway prescriptions.
Notice of availability of the EA
Filing comments on EA ...........
Filing modified terms and conditions.
Target date
September
25, 2009.
November
24, 2009.
March 24,
2010.
April 23,
2010.
June 22,
2010.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. E9–19136 Filed 8–10–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings # 1
August 4, 2009.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER98–511–013;
ER97–4345–025.
Applicants: Oklahoma Gas and
Electric Company, OGE Energy
Resources, Inc.
Description: Oklahoma Gas and
Electric company et al submit an
updated market power analysis.
Filed Date: 07/31/2009.
Accession Number: 20090803–0063.
E:\FR\FM\11AUN1.SGM
11AUN1
Agencies
[Federal Register Volume 74, Number 153 (Tuesday, August 11, 2009)]
[Notices]
[Page 40175]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-19136]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12555-004]
Mahoning Creek Hydroelectric Company, LLC; Notice of Application
Tendered for Filing With the Commission and Establishing Procedural
Schedule for Licensing and Deadline for Submission of Final Amendments
August 4, 2009.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: 12555-004.
c. Date Filed: July 27, 2009.
d. Applicant: Mahoning Creek Hydroelectric Company, LLC.
e. Name of Project: Mahoning Creek Hydroelectric Project.
f. Location: On Mahoning Creek in Armstrong County, Pennsylvania.
The proposed project would occupy Federal land managed by the U.S. Army
Corps of Engineers.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: M. Clifford Phillips, Vice President,
Mahoning Creek Hydroelectric Company, LLC, 150 North Miller Road, Suite
450 C, Fairlawn, OH 44333, (330) 869-8451.
i. FERC Contact: Thomas Dean, (202) 502-6041.
j. This application is not ready for environmental analysis at this
time.
k. The proposed Mahoning Creek Project would use the U.S. Army
Corps of Engineers' (Corps) Mahoning Creek dam and would consist of:
(1) A new 50-foot-high intake structure attached to the upstream face
of the dam, equipped with removable trashracks, dewatering bulkhead
panels, and a vertical slide gate; (2) a new lining on the existing
(currently plugged), 108-inch-diameter conduit through dam monolith 15;
(3) a new 1,090-foot-long, 120-inch-diameter penstock on the left
(south) bank, bifurcating into two new 110-foot-long, 96-inch-diameter
penstocks; (4) a new powerhouse located approximately 100 feet
downstream of an existing stilling basin weir containing two new Kaplan
turbine/generator units with a total installed capacity of 6.0 MW; (5)
a new 40-foot-wide, 150-foot-long, 10-foot-deep tailrace; (6) a new
2.2-mile-long, 25-kilovolt transmission line; (7) a new 100-foot-long
bridge to span a small stream to the entrance of a refurbished 0.5-
mile-long access road; and (8) appurtenant facilities. The project
would have an estimated annual generation of 20,000 megawatt-hours.
The project would operate using flows released by the Corps in
accordance with the current dam operation as set by the Corps.
l. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
m. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Procedural Schedule: The application will be processed according
to the following Hydro Licensing Schedule. The Commission staff
proposes to issue a single Environmental Assessment (EA) rather than
issuing a draft and final EA. The schedule allows 30 days for entities
to comment on the EA, and 60 days for agencies to file modified
mandatory terms and conditions. Staff will take into consideration all
comments and terms and conditions received on the EA before final
action is taken on the license application. Revisions to the schedule
may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Notice of Acceptance and Ready for September 25, 2009.
Environmental Analysis.
Filing interventions, comments, November 24, 2009.
recommendations, preliminary terms and
conditions, and fishway prescriptions.
Notice of availability of the EA.......... March 24, 2010.
Filing comments on EA..................... April 23, 2010.
Filing modified terms and conditions...... June 22, 2010.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. E9-19136 Filed 8-10-09; 8:45 am]