[Project No. 13497–000]
FFP Project 66, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
mstockstill on DSKH9S0YB1PROD with NOTICES
July 10, 2009.
On May 22, 2009, FFP Project 66, LLC
filed an application for a preliminary
permit, pursuant to section 4(f) of the
Federal Power Act, proposing to study
the feasibility of the Saint Catherine
Bend Hydrokinetic Project, to be located
on the Mississippi River, in Concordia
Parish, Louisiana and Adams County,
Mississippi.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any land
disturbing activities or otherwise enter
upon lands or waters owned by others
without the owners’ express permission.
The proposed Saint Catherine Bend
Hydrokinetic Project consists of: (1)
4,752 proposed 40 kilowatt Free Flow
generating units having a total installed
capacity of 190.08 megawatts; (2) a 6.5mile-long, 69 kilovolt transmission line;
and (3) appurtenant facilities. The
proposed Saint Catherine Bend
Hydrokinetic Project would have an
average annual generation of 833
gigawatt-hours.
Applicant Contact: Ramya
Swaminathan, Vice President of
Development, Free Flow Power
Corporation, 33 Commercial Street,
Gloucester, MA 01930; phone: (978)
226–1531.
FERC Contact: Kim Carter, 202–502–
6486.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and eight
copies should be mailed to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. For
more information on how to submit
VerDate Nov<24>2008
19:20 Jul 16, 2009
Jkt 217001
these types of filings, please go to the
Commission’s Web site located at
https://www.ferc.gov/filingcomments.asp. More information about
this project, including a copy of the
application, can be viewed or printed on
the ‘‘eLibrary’’ link of Commission’s
Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13497) in the docket number field to
access the document. For assistance,
call toll-free 1–866–208–3372.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–16989 Filed 7–16–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13495–000]
FFP Project 85, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
July 10, 2009.
On May 22, 2009, FFP Project 85, LLC
filed an application for a preliminary
permit, pursuant to section 4(f) of the
Federal Power Act, proposing to study
the feasibility of the Missouri Sister
Island Hydrokinetic Project, to be
located on the Mississippi River, in
Mississippi County, Missouri and
Alexander County, Illinois.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any land
disturbing activities or otherwise enter
upon lands or waters owned by others
without the owners’ express permission.
The proposed Missouri Sister Island
Hydrokinetic Project consists of: (1) 4,
118 proposed 40 kilowatt Free Flow
generating units having a total installed
capacity of 164.72 megawatts; (2) a 5.5mile-long, 69 kilovolt transmission line;
and (3) appurtenant facilities. The
proposed Missouri Sister Island
Hydrokinetic Project would have an
average annual generation of 721
gigawatt-hours.
Applicant Contact: Ramya
Swaminathan, Vice President of
Development, Free Flow Power
Corporation, 33 Commercial Street,
Gloucester, MA 01930; phone: (978)
226–1531.
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
FERC Contact: Kim Carter, 202–502–
6486.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and eight
copies should be mailed to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. For
more information on how to submit
these types of filings please go to the
Commission’s Web site located at
https://www.ferc.gov/filingcomments.asp. More information about
this project, including a copy of the
application, can be viewed or printed on
the ‘‘eLibrary’’ link of Commission’s
Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13495) in the docket number field to
access the document. For assistance,
call toll-free 1–866–208–3372.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–16988 Filed 7–16–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13494–000]
FFP Project 84, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
July 10, 2009.
On May 22, 2009, FFP Project 84, LLC
filed an application for a preliminary
permit, pursuant to section 4(f) of the
Federal Power Act, proposing to study
the feasibility of the Twin Pond
Hydrokinetic Project, to be located on
the Mississippi River, in Mississippi
County, Missouri and Carlisle County,
Kentucky.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any land
E:\FR\FM\17JYN1.SGM
17JYN1
Agencies
[Federal Register Volume 74, Number 136 (Friday, July 17, 2009)]
[Notices]
[Page 34748]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-16989]
[[Page 34748]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13497-000]
FFP Project 66, LLC; Notice of Preliminary Permit Application
Accepted for Filing and Soliciting Comments, Motions To Intervene, and
Competing Applications
July 10, 2009.
On May 22, 2009, FFP Project 66, LLC filed an application for a
preliminary permit, pursuant to section 4(f) of the Federal Power Act,
proposing to study the feasibility of the Saint Catherine Bend
Hydrokinetic Project, to be located on the Mississippi River, in
Concordia Parish, Louisiana and Adams County, Mississippi.
The sole purpose of a preliminary permit, if issued, is to grant
the permit holder priority to file a license application during the
permit term. A preliminary permit does not authorize the permit holder
to perform any land disturbing activities or otherwise enter upon lands
or waters owned by others without the owners' express permission.
The proposed Saint Catherine Bend Hydrokinetic Project consists of:
(1) 4,752 proposed 40 kilowatt Free Flow generating units having a
total installed capacity of 190.08 megawatts; (2) a 6.5-mile-long, 69
kilovolt transmission line; and (3) appurtenant facilities. The
proposed Saint Catherine Bend Hydrokinetic Project would have an
average annual generation of 833 gigawatt-hours.
Applicant Contact: Ramya Swaminathan, Vice President of
Development, Free Flow Power Corporation, 33 Commercial Street,
Gloucester, MA 01930; phone: (978) 226-1531.
FERC Contact: Kim Carter, 202-502-6486.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Comments, motions to intervene, notices of intent, and competing
applications may be filed electronically via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. If unable to be filed electronically,
documents may be paper-filed. To paper-file, an original and eight
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For
more information on how to submit these types of filings, please go to
the Commission's Web site located at https://www.ferc.gov/filing-comments.asp. More information about this project, including a copy of
the application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-13497) in the docket number field to access
the document. For assistance, call toll-free 1-866-208-3372.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-16989 Filed 7-16-09; 8:45 am]
BILLING CODE 6717-01-P