FFP Project 83, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 34749 [E9-16986]

Download as PDF Federal Register / Vol. 74, No. 136 / Friday, July 17, 2009 / Notices disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Twin Pond Hydrokinetic Project consists of: (1) 1, 901 proposed 40-kilowatt Free Flow generating units having a total installed capacity of 76.04 megawatts; (2) a 2mile-long, 69-kilovolt transmission line; and (3) appurtenant facilities. The proposed Twin Pond Hydrokinetic Project would have an average annual generation of 333 gigawatt-hours. Applicant Contact: Ramya Swaminathan, Vice President of Development, Free Flow Power Corporation, 33 Commercial Street, Gloucester, MA 01930; phone: 978–226– 1531. FERC Contact: Kim Carter, 202–502– 6486. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13494) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. mstockstill on DSKH9S0YB1PROD with NOTICES Kimberly D. Bose, Secretary. [FR Doc. E9–16987 Filed 7–16–09; 8:45 am] BILLING CODE 6717–01–P VerDate Nov<24>2008 19:20 Jul 16, 2009 Jkt 217001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13493–000] FFP Project 83, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications July 10, 2009. On May 22, 2009, FFP Project 83, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Slough Bend Hydrokinetic Project, to be located on the Mississippi River, in Lake County, Tennessee; New Madrid County, Missouri; and Fulton County, Kentucky. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Slough Bend Hydrokinetic Project consists of: (1) 6,019 proposed 40-kilowatt Free Flow generating units having a total installed capacity of 240.76 megawatts; (2) a 8.5mile-long, 69-kilovolt transmission line; and (3) appurtenant facilities. The proposed Slough Bend Hydrokinetic Project would have an average annual generation of 1,054 gigawatt-hours. Applicant Contact: Ramya Swaminathan, Vice President of Development, Free Flow Power Corporation, 33 Commercial Street, Gloucester, MA 01930; phone: 978–226– 1531. FERC Contact: Kim Carter, 202–502– 6486. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the PO 00000 Frm 00040 Fmt 4703 Sfmt 4703 34749 Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13493) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Kimberly D. Bose, Secretary. [FR Doc. E9–16986 Filed 7–16–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13492–000] FFP Project 82, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications July 10, 2009. On May 22, 2009, FFP Project 82, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Little Cypress Bend Hydrokinetic Project, to be located on the Mississippi River, in Pemiscot County, Missouri and Lake County, Tennessee. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Little Cypress Bend Hydrokinetic Project consists of: (1) 3,168 proposed 40-kilowatt Free Flow generating units having a total installed capacity of 126.72 megawatts; (2) a 4mile-long, 69-kilovolt transmission line; and (3) appurtenant facilities. The proposed Little Cypress Bend Hydrokinetic Project would have an average annual generation of 555 gigawatt-hours. Applicant Contact: Ramya Swaminathan, Vice President of Development, Free Flow Power Corporation, 33 Commercial Street, Gloucester, MA 01930; phone: 978–226– 1531. FERC Contact: Kim Carter, 202–502– 6486. E:\FR\FM\17JYN1.SGM 17JYN1

Agencies

[Federal Register Volume 74, Number 136 (Friday, July 17, 2009)]
[Notices]
[Page 34749]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-16986]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13493-000]


FFP Project 83, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

July 10, 2009.
    On May 22, 2009, FFP Project 83, LLC filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act, 
proposing to study the feasibility of the Slough Bend Hydrokinetic 
Project, to be located on the Mississippi River, in Lake County, 
Tennessee; New Madrid County, Missouri; and Fulton County, Kentucky.
    The sole purpose of a preliminary permit, if issued, is to grant 
the permit holder priority to file a license application during the 
permit term. A preliminary permit does not authorize the permit holder 
to perform any land disturbing activities or otherwise enter upon lands 
or waters owned by others without the owners' express permission.
    The proposed Slough Bend Hydrokinetic Project consists of: (1) 
6,019 proposed 40-kilowatt Free Flow generating units having a total 
installed capacity of 240.76 megawatts; (2) a 8.5-mile-long, 69-
kilovolt transmission line; and (3) appurtenant facilities. The 
proposed Slough Bend Hydrokinetic Project would have an average annual 
generation of 1,054 gigawatt-hours.
    Applicant Contact: Ramya Swaminathan, Vice President of 
Development, Free Flow Power Corporation, 33 Commercial Street, 
Gloucester, MA 01930; phone: 978-226-1531.
    FERC Contact: Kim Carter, 202-502-6486.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Comments, motions to intervene, notices of intent, and competing 
applications may be filed electronically via the Internet. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original and eight 
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For 
more information on how to submit these types of filings please go to 
the Commission's Web site located at https://www.ferc.gov/filing-comments.asp. More information about this project, including a copy of 
the application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-13493) in the docket number field to access 
the document. For assistance, call toll-free 1-866-208-3372.

Kimberly D. Bose,
Secretary.
[FR Doc. E9-16986 Filed 7-16-09; 8:45 am]
BILLING CODE 6717-01-P