Download as PDF Federal Register / Vol. 74, No. 136 / Friday, July 17, 2009 / Notices clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed dockets(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Kimberly D. Bose, Secretary. [FR Doc. E9–16975 Filed 7–16–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13489–000] FFP Project 79, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications mstockstill on DSKH9S0YB1PROD with NOTICES July 10, 2009. On May 22, 2009, FFP Project 79, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Barfield Point Hydrokinetic Project, to be located on the Mississippi River, in Mississippi County, Arkansas and Lauderdale County, Tennessee. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Barfield Point Hydrokinetic Project consists of: (1) 2,851 proposed 40 kilowatt Free Flow generating units having a total installed capacity of 114.04 megawatts; (2) a 3.5mile-long, 69 kilovolt transmission line; and (3) appurtenant facilities. The proposed Barfield Point Hydrokinetic Project would have an average annual generation of 500 gigawatt-hours. Applicant Contact: Ramya Swaminathan, Vice President of Development, Free Flow Power Corporation, 33 Commercial Street, Gloucester, MA 01930; phone: (978) 226–1531. FERC Contact: Kim Carter, 202–502– 6486. VerDate Nov<24>2008 19:20 Jul 16, 2009 Jkt 217001 Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13489) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Kimberly D. Bose, Secretary. [FR Doc. E9–16982 Filed 7–16–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13491–000] FFP Project 81, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications July 10, 2009. On May 22, 2009, FFP Project 81, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Island 14 Bend Hydrokinetic Project, to be located on the Mississippi River, in Pemiscot County, Missouri and Lake County, Tennessee. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter PO 00000 Frm 00038 Fmt 4703 Sfmt 4703 34747 upon lands or waters owned by others without the owners’ express permission. The proposed Island 14 Bend Hydrokinetic Project consists of: (1) 3,295 proposed 40 kilowatt Free Flow generating units having a total installed capacity of 131.80 megawatts; (2) a 4.2mile-long, 69 kilovolt transmission line; and (3) appurtenant facilities. The proposed Island 14 Bend Hydrokinetic Project would have an average annual generation of 577 gigawatt-hours. Applicant Contact: Ramya Swaminathan, Vice President of Development, Free Flow Power Corporation, 33 Commercial Street, Gloucester, MA 01930; phone: (978) 226–1531. FERC Contact: Kim Carter, 202–502– 6486. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13491) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Kimberly D. Bose, Secretary. [FR Doc. E9–16984 Filed 7–16–09; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\17JYN1.SGM 17JYN1

Agencies

[Federal Register Volume 74, Number 136 (Friday, July 17, 2009)]
[Notices]
[Page 34747]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-16984]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13491-000]


FFP Project 81, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

July 10, 2009.

    On May 22, 2009, FFP Project 81, LLC filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act, 
proposing to study the feasibility of the Island 14 Bend Hydrokinetic 
Project, to be located on the Mississippi River, in Pemiscot County, 
Missouri and Lake County, Tennessee.
    The sole purpose of a preliminary permit, if issued, is to grant 
the permit holder priority to file a license application during the 
permit term. A preliminary permit does not authorize the permit holder 
to perform any land disturbing activities or otherwise enter upon lands 
or waters owned by others without the owners' express permission.
    The proposed Island 14 Bend Hydrokinetic Project consists of: (1) 
3,295 proposed 40 kilowatt Free Flow generating units having a total 
installed capacity of 131.80 megawatts; (2) a 4.2-mile-long, 69 
kilovolt transmission line; and (3) appurtenant facilities. The 
proposed Island 14 Bend Hydrokinetic Project would have an average 
annual generation of 577 gigawatt-hours.
    Applicant Contact: Ramya Swaminathan, Vice President of 
Development, Free Flow Power Corporation, 33 Commercial Street, 
Gloucester, MA 01930; phone: (978) 226-1531.
    FERC Contact: Kim Carter, 202-502-6486.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Comments, motions to intervene, notices of intent, and competing 
applications may be filed electronically via the Internet. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original and eight 
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For 
more information on how to submit these types of filings please go to 
the Commission's Web site located at https://www.ferc.gov/filing-comments.asp. More information about this project, including a copy of 
the application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-13491) in the docket number field to access 
the document. For assistance, call toll-free 1-866-208-3372.

Kimberly D. Bose,
Secretary.
[FR Doc. E9-16984 Filed 7-16-09; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.