FFP Project 70, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 34321 [E9-16727]

Download as PDF Federal Register / Vol. 74, No. 134 / Wednesday, July 15, 2009 / Notices Project would have an average annual generation of 888 gigawatt-hours. Applicant Contact: Ramya Swaminathan, Vice President of Development, Free Flow Power Corporation, 33 Commercial Street, Gloucester, MA 01930; phone: (978) 226–1531. FERC Contact: Kim Carter, (202) 502– 6486. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13475) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Kimberly D. Bose, Secretary. [FR Doc. E9–16721 Filed 7–14–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13481–000] sroberts on DSKD5P82C1PROD with NOTICES FFP Project 70, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications July 8, 2009. On May 22, 2009, FFP Project 70, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Filter Bend Hydrokinetic Project, to be located on the Mississippi River, in East Carroll VerDate Nov<24>2008 17:21 Jul 14, 2009 Jkt 217001 Parish, Louisiana and Issaquena County, Mississippi. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters owned by others without the owners’’ express permission. The proposed Filter Bend Hydrokinetic Project consists of: (1) 3,802 proposed 40 kilowatt Free Flow generating units having a total installed capacity of 152.08 megawatts; (2) a 5mile-long, 69 kilovolt transmission line; and (3) appurtenant facilities. The proposed Filter Bend Hydrokinetic Project would have an average annual generation of 666 gigawatt-hours. Applicant Contact: Ramya Swaminathan, Vice President of Development, Free Flow Power Corporation, 33 Commercial Street, Gloucester, MA 01930; phone: (978) 226–1531. FERC Contact: Kim Carter, 202–502– 6486. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s website under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13481) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. Kimberly D. Bose, Secretary. [FR Doc. E9–16727 Filed 7–14–09; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 34321 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13480–000] FFP Project 69, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications July 8, 2009. On May 22, 2009, FFP Project 69, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Breeze Point Hydrokinetic Project, to be located on the Mississippi River, in Concordia Parish, Louisiana and Wilkinson County, Mississippi. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Breeze Point Hydrokinetic Project consists of: (1) 4,942 proposed 40 kilowatt Free Flow generating units having a total installed capacity of 197.68 megawatts; (2) a 6.8mile-long, 69 kilovolt transmission line; and (3) appurtenant facilities. The proposed Breeze Point Hydrokinetic Project would have an average annual generation of 866 gigawatt-hours. Applicant Contact: Ramya Swaminathan, Vice President of Development, Free Flow Power Corporation, 33 Commercial Street, Gloucester, MA 01930; phone: (978) 226–1531. FERC Contact: Kim Carter, 202–502– 6486. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the E:\FR\FM\15JYN1.SGM 15JYN1

Agencies

[Federal Register Volume 74, Number 134 (Wednesday, July 15, 2009)]
[Notices]
[Page 34321]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-16727]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13481-000]


FFP Project 70, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

July 8, 2009.
    On May 22, 2009, FFP Project 70, LLC filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act, 
proposing to study the feasibility of the Filter Bend Hydrokinetic 
Project, to be located on the Mississippi River, in East Carroll 
Parish, Louisiana and Issaquena County, Mississippi.
    The sole purpose of a preliminary permit, if issued, is to grant 
the permit holder priority to file a license application during the 
permit term. A preliminary permit does not authorize the permit holder 
to perform any land disturbing activities or otherwise enter upon lands 
or waters owned by others without the owners'' express permission.
    The proposed Filter Bend Hydrokinetic Project consists of: (1) 
3,802 proposed 40 kilowatt Free Flow generating units having a total 
installed capacity of 152.08 megawatts; (2) a 5-mile-long, 69 kilovolt 
transmission line; and (3) appurtenant facilities. The proposed Filter 
Bend Hydrokinetic Project would have an average annual generation of 
666 gigawatt-hours.
    Applicant Contact: Ramya Swaminathan, Vice President of 
Development, Free Flow Power Corporation, 33 Commercial Street, 
Gloucester, MA 01930; phone: (978) 226-1531.
    FERC Contact: Kim Carter, 202-502-6486.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Comments, motions to intervene, notices of intent, and competing 
applications may be filed electronically via the Internet. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's website 
under the ``e-Filing'' link. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original and eight 
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For 
more information on how to submit these types of filings please go to 
the Commission's Web site located at https://www.ferc.gov/filing-comments.asp. More information about this project, including a copy of 
the application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-13481) in the docket number field to access 
the document. For assistance, call toll-free 1-866-208-3372.

Kimberly D. Bose,
Secretary.
 [FR Doc. E9-16727 Filed 7-14-09; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.