Federal Acquisition Regulation; FAR Case 2005-032, Contractor's Request for Progress Payments, 28430-28434 [E9-13977]
Download as PDF
28430
Federal Register / Vol. 74, No. 113 / Monday, June 15, 2009 / Rules and Regulations
use of equivalent domestic or designated
country construction material other than
Bahrainian, Mexican, or Omani construction
material.
*
*
*
*
*
[FR Doc. E9–13978 Filed 6–12–09; 8:45 am]
BILLING CODE 6820–EP–S
DEPARTMENT OF DEFENSE
GENERAL SERVICES
ADMINISTRATION
NATIONAL AERONAUTICS AND
SPACE ADMINISTRATION
48 CFR Parts 32, 43, 52, and 53
[FAC 2005–33; FAR Case 2005–032; Item
II; Docket 2008–0002; Sequence 1]
RIN 9000–AI47
Federal Acquisition Regulation; FAR
Case 2005–032, Contractor’s Request
for Progress Payments
AGENCIES: Department of Defense (DoD),
General Services Administration (GSA),
and National Aeronautics and Space
Administration (NASA).
ACTION: Final rule.
pwalker on PROD1PC71 with RULES4
SUMMARY: The Civilian Agency
Acquisition Council and the Defense
Acquisition Regulations Council
(Councils) have agreed on a final rule
amending the Federal Acquisition
Regulation (FAR) to incorporate
improvements related to requests for
progress payments and the Standard
Form (SF) 1443, Contractor’s Request for
Progress Payments, used to request
those progress payments. Changes made
to the Standard Form as published in
the proposed rule include correction of
misspellings, and an editorial change
made at Item 4 to better describe the
order number.
DATES: Effective Date: July 15, 2009.
FOR FURTHER INFORMATION CONTACT: For
clarification of content, contact Ms.
Meredith Murphy, Procurement
Analyst, at (202) 208–6925. For
information pertaining to status or
publication schedules, contact the
Regulatory Secretariat, 1800 F Street,
NW, Room 4041, Washington, DC
20405, (202) 501–4755. Please cite FAC
2005–33, FAR case 2005–032.
SUPPLEMENTARY INFORMATION:
A. Background
The Councils published a proposed
rule in the Federal Register at 73 FR
19035 on April 8, 2008, to (1) address
revisions necessary to implement the
paid-cost rule and (2) simplify the SF
1443 and related regulations and
instructions to improve clarity.
VerDate Nov<24>2008
17:19 Jun 12, 2009
Jkt 217001
No comments were received by the
close of the public comment period on
June 9, 2008. Subsequently, one
comment was received from one
commenter. The commenter specifically
took no issue with the proposed FAR
changes, but objected to the costs that
would be incurred by its member
companies to make programming
changes that ensue from altering the SF
1443. The commenter reasoned that
‘‘(s)ince DOD’s goal is to significantly
expand the use of performance based
payments, it would appear to be more
cost effective not to incur significant
expenditures on changes to a form (i.e.,
SF 1443) that is part of a system
(progress payments) that is no longer the
preferred system for providing financing
payments.’’
The Councils were puzzled at the
commenter’s cost estimate of $87,000 to
update software to use the new SF 1443
because the changes incorporated into
the SF 1443 by this case were, generally,
necessitated by prior changes to the
paid-cost rule and other changes to FAR
Part 32. These changes had been in
effect for some time, so contractors
using SF 1443 to request progress
payments have already made changes to
their software to conform their progress
payment requests to the updated FAR
text.
The commenter, an association
representing large defense aerospace
corporations, was requested to provide
the cost analysis upon which it based its
estimate of the cost to reprogram
software in order to enable electronic
generation and submittal of the SF 1443
to request a progress payment. The
commenter subsequently provided data
supporting its estimate of approximately
$87,000 per contractor. This estimate
and the supporting data were forwarded
to the Small Business Administration
(SBA) Office of Advocacy for review
specifically to determine the impact of
modifying the SF 1443 on small
businesses. Two independent reviews
were conducted, one by the SBA’s
regulatory economist and one by an
outside small business expert selected
by the SBA. Neither of these reviews
discovered a substantial economic
impact on a significant number of small
entities.
Further, the Councils did not find the
commenter’s rationale regarding
performance-based payments
convincing. While it is the goal of
Federal Government agencies, not just
DoD, to use performance-based
payments wherever possible, there
remain many circumstances in which
progress payments are an important
financing mechanism. Therefore, the
PO 00000
Frm 00006
Fmt 4701
Sfmt 4700
Councils approved this case as a final
rule.
During a final review by the Councils’
Acquisition Finance Team, it was
discovered that the last item in the
‘‘INSTRUCTIONS’’ section of the form
on page 2 was labeled in error as
pertaining to ‘‘Item 26.’’ However, the
instruction actually refers to paragraph
(f) of the ‘‘CERTIFICATION’’ section.
That correction has been made to the
form. In addition, a sentence was added
to the SF 1443 instructions for Items
14a–14e to clarify that the ‘‘financing
payments’’ to be included do not
include interim payments under a cost
reimbursement contract.
This is not a significant regulatory
action and, therefore, was not subject to
review under Section 6(b) of Executive
Order 12866, Regulatory Planning and
Review, dated September 30, 1993. This
rule is not a major rule under 5 U.S.C.
804.
B. Regulatory Flexibility Act
The Department of Defense, the
General Services Administration, and
the National Aeronautics and Space
Administration certify that this final
rule will not have a significant
economic impact on a substantial
number of small entities within the
meaning of the Regulatory Flexibility
Act, 5 U.S.C. 601, et seq., because the
changes are designed to simplify the
form and improve clarity. (See also, the
Background section above for a
thorough discussion of lack of impact
on small entities.)
C. Paperwork Reduction Act
The Paperwork Reduction Act does
apply; however, these changes to the
FAR do not impose additional
information collection requirements to
the paperwork burden previously
approved under OMB Control Number
9000–0010.
List of Subjects in 48 CFR Parts 32, 43,
52, and 53
Government procurement.
Dated: June 9, 2009.
Al Matera,
Director, Office of Acquisition Policy.
Therefore, DoD, GSA, and NASA
amend 48 CFR parts 32, 43, 52, and 53
as set forth below:
■ 1. The authority citation for 48 CFR
parts 32, 43, 52, and 53 continues to
read as follows:
■
Authority: 40 U.S.C. 121(c); 10 U.S.C.
chapter 137; and 42 U.S.C. 2473(c).
E:\FR\FM\15JNR4.SGM
15JNR4
Federal Register / Vol. 74, No. 113 / Monday, June 15, 2009 / Rules and Regulations
PART 32—CONTRACT FINANCING
2. Amend section 32.001 by adding, in
alphabetical order, the definition
‘‘Liquidate’’ to read as follows:
■
32.001
Definitions.
*
*
*
*
*
Liquidate means to decrease a
payment for an accepted supply item or
service under a contract for the purpose
of recouping financing payments
previously paid to the contractor.
*
*
*
*
*
■ 3. Amend section 32.501–3 by
revising paragraph (a)(1) and the first
sentence of paragraph (a)(3) to read as
follows:
32.501–3
Contract price.
(a) * * *
(1) Under firm-fixed price contracts,
the contract price is the current amount
fixed by the contract plus the not-toexceed amount for any unpriced
modifications.
*
*
*
*
*
(3) Under a fixed-price incentive
contract, the contract price is the target
price plus the not-to-exceed amount of
unpriced modifications. * * *
*
*
*
*
*
32.503–1
[Removed and Reserved]
4. Remove and reserve section
32.503–1.
■ 5. Amend section 32.503–6 by
revising paragraphs (a)(3), (f), and
(g)(1)(i) to read as follows:
■
pwalker on PROD1PC71 with RULES4
Jkt 217001
43.102
[Amended]
6. Amend section 43.102 by removing
from paragraph (b) the word
‘‘maximum’’ and adding the word
‘‘ceiling’’ in its place.
■
7. Amend section 52.232–16 by
revising the date of the clause; adding
paragraph (a)(9); and revising
paragraphs (c)(5) and (g) to read as
follows:
■
(a) * * *
(3) In all cases, the contracting officer
shall—
(i) Act fairly and reasonably;
(ii) Base decisions on substantial
evidence; and
(iii) Document the contract file.
Findings made under paragraph (c) of
17:19 Jun 12, 2009
PART 43—CONTRACT
MODIFICATIONS
PART 52—SOLICITATION PROVISIONS
AND CONTRACT CLAUSES
32.503–6 Suspension or reduction of
payments.
VerDate Nov<24>2008
the Progress Payments clause shall be in
writing.
*
*
*
*
*
(f) Fair value of undelivered work.
Progress payments must be
commensurate with the fair value of
work accomplished in accordance with
contract requirements. The contracting
officer must adjust progress payments
when necessary to ensure that the fair
value of undelivered work equals or
exceeds the amount of unliquidated
progress payments. On loss contracts,
the application of a loss ratio as
provided at paragraph (g) of this
subsection constitutes this adjustment.
(g) * * *
(1) * * *
(i) Revise the current contract price
used in progress payment computations
(the current ceiling price under fixedprice incentive contracts) to include the
not-to-exceed amount for any pending
change orders and unpriced orders.
*
*
*
*
*
52.232–16
Progress Payments.
*
*
*
*
*
Progress Payments (JUL 2009)
*
*
*
*
*
(a) * * *
(9) The costs applicable to items delivered,
invoiced, and accepted shall not include
PO 00000
Frm 00007
Fmt 4701
Sfmt 4700
28431
costs in excess of the contract price of the
items.
*
*
*
*
*
(c) * * *
(5) The fair value of the undelivered work
is less than the amount of unliquidated
progress payments for that work.
*
*
*
*
*
(g) Reports, forms, and access to records.
(1) The Contractor shall promptly furnish
reports, certificates, financial statements, and
other pertinent information (including
estimates to complete) reasonably requested
by the Contracting Officer for the
administration of this clause. Also, the
Contractor shall give the Government
reasonable opportunity to examine and verify
the Contractor’s books, records, and
accounts.
(2) The Contractor shall furnish estimates
to complete that have been developed or
updated within six months of the date of the
progress payment request. The estimates to
complete shall represent the Contractor’s best
estimate of total costs to complete all
remaining contract work required under the
contract. The estimates shall include
sufficient detail to permit Government
verification.
(3) Each Contractor request for progress
payment shall:
(i) Be submitted on Standard Form 1443,
Contractor’s Request for Progress Payment, or
the electronic equivalent as required by
agency regulations, in accordance with the
form instructions and the contract terms; and
(ii) Include any additional supporting
documentation requested by the Contracting
Officer.
*
*
*
*
*
PART 53—FORMS
53.232
[Amended]
8. Amend section 53.232 by removing
‘‘(10/82)’’ and adding ‘‘(JUL 2009)’’ in
its place; and by removing ‘‘, as
specified in 32.503.1’’.
■ 9. Amend section 53.301–1443 by
revising the form to read as follows:
■
53.301–1443 Contractor’s Request for
Progress Payment.
BILLING CODE 6820–EP–S
E:\FR\FM\15JNR4.SGM
15JNR4
VerDate Nov<24>2008
Federal Register / Vol. 74, No. 113 / Monday, June 15, 2009 / Rules and Regulations
17:19 Jun 12, 2009
Jkt 217001
PO 00000
Frm 00008
Fmt 4701
Sfmt 4725
E:\FR\FM\15JNR4.SGM
15JNR4
ER15JN09.001
pwalker on PROD1PC71 with RULES4
28432
VerDate Nov<24>2008
17:19 Jun 12, 2009
Jkt 217001
PO 00000
Frm 00009
Fmt 4701
Sfmt 4700
E:\FR\FM\15JNR4.SGM
15JNR4
28433
ER15JN09.002
pwalker on PROD1PC71 with RULES4
Federal Register / Vol. 74, No. 113 / Monday, June 15, 2009 / Rules and Regulations
28434
Federal Register / Vol. 74, No. 113 / Monday, June 15, 2009 / Rules and Regulations
[FR Doc. E9–13977 Filed 6–12–09; 8:45 am]
BILLING CODE 6820–EP–C
and National Aeronautics and Space
Administration (NASA).
ACTION:
DEPARTMENT OF DEFENSE
Small Entity Compliance Guide.
This document is issued
under the joint authority of the
Secretary of Defense, the Administrator
of General Services and the
Administrator of the National
Aeronautics and Space Administration.
This Small Entity Compliance Guide has
been prepared in accordance with
Section 212 of the Small Business
Regulatory Enforcement Fairness Act of
1996. It consists of a summary of rules
appearing in Federal Acquisition
Circular (FAC) 2005–33 which amend
the FAR. Interested parties may obtain
further information regarding these
rules by referring to FAC 2005–33,
SUMMARY:
GENERAL SERVICES
ADMINISTRATION
NATIONAL AERONAUTICS AND
SPACE ADMINISTRATION
48 CFR Chapter 1
[Docket FAR 2009–0002, Sequence 4]
Federal Acquisition Regulation;
Federal Acquisition Circular 2005–33;
Small Entity Compliance Guide
AGENCIES: Department of Defense (DoD),
General Services Administration (GSA),
which precedes this document. These
documents are also available via the
Internet at https://www.regulations.gov.
FOR FURTHER INFORMATION CONTACT: Ms.
Hada Flowers, Regulatory Secretariat,
(202) 208–7282. For clarification of
content, contact the analyst whose name
appears in the table below.
LIST OF RULES IN FAC 2005–33
Item
Subject
I ............
II ...........
Trade Agreements—Costa Rica, Oman, and Peru (Interim) ..........................................................
Contractor’s Request for Progress Payments .................................................................................
SUPPLEMENTARY INFORMATION:
Summaries for each FAR rule follow.
For the actual revisions and/or
amendments to these FAR cases, refer to
the specific item number and subject set
forth in the documents following these
item summaries.
FAC 2005–33 amends the FAR as
specified below:
Item I—Trade Agreements—Costa Rica,
Oman, and Peru (FAR Case 2008–036)
(Interim)
pwalker on PROD1PC71 with RULES4
This interim rule allows contracting
officers to purchase the goods and
services of Costa Rica, Oman, and Peru
without application of the Buy
American Act if the acquisition is
subject to the applicable trade
VerDate Nov<24>2008
18:49 Jun 12, 2009
Jkt 217001
FAR case
agreements. The free trade agreements
with Costa Rica, Oman, and Peru join
the North American Free Trade
Agreement (NAFTA), the Australia,
Bahrain, Chile, Morocco, and Singapore
Free Trade Agreements, and the
Dominican Republic-Central AmericaUnited States Free Trade Agreement
(CAFTA–DR) with respect to the
Dominican Republic, El Salvador,
Guatemala, Honduras, and Nicaragua,
which are already in the FAR.
The threshold for supplies and
services is $67,826 for the CAFTA-DR
and $194,000 for the Oman and Peru
FTAs. The threshold for construction is
$7,443,000 for the CAFTA-DR and the
Peru FTA and $8,817,449 for the Oman
FTA.
PO 00000
Frm 00010
Fmt 4701
Sfmt 4700
2008–036
2005–032
Analyst
Murphy.
Murphy.
Item II—Contractor’s Request for
Progress Payments (FAR Case 2005–
032)
This final rule converts the proposed
rule published at 73 FR 19035 on April
8, 2008, to a final rule with one editorial
change. This final rule incorporates
improvements related to requests for
progress payments and the Standard
Form (SF) 1443, Contractor’s Request for
Progress Payments, used to request
those progress payments.
Dated: June 9, 2009.
Al Matera,
Director, Office of Acquisition Policy.
[FR Doc. E9–13976 Filed 6–12–09; 8:45 am]
BILLING CODE 6820–EP–C
E:\FR\FM\15JNR4.SGM
15JNR4
Agencies
[Federal Register Volume 74, Number 113 (Monday, June 15, 2009)]
[Rules and Regulations]
[Pages 28430-28434]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-13977]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
GENERAL SERVICES ADMINISTRATION
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
48 CFR Parts 32, 43, 52, and 53
[FAC 2005-33; FAR Case 2005-032; Item II; Docket 2008-0002; Sequence 1]
RIN 9000-AI47
Federal Acquisition Regulation; FAR Case 2005-032, Contractor's
Request for Progress Payments
AGENCIES: Department of Defense (DoD), General Services Administration
(GSA), and National Aeronautics and Space Administration (NASA).
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The Civilian Agency Acquisition Council and the Defense
Acquisition Regulations Council (Councils) have agreed on a final rule
amending the Federal Acquisition Regulation (FAR) to incorporate
improvements related to requests for progress payments and the Standard
Form (SF) 1443, Contractor's Request for Progress Payments, used to
request those progress payments. Changes made to the Standard Form as
published in the proposed rule include correction of misspellings, and
an editorial change made at Item 4 to better describe the order number.
DATES: Effective Date: July 15, 2009.
FOR FURTHER INFORMATION CONTACT: For clarification of content, contact
Ms. Meredith Murphy, Procurement Analyst, at (202) 208-6925. For
information pertaining to status or publication schedules, contact the
Regulatory Secretariat, 1800 F Street, NW, Room 4041, Washington, DC
20405, (202) 501-4755. Please cite FAC 2005-33, FAR case 2005-032.
SUPPLEMENTARY INFORMATION:
A. Background
The Councils published a proposed rule in the Federal Register at
73 FR 19035 on April 8, 2008, to (1) address revisions necessary to
implement the paid-cost rule and (2) simplify the SF 1443 and related
regulations and instructions to improve clarity.
No comments were received by the close of the public comment period
on June 9, 2008. Subsequently, one comment was received from one
commenter. The commenter specifically took no issue with the proposed
FAR changes, but objected to the costs that would be incurred by its
member companies to make programming changes that ensue from altering
the SF 1443. The commenter reasoned that ``(s)ince DOD's goal is to
significantly expand the use of performance based payments, it would
appear to be more cost effective not to incur significant expenditures
on changes to a form (i.e., SF 1443) that is part of a system (progress
payments) that is no longer the preferred system for providing
financing payments.''
The Councils were puzzled at the commenter's cost estimate of
$87,000 to update software to use the new SF 1443 because the changes
incorporated into the SF 1443 by this case were, generally,
necessitated by prior changes to the paid-cost rule and other changes
to FAR Part 32. These changes had been in effect for some time, so
contractors using SF 1443 to request progress payments have already
made changes to their software to conform their progress payment
requests to the updated FAR text.
The commenter, an association representing large defense aerospace
corporations, was requested to provide the cost analysis upon which it
based its estimate of the cost to reprogram software in order to enable
electronic generation and submittal of the SF 1443 to request a
progress payment. The commenter subsequently provided data supporting
its estimate of approximately $87,000 per contractor. This estimate and
the supporting data were forwarded to the Small Business Administration
(SBA) Office of Advocacy for review specifically to determine the
impact of modifying the SF 1443 on small businesses. Two independent
reviews were conducted, one by the SBA's regulatory economist and one
by an outside small business expert selected by the SBA. Neither of
these reviews discovered a substantial economic impact on a significant
number of small entities.
Further, the Councils did not find the commenter's rationale
regarding performance-based payments convincing. While it is the goal
of Federal Government agencies, not just DoD, to use performance-based
payments wherever possible, there remain many circumstances in which
progress payments are an important financing mechanism. Therefore, the
Councils approved this case as a final rule.
During a final review by the Councils' Acquisition Finance Team, it
was discovered that the last item in the ``INSTRUCTIONS'' section of
the form on page 2 was labeled in error as pertaining to ``Item 26.''
However, the instruction actually refers to paragraph (f) of the
``CERTIFICATION'' section. That correction has been made to the form.
In addition, a sentence was added to the SF 1443 instructions for Items
14a-14e to clarify that the ``financing payments'' to be included do
not include interim payments under a cost reimbursement contract.
This is not a significant regulatory action and, therefore, was not
subject to review under Section 6(b) of Executive Order 12866,
Regulatory Planning and Review, dated September 30, 1993. This rule is
not a major rule under 5 U.S.C. 804.
B. Regulatory Flexibility Act
The Department of Defense, the General Services Administration, and
the National Aeronautics and Space Administration certify that this
final rule will not have a significant economic impact on a substantial
number of small entities within the meaning of the Regulatory
Flexibility Act, 5 U.S.C. 601, et seq., because the changes are
designed to simplify the form and improve clarity. (See also, the
Background section above for a thorough discussion of lack of impact on
small entities.)
C. Paperwork Reduction Act
The Paperwork Reduction Act does apply; however, these changes to
the FAR do not impose additional information collection requirements to
the paperwork burden previously approved under OMB Control Number 9000-
0010.
List of Subjects in 48 CFR Parts 32, 43, 52, and 53
Government procurement.
Dated: June 9, 2009.
Al Matera,
Director, Office of Acquisition Policy.
0
Therefore, DoD, GSA, and NASA amend 48 CFR parts 32, 43, 52, and 53 as
set forth below:
0
1. The authority citation for 48 CFR parts 32, 43, 52, and 53 continues
to read as follows:
Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 42
U.S.C. 2473(c).
[[Page 28431]]
PART 32--CONTRACT FINANCING
0
2. Amend section 32.001 by adding, in alphabetical order, the
definition ``Liquidate'' to read as follows:
32.001 Definitions.
* * * * *
Liquidate means to decrease a payment for an accepted supply item
or service under a contract for the purpose of recouping financing
payments previously paid to the contractor.
* * * * *
0
3. Amend section 32.501-3 by revising paragraph (a)(1) and the first
sentence of paragraph (a)(3) to read as follows:
32.501-3 Contract price.
(a) * * *
(1) Under firm-fixed price contracts, the contract price is the
current amount fixed by the contract plus the not-to-exceed amount for
any unpriced modifications.
* * * * *
(3) Under a fixed-price incentive contract, the contract price is
the target price plus the not-to-exceed amount of unpriced
modifications. * * *
* * * * *
32.503-1 [Removed and Reserved]
0
4. Remove and reserve section 32.503-1.
0
5. Amend section 32.503-6 by revising paragraphs (a)(3), (f), and
(g)(1)(i) to read as follows:
32.503-6 Suspension or reduction of payments.
(a) * * *
(3) In all cases, the contracting officer shall--
(i) Act fairly and reasonably;
(ii) Base decisions on substantial evidence; and
(iii) Document the contract file. Findings made under paragraph (c)
of the Progress Payments clause shall be in writing.
* * * * *
(f) Fair value of undelivered work. Progress payments must be
commensurate with the fair value of work accomplished in accordance
with contract requirements. The contracting officer must adjust
progress payments when necessary to ensure that the fair value of
undelivered work equals or exceeds the amount of unliquidated progress
payments. On loss contracts, the application of a loss ratio as
provided at paragraph (g) of this subsection constitutes this
adjustment.
(g) * * *
(1) * * *
(i) Revise the current contract price used in progress payment
computations (the current ceiling price under fixed-price incentive
contracts) to include the not-to-exceed amount for any pending change
orders and unpriced orders.
* * * * *
PART 43--CONTRACT MODIFICATIONS
43.102 [Amended]
0
6. Amend section 43.102 by removing from paragraph (b) the word
``maximum'' and adding the word ``ceiling'' in its place.
PART 52--SOLICITATION PROVISIONS AND CONTRACT CLAUSES
0
7. Amend section 52.232-16 by revising the date of the clause; adding
paragraph (a)(9); and revising paragraphs (c)(5) and (g) to read as
follows:
52.232-16 Progress Payments.
* * * * *
Progress Payments (JUL 2009)
* * * * *
(a) * * *
(9) The costs applicable to items delivered, invoiced, and
accepted shall not include costs in excess of the contract price of
the items.
* * * * *
(c) * * *
(5) The fair value of the undelivered work is less than the
amount of unliquidated progress payments for that work.
* * * * *
(g) Reports, forms, and access to records. (1) The Contractor
shall promptly furnish reports, certificates, financial statements,
and other pertinent information (including estimates to complete)
reasonably requested by the Contracting Officer for the
administration of this clause. Also, the Contractor shall give the
Government reasonable opportunity to examine and verify the
Contractor's books, records, and accounts.
(2) The Contractor shall furnish estimates to complete that have
been developed or updated within six months of the date of the
progress payment request. The estimates to complete shall represent
the Contractor's best estimate of total costs to complete all
remaining contract work required under the contract. The estimates
shall include sufficient detail to permit Government verification.
(3) Each Contractor request for progress payment shall:
(i) Be submitted on Standard Form 1443, Contractor's Request for
Progress Payment, or the electronic equivalent as required by agency
regulations, in accordance with the form instructions and the
contract terms; and
(ii) Include any additional supporting documentation requested
by the Contracting Officer.
* * * * *
PART 53--FORMS
53.232 [Amended]
0
8. Amend section 53.232 by removing ``(10/82)'' and adding ``(JUL
2009)'' in its place; and by removing ``, as specified in 32.503.1''.
0
9. Amend section 53.301-1443 by revising the form to read as follows:
53.301-1443 Contractor's Request for Progress Payment.
BILLING CODE 6820-EP-S
[[Page 28432]]
[GRAPHIC] [TIFF OMITTED] TR15JN09.001
[[Page 28433]]
[GRAPHIC] [TIFF OMITTED] TR15JN09.002
[[Page 28434]]
[FR Doc. E9-13977 Filed 6-12-09; 8:45 am]