Transcontinental Gas Pipe Line Company LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Delta Lateral Project and Request for Comments on Environmental Issues, 27138-27139 [E9-13229]
Download as PDF
27138
Federal Register / Vol. 74, No. 108 / Monday, June 8, 2009 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP09–237–000]
Transcontinental Gas Pipe Line
Company LLC; Notice of Intent To
Prepare an Environmental Assessment
for the Proposed Delta Lateral Project
and Request for Comments on
Environmental Issues
May 29, 2009.
cprice-sewell on PRODPC61 with NOTICES
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
Environmental Assessment (EA) that
will discuss the environmental impacts
of the Delta Lateral Project involving
construction and operation of facilities
by Transcontinental Gas Pipe Line
Company LLC (Transco) in York
County, Pennsylvania. This EA will be
used by the Commission in its decisionmaking process to determine whether
the project is in the public convenience
and necessity.
This notice announces the opening of
the scoping process we will use to
gather input from the public and
interested agencies on the project. Your
input will help the Commission staff
determine what issues need to be
evaluated in the EA. Please note that the
scoping period will close on June 30,
2009.
This notice is being sent to affected
landowners; Federal, State, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties in this proceeding;
and local libraries and newspapers.
State and local government
representatives are asked to notify their
constituents of this proposed project
and encourage them to comment on
their areas of concern.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (https://
www.ferc.gov). This fact sheet addresses
a number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is
available for viewing on the FERC
Internet Web site (https://www.ferc.gov).
Summary of the Proposed Project
Transco proposes to construct its
Delta Lateral Project in York County,
Pennsylvania, in order to provide
208,800 dekatherms per day of firm
transportation service to the Delta
VerDate Nov<24>2008
15:15 Jun 05, 2009
Jkt 217001
Power Plant, a natural gas and oil fired
electric power generation plant that is
currently under construction in York
County.
Transco is proposing to construct:
• 3.42 miles of 16-inch-diameter
pipeline lateral from Compressor
Station 195 located at milepost (MP)
1674.6 of Transco’s Mainlines A and C
to the interconnection with the Delta
Power Plant;
• Two 12-inch taps at MP 1674.6, one
each on Mainlines A and C discharge
headers;
• Minor aboveground facilities and
modifications including a new pig
launcher and receiver;
• A delivery point meter station at the
Delta Power Plant site, including two 8inch ultrasonic meters, 12-inch yard
piping, electronic flow measurement
equipment and a radio with a tower;
• An odorization system within the
Delta Power Plant site;
• A chromatograph with accessories,
and a radio and building within the
Delta Power Plant site; and
• A 630-foot-long cathodic protection
ground bed at MP 1.9, adjacent to Delta
Road.
The general location of the project
facilities is shown in Appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would require about 54.1 acres of land.
Following construction, about 14.8 acres
would be maintained as new
aboveground facility sites and
permanent pipeline right-of-way. The
remaining 39.3 acres of land would be
restored and allowed to revert to their
former use.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission staff requests
public comments on the scope of the
1 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices are available on the Commission’s Web
site at the ‘‘eLibrary’’ link or from the Commission’s
Public Reference Room, 888 First Street, NE.,
Washington, DC 20426, or call (202) 502–8371. For
instructions on connecting to eLibrary, refer to the
last page of this notice. Copies of the appendices
were sent to all those receiving this notice in the
mail.
PO 00000
Frm 00051
Fmt 4703
Sfmt 4703
issues to address in the EA. All
comments received will be considered
during the preparation of the EA. State
and local government representatives
are encouraged to notify their
constituents of this proposed action and
encourage them to comment on their
areas of concern.
In the EA, we 2 will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Land use;
• Geology and soils;
• Water resources, fisheries, and
wetlands;
• Cultural resources;
• Vegetation and wildlife;
• Endangered and threatened species;
and
• Public safety.
We will also evaluate possible
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Our independent analysis of the
issues will be presented in the EA.
Depending on the comments received
during the scoping process, the EA may
be published and mailed to the entities
on our mailing list (see how to remain
on our mailing list under Environmental
Mailing List, below). A comment period
will be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission. To ensure your comments
are considered, please carefully follow
the instructions in the public
participation section below.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the Delta
Lateral Project. Your comments should
focus on the potential environmental
effects, reasonable alternatives, and
measures to avoid or lessen
environmental impacts. The more
specific your comments, the more useful
they will be. To ensure that your
comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before June 30,
2009.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances, please reference the
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
E:\FR\FM\08JNN1.SGM
08JNN1
Federal Register / Vol. 74, No. 108 / Monday, June 8, 2009 / Notices
project docket number CP09–237–000
with your submission. The Commission
encourages electronic filing of
comments and has dedicated eFiling
expert staff available to assist you at
202–502–8258 or efiling@ferc.gov.
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located on
the Commission’s Web site at https://
www.ferc.gov under the link to
Documents and Filings. A Quick
Comment is an easy method for
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Web site at https://
www.ferc.gov under the link to
Documents and Filings. eFiling involves
preparing your submission in the same
manner as you would if filing on paper,
and then saving the file on your
computer’s hard drive. You will attach
that file as your submission. New
eFiling users must first create an
account by clicking on ‘‘Sign up’’ or
‘‘eRegister.’’ You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing;’’ or
(3) You may file your comments via
mail to the Commission by sending an
original and two copies of your letter to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Room 1A, Washington,
DC 20426.
Label one copy of the comments for
the attention of Gas Branch 3, PJ–11.3.
cprice-sewell on PRODPC61 with NOTICES
Environmental Mailing List
An effort is being made to send this
notice to all individuals, organizations,
and government entities interested in
and/or potentially affected by the
proposed project. This includes all
landowners who are potential right-ofway grantors, whose property may be
used temporarily for project purposes,
or who own property within distances
defined in the Commission’s regulations
of certain aboveground facilities.
If you do not want to send comments
at this time but still want to remain on
our mailing list, please return the
Information Request (Appendix 2). If
you do not return the Information
Request, you will be taken off the
mailing list.
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor,’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
VerDate Nov<24>2008
15:15 Jun 05, 2009
Jkt 217001
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are included in the User’s
Guide under the ‘‘e-filing’’ link on the
Commission’s Web site.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Web site (https://www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number (CP09–237) excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–13229 Filed 6–5–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER09–1195–000]
Palmco Power PA, LLC; Supplemental
Notice That Initial Market-Based Rate
Filing Includes Request for Blanket
Section 204 Authorization
May 29, 2009.
This is a supplemental notice in the
above-referenced proceeding of Palmco
Power PA, LLC’s application for marketbased rate authority, with an
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
27139
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
Part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the Applicant’s request for blanket
authorization, under 18 CFR Part 34, of
future issuances of securities and
assumptions of liability, is June 19,
2009.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–13226 Filed 6–5–09; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\08JNN1.SGM
08JNN1
Agencies
[Federal Register Volume 74, Number 108 (Monday, June 8, 2009)]
[Notices]
[Pages 27138-27139]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-13229]
[[Page 27138]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP09-237-000]
Transcontinental Gas Pipe Line Company LLC; Notice of Intent To
Prepare an Environmental Assessment for the Proposed Delta Lateral
Project and Request for Comments on Environmental Issues
May 29, 2009.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an Environmental Assessment (EA) that will
discuss the environmental impacts of the Delta Lateral Project
involving construction and operation of facilities by Transcontinental
Gas Pipe Line Company LLC (Transco) in York County, Pennsylvania. This
EA will be used by the Commission in its decision-making process to
determine whether the project is in the public convenience and
necessity.
This notice announces the opening of the scoping process we will
use to gather input from the public and interested agencies on the
project. Your input will help the Commission staff determine what
issues need to be evaluated in the EA. Please note that the scoping
period will close on June 30, 2009.
This notice is being sent to affected landowners; Federal, State,
and local government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties in this proceeding; and local libraries and
newspapers. State and local government representatives are asked to
notify their constituents of this proposed project and encourage them
to comment on their areas of concern.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Web site (https://www.ferc.gov). This fact sheet
addresses a number of typically asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
It is available for viewing on the FERC Internet Web site (https://www.ferc.gov).
Summary of the Proposed Project
Transco proposes to construct its Delta Lateral Project in York
County, Pennsylvania, in order to provide 208,800 dekatherms per day of
firm transportation service to the Delta Power Plant, a natural gas and
oil fired electric power generation plant that is currently under
construction in York County.
Transco is proposing to construct:
3.42 miles of 16-inch-diameter pipeline lateral from
Compressor Station 195 located at milepost (MP) 1674.6 of Transco's
Mainlines A and C to the interconnection with the Delta Power Plant;
Two 12-inch taps at MP 1674.6, one each on Mainlines A and
C discharge headers;
Minor aboveground facilities and modifications including a
new pig launcher and receiver;
A delivery point meter station at the Delta Power Plant
site, including two 8-inch ultrasonic meters, 12-inch yard piping,
electronic flow measurement equipment and a radio with a tower;
An odorization system within the Delta Power Plant site;
A chromatograph with accessories, and a radio and building
within the Delta Power Plant site; and
A 630-foot-long cathodic protection ground bed at MP 1.9,
adjacent to Delta Road.
The general location of the project facilities is shown in Appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of all appendices are
available on the Commission's Web site at the ``eLibrary'' link or
from the Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
Copies of the appendices were sent to all those receiving this
notice in the mail.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would require about 54.1
acres of land. Following construction, about 14.8 acres would be
maintained as new aboveground facility sites and permanent pipeline
right-of-way. The remaining 39.3 acres of land would be restored and
allowed to revert to their former use.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
to discover and address concerns the public may have about proposals.
This process is referred to as ``scoping.'' The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission staff requests
public comments on the scope of the issues to address in the EA. All
comments received will be considered during the preparation of the EA.
State and local government representatives are encouraged to notify
their constituents of this proposed action and encourage them to
comment on their areas of concern.
In the EA, we \2\ will discuss impacts that could occur as a result
of the construction and operation of the proposed project under these
general headings:
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
Land use;
Geology and soils;
Water resources, fisheries, and wetlands;
Cultural resources;
Vegetation and wildlife;
Endangered and threatened species; and
Public safety.
We will also evaluate possible alternatives to the proposed project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Our independent analysis of the issues will be presented in the EA.
Depending on the comments received during the scoping process, the EA
may be published and mailed to the entities on our mailing list (see
how to remain on our mailing list under Environmental Mailing List,
below). A comment period will be allotted for review if the EA is
published. We will consider all comments on the EA before we make our
recommendations to the Commission. To ensure your comments are
considered, please carefully follow the instructions in the public
participation section below.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the Delta Lateral Project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
The more specific your comments, the more useful they will be. To
ensure that your comments are timely and properly recorded, please send
in your comments so that they will be received in Washington, DC on or
before June 30, 2009.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances, please
reference the
[[Page 27139]]
project docket number CP09-237-000 with your submission. The Commission
encourages electronic filing of comments and has dedicated eFiling
expert staff available to assist you at 202-502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the Quick
Comment feature, which is located on the Commission's Web site at
https://www.ferc.gov under the link to Documents and Filings. A Quick
Comment is an easy method for interested persons to submit text-only
comments on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. eFiling involves
preparing your submission in the same manner as you would if filing on
paper, and then saving the file on your computer's hard drive. You will
attach that file as your submission. New eFiling users must first
create an account by clicking on ``Sign up'' or ``eRegister.'' You will
be asked to select the type of filing you are making. A comment on a
particular project is considered a ``Comment on a Filing;'' or
(3) You may file your comments via mail to the Commission by
sending an original and two copies of your letter to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas Branch 3,
PJ-11.3.
Environmental Mailing List
An effort is being made to send this notice to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project. This includes all landowners who are
potential right-of-way grantors, whose property may be used temporarily
for project purposes, or who own property within distances defined in
the Commission's regulations of certain aboveground facilities.
If you do not want to send comments at this time but still want to
remain on our mailing list, please return the Information Request
(Appendix 2). If you do not return the Information Request, you will be
taken off the mailing list.
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor,'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are
included in the User's Guide under the ``e-filing'' link on the
Commission's Web site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Web site (https://www.ferc.gov) using the eLibrary link. Click on
the eLibrary link, click on ``General Search'' and enter the docket
number (CP09-237) excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-13229 Filed 6-5-09; 8:45 am]
BILLING CODE 6717-01-P