Richard Blumenthal, Attorney General for the State of Connecticut, Complainant v. ISO New England Inc., Brookfield Energy Marketing Inc., H.Q Energy Services (US) Inc., Constellation Energy Commodities Group, Inc. and Other Unidentified Installed Capacity Resources Committed To Import Over the Northern New York AC Interface, Respondent; The Connecticut Department of Public Utility Control and The Connecticut Office of Consumer Counsel, Complainant v. ISO New England Inc., Brookfield Energy Marketing Inc., H.Q Energy Services (US) Inc., Constellation Energy Commodities Group, Inc. and Other Unidentified Installed Capacity Resources Committed To Import Over the Northern New York AC Interface, Respondent; Notice of Complaint, 26850 [E9-13003]

Download as PDF 26850 Federal Register / Vol. 74, No. 106 / Thursday, June 4, 2009 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL09–47–000, Docket No. EL09–48–000] Richard Blumenthal, Attorney General for the State of Connecticut, Complainant v. ISO New England Inc., Brookfield Energy Marketing Inc., H.Q Energy Services (US) Inc., Constellation Energy Commodities Group, Inc. and Other Unidentified Installed Capacity Resources Committed To Import Over the Northern New York AC Interface, Respondent; The Connecticut Department of Public Utility Control and The Connecticut Office of Consumer Counsel, Complainant v. ISO New England Inc., Brookfield Energy Marketing Inc., H.Q Energy Services (US) Inc., Constellation Energy Commodities Group, Inc. and Other Unidentified Installed Capacity Resources Committed To Import Over the Northern New York AC Interface, Respondent; Notice of Complaint May 28, 2009. Take notice that on May 22, 2009, pursuant to sections 206, 222, and 309 of the Federal Power Act, 16 U.S.C. 824(e), 824(v), and 825h (2006) and Rules 206 and 215 of the Rules of Practice and Procedure, 18 CFR 385.206 and 385.215 (2008) and Part 1(c) of the Commission’s Rules and Regulations, 18 CFR part 1c, Richard Blumenthal, Attorney General for the State of Connecticut, the Connecticut Department of Public Utility Control, and the Connecticut Office of Consumer Counsel (collectively the Complainants) filed a Consolidated Amended Complaint against the ISO New England Inc., Brookfield Energy Marketing, Inc. HQ Energy Services (US) Inc., Constellation Energy Commodities Group, Inc. and Other Unidentified Installed Capacity Resources Committed to Import over the Northern New York AC Interface (NNY Capacity Resources) (collectively the Respondents), seeking a Commission investigation and hearing into installed capacity resources who received capacity payments but were unavailable to provide capacity services when called upon and seeking market monitor reforms. The Complainants state that a copy of the complaint has been served on the Respondents and New England Power Pool, Inc, who represents the NNY Capacity Resources. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of VerDate Nov<24>2008 15:16 Jun 03, 2009 Jkt 217001 the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on June 11, 2009. Kimberly D. Bose, Secretary. [FR Doc. E9–13003 Filed 6–3–09; 8:45 am] Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant and all the parties in this proceeding. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on June 16, 2009. Kimberly D. Bose, Secretary. [FR Doc. E9–13007 Filed 6–3–09; 8:45 am] BILLING CODE 6717–01–P BILLING CODE 6717–01–P DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission [Docket No. EL09–12–001] [Docket No. ER09–993–000] Bonneville Power Administration; Notice of Filing Lake Cogen, Ltd.; Notice of Filing May 28, 2009. Take notice that, on May 26, 2009, Lake Cogen, Ltd. filed to amend its filing in the above-captioned proceeding to include information required under the Commission’s regulations. Such filing serves to reset the filing date in this proceeding. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 May 27, 2009. Take notice that on January 28, 2009, the Bonneville Power Administration (Bonneville) filed, in the abovecaptioned proceeding, an errata to its Tiered Rate Methodology Rate Case, TRM–12–A–02 (errata filing), which accompanied its Petition for Declaratory Order filed on November 11, 2008 (November 11 Filing). Interventions and protests should be limited to Bonneville’s errata filing. The Commission will address all interventions and protests for both the E:\FR\FM\04JNN1.SGM 04JNN1

Agencies

[Federal Register Volume 74, Number 106 (Thursday, June 4, 2009)]
[Notices]
[Page 26850]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-13003]



[[Page 26850]]

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL09-47-000, Docket No. EL09-48-000]


Richard Blumenthal, Attorney General for the State of 
Connecticut, Complainant v. ISO New England Inc., Brookfield Energy 
Marketing Inc., H.Q Energy Services (US) Inc., Constellation Energy 
Commodities Group, Inc. and Other Unidentified Installed Capacity 
Resources Committed To Import Over the Northern New York AC Interface, 
Respondent; The Connecticut Department of Public Utility Control and 
The Connecticut Office of Consumer Counsel, Complainant v. ISO New 
England Inc., Brookfield Energy Marketing Inc., H.Q Energy Services 
(US) Inc., Constellation Energy Commodities Group, Inc. and Other 
Unidentified Installed Capacity Resources Committed To Import Over the 
Northern New York AC Interface, Respondent; Notice of Complaint

May 28, 2009.
    Take notice that on May 22, 2009, pursuant to sections 206, 222, 
and 309 of the Federal Power Act, 16 U.S.C. 824(e), 824(v), and 825h 
(2006) and Rules 206 and 215 of the Rules of Practice and Procedure, 18 
CFR 385.206 and 385.215 (2008) and Part 1(c) of the Commission's Rules 
and Regulations, 18 CFR part 1c, Richard Blumenthal, Attorney General 
for the State of Connecticut, the Connecticut Department of Public 
Utility Control, and the Connecticut Office of Consumer Counsel 
(collectively the Complainants) filed a Consolidated Amended Complaint 
against the ISO New England Inc., Brookfield Energy Marketing, Inc. HQ 
Energy Services (US) Inc., Constellation Energy Commodities Group, Inc. 
and Other Unidentified Installed Capacity Resources Committed to Import 
over the Northern New York AC Interface (NNY Capacity Resources) 
(collectively the Respondents), seeking a Commission investigation and 
hearing into installed capacity resources who received capacity 
payments but were unavailable to provide capacity services when called 
upon and seeking market monitor reforms.
    The Complainants state that a copy of the complaint has been served 
on the Respondents and New England Power Pool, Inc, who represents the 
NNY Capacity Resources.
    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. The Respondent's 
answer and all interventions, or protests must be filed on or before 
the comment date. The Respondent's answer, motions to intervene, and 
protests must be served on the Complainants.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an 
original and 14 copies of the protest or intervention to the Federal 
Energy Regulatory Commission, 888 First Street, NE., Washington, DC 
20426.
    This filing is accessible on-line at https://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive e-mail 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please e-mail 
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.
    Comment Date: 5 p.m. Eastern Time on June 11, 2009.

Kimberly D. Bose,
Secretary.
[FR Doc. E9-13003 Filed 6-3-09; 8:45 am]
BILLING CODE 6717-01-P