Application to Export Electric Energy; Endure Energy, L.L.C., 26668 [E9-12916]
Download as PDF
26668
Federal Register / Vol. 74, No. 105 / Wednesday, June 3, 2009 / Notices
Comments, protests, or
requests to intervene should be
addressed as follows: Office of
Electricity Delivery and Energy
Reliability, Mail Code: OE–20, U.S.
Department of Energy, 1000
Independence Avenue, SW.,
Washington, DC 20585–0350 (FAX 202–
586–8008).
FOR FURTHER INFORMATION CONTACT:
Ellen Russell (Program Office) 202–586–
9624 or Michael Skinker (Program
Attorney) 202–586–2793.
SUPPLEMENTARY INFORMATION: Exports of
electricity from the United States to a
foreign country are regulated by the
Department of Energy (DOE) pursuant to
sections 301(b) and 402(f) of the
Department of Energy Organization Act
(42 U.S.C. 7151(b), 7172(f)) and require
authorization under section 202(e) of
the FPA (16 U.S.C. 824a(e)).
On May 26, 2009, DOE received an
application from JPMCCC for authority
to transmit electric energy from the
United States to Canada as a power
marketer. The energy to be exported
would be delivered to Canada over
existing transmission interconnections
between the United States and Canada
over any facility determined by DOE to
be appropriate for third-party use. The
electric energy which JPMCCC proposes
to export to Canada would be surplus to
the needs of the selling entities.
JPMCCC has requested an electricity
export authorization with a 5-year term.
Procedural Matters: Any person
desiring to become a party to these
proceedings or to be heard by filing
comments or protests to this application
should file a petition to intervene,
comment, or protest at the address
provided above in accordance with
385.211 or 385.214 of the Federal
Energy Regulatory Commission’s Rules
of Practice and Procedures (18 CFR
385.211, 385.214). Fifteen copies of each
petition and protest should be filed with
DOE on or before the date listed above.
Comments on the JPMCC application
to export electric energy to Canada
should be clearly marked with Docket
No. EA–356. Additional copies are to be
filed directly with Ike Gibbs,
Compliance Director & Assistant
General Counsel, JPMorgan Chase Bank,
NM.A., 700 Louisiana Street, Suite
1000, Houston, TX 77002. A final
decision will be made on this
application after the environmental
impacts have been evaluated pursuant
to the National Environmental Policy
Act of 1969, and a determination is
made by DOE that the proposed action
will not adversely impact on the
reliability of the U.S. electric power
supply system.
PWALKER on PROD1PC71 with NOTICES
ADDRESSES:
VerDate Nov<24>2008
16:08 Jun 02, 2009
Jkt 217001
Copies of this application will be
made available, upon request, for public
inspection and copying at the address
provided above, by accessing the
program Web site at https://
www.oe.energy.gov/
permits_pending.htm, or by e-mailing
Odessa Hopkins at
Odessa.hopkins@hq.doe.gov.
Issued in Washington, DC, on May 29,
2009.
Anthony J. Como,
Director, Permitting and Siting, Office of
Electricity Delivery and Energy Reliability.
[FR Doc. E9–12921 Filed 6–2–09; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
[OE Docket No. EA–354]
Application to Export Electric Energy;
Endure Energy, L.L.C.
AGENCY: Office of Electricity Delivery
and Energy Reliability, DOE.
ACTION: Notice of application.
SUMMARY: Endure Energy, L.L.C.
(Endure Energy) has applied for
authority to transmit electric energy
from the United States to Canada
pursuant to section 202(e) of the Federal
Power Act.
DATES: Comments, protests, or requests
to intervene must be submitted on or
before July 6, 2009.
ADDRESSES: Comments, protests, or
requests to intervene should be
addressed as follows: Office of
Electricity Delivery and Energy
Reliability, Mail Code: OE–20, U.S.
Department of Energy, 1000
Independence Avenue, SW.,
Washington, DC 20585–0350 (FAX 202–
586–8008).
FOR FURTHER INFORMATION CONTACT:
Ellen Russell (Program Office) 202–586–
9624 or Michael Skinker (Program
Attorney) 202–586–2793.
SUPPLEMENTARY INFORMATION: Exports of
electricity from the United States to a
foreign country are regulated by the
Department of Energy (DOE) pursuant to
sections 301(b) and 402(f) of the
Department of Energy Organization Act
(42 U.S.C. 7151(b), 7172(f)) and require
authorization under section 202(e) of
the FPA (16 U.S.C. 824a(e)).
On May 15, 2009, DOE received an
application from Endure Energy for
authority to transmit electric energy
from the United States to Canada as a
power marketer. The energy to be
exported would be delivered to Canada
over international electric transmission
facilities deemed to be appropriate by
DOE for third party transportation. The
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
electric energy which Endure Energy
proposes to export to Canada would be
surplus energy purchased from electric
utilities, Federal power marketing
agencies, and other entities within the
United States. Endure Energy has
requested an electricity export
authorization with a 5-year term.
Procedural Matters: Any person
desiring to become a party to these
proceedings or to be heard by filing
comments or protests to this application
should file a petition to intervene,
comment, or protest at the address
provided above in accordance with
§§ 385.211 or 385.214 of the Federal
Energy Regulatory Commission’s Rules
of Practice and Procedures (18 CFR
385.211, 385.214). Fifteen copies of each
petition and protest should be filed with
DOE on or before the date listed above.
Comments on the Endure Energy
application to export electric energy to
Canada should be clearly marked with
Docket No. EA–354. Additional copies
are to be filed directly with Mark A.
Blackton, Executive Vice President,
Endure Energy, L.L.C., 7300 College
Boulevard, Suite 600, Overland Park, KS
66210 and William A. Mogel, Attorney
at Law, 5812 Madaket Road, Bethesda,
MD 20816. A final decision will be
made on this application after the
environmental impacts have been
evaluated pursuant to the National
Environmental Policy Act of 1969, and
a determination is made by DOE that the
proposed action will not adversely
impact on the reliability of the U.S.
electric power supply system.
Copies of this application will be
made available, upon request, for public
inspection and copying at the address
provided above, by accessing the
program Web site at https://
www.oe.energy.gov/
permits_pending.htm, or by e-mailing
Odessa Hopkins at
Odessa.hopkins@hq.doe.gov.
Issued in Washington, DC, on May 28,
2009.
Anthony J. Como,
Director, Permitting and Siting, Office of
Electricity Delivery and Energy Reliability.
[FR Doc. E9–12916 Filed 6–2–09; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
[OE Docket No. EA–355]
Application to Export Electric Energy;
Scotia Capital Energy Inc.
AGENCY: Office of Electricity Delivery
and Energy Reliability, DOE.
ACTION: Notice of application.
E:\FR\FM\03JNN1.SGM
03JNN1
Agencies
[Federal Register Volume 74, Number 105 (Wednesday, June 3, 2009)]
[Notices]
[Page 26668]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-12916]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[OE Docket No. EA-354]
Application to Export Electric Energy; Endure Energy, L.L.C.
AGENCY: Office of Electricity Delivery and Energy Reliability, DOE.
ACTION: Notice of application.
-----------------------------------------------------------------------
SUMMARY: Endure Energy, L.L.C. (Endure Energy) has applied for
authority to transmit electric energy from the United States to Canada
pursuant to section 202(e) of the Federal Power Act.
DATES: Comments, protests, or requests to intervene must be submitted
on or before July 6, 2009.
ADDRESSES: Comments, protests, or requests to intervene should be
addressed as follows: Office of Electricity Delivery and Energy
Reliability, Mail Code: OE-20, U.S. Department of Energy, 1000
Independence Avenue, SW., Washington, DC 20585-0350 (FAX 202-586-8008).
FOR FURTHER INFORMATION CONTACT: Ellen Russell (Program Office) 202-
586-9624 or Michael Skinker (Program Attorney) 202-586-2793.
SUPPLEMENTARY INFORMATION: Exports of electricity from the United
States to a foreign country are regulated by the Department of Energy
(DOE) pursuant to sections 301(b) and 402(f) of the Department of
Energy Organization Act (42 U.S.C. 7151(b), 7172(f)) and require
authorization under section 202(e) of the FPA (16 U.S.C. 824a(e)).
On May 15, 2009, DOE received an application from Endure Energy for
authority to transmit electric energy from the United States to Canada
as a power marketer. The energy to be exported would be delivered to
Canada over international electric transmission facilities deemed to be
appropriate by DOE for third party transportation. The electric energy
which Endure Energy proposes to export to Canada would be surplus
energy purchased from electric utilities, Federal power marketing
agencies, and other entities within the United States. Endure Energy
has requested an electricity export authorization with a 5-year term.
Procedural Matters: Any person desiring to become a party to these
proceedings or to be heard by filing comments or protests to this
application should file a petition to intervene, comment, or protest at
the address provided above in accordance with Sec. Sec. 385.211 or
385.214 of the Federal Energy Regulatory Commission's Rules of Practice
and Procedures (18 CFR 385.211, 385.214). Fifteen copies of each
petition and protest should be filed with DOE on or before the date
listed above.
Comments on the Endure Energy application to export electric energy
to Canada should be clearly marked with Docket No. EA-354. Additional
copies are to be filed directly with Mark A. Blackton, Executive Vice
President, Endure Energy, L.L.C., 7300 College Boulevard, Suite 600,
Overland Park, KS 66210 and William A. Mogel, Attorney at Law, 5812
Madaket Road, Bethesda, MD 20816. A final decision will be made on this
application after the environmental impacts have been evaluated
pursuant to the National Environmental Policy Act of 1969, and a
determination is made by DOE that the proposed action will not
adversely impact on the reliability of the U.S. electric power supply
system.
Copies of this application will be made available, upon request,
for public inspection and copying at the address provided above, by
accessing the program Web site at https://www.oe.energy.gov/permits_pending.htm, or by e-mailing Odessa Hopkins at
Odessa.hopkins@hq.doe.gov.
Issued in Washington, DC, on May 28, 2009.
Anthony J. Como,
Director, Permitting and Siting, Office of Electricity Delivery and
Energy Reliability.
[FR Doc. E9-12916 Filed 6-2-09; 8:45 am]