Dairyland Power Cooperative, Inc.: Notice of Intent To Prepare an Environmental Impact Statement and Hold Public Scoping Meetings, 25485-25486 [E9-12407]
Download as PDF
Federal Register / Vol. 74, No. 101 / Thursday, May 28, 2009 / Notices
and the original wooden bridge stringers
and deck are beginning to fall into the
stream channel. Constructing the bridge
so the structure does not impede water
flow, particularily during periods of
high water, will be beneficial to the
aquatic habitats. As part of the proposed
action the West Fork Blacks Fork bridge
will be replaced to provide access to
salvage the lodgepole pine stands in
Section 18, which are heavily infested
by mountain pine beetles. Over the long
term, it would provide access for the
private property owner while allowing
fire access, and other types of
administrative uses on the National
Forest by the Forest Service. This road
has been gated for many years and this
would continue if the bridge were
replaced. The road would be
periodically maintained to prevent
erosion and deterioration of the road
prism. The execution of easements
would establish legal access and also
provide for future maintenance.
There are five basic techniques that
will be used to contain prescribed fire
in the treatment units. Fire will be used
alone or in conjunction with
commercial timber harvest to achieve a
mosaic of burned and unburned patches
within some of the units. Specific
methods of line control will be specified
in the burn plan. Construction of line
will use the minimum necessary
disturbance. The following estimates of
miles of each kind of fire line are
approximate, but represent the upper
end (most line construction) for control
lines. It is likely that firing techniques
will be utilized more and constructed
lines less than the estimates given.
At least 3.9 miles of unit perimeter
will utilize terrain features in
conjunction with the firing patterns to
selectively burn portions of the units.
Natural features such as rock outcrops,
openings, and wet riparian/stream
corridors, will serve as anchors for
utilizing firing techniques. In particular,
Blacks Fork will function as the west
fireline for most of the eastern burn
unit. Created features such as areas
where timber has been harvested may
also be appropriate for control lines,
depending on fuel conditions.
Up to about 0.3 miles of handline
(averaging 24 to 36 inches wide and
cleared to mineral soil) will be built and
rehabilitated. Where vegetation is short
and light, such as in sage and grass,
fireline constructed by hand will be
used to anchor the burning. Line will be
appropriately rehabilitated (by
mulching, seeding, and/or water
barring, as needed) following
completion of the burning to prevent
erosion.
VerDate Nov<24>2008
17:11 May 27, 2009
Jkt 217001
Approximately 1.0 miles of machine
line could be used. Heavy equipment
will be used to construct fireline where
fuels are larger than feasible for
handline, and natural features/firing
techniques are not adequate for control.
Line will average 72 to 96 inches in
width and be cleared to mineral soil.
Possible equipment includes (but is not
limited to) bulldozers, rubber tired
skidders, trail cats, and tracked
excavators. Following burning, the lines
will be rehabilitated (seeded and water
barred as needed, and where available
woody debris may be scattered along for
microsite protection).
Approximately 0.9 miles of skid trails
(including incidental machine line) will
be used as fire containment lines. In
timber sale units that have burning as
secondary treatments skid trails for log
removal will be placed along the
perimeter and used also for containment
of the fire. Skid trails are generally
about 96 inches in width and have
mineral soil exposed throughout much
of their surface. As in the machine line,
these will be rehabilitated following
burning to prevent erosion. In small
portions where it is not feasible to skid
along the boundary then machine line
will be built.
Approximately 4.1 miles of Forest
System Road will be used for fire
containment. Where existing roads
coincide with burn unit boundaries
these will be used as fire lines, such as
along the eastern boundary of the
eastern burn unit.
Possible Alternatives
In addition to the Proposed Action, a
no action alternative will be considered.
This alternative would simply continue
current management without the actions
of this proposal. Other alternatives may
be developed in response to issues
generated during the scoping process.
Responsible Official
Evanston-Mountain View District
Ranger.
Nature of Decision To Be Made
The decision to be made is whether or
not to implement vegetation treatments
in the Blacks Fork project area, and if
so, to what degree and where.
Preliminary Issues
Preliminary issues are the effects of
treatments on wildlife habitat, and the
effects of insect and disease outbreaks
on current forest health.
Scoping Process
This notice of intent initiates the
scoping process, which guides the
PO 00000
Frm 00007
Fmt 4703
Sfmt 4703
25485
development of the environmental
impact statement.
It is important that reviewers provide
their comments at such times and in
such manner that they are useful to the
agency’s preparation of the
environmental impact statement.
Therefore, comments should be
provided prior to the close of the
comment period and should clearly
articulate the reviewer’s concerns and
contentions. The submission of timely
and specific comments can affect a
reviewer’s ability to participate in
subsequent administrative appeal or
judicial review.
Dated: May 19, 2009.
Stephen M. Ryberg,
District Ranger.
[FR Doc. E9–12124 Filed 5–27–09; 8:45 am]
BILLING CODE 3410–11–M
DEPARTMENT OF AGRICULTURE
Rural Utilities Service
Dairyland Power Cooperative, Inc.:
Notice of Intent To Prepare an
Environmental Impact Statement and
Hold Public Scoping Meetings
Rural Utilities Service, USDA.
Notice of Intent To Prepare an
Environmental Impact Statement and
Hold Public Scoping Meetings.
AGENCY:
ACTION:
SUMMARY: The Rural Utilities Service
(RUS) intends to prepare an
Environmental Impact Statement (EIS)
and hold public scoping meetings and
in connection with possible impacts
related to a project proposed by
Dairyland Power Cooperative in the
CapX 2020 Hampton-Rochester-La
Crosse Transmission Line Project. The
proposal consists of the construction of
a 345-kilovolt (kV) transmission line
and associated infrastructure between
Hampton, Minnesota and the La Crosse
area in Wisconsin. The project also
includes construction of new 161-kV
transmission lines and associated
facilities in the area of Rochester,
Minnesota. The total length of 345-kV
and 161-kV transmission lines
associated with the proposed project
will be approximately 150 miles.
Proposed and alternate transmission
segments and locations for proposed
and alternate associated facilities have
been identified by Dairyland Power
Cooperative. Dairyland Power
Cooperative is requesting RUS to
provide financing for its portion of the
proposed project.
DATES: RUS will conduct six public
scoping meetings in an open-house
format followed by a discussion period:
E:\FR\FM\28MYN1.SGM
28MYN1
25486
Federal Register / Vol. 74, No. 101 / Thursday, May 28, 2009 / Notices
June 16, 2009, Plainview-Elgin-Millville
High School, 500 West Broadway,
Plainview, Minnesota; June 17, 2009,
Wanamingo Community Center, 401
Main Street, Wanamingo, Minnesota;
June 18, 2009, City of St. Charles
Community Meeting Room, 830
Whitewater Avenue, St. Charles,
Minnesota; June 23, 2009, La Crescent
American Legion, 509 N. Chestnut, La
Crescent, Minnesota; June 24, 2009,
Centerville/Town of Trempealeau
Community Center, W24854 State Road
54/93, Galesville, Wisconsin; and June
25, 2009, Cochrane-Fountain City High
School, S2770 State Road 35, Fountain
City, Wisconsin. All meetings will be
held between 6–8:00 PM local time.
Comments regarding the proposed
project may be submitted (orally or in
writing) at the public scoping meetings
or in writing to RUS at the address
listed in this notice no later than June
29, 2009.
ADDRESSES: To send comments or for
further information, contact Stephanie
Strength, Environmental Protection
Specialist, USDA, Rural Utilities
Service, Engineering and Environmental
Staff, 1400 Independence Avenue, SW.,
Stop 1571, Washington, DC 20250–
1571, telephone: (202) 720–0468 or email: stephanie.strength@usda.gov.
An Alternative Evaluation Study
(AES) and Macro Corridor Study (MCS),
prepared by Dairyland Power
Cooperative, will be presented at the
public scoping meetings. The reports are
available for public review at the RUS
address provided in this notice and at
Dairyland Power Cooperative, 3251 East
Avenue, South, La Crosse, WI 54602. In
Addition, the reports will be available at
RUS’ Web site, https://www.usda.gov/
rus/water/ees/eis.htm and at the
following repositories:
Alma Public Library, 312 North Main
Street, Alma, WI 54610, Phone: 608–
685–3823.
Arcadia Public Library, 406 E Main
Street, Arcadia, WI 54612, Phone:
608–323–7505.
Blair-Preston Library, 122 Urberg Street,
Blair, WI 54616, Phone: 608–989–
2502.
Campbell Library, 2219 Bainbridge
Street, La Crosse, WI 54603, Phone:
608–783–0052.
Cannon Falls Library, 306 West Mill
Street, Cannon Falls, MN 55009,
Phone: 507–263–2804.
Dairyland Power Cooperative, 500 Old
State Highway 35, Alma, WI 54610,
Phone: 608–685–4497.
Galesville Public Library, 16787 South
Main Street, Galesville, WI 54630,
Phone: 608–582–2552.
VerDate Nov<24>2008
17:11 May 27, 2009
Jkt 217001
Hokah Public Library, 57 Main Street,
Hokah, MN 55941, Phone: 507–894–
2665.
Holmen Area Library, 16787 South
Main Street, Galesville, WI 54630,
Phone: 608–526–4198.
Kenyon Public Library, 709 2nd Street,
Kenyon, MN 55946, Phone: 507–789–
6821.
Riverland Energy Cooperative, N28988
State Road 93, Arcadia, WI 54612,
Phone: 608–323–3381.
Rochester Public Library, 101 2nd Street
SE., Rochester, MN 55963, Phone:
507–328–2309.
Shirley M. Wright Memorial Library,
11455 Fremont Street, Trempealeau,
WI 54650, Phone: 608–534–6197.
St. Charles Public Library, 125 W 11th
Street, St. Charles, MN 55927, Phone:
507–932–3227.
Tri-County Electric, 31110 Cooperative
Way, Rushford, MN 55971, Phone:
507–864–7783.
La Crescent Public Library, 321 Main
Street, La Crescent, MN 55947, Phone:
507–895–4047.
La Crosse Public Library, 800 Main
Street, La Crosse, WI 54601, Phone:
608–789–7109.
Onalaska Public Library, 741 Oak
Avenue, South, Onalaska, WI 54650,
Phone: 608–781–9568.
People’s Cooperative Services, 3935
Hwy 14 E, Rochester, MN 55903,
Phone: 507–288–4004.
Plainview Public Library, 115 SE 3rd
Street, Pine Island, MN 55963, Phone:
507–534–3425.
Van Horn Public Library, 115 SE 3rd
Street, Pine Island, MN 55963, Phone:
507–356–8558.
Winona Public Library, 151 West 5th
Street, Winona, MN 55987, Phone:
507–452–4582.
Xcel Energy, 5050 Service Drive,
Winona, MN 55987, Phone: 800–422–
0782.
Xcel Energy, 1414 West Hamilton
Avenue, Eau Claire, WI 54701, Phone:
715–839–2621.
Zumbrota Public Library, 100 West
Avenue, Zumbrota, MN 55992, Phone:
507–732–5211.
SUPPLEMENTARY INFORMATION:
Preliminary proposed transmission line
corridors and siting areas for substations
have been identified. The EIS will
address the construction, operation, and
management of the proposed project,
which includes a 345-kV transmission
line and associated infrastructure
between Hampton, Minnesota and the
La Crosse area of Wisconsin; 161-kV
transmission lines in the vicinity of
Rochester, Minnesota; construction and
maintenance of access roads for all
proposed transmission lines;
PO 00000
Frm 00008
Fmt 4703
Sfmt 4703
construction of up to three new
substations, and expansion of up to
three existing substations. Total length
of the transmission lines for the
proposed project will be approximately
150 miles. The project study area
includes part or all of the following
counties in Minnesota: Dakota,
Goodhue, Wabasha, Winona, Houston,
Olmsted, Rice, and Dodge. In
Wisconsin, the project area includes
parts of the following counties: La
Crosse, Trempealeau, and Buffalo.
Among the alternatives RUS will
address in the EIS is the No Action
alternative, under which the project
would not be undertaken. In the EIS, the
effects of the proposed project will be
compared to the existing conditions in
the area affected. Alternative
transmission line corridors and
substation locations will be refined as
part of the EIS scoping process and will
be addressed in the Draft EIS. RUS will
carefully study public health and safety,
environmental impacts, and engineering
aspects of the proposed project and all
related facilities.
RUS will use input provided by
government agencies, private
organizations, and the public in the
preparation of the Draft EIS. The Draft
EIS will be available for review and
comment for 45 days. A Final EIS that
considers all comments received will
subsequently be prepared. The Final EIS
will be available for review and
comment for 30 days. Following the 30day comment period, RUS will prepare
a Record of Decision (ROD). Notices
announcing the availability of the Draft
EIS, the Final EIS, and the ROD will be
published in the Federal Register and in
local newspapers.
Any final action by RUS related to the
proposed project will be subject to, and
contingent upon, compliance with all
relevant federal, state, and local
environmental laws and regulations and
completion of the environmental review
requirements as prescribed in the RUS
Environmental Policies and Procedures
(7 CFR part 1794).
Dated: May 22, 2009.
Mark S. Plank,
Director, Engineering and Environmental
Staff, USDA/Rural Utilities Service.
[FR Doc. E9–12407 Filed 5–27–09; 8:45 am]
BILLING CODE P
E:\FR\FM\28MYN1.SGM
28MYN1
Agencies
[Federal Register Volume 74, Number 101 (Thursday, May 28, 2009)]
[Notices]
[Pages 25485-25486]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-12407]
-----------------------------------------------------------------------
DEPARTMENT OF AGRICULTURE
Rural Utilities Service
Dairyland Power Cooperative, Inc.: Notice of Intent To Prepare an
Environmental Impact Statement and Hold Public Scoping Meetings
AGENCY: Rural Utilities Service, USDA.
ACTION: Notice of Intent To Prepare an Environmental Impact Statement
and Hold Public Scoping Meetings.
-----------------------------------------------------------------------
SUMMARY: The Rural Utilities Service (RUS) intends to prepare an
Environmental Impact Statement (EIS) and hold public scoping meetings
and in connection with possible impacts related to a project proposed
by Dairyland Power Cooperative in the CapX 2020 Hampton-Rochester-La
Crosse Transmission Line Project. The proposal consists of the
construction of a 345-kilovolt (kV) transmission line and associated
infrastructure between Hampton, Minnesota and the La Crosse area in
Wisconsin. The project also includes construction of new 161-kV
transmission lines and associated facilities in the area of Rochester,
Minnesota. The total length of 345-kV and 161-kV transmission lines
associated with the proposed project will be approximately 150 miles.
Proposed and alternate transmission segments and locations for proposed
and alternate associated facilities have been identified by Dairyland
Power Cooperative. Dairyland Power Cooperative is requesting RUS to
provide financing for its portion of the proposed project.
DATES: RUS will conduct six public scoping meetings in an open-house
format followed by a discussion period:
[[Page 25486]]
June 16, 2009, Plainview-Elgin-Millville High School, 500 West
Broadway, Plainview, Minnesota; June 17, 2009, Wanamingo Community
Center, 401 Main Street, Wanamingo, Minnesota; June 18, 2009, City of
St. Charles Community Meeting Room, 830 Whitewater Avenue, St. Charles,
Minnesota; June 23, 2009, La Crescent American Legion, 509 N. Chestnut,
La Crescent, Minnesota; June 24, 2009, Centerville/Town of Trempealeau
Community Center, W24854 State Road 54/93, Galesville, Wisconsin; and
June 25, 2009, Cochrane-Fountain City High School, S2770 State Road 35,
Fountain City, Wisconsin. All meetings will be held between 6-8:00 PM
local time. Comments regarding the proposed project may be submitted
(orally or in writing) at the public scoping meetings or in writing to
RUS at the address listed in this notice no later than June 29, 2009.
ADDRESSES: To send comments or for further information, contact
Stephanie Strength, Environmental Protection Specialist, USDA, Rural
Utilities Service, Engineering and Environmental Staff, 1400
Independence Avenue, SW., Stop 1571, Washington, DC 20250-1571,
telephone: (202) 720-0468 or e-mail: stephanie.strength@usda.gov.
An Alternative Evaluation Study (AES) and Macro Corridor Study
(MCS), prepared by Dairyland Power Cooperative, will be presented at
the public scoping meetings. The reports are available for public
review at the RUS address provided in this notice and at Dairyland
Power Cooperative, 3251 East Avenue, South, La Crosse, WI 54602. In
Addition, the reports will be available at RUS' Web site, https://www.usda.gov/rus/water/ees/eis.htm and at the following repositories:
Alma Public Library, 312 North Main Street, Alma, WI 54610, Phone: 608-
685-3823.
Arcadia Public Library, 406 E Main Street, Arcadia, WI 54612, Phone:
608-323-7505.
Blair-Preston Library, 122 Urberg Street, Blair, WI 54616, Phone: 608-
989-2502.
Campbell Library, 2219 Bainbridge Street, La Crosse, WI 54603, Phone:
608-783-0052.
Cannon Falls Library, 306 West Mill Street, Cannon Falls, MN 55009,
Phone: 507-263-2804.
Dairyland Power Cooperative, 500 Old State Highway 35, Alma, WI 54610,
Phone: 608-685-4497.
Galesville Public Library, 16787 South Main Street, Galesville, WI
54630, Phone: 608-582-2552.
Hokah Public Library, 57 Main Street, Hokah, MN 55941, Phone: 507-894-
2665.
Holmen Area Library, 16787 South Main Street, Galesville, WI 54630,
Phone: 608-526-4198.
Kenyon Public Library, 709 2nd Street, Kenyon, MN 55946, Phone: 507-
789-6821.
Riverland Energy Cooperative, N28988 State Road 93, Arcadia, WI 54612,
Phone: 608-323-3381.
Rochester Public Library, 101 2nd Street SE., Rochester, MN 55963,
Phone: 507-328-2309.
Shirley M. Wright Memorial Library, 11455 Fremont Street, Trempealeau,
WI 54650, Phone: 608-534-6197.
St. Charles Public Library, 125 W 11th Street, St. Charles, MN 55927,
Phone: 507-932-3227.
Tri-County Electric, 31110 Cooperative Way, Rushford, MN 55971, Phone:
507-864-7783.
La Crescent Public Library, 321 Main Street, La Crescent, MN 55947,
Phone: 507-895-4047.
La Crosse Public Library, 800 Main Street, La Crosse, WI 54601, Phone:
608-789-7109.
Onalaska Public Library, 741 Oak Avenue, South, Onalaska, WI 54650,
Phone: 608-781-9568.
People's Cooperative Services, 3935 Hwy 14 E, Rochester, MN 55903,
Phone: 507-288-4004.
Plainview Public Library, 115 SE 3rd Street, Pine Island, MN 55963,
Phone: 507-534-3425.
Van Horn Public Library, 115 SE 3rd Street, Pine Island, MN 55963,
Phone: 507-356-8558.
Winona Public Library, 151 West 5th Street, Winona, MN 55987, Phone:
507-452-4582.
Xcel Energy, 5050 Service Drive, Winona, MN 55987, Phone: 800-422-0782.
Xcel Energy, 1414 West Hamilton Avenue, Eau Claire, WI 54701, Phone:
715-839-2621.
Zumbrota Public Library, 100 West Avenue, Zumbrota, MN 55992, Phone:
507-732-5211.
SUPPLEMENTARY INFORMATION: Preliminary proposed transmission line
corridors and siting areas for substations have been identified. The
EIS will address the construction, operation, and management of the
proposed project, which includes a 345-kV transmission line and
associated infrastructure between Hampton, Minnesota and the La Crosse
area of Wisconsin; 161-kV transmission lines in the vicinity of
Rochester, Minnesota; construction and maintenance of access roads for
all proposed transmission lines; construction of up to three new
substations, and expansion of up to three existing substations. Total
length of the transmission lines for the proposed project will be
approximately 150 miles. The project study area includes part or all of
the following counties in Minnesota: Dakota, Goodhue, Wabasha, Winona,
Houston, Olmsted, Rice, and Dodge. In Wisconsin, the project area
includes parts of the following counties: La Crosse, Trempealeau, and
Buffalo.
Among the alternatives RUS will address in the EIS is the No Action
alternative, under which the project would not be undertaken. In the
EIS, the effects of the proposed project will be compared to the
existing conditions in the area affected. Alternative transmission line
corridors and substation locations will be refined as part of the EIS
scoping process and will be addressed in the Draft EIS. RUS will
carefully study public health and safety, environmental impacts, and
engineering aspects of the proposed project and all related facilities.
RUS will use input provided by government agencies, private
organizations, and the public in the preparation of the Draft EIS. The
Draft EIS will be available for review and comment for 45 days. A Final
EIS that considers all comments received will subsequently be prepared.
The Final EIS will be available for review and comment for 30 days.
Following the 30-day comment period, RUS will prepare a Record of
Decision (ROD). Notices announcing the availability of the Draft EIS,
the Final EIS, and the ROD will be published in the Federal Register
and in local newspapers.
Any final action by RUS related to the proposed project will be
subject to, and contingent upon, compliance with all relevant federal,
state, and local environmental laws and regulations and completion of
the environmental review requirements as prescribed in the RUS
Environmental Policies and Procedures (7 CFR part 1794).
Dated: May 22, 2009.
Mark S. Plank,
Director, Engineering and Environmental Staff, USDA/Rural Utilities
Service.
[FR Doc. E9-12407 Filed 5-27-09; 8:45 am]
BILLING CODE P