Hydrodynamics, Inc.; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 20475 [E9-10101]
Download as PDF
Federal Register / Vol. 74, No. 84 / Monday, May 4, 2009 / Notices
powerhouse; (6) a new powerhouse
containing two generating units with a
combined installed capacity of 0.8
megawatts; (7) a new tailrace
discharging flows into Red Lodge Creek
at the base of the dam; (8) a new
substation; (9) a proposed 15-kilovolt, 8mile-long transmission line; and (10)
appurtenant facilities. The proposed
project would have an average annual
generation of 4.2 gigawatt-hours.
Applicant Contact: Ben Singer,
Project Manager, Hydrodynamics, Inc.,
P.O. Box 1136, Bozeman, MT 59771;
phone: (406) 587–5086.
FERC Contact: Dianne Rodman, (202)
502–6077.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and eight
copies should be mailed to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. For
more information on how to submit
these types of filings please go to the
Commission’s Web site located at https://
www.ferc.gov/filing-comments.asp.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13373) in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3372.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–10100 Filed 5–1–09; 8:45 am]
tjames on PRODPC75 with NOTICES
BILLING CODE 6717–01–P
VerDate Nov<24>2008
15:26 May 01, 2009
Jkt 217001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13372–000]
Hydrodynamics, Inc.; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
April 23, 2009.
On February 11, 2009,
Hydrodynamics, Inc. filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act, proposing to study the
feasibility of the Tongue River Reservoir
Hydroelectric Project, which would be
located at the existing Tongue River
Reservoir dam on the Tongue River near
the town of Decker in Bighorn County,
Montana. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist of
the following:
(1) An existing 1,824-foot-long, 91foot-high earthen dam; (2) an existing
reservoir with a surface area of 3,700
acres and a storage capacity of 79,071
acre-feet at the normal water surface
elevation of 3,138 feet mean sea level;
(3) an existing concrete outlet works
tunnel, which would be lined with
steel; (4) a new 84-inch, 520-foot-long
steel penstock in the tunnel; (5) a new
40-foot-long penstock extending from
the tunnel to the powerhouse; (6) a new
powerhouse containing two generating
units with a combined installed
capacity of 2.0 megawatts; (7) a new
tailrace discharging flows into the
Tongue River at the base of the dam; (8)
a new substation; (9) a new 125-kilovolt,
8.5-mile-long transmission line; and (10)
appurtenant facilities. The proposed
project would have an average annual
generation of 11.0 gigawatt-hours.
Applicant Contact: Ben Singer,
Project Manager, Hydrodynamics, Inc.,
P.O. Box 1136, Bozeman, MT 59771;
phone: (406) 587–5086.
FERC Contact: Dianne Rodman, (202)
502–6077.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
20475
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and eight
copies should be mailed to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. For
more information on how to submit
these types of filings please go to the
Commission’s Web site located at https://
www.ferc.gov/filing-comments.asp.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13373) in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3372.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–10101 Filed 5–1–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER09–1020–000]
Panoche Energy Center, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
April 24, 2009.
This is a supplemental notice in the
above-referenced proceeding of Panoche
Energy Center, LLC’s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC,
20426, in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
E:\FR\FM\04MYN1.SGM
04MYN1
Agencies
[Federal Register Volume 74, Number 84 (Monday, May 4, 2009)]
[Notices]
[Page 20475]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-10101]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13372-000]
Hydrodynamics, Inc.; Notice of Preliminary Permit Application
Accepted for Filing and Soliciting Comments, Motions To Intervene, and
Competing Applications
April 23, 2009.
On February 11, 2009, Hydrodynamics, Inc. filed an application for
a preliminary permit, pursuant to section 4(f) of the Federal Power
Act, proposing to study the feasibility of the Tongue River Reservoir
Hydroelectric Project, which would be located at the existing Tongue
River Reservoir dam on the Tongue River near the town of Decker in
Bighorn County, Montana. The sole purpose of a preliminary permit, if
issued, is to grant the permit holder priority to file a license
application during the permit term. A preliminary permit does not
authorize the permit holder to perform any land disturbing activities
or otherwise enter upon lands or waters owned by others without the
owners' express permission.
The proposed project would consist of the following:
(1) An existing 1,824-foot-long, 91-foot-high earthen dam; (2) an
existing reservoir with a surface area of 3,700 acres and a storage
capacity of 79,071 acre-feet at the normal water surface elevation of
3,138 feet mean sea level; (3) an existing concrete outlet works
tunnel, which would be lined with steel; (4) a new 84-inch, 520-foot-
long steel penstock in the tunnel; (5) a new 40-foot-long penstock
extending from the tunnel to the powerhouse; (6) a new powerhouse
containing two generating units with a combined installed capacity of
2.0 megawatts; (7) a new tailrace discharging flows into the Tongue
River at the base of the dam; (8) a new substation; (9) a new 125-
kilovolt, 8.5-mile-long transmission line; and (10) appurtenant
facilities. The proposed project would have an average annual
generation of 11.0 gigawatt-hours.
Applicant Contact: Ben Singer, Project Manager, Hydrodynamics,
Inc., P.O. Box 1136, Bozeman, MT 59771; phone: (406) 587-5086.
FERC Contact: Dianne Rodman, (202) 502-6077.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Comments, motions to intervene, notices of intent, and competing
applications may be filed electronically via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. If unable to be filed electronically,
documents may be paper-filed. To paper-file, an original and eight
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For
more information on how to submit these types of filings please go to
the Commission's Web site located at https://www.ferc.gov/filing-comments.asp. More information about this project, including a copy of
the application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-13373) in the docket number field to access
the document. For assistance, call toll-free 1-866-208-3372.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-10101 Filed 5-1-09; 8:45 am]