Kinder Morgan Interstate Gas Transmission LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Kinder Morgan Huntsman Storage Expansion Project and Request for Comments on Environmental Issues, 19077-19078 [E9-9543]
Download as PDF
Federal Register / Vol. 74, No. 79 / Monday, April 27, 2009 / Notices
The filings in the above proceedings
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please email FERCOnlineSupport@ferc.gov or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. E9–9502 Filed 4–24–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP09–109–000]
Kinder Morgan Interstate Gas
Transmission LLC; Notice of Intent To
Prepare an Environmental Assessment
for the Proposed Kinder Morgan
Huntsman Storage Expansion Project
and Request for Comments on
Environmental Issues
pwalker on PROD1PC71 with NOTICES
April 20, 2009.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Huntsman Storage Expansion
Project involving construction and
operation of facilities by Kinder Morgan
Interstate Gas Transmission LLC (Kinder
Morgan) in Cheyenne County, Nebraska.
This EA will be used by the
Commission in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process we will use to
gather input from the public and
interested agencies on the project. Your
input will help the Commission staff
determine which issues need to be
evaluated in the EA. Please note that the
scoping period will close on May 20,
2009.
This notice is being sent to affected
landowners; Federal, State, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. State and local
VerDate Nov<24>2008
15:55 Apr 24, 2009
Jkt 217001
government representatives are asked to
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
Kinder Morgan representative about
survey permission and/or the
acquisition of an easement to construct,
operate, and maintain the proposed
facilities. The company would seek to
negotiate a mutually acceptable
agreement. However, if the project is
approved by the Commission, that
approval conveys with it the right of
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement, the natural gas company
could initiate condemnation
proceedings in accordance with State
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (https://
www.ferc.gov). This fact sheet addresses
a number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is
available for viewing on the FERC
Internet Web site (https://www.ferc.gov).
Summary of the Proposed Project
Kinder Morgan proposes to construct
and modify its existing Huntsman
Storage Facility. Kinder Morgan says
that the completion of the Huntsman
Ridge Expansion Project would benefit
the Rocky Mountain region by meeting
the immediate and long-term needs of
the region as well as providing
flexibility in managing and storing gas
supplies.
Kinder Morgan is proposing to:
• Abandon in place two 1,200 foot
sections of 8-inch diameter pipeline;
• Install two injection/withdrawal
wells;
• Rework two existing injection/
withdrawal wells;
• Install various ancillary facilities
including a 400 bbl tank, pig receivers,
a slug catcher, and a gas cooler; and
• Install 2,000 feet of 12-inch
diameter pipeline.
The general location of the project
facilities is shown in Appendix 1.1
1 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices are available on the Commission’s Web
site at the ‘‘eLibrary’’ link or from the Commission’s
Public Reference Room, 888 First Street, NE.,
Washington, DC 20426, or call (202) 502–8371. For
instructions on connecting to eLibrary, refer to the
last page of this notice. Copies of the appendices
were sent to all those receiving this notice in the
mail.
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
19077
If approved, Kinder Morgan proposes
to commence construction of the
proposed facilities in October 2009,
with an in-service date of mid-year
2010.
Land Requirements for Construction
Construction and renovation of the
Huntsman Storage Facility would
impact about 15.6 temporary acres
where 0.8 acres would be permanently
impacted. All land disturbances would
occur entirely on private lands.
Kinder Morgan is proposing to utilize
existing access roads for the proposed
project. No land disturbance would be
required for additional access roads.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, the Commission staff
requests public comments on the scope
of the issues to address in the EA. All
comments received are considered
during the preparation of the EA. State
and local government representatives
are encouraged to notify their
constituents of this proposed action and
encourage them to comment on their
areas of concern.
In the EA we 2 will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils,
• Land use,
• Water resources, fisheries, and
wetlands,
• Cultural resources,
• Vegetation and wildlife,
• Air quality and noise,
• Endangered and threatened species,
• Public safety.
We will also evaluate possible
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
2 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects
(OEP).
E:\FR\FM\27APN1.SGM
27APN1
19078
Federal Register / Vol. 74, No. 79 / Monday, April 27, 2009 / Notices
scoping process, the EA may be
published and mailed to Federal, State,
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission. To ensure your comments
are considered, please carefully follow
the instructions in the public
participation section below.
With this NOI, we are asking Federal,
State, and local agencies with
jurisdiction and/or special expertise
with respect to environmental issues to
formally cooperate with us in the
preparation of the EA. These agencies
may choose to participate once they
have evaluated the proposal relative to
their responsibilities. Additional
agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this NOI.
pwalker on PROD1PC71 with NOTICES
Currently Identified Environmental
Issues
We have already identified an issue
that we think deserves attention based
on a preliminary review of the proposed
facilities and the environmental
information provided by Kinder
Morgan. This preliminary list of issues
may be changed based on your
comments and our analysis.
• Potential impacts may occur to the
whooping crane, black-footed ferret,
spectaclecase, burrowing owl, swift fox,
and mountain plover.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the
Huntsman Ridge Expansion Project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before May 20,
2009.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number CP09–109–000 with
your submission. The docket number
can be found on the front of this notice.
The Commission encourages electronic
VerDate Nov<24>2008
17:28 Apr 24, 2009
Jkt 217001
filing of comments and has dedicated
eFiling expert staff available to assist
you at 202–502–8258 or
efiling@ferc.gov.
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located on
the Commission’s Internet Web site at
https://www.ferc.gov under the link to
Documents and Filings. A Quick
Comment is an easy method for
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Internet Web site at
https://www.ferc.gov under the link to
Documents and Filings. eFiling involves
preparing your submission in the same
manner as you would if filing on paper,
and then saving the file on your
computer’s hard drive. You will attach
that file as your submission. New
eFiling users must first create an
account by clicking on ‘‘Sign up’’ or
‘‘eRegister.’’ You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing;’’ or
(3) You may file your comments via
mail to the Commission by sending an
original and two copies of your letter to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First St., NE., Room 1A, Washington, DC
20426;
Label one copy of the comments for
the attention of Gas Branch 2, PJ11.2.
Environmental Mailing List
An effort is being made to send this
notice to all individuals, organizations,
and government entities interested in
and/or potentially affected by the
proposed project. This includes all
landowners who are potential right-ofway grantors, whose property may be
used temporarily for project purposes,
or who own homes within distances
defined in the Commission’s regulations
of certain aboveground facilities.
If you do not want to send comments
at this time but still want to remain on
our mailing list, please return the
Information Request (Appendix 2). If
you do not return the Information
Request, you will be taken off the
mailing list.
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor,’’ which is an
official party to the proceeding.
Intervenors play a more formal role in
the process and are able to file briefs,
appear at hearings, and be heard by the
courts if they choose to appeal the
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
Commission’s final ruling. An
intervenor formally participates in a
Commission proceeding by filing a
request to intervene. Instructions for
becoming an intervenor are included in
the User’s Guide under the ‘‘e-filing’’
link on the Commission’s Web site.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the eLibrary link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–9543 Filed 4–24–09; 8:45 am]
BILLING CODE P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. ER06–615–000, ER07–1257–
000, ER08–1113–000, ER08–1178–000,
ER09–241–000]
California Independent System
Operator Corporation; Notice of FERC
Staff Attendance
April 20, 2009.
The Federal Energy Regulatory
Commission (Commission) hereby gives
notice that on the following dates
members of its staff will participate in
teleconferences and meetings to be
E:\FR\FM\27APN1.SGM
27APN1
Agencies
[Federal Register Volume 74, Number 79 (Monday, April 27, 2009)]
[Notices]
[Pages 19077-19078]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-9543]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP09-109-000]
Kinder Morgan Interstate Gas Transmission LLC; Notice of Intent
To Prepare an Environmental Assessment for the Proposed Kinder Morgan
Huntsman Storage Expansion Project and Request for Comments on
Environmental Issues
April 20, 2009.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Huntsman Storage Expansion
Project involving construction and operation of facilities by Kinder
Morgan Interstate Gas Transmission LLC (Kinder Morgan) in Cheyenne
County, Nebraska. This EA will be used by the Commission in its
decision-making process to determine whether the project is in the
public convenience and necessity.
This notice announces the opening of the scoping process we will
use to gather input from the public and interested agencies on the
project. Your input will help the Commission staff determine which
issues need to be evaluated in the EA. Please note that the scoping
period will close on May 20, 2009.
This notice is being sent to affected landowners; Federal, State,
and local government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. State and local
government representatives are asked to notify their constituents of
this planned project and encourage them to comment on their areas of
concern.
If you are a landowner receiving this notice, you may be contacted
by a Kinder Morgan representative about survey permission and/or the
acquisition of an easement to construct, operate, and maintain the
proposed facilities. The company would seek to negotiate a mutually
acceptable agreement. However, if the project is approved by the
Commission, that approval conveys with it the right of eminent domain.
Therefore, if easement negotiations fail to produce an agreement, the
natural gas company could initiate condemnation proceedings in
accordance with State law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Web site (https://www.ferc.gov). This fact sheet
addresses a number of typically asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
It is available for viewing on the FERC Internet Web site (https://www.ferc.gov).
Summary of the Proposed Project
Kinder Morgan proposes to construct and modify its existing
Huntsman Storage Facility. Kinder Morgan says that the completion of
the Huntsman Ridge Expansion Project would benefit the Rocky Mountain
region by meeting the immediate and long-term needs of the region as
well as providing flexibility in managing and storing gas supplies.
Kinder Morgan is proposing to:
Abandon in place two 1,200 foot sections of 8-inch
diameter pipeline;
Install two injection/withdrawal wells;
Rework two existing injection/withdrawal wells;
Install various ancillary facilities including a 400 bbl
tank, pig receivers, a slug catcher, and a gas cooler; and
Install 2,000 feet of 12-inch diameter pipeline.
The general location of the project facilities is shown in Appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of all appendices are
available on the Commission's Web site at the ``eLibrary'' link or
from the Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
Copies of the appendices were sent to all those receiving this
notice in the mail.
---------------------------------------------------------------------------
If approved, Kinder Morgan proposes to commence construction of the
proposed facilities in October 2009, with an in-service date of mid-
year 2010.
Land Requirements for Construction
Construction and renovation of the Huntsman Storage Facility would
impact about 15.6 temporary acres where 0.8 acres would be permanently
impacted. All land disturbances would occur entirely on private lands.
Kinder Morgan is proposing to utilize existing access roads for the
proposed project. No land disturbance would be required for additional
access roads.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
to discover and address concerns the public may have about proposals.
This process is referred to as ``scoping.'' The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this Notice of Intent, the Commission staff
requests public comments on the scope of the issues to address in the
EA. All comments received are considered during the preparation of the
EA. State and local government representatives are encouraged to notify
their constituents of this proposed action and encourage them to
comment on their areas of concern.
In the EA we \2\ will discuss impacts that could occur as a result
of the construction and operation of the proposed project under these
general headings:
---------------------------------------------------------------------------
\2\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
Geology and soils,
Land use,
Water resources, fisheries, and wetlands,
Cultural resources,
Vegetation and wildlife,
Air quality and noise,
Endangered and threatened species,
Public safety.
We will also evaluate possible alternatives to the proposed project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the
[[Page 19078]]
scoping process, the EA may be published and mailed to Federal, State,
and local agencies, public interest groups, interested individuals,
affected landowners, newspapers, libraries, and the Commission's
official service list for this proceeding. A comment period will be
allotted for review if the EA is published. We will consider all
comments on the EA before we make our recommendations to the
Commission. To ensure your comments are considered, please carefully
follow the instructions in the public participation section below.
With this NOI, we are asking Federal, State, and local agencies
with jurisdiction and/or special expertise with respect to
environmental issues to formally cooperate with us in the preparation
of the EA. These agencies may choose to participate once they have
evaluated the proposal relative to their responsibilities. Additional
agencies that would like to request cooperating agency status should
follow the instructions for filing comments provided under the Public
Participation section of this NOI.
Currently Identified Environmental Issues
We have already identified an issue that we think deserves
attention based on a preliminary review of the proposed facilities and
the environmental information provided by Kinder Morgan. This
preliminary list of issues may be changed based on your comments and
our analysis.
Potential impacts may occur to the whooping crane, black-
footed ferret, spectaclecase, burrowing owl, swift fox, and mountain
plover.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the Huntsman Ridge Expansion Project. Your
comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. The more specific your comments, the more useful they will be.
To ensure that your comments are timely and properly recorded, please
send in your comments so that they will be received in Washington, DC
on or before May 20, 2009.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the project docket number CP09-109-000 with your submission.
The docket number can be found on the front of this notice. The
Commission encourages electronic filing of comments and has dedicated
eFiling expert staff available to assist you at 202-502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the Quick
Comment feature, which is located on the Commission's Internet Web site
at https://www.ferc.gov under the link to Documents and Filings. A Quick
Comment is an easy method for interested persons to submit text-only
comments on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Internet Web site at
https://www.ferc.gov under the link to Documents and Filings. eFiling
involves preparing your submission in the same manner as you would if
filing on paper, and then saving the file on your computer's hard
drive. You will attach that file as your submission. New eFiling users
must first create an account by clicking on ``Sign up'' or
``eRegister.'' You will be asked to select the type of filing you are
making. A comment on a particular project is considered a ``Comment on
a Filing;'' or
(3) You may file your comments via mail to the Commission by
sending an original and two copies of your letter to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First St., NE.,
Room 1A, Washington, DC 20426;
Label one copy of the comments for the attention of Gas Branch 2,
PJ11.2.
Environmental Mailing List
An effort is being made to send this notice to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project. This includes all landowners who are
potential right-of-way grantors, whose property may be used temporarily
for project purposes, or who own homes within distances defined in the
Commission's regulations of certain aboveground facilities.
If you do not want to send comments at this time but still want to
remain on our mailing list, please return the Information Request
(Appendix 2). If you do not return the Information Request, you will be
taken off the mailing list.
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor,'' which is an official party to the
proceeding. Intervenors play a more formal role in the process and are
able to file briefs, appear at hearings, and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in a Commission proceeding by filing a request to
intervene. Instructions for becoming an intervenor are included in the
User's Guide under the ``e-filing'' link on the Commission's Web site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on ``General Search'' and enter the
docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-9543 Filed 4-24-09; 8:45 am]
BILLING CODE P