CenterPoint Energy Gas Transmission Company; Notice of Request Under Blanket Authorization, 17472-17473 [E9-8550]
Download as PDF
17472
Federal Register / Vol. 74, No. 71 / Wednesday, April 15, 2009 / Notices
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR Part 34, of
future issuances of securities and
assumptions of liability, is April 27,
2009.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
dockets(s). For assistance with any
FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–8556 Filed 4–14–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
rwilkins on PROD1PC63 with PROPOSALS
[Docket No. ER09–903–000]
PPL New Jersey Solar, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
April 8, 2009.
This is a supplemental notice in the
above-referenced proceeding of PPL
New Jersey Solar, LLC’s application for
market-based rate authority, with an
VerDate Nov<24>2008
16:44 Apr 14, 2009
Jkt 217001
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
Part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR Part 34, of
future issuances of securities and
assumptions of liability, is April 27,
2009.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
dockets(s). For assistance with any
FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–8554 Filed 4–14–09; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP09–89–000]
CenterPoint Energy Gas Transmission
Company; Notice of Request Under
Blanket Authorization
April 8, 2008.
Take notice that on March 26, 2009,
CenterPoint Energy Gas Transmission
Company (CenterPoint), 1111 Louisiana
Street, Houston, Texas, filed in Docket
No. CP09–89–000 a prior notice request
pursuant to sections 157.205 of the
Commission’s regulations under the
Natural Gas Act (NGA), and
CenterPoint’s blanket certificate issued
in Docket No. CP82–384–000 on
September 1, 1982,1 and amended in
Docket No. CP82–384–001 on February
10, 1983.2 CenterPoint seeks
authorization to install approximately
5.6 mile of 16-inch pipe, Line F–625,
and an 8-inch delivery meter in Caddo
Parish, Louisiana, all as more fully set
forth in the application which is on file
with the Commission and open to
public inspection. The filing may also
be viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
Specifically, CenterPoint proposes to
install approximately 5.6 miles of 16inch diameter steel pipe, Line 625,
extending from a 16-inch tap on
CenterPoint’s existing Line F-West at
372+00, and an 8-inch ultrasonic meter
skid at the terminus of Line F–625
located within the Arsenal Hills Plant
facilities. The 8-inch meter station will
consist of ultrasonic and low flow
turbine meters, worker and monitor
regulators, and a control/gas
chromatograph package which includes
a Daniel gas chromatograph, moisture
analyzer and Bristol electronic gas
measurement. Additional auxiliary
materials will be installed including
filter separators, a 25 barrel drain tank,
a 24-volt DC battery system, marshalling
panels, SCADA and communications
package, transmitters, yard piping and
valves. The proposed facilities will be
designed for a maximum allowable
operating pressure of 1000 psig and a
650 psig delivery pressure with a
capacity of 80,000 Dth/d. The estimated
1 20
2 22
Frm 00026
Fmt 4703
Sfmt 4703
E:\FR\FM\15APN1.SGM
FERC ¶ 62,408 (1982).
FERC ¶ 61,148 (1983).
15APN1
Federal Register / Vol. 74, No. 71 / Wednesday, April 15, 2009 / Notices
cost of the project is $15.0 million. The
proposed project will allow CenterPoint
to provide firm transportation service to
meet the needs of a new power
generation unit being installed at the
Arsenal Hill Plant facility by American
Electric Power’s Southwestern Electric
Power Company.
Any questions regarding this
application should be directed to Larry
Thomas, Director, Rates & Regulatory,
CenterPoint Energy Gas Transmission
Company, P. O. Box 21734, Shreveport,
Louisiana 71151, or call (318) 429–2804.
Any person or the Commission’s Staff
may, within 60 days after the issuance
of the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and, pursuant to section
157.205 of the Commission’s
Regulations under the Natural Gas Act
(NGA) (18 CFR 157.205) a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request shall be
treated as an application for
authorization pursuant to section 7 of
the NGA.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the Internet in lieu
of paper. See 18 CFR 385.2001(a) (1) (iii)
and the instructions on the
Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
Comment Date: May 8, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–8550 Filed 4–14–09; 8:45 am]
rwilkins on PROD1PC63 with PROPOSALS
BILLING CODE 6717–01–P
VerDate Nov<24>2008
16:44 Apr 14, 2009
Jkt 217001
dockets(s). For assistance with any
FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER09–900–000]
Victory Garden Phase IV, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of Victory
Garden Phase IV, LLC’s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
Part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR Part 34, of
future issuances of securities and
assumptions of liability, is April 27,
2009.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
Frm 00027
Kimberly D. Bose,
Secretary.
[FR Doc. E9–8551 Filed 4–14–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
April 8, 2009.
PO 00000
17473
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[Docket No. ER09–902–000]
FPL Energy Cabazon Wind, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
April 8, 2009.
This is a supplemental notice in the
above-referenced proceeding of FPL
Energy Cabazon Wind, LLC’s
application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR Part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC,
20426, in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR Part 34, of
future issuances of securities and
assumptions of liability, is April 27,
2009.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
E:\FR\FM\15APN1.SGM
15APN1
Agencies
[Federal Register Volume 74, Number 71 (Wednesday, April 15, 2009)]
[Notices]
[Pages 17472-17473]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-8550]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP09-89-000]
CenterPoint Energy Gas Transmission Company; Notice of Request
Under Blanket Authorization
April 8, 2008.
Take notice that on March 26, 2009, CenterPoint Energy Gas
Transmission Company (CenterPoint), 1111 Louisiana Street, Houston,
Texas, filed in Docket No. CP09-89-000 a prior notice request pursuant
to sections 157.205 of the Commission's regulations under the Natural
Gas Act (NGA), and CenterPoint's blanket certificate issued in Docket
No. CP82-384-000 on September 1, 1982,\1\ and amended in Docket No.
CP82-384-001 on February 10, 1983.\2\ CenterPoint seeks authorization
to install approximately 5.6 mile of 16-inch pipe, Line F-625, and an
8-inch delivery meter in Caddo Parish, Louisiana, all as more fully set
forth in the application which is on file with the Commission and open
to public inspection. The filing may also be viewed on the Web at
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket
number excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TTY,
(202) 502-8659.
---------------------------------------------------------------------------
\1\ 20 FERC ] 62,408 (1982).
\2\ 22 FERC ] 61,148 (1983).
---------------------------------------------------------------------------
Specifically, CenterPoint proposes to install approximately 5.6
miles of 16-inch diameter steel pipe, Line 625, extending from a 16-
inch tap on CenterPoint's existing Line F-West at 372+00, and an 8-inch
ultrasonic meter skid at the terminus of Line F-625 located within the
Arsenal Hills Plant facilities. The 8-inch meter station will consist
of ultrasonic and low flow turbine meters, worker and monitor
regulators, and a control/gas chromatograph package which includes a
Daniel gas chromatograph, moisture analyzer and Bristol electronic gas
measurement. Additional auxiliary materials will be installed including
filter separators, a 25 barrel drain tank, a 24-volt DC battery system,
marshalling panels, SCADA and communications package, transmitters,
yard piping and valves. The proposed facilities will be designed for a
maximum allowable operating pressure of 1000 psig and a 650 psig
delivery pressure with a capacity of 80,000 Dth/d. The estimated
[[Page 17473]]
cost of the project is $15.0 million. The proposed project will allow
CenterPoint to provide firm transportation service to meet the needs of
a new power generation unit being installed at the Arsenal Hill Plant
facility by American Electric Power's Southwestern Electric Power
Company.
Any questions regarding this application should be directed to
Larry Thomas, Director, Rates & Regulatory, CenterPoint Energy Gas
Transmission Company, P. O. Box 21734, Shreveport, Louisiana 71151, or
call (318) 429-2804.
Any person or the Commission's Staff may, within 60 days after the
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and, pursuant to section 157.205 of
the Commission's Regulations under the Natural Gas Act (NGA) (18 CFR
157.205) a protest to the request. If no protest is filed within the
time allowed therefore, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request shall be treated as
an application for authorization pursuant to section 7 of the NGA.
The Commission strongly encourages electronic filings of comments,
protests, and interventions via the Internet in lieu of paper. See 18
CFR 385.2001(a) (1) (iii) and the instructions on the Commission's Web
site (https://www.ferc.gov) under the ``e-Filing'' link. Persons unable
to file electronically should submit an original and 14 copies of the
protest or intervention to the Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC 20426.
Comment Date: May 8, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-8550 Filed 4-14-09; 8:45 am]