Approval and Promulgation of Air Quality Implementation Plans; Pennsylvania; Update to Materials Incorporated by Reference, 13014-13054 [E9-6007]
Download as PDF
13014
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
ENVIRONMENTAL PROTECTION
AGENCY
40 CFR Part 52
[PA200–4202; FRL–8774–8]
Approval and Promulgation of Air
Quality Implementation Plans;
Pennsylvania; Update to Materials
Incorporated by Reference
AGENCY: Environmental Protection
Agency (EPA).
ACTION: Final rule; administrative
change.
PWALKER on PROD1PC71 with RULES2
SUMMARY: EPA is updating the materials
submitted by Pennsylvania that are
incorporated by reference (IBR) into the
State implementation plan (SIP). The
regulations affected by this update have
been previously submitted by the
Pennsylvania Department of
Environmental Protection and approved
by EPA. This update affects the SIP
materials that are available for public
inspection at the National Archives and
Records Administration (NARA), the
Air and Radiation Docket and
Information Center located at EPA
Headquarters in Washington, D.C., and
the Regional Office.
DATES: Effective Date: This action is
effective March 25, 2009.
ADDRESSES: SIP materials which are
incorporated by reference into 40 CFR
part 52 are available for inspection at
the following locations: Air Protection
Division, U.S. Environmental Protection
Agency, Region III, 1650 Arch Street,
Philadelphia, Pennsylvania 19103; the
Air and Radiation Docket and
Information Center, EPA Headquarters
Library, Room Number 3334, EPA West
Building, 1301 Constitution Ave., NW.,
Washington, DC 20460, and the
National Archives and Records
Administration. If you wish to obtain
materials from a docket in the EPA
Headquarters Library, please call the
Office of Air and Radiation (OAR)
Docket/Telephone number: (202) 566–
1742; or the National Archives and
Records Administration (NARA). For
information on the availability of this
material at NARA, call 202–741–6030,
or go to: https://www.archives.gov/
federal_register/
code_of_federal_regulations/
ibr_locations.html.
FOR FURTHER INFORMATION CONTACT:
Harold A. Frankford, (215) 814–2108 or
by e-mail at frankford.harold@epa.gov.
SUPPLEMENTARY INFORMATION:
I. Background
The SIP is a living document which
the State revises as necessary to address
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
the unique air pollution problems.
Therefore, EPA, from time to time must
take action on SIP revisions containing
new and/or revised regulations to make
them part of the SIP. On May 22, 1997
(62 FR 27968), EPA revised the
procedures for incorporating by
reference Federally-approved SIPs, as a
result of consultations between EPA and
the Office of the Federal Register (OFR).
The description of the revised SIP
document, IBR procedures and
‘‘Identification of plan’’ format are
discussed in further detail in the May
22, 1997 Federal Register document. On
February 25, 2005 (70 FR 9450), EPA
published a document in the Federal
Register beginning the new IBR
procedure for Pennsylvania, including
Philadelphia and Allegheny Counties.
On January 3, 2007 (72 FR 200), EPA
published an update to the IBR
materials for Pennsylvania, as of
November 1, 2006.
II. EPA Action
In this document, EPA is doing the
following:
1. Announcing the update to the IBR
material as of December 1, 2008. This
update includes specifically-identified
material which has not been revised
between November 1, 2006 and
December 1, 2008.
2. Making corrections to the following
entries listed in the paragraph
52.2020(c)(1) table, as described below:
a. Restoring the entry for Section
129.51 (Sources of VOC’s-General). This
rule, which is currently part of the
Pennsylvania SIP, was listed in the
original version of the table published at
40 CFR 52.2020(c)(1) (See, 70 FR 9450
at 9457), but inadvertently removed in
a subsequent IBR update rulemaking
action.
b. Correcting the Federal Register
page citation in the ‘‘EPA approval
date’’ column for rules in Title 25,
Chapter 127, subchapters A, B, C, F, H,
and I which EPA had approved on July
30, 1996 (61 FR 39594 and 61 FR
39597).
c. Correcting the Federal Register
page citation in the ‘‘EPA approval
date’’ column for rules in Title 25,
Sections 139.5, 139.13, 139.32, 139.102
and 139.103 which EPA had approved
on July 30, 1996 (61 FR 39594 and 61
FR 39597).
d. Removing a duplicate and outdated
entry for Title 67, Section 175.41.
3. Making corrections to the following
entries listed in the paragraph
52.2020(c)(2) table, as described below:
a. Removing the entry for Aricle XX,
Section 532. EPA has determined that
this entry has been erroneously
included because the SIP approval
PO 00000
Frm 00002
Fmt 4701
Sfmt 4700
action taken on January 21, 1983 (48 FR
2768) specifically excluded EPA action
on this Article XX rule (48 FR 2768 at
2769).
b. Correcting the Federal Register
page citation in the ‘‘EPA approval
date’’ column for Article XXI,
Regulation 2105.14.
4. In the 52.2020(d)(1) table,
correcting text errors in the ‘‘County’’
and ‘‘State effective date’’ column in the
entry for Cogentrix of Pennsylvania Inc.
5. Making corrections to the following
entries listed in the paragraph
52.2020(e)(1) table, as described below:
a. Source Testing Manual—correcting
the Federal Register page citation in the
‘‘EPA approval date’’ column.
b. Continuous Source Testing
Manual—correcting the text in ‘‘Name’’
and ‘‘Geographic area’’ columns and
correcting the Federal Register page
citation in the ‘‘EPA approval date’’
column.
c. 8-hour Ozone Maintenance Plan
and 2002 Base Year Emissions
Inventory, Erie County—relocating this
entry within the chart so as to be in its
proper chronological order and adding a
reference in the ‘‘Additional
explanation’’ column regarding a related
correction Federal Register notice.
d. 8-hour Ozone Maintenance Plan
and 2002 Base Year Emissions
Inventory, Reading Area (Berks
County)—correcting the date format in
‘‘State submittal date’’ column and
adding a reference in the ‘‘Additional
explanation’’ column regarding a related
correction Federal Register notice.
e. 8-hour Ozone Maintenance Plan
and 2002 Base Year Emissions
Inventory, Johnstown (Cambria County)
and Mercer County—adding reference
in the ‘‘Additional explanation’’ column
regarding related correction Federal
Register notices.
f. 8-hour Ozone Maintenance Plan
and 2002 Base Year Emissions
Inventory, Wayne County—correcting
the date format in ‘‘State submittal date’’
column.
EPA has determined that today’s rule
falls under the ‘‘good cause’’ exemption
in section 553(b)(3)(B) of the
Administrative Procedures Act (APA)
which, upon finding ‘‘good cause,’’
authorizes agencies to dispense with
public participation, and section
553(d)(3) which allows an agency to
make a rule effective immediately
(thereby avoiding the 30-day delayed
effective date otherwise provided for in
the APA). Today’s rule simply codifies
provisions which are already in effect as
a matter of law in Federal and approved
State programs. Under section 553 of the
APA, an agency may find good cause
where procedures are ‘‘impractical,
E:\FR\FM\25MRR2.SGM
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
unnecessary, or contrary to the public
interest.’’ Public comment is
‘‘unnecessary’’ and ‘‘contrary to the
public interest’’ since the codification
only reflects existing law. Immediate
notice in the CFR benefits the public by
removing outdated citations and
incorrect chart entries.
III. Statutory and Executive Order
Reviews
PWALKER on PROD1PC71 with RULES2
A. General Requirements
Under the Clean Air Act, the
Administrator is required to approve a
SIP submission that complies with the
provisions of the Act and applicable
Federal regulations. 42 U.S.C. 7410(k);
40 CFR 52.02(a). Thus, in reviewing SIP
submissions, EPA’s role is to approve
state choices, provided that they meet
the criteria of the Clean Air Act.
Accordingly, this action merely
approves state law as meeting Federal
requirements and does not impose
additional requirements beyond those
imposed by state law. For that reason,
this action:
• Is not a ‘‘significant regulatory
action’’ subject to review by the Office
of Management and Budget under
Executive Order 12866 (58 FR 51735,
October 4, 1993);
• Does not impose an information
collection burden under the provisions
of the Paperwork Reduction Act (44
U.S.C. 3501 et seq.);
• Is certified as not having a
significant economic impact on a
substantial number of small entities
under the Regulatory Flexibility Act (5
U.S.C. 601 et seq.);
• Does not contain any unfunded
mandate or significantly or uniquely
affect small governments, as described
in the Unfunded Mandates Reform Act
of 1995 (Pub. L. 104–4);
• Does not have Federalism
implications as specified in Executive
Order 13132 (64 FR 43255, August 10,
1999);
• Is not an economically significant
regulatory action based on health or
safety risks subject to Executive Order
13045 (62 FR 19885, April 23, 1997);
• Is not a significant regulatory action
subject to Executive Order 13211 (66 FR
28355, May 22, 2001);
• Is not subject to requirements of
Section 12(d) of the National
Technology Transfer and Advancement
Act of 1995 (15 U.S.C. 272 note) because
application of those requirements would
be inconsistent with the Clean Air Act;
and
• Does not provide EPA with the
discretionary authority to address, as
appropriate, disproportionate human
health or environmental effects, using
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
practicable and legally permissible
methods, under Executive Order 12898
(59 FR 7629, February 16, 1994).
B. Submission to Congress and the
Comptroller General
The Congressional Review Act, 5
U.S.C. 801 et seq., as added by the Small
Business Regulatory Enforcement
Fairness Act of 1996, generally provides
that before a rule may take effect, the
agency promulgating the rule must
submit a rule report, which includes a
copy of the rule, to each House of the
Congress and to the Comptroller General
of the United States. EPA will submit a
report containing this rule and other
required information to the U.S. Senate,
the U.S. House of Representatives, and
the Comptroller General of the United
States prior to publication of the rule in
the Federal Register. This rule is not a
‘‘major rule’’ as defined by 5 U.S.C.
804(2).
C. Petitions for Judicial Review
EPA has also determined that the
provisions of section 307(b)(1) of the
Clean Air Act pertaining to petitions for
judicial review are not applicable to this
action. Prior EPA rulemaking actions for
each individual component of the
Pennsylvania SIP compilations had
previously afforded interested parties
the opportunity to file a petition for
judicial review in the United States
Court of Appeals for the appropriate
circuit within 60 days of such
rulemaking action. Thus, EPA sees no
need in this action to reopen the 60-day
period for filing such petitions for
judicial review for this ‘‘Identification of
plan’’ reorganization update action for
Pennsylvania.
List of Subjects in 40 CFR Part 52
Environmental protection, Air
pollution control, Carbon monoxide,
Incorporation by reference,
Intergovernmental relations, Lead,
Nitrogen dioxide, Ozone, Particulate
matter, Reporting and recordkeeping
requirements, Sulfur oxides, Volatile
organic compounds.
Dated: February 2, 2009.
William T. Wisniewski,
Acting Regional Administrator, Region III.
■
40 CFR part 52 is amended as follows:
PART 52—[AMENDED]
1. The authority for citation for part 52
continues to read as follows:
■
Authority: 42 U.S.C. 7401 et seq.
PO 00000
Frm 00003
Fmt 4701
Sfmt 4700
13015
Subpart NN—Pennsylvania
2. Section 52.2020 is amended by
revising paragraphs (b), (c), (d), and
(e)(1) to read as follows:
■
§ 52.2020
Identification of plan.
*
*
*
*
*
(b) Incorporation by reference.
(1) Material listed as incorporated by
reference in paragraphs (c) and (d) of
this section was approved for
incorporation by reference by the
Director of the Federal Register in
accordance with 5 U.S.C. 552(a) and 1
CFR part 51. Material incorporated as it
exists on the date of the approval, and
notice of any change in the material will
be published in the Federal Register.
Entries in paragraphs (c) and (d) of this
section with EPA approval dates on or
after December 1, 2008 will be
incorporated by reference in the next
update to the SIP compilation.
(2)(i) EPA Region III certifies that the
following rules/regulations and sourcespecific requirements provided by EPA
at the addresses in paragraph (b)(3) of
this section are an exact duplicate of the
officially promulgated State rules/
regulations and source-specific
requirements which have been
approved as part of the State
implementation plan as of December 1,
2008:
(A) Materials in Notebook ‘‘1. 40 CFR
52.2020(c)(1)—Pa Department of
Transportation (Pa DOT); 2. 40 CFR
52.2020(c)(2)—Allegheny County Health
Department (ACHD); 3. 40 CFR
52.2020(c)(3)—Philadelphia Air
Management Services (AMS).’’
(B) Materials in Notebook ‘‘40 CFR
52.2020(d)(1)—Source-specific
Requirements—Volume 6.’’
(ii) EPA Region III certifies that the
following rules/regulations and source
specifc requirements provided by EPA
at the addresses in paragraph (b)(3) of
this section are an exact duplicate of the
officially promulgated State rules/
regulations which have been approved
as part of the State implementation plan
as of November 1, 2006. No additional
revisions were made between November
1, 2006 and December 1, 2008:
(A) Materials in Notebook ‘‘40 CFR
52.2020(c)(1)—Pa Department of
Environmental Protection (DEP).’’
(B) Materials in Notebook ‘‘40 CFR
52.2020(d)(1)—Source-specific
Requirements—Volume 1, Part 1.’’
(C) Materials in Notebook ‘‘40 CFR
52.2020(d)(1)—Source-specific
Requirements—Volume 1, Part 2.’’
(D) Materials in Notebook ‘‘40 CFR
52.2020(d)(1)—Source-specific
Requirements—Volume 2, Part 1.’’
E:\FR\FM\25MRR2.SGM
25MRR2
13016
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(E) Materials in Notebook ‘‘40 CFR
52.2020(d)(1)—Source-specific
Requirements—Volume 2, Part 2.’’
(F) Materials in Notebook ‘‘40 CFR
52.2020(d)(1)—Source-specific
Requirements—Volume 3.’’
(G) Materials in Notebook ‘‘40 CFR
52.2020(d)(1)—Source-specific
Requirements—Volume 4.’’
(H) Materials in Notebook ‘‘40 CFR
52.2020(d)(1)—Source-specific
Requirements—Volume 5.’’
(I) Materials in Notebook ‘‘40 CFR
52.2020(d)(2)–(d)(4)—Source-specific
Requirements.’’
(3) Copies of the materials
incorporated by reference may be
inspected at the EPA Region III Office at
1650 Arch Street, Philadelphia, PA
19103. For further information, call
(215) 814–2108; the EPA, Air and
Radiation Docket and Information
Center, Room Number 3334, EPA West
Building, 1301Constitution Avenue
NW., Washington, DC 20460. For further
information, call (202) 566–1742; or at
the National Archives and Records
Administration (NARA). For
information on the availability of this
material at NARA, call 202–741–6030,
or go to: https://www.archives.gov/
federal_register/
code_of_federal_regulations/
ibr_locations.html.
(c) EPA-Approved Regulations
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS
State citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Title 25—Environmental Protection
Article III—Air Resources
Chapter 121—General Provisions
Section 121.1 .................
Definitions ........................................
12/11/04
9/29/06, 71 FR 57428 ....
Section 121.2 .................
Section 121.3 .................
Section 121.4 .................
3/20/72
3/20/72
5/23/92
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
12/22/94, 59 FR 65971 ..
Section 121.7 .................
Section 121.8 .................
Purpose ............................................
Applicability ......................................
Regional Organization of the Department.
Prohibition of Air Pollution ...............
Compliance responsibilities .............
3/20/72
8/13/77
5/31/72, 37 FR 10842 ....
12/17/79, 44 FR 73031 ..
Section 121.9 .................
Section 121.10 ...............
Section 121.11 ...............
Circumvention ..................................
Existing orders .................................
Severability clause ...........................
3/20/72
3/20/72
3/20/72
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
Revised; SIP-effective date is 10/
30/06.
(c)(1).
(c)(1).
(c)(94).
(c)(1).
(c)(21); correction published 8/22/80
(45 FR 56060).
(c)(1).
(c)(1).
(c)(1); no longer in PA DEP rules.
Chapter 123—Standards for Contaminants
Fugitive Emissions
Section 123.1(a) through
(c).
Section 123.2 .................
Prohibition of certain fugitive emissions.
Fugitive particulate matter ...............
8/29/77
12/17/79, 44 FR 73031 ..
8/13/83
7/27/84, 49 FR 30183 ....
(c)(21); Paragraph 123.1(d) is not in
the SIP.
(c)(60).
Particulate Matter Emissions
Section 123.11 ...............
Appendix A [Graph] ........
Section 123.12 ...............
Section 123.13(a)
through (c).
Appendix B [Graph] ........
Appendix C [Graph] ........
Combustion units .............................
Particulate
Matter—Combustion
Units.
Incinerators ......................................
Processes ........................................
Particulate Matter—Processes Listed in Table 1.
Particulate Matter—Processes Not
Listed in Table 1.
3/20/72
3/20/72
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
(c)(1).
(c)(1).
3/20/72
8/27/80
5/31/72, 37 FR 10842 ....
11/13/81, 46 FR 55971 ..
3/20/72
5/31/72, 37 FR 10842 ....
(c)(1).
(c)(39); paragraph 123.13(d) is not
in the SIP.
(c)(1).
3/20/72
5/31/72, 37 FR 10842 ....
(c)(1).
Sulfur Compound Emissions
General ............................................
Combustion units. [General provisions—air basins and non-air basins.
Combustion units—non air basins ...
3/20/72
3/20/72
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
(c)(1).
(c)(1).
Section 123.22(a) ...........
8/1/79
8/18/81, 46 FR 43423 ....
Section 123.22(b) ...........
PWALKER on PROD1PC71 with RULES2
Section 123.21 ...............
Section 123.22 ...............
Combustion units—Erie Air Basin ...
8/1/79
8/8/79, 44 FR 46465 ......
Section 123.22(c) ...........
Combustion units—Southeast PA
Air Basin.
Combustion units—Upper Beaver
Valley Air Basin.
Combustion units—Lower Beaver
Valley Air Basin.
Sulfur Oxides—Combustion Units ...
10/1/78
6/4/79, 44 FR 31980 ......
(c)(36); approved as part of the
control strategy for the Armstrong
County sulfur dioxide nonattainment area.
(c)(20); correction published 1/23/80
(45 FR 5303).
(c)(18).
8/21/82
7/5/83, 48 FR 30630 ......
(c)(53).
1/1/81
12/16/81, 46 FR 61267 ..
(c)(40).
3/20/72
5/31/72, 37 FR 10842 ....
(c)(1).
Section 123.22(c) ...........
Section 123.22(d) ...........
Figure 4 [Graph] .............
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00004
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13017
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 123.24 ...............
Section 123.25 ...............
Primary zinc smelters ......................
Monitoring requirements ..................
8/11/75
10/27/90
Additional explanation/
§ 52.2063 citation
EPA approval date
4/30/76, 41 FR 18077 ....
6/30/93, 58 FR 34911 ....
(c)(14).
(c)(81).
5/31/72, 37 FR 10842 ....
(c)(1); SIP version of Section
123.31 is different from State
version.
Odor Emissions
Section 123.31 ...............
Limitations ........................................
3/20/72
Visible Emissions
Section 123.41 ...............
Section 123.42 (Except
paragraph 123.42(4)).
Section 123.43 ...............
Section 123.44 ...............
Section 123.45 ...............
Appendix D [Chart] .........
Section 123.46 ...............
Limitations ........................................
Exceptions .......................................
3/20/72
3/20/72
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
Measuring Techniques ....................
Limitations of visible fugitive air contaminants from operation of any
coke oven battery.
Alternative opacity limitations ..........
Alternate Opacity Limitation—Application.
Monitoring requirements ..................
3/20/72
12/27/97
5/31/72, 37 FR 10842 ....
6/11/02, 67 FR 39854 ....
(c)(1).
(c)(1); Paragraph 123.42(4) is declared not in SIP at (c)(21).
(c)(1).
(c)(189).
6/20/81
6/20/81
1/19/83, 48 FR 2319 ......
1/19/83, 48 FR 2319 ......
(c)(48).
(c)(48).
6/20/81
1/19/83, 48 FR 2319 ......
(c)(48).
Nitrogen Compound Emissions
Section 123.51 ...............
Monitoring requirements ..................
10/20/90
9/23/92, 57 FR 43905 ....
(c)(74).
NOX Allowance Requirements
Section 123.101 .............
Section 123.102 .............
Section 123.103 .............
Section 123.104 .............
Section
Section
Section
Section
123.105
123.106
123.107
123.108
.............
.............
.............
.............
Section 123.109 .............
Section 123.110 .............
Section 123.111 .............
Section 123.112 .............
Section 123.113 .............
Section 123.114 .............
Section 123.115 .............
Section 123.116 .............
Section 123.117 .............
Section 123.118 .............
Section 123.119 .............
Section 123.120 .............
Appendix E [Chart] .........
Purpose ............................................
Source NOX allowance requirements and NOX allowance control
period.
General NOX allowance provisions
Source authorized account representative requirements.
NATS provisions ..............................
NOX allowance transfer protocol .....
NOX allowance transfer procedures
Source emissions monitoring requirements.
Source emissions reporting requirements.
Source compliance requirements ....
Failure to meet source compliance
requirements.
Source operating permit provision
requirements.
Source recordkeeping requirements
General NOX allocation provisions ..
Initial NOX allowance NOX allocations.
Source opt-in provisions ..................
New NOX affected source provisions.
Emission reduction credit provisions
Bonus NOX allowance awards ........
Audit .................................................
Appendix E [NOX Allowances Chart]
11/1/97
11/1/97
6/6/00, 65 FR 35840 ......
6/6/00, 65 FR 35840 ......
(c)(145).
(c)(145).
11/1/97
11/1/97
6/6/00, 65 FR 35840 ......
6/6/00, 65 FR 35840 ......
(c)(145).
(c)(145).
11/1/97
11/1/97
11/1/97
11/1/97
6/6/00,
6/6/00,
6/6/00,
6/6/00,
......
......
......
......
(c)(145).
(c)(145).
(c)(145).
(c)(145).
11/1/97
6/6/00, 65 FR 35840 ......
(c)(145).
11/1/97
11/1/97
6/6/00, 65 FR 35840 ......
6/6/00, 65 FR 35840 ......
(c)(145).
(c)(145).
11/1/97
6/6/00, 65 FR 35840 ......
(c)(145)
11/1/97
11/1/97
3/11/00
6/6/00, 65 FR 35840 ......
6/6/00, 65 FR 35840 ......
6/6/00, 65 FR 35840 ......
(c)(145).
(c)(145).
(c)(145).
11/1/97
11/1/97
6/6/00, 65 FR 35840 ......
6/6/00, 65 FR 35840 ......
(c)(145).
(c)(145).
11/1/97
11/1/97
11/1/97
3/11/00
6/6/00,
6/6/00,
6/6/00,
6/6/00,
(c)(145).
(c)(145).
(c)(145).
(c)(145).
65
65
65
65
65
65
65
65
FR
FR
FR
FR
FR
FR
FR
FR
35840
35840
35840
35840
35840
35840
35840
35840
......
......
......
......
PWALKER on PROD1PC71 with RULES2
Chapter 126—Standard for Motor Fuels
Subchapter A—Oxygenate Content of Gasoline
Section
Section
Section
Section
126.101
126.102
126.103
126.104
VerDate Nov<24>2008
.............
.............
.............
.............
General ............................................
Sampling and testing .......................
Recordkeeping and reporting ..........
Labeling requirements .....................
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00005
8/19/95
8/19/95
8/19/95
8/19/95
Fmt 4701
12/17/99,
12/17/99,
12/17/99,
12/17/99,
Sfmt 4700
64
64
64
64
FR
FR
FR
FR
70589
70589
70589
70589
E:\FR\FM\25MRR2.SGM
..
..
..
..
(c)(142).
(c)(142).
(c)(142).
(c)(142).
25MRR2
13018
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Subchapter C—Gasoline Volatility Requirements
Section 126.301 (a)
through (c).
Section 126.302 (Except
Paragraph (a)(6) pertaining to RFG).
Section 126.303(a) .........
Compliant fuel requirement .............
11/1/97
6/8/98, 63 FR 31116 ......
(c)(131).
Recordkeeping and reporting ..........
11/1/97
6/8/98, 63 FR 31116 ......
(c)(131).
Compliance and test methods .........
11/1/97
6/8/98, 63 FR 31116 ......
(c)(131).
Subchapter D—Motor Vehicle Emissions Control Program
General Provisions
Section 126.401 .............
Section 126.402 .............
Purpose ............................................
NLEV scope and applicability ..........
12/5/98
12/5/98
12/28/99, 64 FR 72564 ..
12/28/99, 64 FR 72564 ..
(c)(141)(i)(C).
(c)(141)(i)(C).
Pennsylvania Clean Vehicles Program
Section 126.411 .............
Section 126.412 .............
Section 126.413 .............
General Requirements .....................
Emission requirements ....................
Exemptions ......................................
12/5/98
12/5/98
12/5/98
12/28/99, 64 FR 72564 ..
12/28/99, 64 FR 72564 ..
12/28/99, 64 FR 72564 ..
(c)(141)(i)(C).
(c)(141)(i)(C).
(c)(141)(i)(C).
Applicable Motor Vehicle Testing
Section 126.421 .............
Section 126.422 .............
Section 126.423 .............
Section 126.424 .............
Section 126.425 .............
New motor vehicle certification testing.
New motor vehicle compliance testing.
Assembly line testing .......................
In-use motor vehicle enforcement
testing.
In-use surveillance testing ...............
12/5/98
12/28/99, 64 FR 72564 ..
(c)(141)(i)(C).
12/5/98
12/28/99, 64 FR 72564 ..
(c)(141)(i)(C).
12/5/98
12/5/98
12/28/99, 64 FR 72564 ..
12/28/99, 64 FR 72564 ..
(c)(141)(i)(C).
(c)(141)(i)(C).
12/5/98
12/28/99, 64 FR 72564 ..
(c)(141)(i)(C).
Motor Vehicle Manufacturers’ Obligations
Section 126.431 .............
Section 126.432 .............
Warranty and recall .........................
Reporting requirements ...................
12/5/98
12/5/98
12/28/99, 64 FR 72564 ..
12/28/99, 64 FR 72564 ..
(c)(141)(i)(C).
(c)(141)(i)(C).
Motor Vehicle Dealer Responsibilities
Section 126.441 .............
Responsibilities of motor vehicle
dealers.
12/5/98
12/28/99, 64 FR 72564 ..
(c)(141)(i)(C).
Chapter 127—Construction, Modification, Reactivation, and Operation of Sources
Subchapter A—General
Section 127.1 .................
Section 127.3 .................
Purpose ............................................
Operational flexibility ........................
11/26/94
11/26/94
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
(c)(110)(i)(C).
Subchapter B—Plan Approval Requirements
127.11 ...............
127.11a .............
127.12 ...............
127.12a .............
127.12b .............
127.12c ..............
Section
Section
Section
Section
PWALKER on PROD1PC71 with RULES2
Section
Section
Section
Section
Section
Section
127.13 ...............
127.13a .............
127.13b .............
127.13c ..............
Section
Section
Section
Section
127.14
127.25
127.32
127.35
VerDate Nov<24>2008
...............
...............
...............
...............
Plan approval requirements .............
Reactivation of sources ...................
Content of applications ....................
Compliance review ..........................
Plan approval terms and conditions
Plan approval reporting requirements.
Extensions .......................................
Plan approval changes for cause ....
Denial of Plan approval application
Notice of basis for certain plan approval decisions.
Exemptions ......................................
Compliance requirement ..................
Transfer of plan approvals ...............
Maximum achievable control technology standards for hazardous
air pollutants.
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00006
11/26/94
11/26/94
11/26/94
11/26/94
11/26/94
11/26/94
7/30/96,
7/30/96,
7/30/96,
7/30/96,
7/30/96,
7/30/96,
61
61
61
61
61
61
FR
FR
FR
FR
FR
FR
39597
39597
39597
39597
39597
39597
....
....
....
....
....
....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
11/26/94
11/26/94
11/26/94
11/26/94
7/30/96,
7/30/96,
7/30/96,
7/30/96,
61
61
61
61
FR
FR
FR
FR
39597
39597
39597
39597
....
....
....
....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
11/26/94
11/26/94
11/26/94
11/26/94
7/30/96,
7/30/96,
7/30/96,
7/30/96,
61
61
61
61
FR
FR
FR
FR
39597
39597
39597
39597
....
....
....
....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13019
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 127.36 ...............
Health risk-based emission standards and operating practice requirements.
Public Notice ....................................
Contents of notice ............................
Filing protests ..................................
Consideration of protests .................
Conferences and hearings ..............
Conference or hearing procedure ...
Conference or hearing record .........
Plan approval disposition .................
Section
Section
Section
Section
Section
Section
Section
Section
127.44
127.45
127.46
127.47
127.48
127.49
127.50
127.51
...............
...............
...............
...............
...............
...............
...............
...............
Additional explanation/
§ 52.2063 citation
EPA approval date
11/26/94
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
11/26/94
11/26/94
8/13/83
11/26/94
8/13/83
11/26/94
11/26/94
11/26/94
7/30/96,
7/30/96,
7/27/84,
7/30/96,
7/27/84,
7/30/96,
7/30/96,
7/30/96,
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(60).
(c)(110)(i)(C).
(c)(60).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
61
61
49
61
49
61
61
61
FR
FR
FR
FR
FR
FR
FR
FR
39597
39597
30183
39597
30183
39597
39597
39597
....
....
....
....
....
....
....
....
Subchapter D—Prevention of Significant Deterioration of Air Quality
Section 127.81 ...............
Section 127.82 ...............
Section 127.83 ...............
Purpose ............................................
Scope ...............................................
Adoption of Program ........................
6/18/83
6/18/83
6/18/83
8/21/84, 49 FR 33127 ....
8/21/84, 49 FR 33127 ....
8/21/84, 49 FR 33127 ....
(c)(57).
(c)(57).
(c)(57).
Subchapter E—New Source Review
Section 127.201 .............
Section 127.202 .............
Section 127.203 .............
Section 127.204 .............
Section
Section
Section
Section
Section
Section
Section
Section
Section
Section
Section
Section
Section
127.205
127.206
127.207
127.208
127.209
127.210
127.211
127.212
127.213
127.214
127.215
127.216
127.217
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
General requirements ......................
Effective date ...................................
Facilities subject to special permit
requirements.
Emissions subject to this subchapter.
Special permit requirements ............
ERC general requirements ..............
ERC generation and creation ..........
ERC use and transfer requirements
ERC registry system ........................
Offset ratios .....................................
Applicability determination ...............
Portable facilities ..............................
Construction and demolition ............
Exemption ........................................
Reactivation .....................................
Circumvention ..................................
Clean Air Act Titles III–V applicability.
1/15/94
1/15/94
1/15/94
12/9/97, 62 FR 64722 ....
12/9/97, 62 FR 64722 ....
12/9/97, 62 FR 64722 ....
(c)(107).
(c)(107).
(c)(107).
1/15/94
12/9/97, 62 FR 64722 ....
(c)(107).
1/15/94
1/15/94
1/15/94
1/15/94
1/15/94
1/15/94
1/15/94
1/15/94
1/15/94
1/15/94
1/15/94
1/15/94
1/15/94
12/9/97,
12/9/97,
12/9/97,
12/9/97,
12/9/97,
12/9/97,
12/9/97,
12/9/97,
12/9/97,
12/9/97,
12/9/97,
12/9/97,
12/9/97,
(c)(107).
(c)(107).
(c)(107).
(c)(107).
(c)(107).
(c)(107).
(c)(107).
(c)(107).
(c)(107).
(c)(107).
(c)(107).
(c)(107).
(c)(107).
62
62
62
62
62
62
62
62
62
62
62
62
62
FR
FR
FR
FR
FR
FR
FR
FR
FR
FR
FR
FR
FR
64722
64722
64722
64722
64722
64722
64722
64722
64722
64722
64722
64722
64722
....
....
....
....
....
....
....
....
....
....
....
....
....
Subchapter F—Operating Permit Requirements
General
Section 127.401 .............
Section 127.402 .............
Section 127.403 .............
Section 127.404 .............
Scope ...............................................
General provisions ...........................
Permitting of sources operating lawfully without a permit.
Compliance schedule for repermitting.
11/26/94
11/26/94
11/26/94
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
11/26/94
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
Permit Applications
Section
Section
Section
Section
127.411
127.412
127.413
127.414
.............
.............
.............
.............
Content of applications. ...................
Compliance review forms ................
Municipal notification .......................
Supplemental information ................
11/26/94
11/26/94
11/26/94
11/26/94
7/30/96,
7/30/96,
7/30/96,
7/30/96,
61
61
61
61
FR
FR
FR
FR
39597
39597
39597
39597
....
....
....
....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
11/26/94
11/26/94
11/26/94
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
11/26/94
11/26/94
11/26/94
11/26/94
11/26/94
11/26/94
11/26/94
7/30/96,
7/30/96,
7/30/96,
7/30/96,
7/30/96,
7/30/96,
7/30/96,
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
Review of Applications
PWALKER on PROD1PC71 with RULES2
Section 127.421 .............
Section 127.422 .............
Section 127.423 .............
Section
Section
Section
Section
Section
Section
Section
127.424
127.425
127.426
127.427
127.428
127.429
127.430
VerDate Nov<24>2008
.............
.............
.............
.............
.............
.............
.............
Review of Applications ....................
Denial of permits ..............................
Notice of basis for certain operating
permit decisions.
Public notice ....................................
Contents of notice ............................
Filing protests ..................................
Consideration of protest ..................
Conferences and hearings ..............
Conference or hearing procedure ...
Conference or hearing record .........
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00007
Fmt 4701
Sfmt 4700
61
61
61
61
61
61
61
FR
FR
FR
FR
FR
FR
FR
39597
39597
39597
39597
39597
39597
39597
....
....
....
....
....
....
....
E:\FR\FM\25MRR2.SGM
25MRR2
13020
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 127.431 .............
Operating permit disposition ............
11/26/94
Additional explanation/
§ 52.2063 citation
EPA approval date
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
Operating Permit Conditions
Section 127.441 .............
Section
Section
Section
Section
127.442
127.443
127.444
127.445
.............
.............
.............
.............
Section 127.446 .............
Section 127.447 .............
Section 127.448 .............
Section 127.449 .............
Section 127.450 .............
Operating permit terms and conditions.
Reporting requirements ...................
Operating permit requirements ........
Compliance requirements ................
Operating permit compliance schedules.
Operating permit duration ................
Alternate operating scenarios ..........
Emissions trading at facilities with
Federally enforceable emissions
cap.
De minimis emission increases .......
Administrative
operating
permit
amendments.
11/26/94
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
11/26/94
11/26/94
11/26/94
11/26/94
7/30/96,
7/30/96,
7/30/96,
7/30/96,
....
....
....
....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
11/26/94
11/26/94
11/26/94
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
11/26/94
11/26/94
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
(c)(110)(i)(C).
61
61
61
61
FR
FR
FR
FR
39597
39597
39597
39597
Operating Permit Modifications
Section 127.461 .............
Section 127.462 .............
Section 127.463 .............
Section 127.464 .............
Operating permit changes for cause
Minor operating permit modifications
Operating permit revisions to incorporate applicable standards.
Transfer of operating permits ..........
11/26/94
11/26/94
11/26/94
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
11/26/94
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
Subchapter H—General Plan Approvals and Operating Permits
General
Section 127.601 .............
Scope ...............................................
11/26/94
7/30/96, 61 FR 39594 ....
(c)(111).
Issuance of General Plan Approvals and General Operating Permits
Section 127.611 .............
Section 127.612 .............
General plan approvals and general
operating permits.
Public notice and review period ......
11/26/94
7/30/96, 61 FR 39594 ....
(c)(111).
11/26/94
7/30/96, 61 FR 39594 ....
(c)(111).
Use of General Plan Approvals and Permits
Section 127.621 .............
Section 127.622 .............
Application for use of general plan
approvals and general operating
permits.
Compliance with general plan approvals and general operating
permits.
11/26/94
7/30/96, 61 FR 39594 ....
(c)(111).
11/26/94
7/30/96, 61 FR 39594 ....
(c)(111).
Subchapter I—Plan Approval and Operating Permit Fees
Section 127.701 .............
Section 127.702 .............
Section 127.703 .............
Section 127.707 .............
General provisions ...........................
Plan approval fees ...........................
Operating permit fees under Subchapter F.
Failure to pay fee .............................
11/26/94
11/26/94
11/26/94
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
(c)(110)(i)(C).
(c)(110)(i)(C).
11/26/94
7/30/96, 61 FR 39597 ....
(c)(110)(i)(C).
Subchapter J—General Conformity
Section 127.801 .............
Section 127.802 .............
Purpose ............................................
Adoption of Standards .....................
11/9/96
11/9/96
9/29/97, 62 FR 50870 ....
9/29/97, 62 FR 50870 ....
(c)(126).
(c)(126).
Chapter 129—Standards for Sources
PWALKER on PROD1PC71 with RULES2
Miscellaneous Sources
Section 129.11 ...............
Section 129.12 ...............
Section 129.13 ...............
APPENDIX A ..................
Section 129.14 ...............
VerDate Nov<24>2008
Nitric acid plants ..............................
Sulfuric acid plants ..........................
Sulfur recovery plants ......................
Allowable emissions, sulfur oxides—sulfur recovery plants.
Open burning operations .................
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00008
3/20/72
3/20/72
3/20/72
4/23/94
8/9/76
Fmt 4701
5/31/72,
5/31/72,
5/31/72,
3/23/98,
37
37
37
63
FR
FR
FR
FR
10842
10842
10842
13789
....
....
....
....
8/19/80, 45 FR 55178 ....
Sfmt 4700
E:\FR\FM\25MRR2.SGM
(c)(1).
(c)(1).
(c)(1).
(c)(129).
(c)(33).
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13021
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 129.15 ...............
Coke pushing operations .................
Section 129.16 ...............
Door maintenance, adjustment and
replacement practices.
Municipal waste incinerators ...........
Section 129.18 ...............
EPA approval date
Additional explanation/
§ 52.2063 citation
8/29/77,
12/31/77
12/12/77
12/17/79, 44 FR 73031 ..
7/17/79, 44 FR 41429 ....
(c)(21); correction published 8/22/
80, 45 FR 56060.
(c)(19).
10/27/90
6/30/93, 58 FR 34911 ....
(c)(81).
Sources of VOCs
Section 129.51 ...............
Section 129.52 ...............
Section 129.54 ...............
Section 129.55 ...............
Section 129.56 ...............
Section 129.57 ...............
Section 129.58 ...............
Section 129.59 ...............
Section 129.60 ...............
Section 129.61 ...............
Section 129.62 ...............
Section
Section
Section
Section
129.63
129.64
129.65
129.66
...............
...............
...............
...............
Section 129.67 ...............
Section 129.68 ...............
Section 129.69 ...............
Section 129.71 ...............
Section 129.72 ...............
Section 129.73 ...............
Section 129.75 ...............
General ............................................
Surface coating processes ..............
Seasonal operation of auxiliary incineration equipment.
Petroleum
refineries—specific
sources.
Storage tanks greater than 40,000
gallons capacity containing VOCs.
Storage tanks less than or equal to
40,000 gallons capacity containing VOCs.
Petroleum
refineries—fugitive
sources.
Bulk gasoline terminals ....................
Bulk gasoline plants .........................
Small gasoline storage tank control
(Stage I control).
General standards for bulk gasoline
terminals, bulk gasoline plants,
and small gasoline storage tanks.
Degreasing operations .....................
Cutback asphalt paving ...................
Ethylene production plants ..............
Compliance schedules and final
compliance dates.
Graphic arts systems .......................
Manufacture of synthesized pharmaceutical products.
Manufacture of pneumatic rubber
tires.
Synthetic organic chemical and
polymer manufacturing—fugitive
sources.
Manufacture of surface active
agents.
Aerospace manufacturing and rework.
Mobile equipment repair and refinishing.
4/10/99
6/10/00
8/3/91
6/25/01, 66 FR 33645 ....
7/20/01, 66 FR 37908 ....
5/13/93, 58 FR 28362 ....
(c)(155).
(c)(152).
(c)(79).
6/20/81
1/19/83, 48 FR 2319 ......
(c)(48).
9/5/98
7/26/00, 65 FR 45920 ....
(c)(147).
6/20/81
1/19/83, 48 FR 2319 ......
(c)(48).
8/13/83
7/27/84, 49 FR 30183 ....
(c)(60).
8/3/91
8/3/91
8/3/91
5/13/93, 58 FR 28362 ....
5/13/93, 58 FR 28362 ....
5/13/93, 58 FR 28362 ....
(c)(79).
(c)(79).
(c)(79).
5/23/94
12/22/94, 59 FR 65971 ..
(c)(94).
12/22/01
8/13/83
8/1/79
5/23/92
1/16/03, 68 FR 2208 ......
7/27/84, 49 FR 30183 ....
5/20/80 ...........................
12/22/94, 59 FR 65971 ..
(c)(195)(i)(B)(2).
(c)(60).
(c)(22).
(c)(94).
9/5/98
8/3/91
7/26/00, 65 FR 45920 ....
5/13/93, 58 FR 28362 ....
(c)(147).
(c)(79).
5/23/92
12/22/94, 59 FR 65971 ..
(c)(94).
5/23/92
12/22/94, 59 FR 65971 ..
(c)(94).
5/23/92
12/22/94, 59 FR 65971 ..
(c)(94).
4/10/99
6/25/01, 66 FR 33645 ....
(c)(155).
11/27/99
8/14/00, 65 FR 49501 ....
(c)(148).
9/28/91
9/28/93, 58 FR 50517 ....
(c)(84).
4/10/99
5/21/01, 66 FR 27875 ....
(c)(153).
Mobile Sources
Section 129.81 ...............
Section 129.82 ...............
Organic liquid cargo vessel loading
and ballasting.
Control of VOCs from gasoline dispensing facilities (Stage II).
Stationary Sources of NOX and VOCs
Section 129.91 ...............
PWALKER on PROD1PC71 with RULES2
Section 129.92 ...............
Section 129.93 [Except
for 129.93(c)(6 & 7)].
Section 129.94 ...............
Section 129.95 ...............
Control of major sources of NOX
and VOCs.
RACT proposal requirements ..........
Presumptive RACT emission limitations.
NOX RACT emission averaging
general requirements.
Recordkeeping .................................
6/10/00
7/20/01, 66 FR 37908 ....
(c)(152).
4/23/94
4/23/94
3/23/98, 63 FR 13789 ....
3/23/98, 63 FR 13789 ....
(c)(129).
(c)(129).
4/23/94
3/23/98, 63 FR 13789 ....
(c)(129).
4/23/94
3/23/98, 63 FR 13789 ....
(c)(129).
Wood Furniture Manufacturing Operations
Section 129.101 .............
Section 129.102 .............
Section 129.103 .............
VerDate Nov<24>2008
General provisions and applicability
Emission standards .........................
Work practice standards ..................
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00009
6/10/00
6/10/00
6/10/00
Fmt 4701
7/20/01, 66 FR 37908 ....
7/20/01, 66 FR 37908 ....
7/20/01, 66 FR 37908 ....
Sfmt 4700
E:\FR\FM\25MRR2.SGM
(c)(152).
(c)(152).
(c)(152).
25MRR2
13022
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 129.104 .............
Compliance procedures and monitoring requirements.
Recordkeeping requirements ...........
Reporting requirements ...................
Special provisions for facilities using
an emissions averaging approach.
Section 129.105 .............
Section 129.106 .............
Section 129.107 .............
Additional explanation/
§ 52.2063 citation
EPA approval date
6/10/00
7/20/01, 66 FR 37908 ....
(c)(152).
6/10/00
6/10/00
6/10/00
7/20/01, 66 FR 37908 ....
7/20/01, 66 FR 37908 ....
7/20/01, 66 FR 37908 ....
(c)(152).
(c)(152).
(c)(152).
Additional NOX Requirements
Section 129.201 .............
Section 129.202 .............
Section 129.203 .............
Section 129.204 .............
Section 129.205 .............
Boilers ..............................................
Stationary combustion turbines .......
Stationary internal combustion engines.
Emission accountability ...................
Zero emission renewable energy
production credit.
12/11/04
12/11/04
12/11/04
9/29/06, 71 FR 57428 ....
9/29/06, 71 FR 57428 ....
9/29/06, 71 FR 57428 ....
SIP-effective date is 10/30/06.
SIP-effective date is 10/30/06.
SIP-effective date is 10/30/06.
12/11/04
12/11/04
9/29/06, 71 FR 57428 ....
9/29/06, 71 FR 57428 ....
SIP-effective date is 10/30/06.
SIP-effective date is 10/30/06.
Chapter 130—Standards for Products
Subchapter A—Portable Fuel Containers
Section 130.101 .............
Section 130.102 .............
Section 130.103 .............
Section
Section
Section
Section
Section
130.104
130.105
130.106
130.107
130.108
.............
.............
.............
.............
.............
Applicability ......................................
Definitions ........................................
Performance Standards for portable
fuel containers and spill-proof
spouts.
Exemptions ......................................
Innovative products ..........................
Administrative requirements ............
Variances .........................................
Test procedures ...............................
10/5/02
10/5/02
10/5/02
12/8/04, 69 FR 70893 ....
12/8/04, 69 FR 70893 ....
12/8/04, 69 FR 70893 ....
(c)(229).
(c)(229).
(c)(229).
10/5/02
10/5/02
10/5/02
10/5/02
10/5/02
12/8/04,
12/8/04,
12/8/04,
12/8/04,
12/8/04,
....
....
....
....
....
(c)(229).
(c)(229).
(c)(229).
(c)(229).
(c)(229).
12/8/04, 69 FR 70895 ....
12/8/04, 69 FR 70895 ....
(c)(230).
(c)(230).
10/5/02
10/5/02
10/5/02
10/5/02
12/8/04,
12/8/04,
12/8/04,
12/8/04,
....
....
....
....
(c)(230).
(c)(230).
(c)(230).
(c)(230).
10/5/02
10/5/02
12/8/04, 69 FR 70895 ....
12/8/04, 69 FR 70895 ....
(c)(230).
(c)(230).
10/5/02
12/8/04, 69 FR 70895 ....
(c)(230).
10/5/02
10/5/02
10/5/02
10/5/02
10/5/02
10/5/02
12/8/04,
12/8/04,
12/8/04,
12/8/04,
12/8/04,
12/8/04,
....
....
....
....
....
....
(c)(230).
(c)(230).
(c)(230).
(c)(230).
(c)(230).
(c)(230).
12/8/04, 69 FR 70895 ....
12/8/04, 69 FR 70895 ....
(c)(230).
(c)(230).
69
69
69
69
69
FR
FR
FR
FR
FR
70893
70893
70893
70893
70893
Subchapter B—Consumer Products
General Provisions
Section 130.201 .............
Section 130.202 .............
Applicability ......................................
Definitions ........................................
10/5/02
10/5/02
Standard
Section
Section
Section
Section
130.211
130.212
130.213
130.214
.............
.............
.............
.............
Section 130.215 .............
Section 130.216 .............
Table of standards ...........................
Products diluted prior to use ...........
Products registered under FIFRA ....
Requirements for charcoal lighter
materials..
Requirements for aerosol adhesives
Requirements for floor wax strippers
69
69
69
69
FR
FR
FR
FR
70895
70895
70895
70895
Exemptions
Section 130.331 .............
Section
Section
Section
Section
Section
Section
130.332
130.333
130.334
130.335
130.336
130.337
.............
.............
.............
.............
.............
.............
Products for shipment and use outside this Commonwealth.
Antiperspirants and deodorants .......
LVP–VOC ........................................
Products registered under FIFRA ....
Air fresheners ..................................
Adhesives ........................................
Bait station insecticides ...................
69
69
69
69
69
69
FR
FR
FR
FR
FR
FR
70895
70895
70895
70895
70895
70895
Innovative Products
PWALKER on PROD1PC71 with RULES2
Section 130.351 .............
Section 130.352 .............
Innovative products exemption ........
Request for exemption ....................
10/5/02
10/5/02
Administrative Requirements
Section 130.371 .............
Section 130.372 .............
Section 130.373 .............
VerDate Nov<24>2008
Code-dating .....................................
Most restrictive limit .........................
Additional labeling requirements for
aerosol adhesives.
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00010
10/5/02
10/5/02
10/5/02
Fmt 4701
12/8/04, 69 FR 70895 ....
12/8/04, 69 FR 70895 ....
12/8/04, 69 FR 70895 ....
Sfmt 4700
E:\FR\FM\25MRR2.SGM
(c)(230).
(c)(230).
(c)(230).
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13023
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Reporting Requirements
Section 130.391 .............
Section 130.392 .............
Required reporting of information to
the Department.
Confidentiality ..................................
10/5/02
12/8/04, 69 FR 70895 ....
(c)(230).
10/5/02
12/8/04, 69 FR 70895 ....
(c)(230).
12/8/04,
12/8/04,
12/8/04,
12/8/04,
....
....
....
....
(c)(230).
(c)(230).
(c)(230).
(c)(230).
12/8/04, 69 FR 70895 ....
(c)(230).
Variances
Section
Section
Section
Section
130.411
130.412
130.413
130.414
.............
.............
.............
.............
Application for variance ...................
Variance orders ...............................
Termination of variance ...................
Modification of variance ...................
10/5/02
10/5/02
10/5/02
10/5/02
69
69
69
69
FR
FR
FR
FR
70895
70895
70895
70895
TEST METHODS
Section 130.431 .............
Testing for compliance ....................
10/5/02
ACP for Consumer Products
Section
Section
Section
Section
Section
130.451
130.452
130.453
130.454
130.455
.............
.............
.............
.............
.............
Section 130.456 .............
Section 130.457 .............
Section 130.458 .............
Section 130.459 .............
Section 130.460 .............
Section 130.461 .............
Section 130.462 .............
Section 130.463 .............
Section 130.464 .............
Section 130.465 .............
Alternative methods of compliance
Exemption ........................................
Request for exemption ....................
Application for an ACP ....................
Recordkeeping and availability of
requested information.
Surplus reductions and surplus trading.
Limited-use surplus reduction credits for early reformulations of ACP
products.
Reconciliation of shortfalls ...............
Notification of modifications to an
ACP by the responsible ACP
party.
Modifications that require Department preapproval.
Other modifications ..........................
Modification of an ACP by the Department.
Cancellation of an ACP ...................
Treatment of information .................
Other applicable requirements ........
10/5/02
10/5/02
10/5/02
10/5/02
10/5/02
12/8/04,
12/8/04,
12/8/04,
12/8/04,
12/8/04,
69
69
69
69
69
FR
FR
FR
FR
FR
70895
70895
70895
70895
70895
....
....
....
....
....
(c)(230)
(c)(230).
(c)(230).
(c)(230).
(c)(230).
10/5/02
12/8/04, 69 FR 70895 ....
(c)(230).
10/5/02
12/8/04, 69 FR 70895 ....
(c)(230).
10/5/02
10/5/02
12/8/04, 69 FR 70895 ....
12/8/04, 69 FR 70895 ....
(c)(230).
(c)(230).
10/5/02
12/8/04, 69 FR 70895 ....
(c)(230).
10/5/02
10/5/02
12/8/04, 69 FR 70895 ....
12/8/04, 69 FR 70895 ....
(c)(230).
(c)(230).
10/5/02
10/5/02
10/5/02
12/8/04, 69 FR 70895 ....
12/8/04, 69 FR 70895 ....
12/8/04, 69 FR 70895 ....
(c)(230).
(c)(230).
(c)(230).
Public Hearing Requirements
Section 130.471 .............
Public hearings ................................
10/5/02
12/8/04, 69 FR 70895 ....
(c)(230).
Subchapter C—Architectural and Industrial Maintenance Coatings
Section
Section
Section
Section
Section
Section
Section
Section
Section
130.601
130.602
130.603
130.604
130.605
130.606
130.607
130.608
130.609
.............
.............
.............
.............
.............
.............
.............
.............
.............
Section 130.610 .............
Section 130.611 .............
Applicability ......................................
Definitions ........................................
Standards .........................................
Container labeling requirements ......
Reporting requirements ...................
Application for variance ...................
Variance orders ...............................
Termination of variance ...................
Extension, modification or revocation of variance.
Public hearings ................................
Compliance provisions and test
methods.
10/25/03
10/25/03
10/25/03
10/25/03
10/25/03
10/25/03
10/25/03
10/25/03
10/25/03
11/23/04,
11/23/04,
11/23/04,
11/23/04,
11/23/04,
11/23/04,
11/23/04,
11/23/04,
11/23/04,
69
69
69
69
69
69
69
69
69
FR
FR
FR
FR
FR
FR
FR
FR
FR
68080
68080
68080
68080
68080
68080
68080
68080
68080
..
..
..
..
..
..
..
..
..
(c)(227).
(c)(227).
(c)(227).
(c)(227).
(c)(227).
(c)(227).
(c)(227).
(c)(227).
(c)(227).
10/25/03
10/25/03
11/23/04, 69 FR 68080 ..
11/23/04, 69 FR 68080 ..
(c)(227).
(c)(227).
PWALKER on PROD1PC71 with RULES2
Chapter 131—Ambient Air Quality Standards
Section 131.1 .................
Section 131.2 .................
Section 131.3 .................
VerDate Nov<24>2008
Purpose ............................................
National Ambient Air Quality Standards.
Ambient air quality standards ..........
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00011
3/20/72
3/20/72
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
(c)(1).
(c)(1).
8/13/83
7/27/84, 49 FR 30183 ....
(c)(60); Amendment removed a lead
standard provision. The remaining
standards are not SIP-related.
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
13024
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 131.4 .................
Application of ambient air quality
standards.
3/20/72
Additional explanation/
§ 52.2063 citation
EPA approval date
5/31/72, 37 FR 10842 ....
(c)(1).
Chapter 135—Reporting of Sources
General
Section
Section
Section
Section
Section
135.1
135.2
135.3
135.4
135.5
.................
.................
.................
.................
.................
Definitions ........................................
Applicability [of sources] ..................
Reporting .........................................
Reporting forms and guides ............
Recordkeeping .................................
3/20/72
3/20/72
3/20/72
3/20/72
10/10/92
5/31/72,
5/31/72,
5/31/72,
5/31/72,
1/12/95,
37
37
37
37
60
FR
FR
FR
FR
FR
10842 ....
10842 ....
10842 ....
10842 ....
2081 ......
(c)(1).
(c)(1).
(c)(1).
(c)(1).
(c)(96).
1/12/95, 60 FR 2081 ......
(c)(96).
Emission Statements
Section 135.21 ...............
Emission statements ........................
10/10/92
Chapter 137—Air Pollution Episodes
General
Section
Section
Section
Section
Section
137.1
137.2
137.3
137.4
137.5
.................
.................
.................
.................
.................
Purpose ............................................
Monitoring facilities ..........................
Episode criteria ................................
Standby plans ..................................
Implementation of emission reduction procedures.
1/28/72
1/28/72
6/9/90
12/27/97
1/28/72
5/31/72,
5/31/72,
6/16/93,
6/11/02,
5/31/72,
37
37
58
67
37
FR
FR
FR
FR
FR
10842
10842
33203
39854
10842
....
....
....
....
....
(c)(1).
(c)(1).
(c)(75).
(c)(189).
(c)(1).
5/31/72,
5/31/72,
5/31/72,
5/31/72,
37
37
37
37
FR
FR
FR
FR
10842
10842
10842
10842
....
....
....
....
(c)(1).
(c)(1).
(c)(1).
(c)(1).
Level Actions
Section
Section
Section
Section
137.11
137.12
137.13
137.14
...............
...............
...............
...............
Forecast level actions ......................
Alert level actions ............................
Warning level actions ......................
Emergency level actions ..................
1/28/72
1/28/72
1/28/72
1/28/72
Chapter 139—Sampling and Testing
Subchapter A—Sampling and Testing Methods and Procedures
General
Section 139.1 .................
Section 139.2 .................
Section 139.3 .................
Sampling facilities ............................
Sampling by others ..........................
General requirements ......................
3/20/72
3/20/72
8/1/79
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
8/8/79, 44 FR 46465 ......
Section 139.4 .................
Section 139.5 .................
References .......................................
Revisions to the source testing
manual and continuous source
monitoring manual.
6/10/00
11/26/94
7/20/01, 66 FR 37908 ....
7/30/96, 61 FR 39597 ....
(c)(1).
(c)(1).
(c)(20); Correction published 1/23/
80 (45 FR 5303).
(c)(152).
(c)(110)(i)(D).
Stationary Sources
PWALKER on PROD1PC71 with RULES2
Section 139.11 ...............
Section 139.12 ...............
Section 139.13 (Except
Provisions applicable
to H2S and TRS).
Section 139.14 ...............
Section 139.16 ...............
Section 139.17 ...............
Section 139.18 ...............
General requirements ......................
Emissions of particulate matter .......
Emissions of SO2, H2S, TRS and
NO2.
3/20/72
3/7/98
11/26/94
Emissions of VOCs ..........................
Sulfur in fuel oil ................................
General requirements ......................
Calculation of alternative opacity
limitations.
6/10/00
8/13/83
6/20/81
6/20/81
5/31/72, 37 FR 10842 ....
6/11/02, 67 FR 39854 ....
7/30/96, 61 FR 39597 ....
(c)(1).
(c)(189).
(c)(110)(i)(D).
7/20/01,
7/27/84,
1/19/83,
1/19/83,
(c)(152).
(c)(60).
(c)(48).
(c)(48).
66
49
48
48
FR
FR
FR
FR
37908 ....
30183 ....
2319 ......
2319 ......
Ambient Levels of Air Contaminants
Section 139.31 ...............
Section 139.32 ...............
Section 139.33 ...............
VerDate Nov<24>2008
General ............................................
Sampling and analytical procedures
Incorporation of Federal procedures
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00012
3/20/72
11/26/94
3/20/72
Fmt 4701
5/31/72, 37 FR 10842 ....
7/30/96, 61 FR 39597 ....
5/31/72, 37 FR 10842 ....
Sfmt 4700
E:\FR\FM\25MRR2.SGM
(c)(1).
(c)(110)(i)(D).
(c)(1).
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13025
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Subchapter B—Monitoring Duties of Certain Sources
General
Section 139.51 ...............
Section 139.52 ...............
Section 139.53 ...............
Purpose ............................................
Monitoring methods and techniques
Filing monitoring reports ..................
8/29/77
8/29/77
8/13/83
7/17/79, 44 FR 41429 ....
7/17/79, 44 FR 41429 ....
7/27/84, 49 FR 30183 ....
(c)(19).
(c)(19).
(c)(60).
Subchapter C—Requirements for Continuous In-Stack Monitoring for Stationary Sources
Section
Section
Section
Section
139.101
139.102
139.103
139.111
.............
.............
.............
.............
General Requirements .....................
References .......................................
Opacity monitoring requirements .....
Waste incinerator monitoring requirements.
3/7/98
11/26/94
11/26/94
12/27/97
6/11/02,
7/30/96,
7/30/96,
6/11/02,
67
61
61
67
FR
FR
FR
FR
39854
39597
39597
39854
....
....
....
....
(c)(189).
(c)(110)(i)(D).
(c)(110)(i)(D).
(c)(189).
Chapter 141—Alternate Standards
Section 141.1 .................
Imposing alternate standards authorized.
5/14/88
9/17/92, 57 FR 42894 ....
(c)(73).
Chapter 145—Interstate Pollution Transport Reduction
Subchapter A—NOX Budget Trading Program
General Provisions
Section 145.1 .................
Section 145.2 .................
Section 145.3 .................
Section
Section
Section
Section
145.4
145.5
145.6
145.7
.................
.................
.................
.................
Purpose ............................................
Definitions ........................................
Measurements, abbreviations and
acronyms.
Applicability ......................................
Retired unit exemption .....................
Standard requirements ....................
Computation of time ........................
9/23/00
9/23/00
9/23/00
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
(c)(168).
(c)(168).
(c)(168).
9/23/00
9/23/00
9/23/00
9/23/00
8/21/01,
8/21/01,
8/21/01,
8/21/01,
....
....
....
....
(c)(168).
(c)(168).
(c)(168).
(c)(168).
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
9/23/00
9/23/00
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
(c)(168).
(c)(168).
66
66
66
66
FR
FR
FR
FR
43795
43795
43795
43795
NOX Account
Section 145.10 ...............
Section 145.11 ...............
Section 145.12 ...............
Section 145.13 ...............
Section 145.14 ...............
Authorization and responsibilities of
the NOX authorized account representative.
Alternate NOX authorized account
representative.
Changing the NOX authorized account
representative;
and
changes in the Alternate NOX authorized account representative;
changes in the owners and operators.
Account certificate of representation
Objections concerning the NOX authorized account representative.
Compliance Certification
Section 145.30 ...............
Section 145.31 ...............
Compliance certification report ........
Department’s action on compliance
certifications.
9/23/00
9/23/00
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
(c)(168).
(c)(168).
NOX Allowance Allocations
State Trading Program budget ........
Timing Requirements for NOX allowance allocations.
NOX Allowance allocations ..............
9/23/00
9/23/00
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
(c)(168).
(c)(168).
Section 145.42 ...............
PWALKER on PROD1PC71 with RULES2
Section 145.40 ...............
Section 145.41 ...............
12/11/04
9/29/06, 71 FR 57428 ....
Section 145.43 ...............
Compliance supplement pool ..........
9/23/00
8/21/01, 66 FR 43795 ....
Revised; SIP-effective date is 10/
30/06.
(c)(168).
Accounting Process for Deposit Use and Transfer of Allowances
Section 145.50 ...............
VerDate Nov<24>2008
NOX Allowance Tracking System
accounts.
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00013
9/23/00
Fmt 4701
8/21/01, 66 FR 43795 ....
Sfmt 4700
E:\FR\FM\25MRR2.SGM
(c)(168).
25MRR2
13026
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 145.51 ...............
Section 145.52 ...............
Establishment of accounts ...............
NOX Allowance Tracking System
responsibilities of NOX authorized
account representative.
Recordation of NOX allowance allocations.
Compliance ......................................
Banking ............................................
Account error ...................................
Closing of general accounts ............
Section 145.53 ...............
Section
Section
Section
Section
145.54
145.55
145.56
145.57
...............
...............
...............
...............
Additional explanation/
§ 52.2063 citation
EPA approval date
9/23/00
9/23/00
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
(c)(168).
(c)(168).
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
9/23/00
9/23/00
9/23/00
9/23/00
8/21/01,
8/21/01,
8/21/01,
8/21/01,
....
....
....
....
(c)(168).
(c)(168).
(c)(168).
(c)(168).
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
9/23/00
9/23/00
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
(c)(168).
(c)(168).
66
66
66
66
FR
FR
FR
FR
43795
43795
43795
43795
NOX Allowance Transfers
Section 145.60 ...............
Section 145.61 ...............
Section 145.62 ...............
Submission of NOX allowance
transfers.
NOX transfer recordation .................
Notification .......................................
Recording and Recordkeeping Requirements
Section 145.70 ...............
Section 145.71 ...............
Section
Section
Section
Section
Section
145.72
145.73
145.74
145.75
145.76
...............
...............
...............
...............
...............
General monitoring requirements ....
Initial certification and recertification
procedures.
Out of control periods ......................
Notifications .....................................
Recordkeeping and reporting ..........
Petitions ...........................................
Additional requirements to provide
heat input data.
9/23/00
9/23/00
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
(c)(168).
(c)(168).
9/23/00
9/23/00
9/23/00
9/23/00
9/23/00
8/21/01,
8/21/01,
8/21/01,
8/21/01,
8/21/01,
....
....
....
....
....
(c)(168).
(c)(168).
(c)(168).
(c)(168).
(c)(168).
9/23/00
9/23/00
9/23/00
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
(c)(168).
(c)(168).
(c)(168).
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
9/23/00
9/23/00
8/21/01, 66 FR 43795 ....
8/21/01, 66 FR 43795 ....
(c)(168).
(c)(168).
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
66
66
66
66
66
FR
FR
FR
FR
FR
43795
43795
43795
43795
43795
Opt-In Process
Section 145.80 ...............
Section 145.81 ...............
Section 145.82 ...............
Section 145.83 ...............
Section 145.84 ...............
Section 145.85 ...............
Section 145.86 ...............
Section 145.87 ...............
Section 145.88 ...............
Applicability for opt-in sources .........
Opt-in source general provisions .....
NOX authorized account representative for opt-in sources.
Applying for a NOX budget opt-in
approval.
Opt-in process .................................
NOX budget opt-in application contents.
Opt-in source withdrawal from NOX
Budget Trading Program.
Opt-in unit change in regulatory status.
NOX allowance allocations to opt-in
units.
Emission Reduction Credit Provisions
Section 145.90 ...............
Emission reduction credit provisions
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
Interstate Pollution Transport Reduction Requirements
Section 145.100 .............
Applicability to upwind states ..........
9/23/00
8/21/01, 66 FR 43795 ....
(c)(168).
Subchapter B—Emissions of NOX from Stationary Internal Combustion Engines
Applicability ......................................
12/11/04
9/29/06, 71 FR 57428 ....
Section 145.112 .............
Definitions ........................................
12/11/04
9/29/06, 71 FR 57428 ....
Section 145.113 .............
PWALKER on PROD1PC71 with RULES2
Section 145.111 .............
Standard requirements ....................
12/11/04
9/29/06, 71 FR 57428 ....
New Section
SIP-effective date is 10/30/06.
New Section
SIP-effective date is 10/30/06.
New Section
SIP-effective date is 10/30/06.
Subchapter C—Emissions of NOX from Cement Manufacturing
Section 145.141 .............
Applicability ......................................
12/11/04
9/29/06, 71 FR 57428 ....
Section 145.142 .............
Definitions ........................................
12/11/04
9/29/06, 71 FR 57428 ....
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00014
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
New Section
SIP-effective date is 10/30/06.
New Section
SIP-effective date is 10/30/06.
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13027
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 145.143 .............
Standard requirements ....................
12/11/04
Additional explanation/
§ 52.2063 citation
EPA approval date
9/29/06, 71 FR 57428 ....
New Section
SIP-effective date is 10/30/06.
Title 67—Transportation
Part I—Department of Transportation
Subpart A—Vehicle Code Provisions
Article VII—Vehicle Characteristics
Chapter 175—Vehicle Equipment and Inspection
Subchapter A—General Provisions
Section 175.2 .................
Definitions ........................................
9/27/97
6/17/99, 64 FR 32411 ....
Section 175.2 .................
Definitions ........................................
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.3 .................
Application of equipment rules ........
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.4 .................
Vehicles required to be inspected ...
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.6 .................
Annual inspection ............................
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.7 .................
Inspection of vehicle reentering this
Commonwealth.
Newly purchased vehicles ...............
12/3/88
10/6/05, 70 FR 58313 ....
2/19/94
10/6/05, 70 FR 58313 ....
9/27/97
6/17/99, 64 FR 32411 ....
Section 175.8 .................
Section 175.11 ...............
Coordination of safety and emission
inspection.
‘‘Temporary Inspection Approval Indicator’’ only.
Definitions which apply to safety inspection program in non-I/M
counties.
Applies to safety inspection program in non-I/M counties.
Applies to safety inspection program in non-I/M counties.
Applies to safety inspection program in non-I/M counties.
Applies to safety inspection program in non-I/M counties.
Applies to safety inspection program in non-I/M counties.
(c)(139).
Subchapter B—Official Inspection Stations
Section 175.21 ...............
Appointment .....................................
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.22 ...............
Making application ...........................
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.23(a) and (c)
Approval ...........................................
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.24 ...............
Required certificates and station
signs.
Inspection area ................................
12/3/88
10/6/05, 70 FR 58313 ....
12/3/88
10/6/05, 70 FR 58313 ....
Tools and equipment .......................
9/28/96
10/6/05, 70 FR 58313 ....
Hours ...............................................
12/3/88
10/6/05, 70 FR 58313 ....
Certified Inspection Mechanics ........
12/3/88
Section 175.29 ...............
Obligations and responsibilities of
station.
Obligations and responsibilities of
stations.
Section 175.31 ...............
Fleet inspection stations ..................
Section 175.25(a), (b)(1),
(b)(3), and (c).
Section 175.26(a) introductory sentence and
(a)(3).
Section 175.27 ...............
Section 175.28 ...............
[Except for (c)(2), (g)(2),
(g)(3), and (g)(5)–((9)].
Section 175.29(f)(4) ........
Applies
gram
Applies
gram
Applies
gram
Applies
gram
Applies
gram
Applies
gram
to safety inspection
in non-I/M counties.
to safety inspection
in non-I/M counties.
to safety inspection
in non-I/M counties.
to safety inspection
in non-I/M counties.
to safety inspection
in non-I/M counties.
to safety inspection
in non-I/M counties.
pro-
10/6/05, 70 FR 58313. ...
Applies
gram
Applies
gram
to safety inspection proin non-I/M counties.
to safety inspection proin non-I/M counties.
9/27/97
6/17/99, 64 FR 32411 ....
(c)(139).
9/27/97
10/6/05, 70 FR 58313 ....
12/3/88
10/6/05, 70 FR 58313 ....
Applies to safety inspection program in non-I/M counties (except
for (f)(4), which applies to I/M and
non-I/M programs).
Applies to safety inspection program in non-I/M counties.
propropropropro-
PWALKER on PROD1PC71 with RULES2
Subchapter C—Certificate of Inspection
Section 175.41(a), (b)(1),
(b)(3), (c), (d), (e)(1),
(e)(3), (e)(5), and (f)(4).
Section 175.42 ...............
Section 175.43 ...............
Section 175.44 ...............
Section 175.45 ...............
VerDate Nov<24>2008
Procedure ........................................
9/27/97
10/6/05, 70 FR 58313 ....
Recording inspection .......................
Security ............................................
Ordering certificates of inspection ...
Violation of use of certificate of inspection.
9/27/97
9/27/97
9/27/97
9/27/97
6/17/99,
6/17/99,
6/17/99,
6/17/99,
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00015
Fmt 4701
Sfmt 4700
64
64
64
64
FR
FR
FR
FR
Applies statewide;
To I/M program and non-I/M safety
inspection program.
32411.
32411.
32411.
32411.
E:\FR\FM\25MRR2.SGM
25MRR2
13028
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Subchapter D—Schedule of Penalties and Suspensions: Official Inspection Stations and Certified Mechanics
Section 175.51 ...............
Cause for suspension ......................
2/19/94
10/6/05, 70 FR 58313 ....
Section 175.52 ...............
Reapplication ...................................
12/3/88
10/6/05, 70 FR 58313 ....
New section;
Applies to safety inspection program in non-I/M counties.
New section;
Applies to safety inspection program in non-I/M counties.
Subchapter E—Passenger Cars and Light Trucks
Section 175.61 ...............
Application of subchapter ................
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.72(d) ...........
Fuel systems ....................................
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.80(d) ...........
Inspection procedure .......................
5/13/99
10/6/05, 70 FR 58313 ....
New section;
Applies to safety inspection program in non-I/M counties.
New section;
Applies to safety inspection program in non-I/M counties.
New section;
Applies to safety inspection program in non-I/M counties.
Subchapter H—Motorcycles
Section 175.141 .............
Application of subchapter ................
12/3/88
10/6/05, 70 FR 58313 ....
New section;
Applies to safety inspection program in non-I/M counties.
Subchapter J—Motor-Driven Cycles and Motorized Pedalcycles
Section 175.171 .............
Application .......................................
12/3/88
10/6/05, 70 FR 58313 ....
New section;
Applies to safety inspection program in non-I/M counties.
Subchapter K—Street Rods, Specially Constructed and Reconstructed Vehicles
Section 175.201 .............
Application of subchapter ................
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.202 .............
Conditions ........................................
12/3/88
10/6/05, 70 FR 58313 ....
Section 175.220(d) [introductory sentence only].
Inspection procedure .......................
5/13/99
10/6/05, 70 FR 58313 ....
New section;
Applies to safety inspection program in non-I/M counties.
Applies to safety inspection program in non-I/M counties.
Applies to safety inspection program in non-I/M counties.
Subchapter L—Animal-Drawn Vehicles, Implements of Husbandry and Special Mobile Equipment
Section 175.221 .............
Application .......................................
12/3/88
10/6/05, 70 FR 58313.
Chapter 177—Enhanced Emission Inspection Program
Subchapter A—General Provisions
Section 177.1 .................
Section 177.2 .................
Section 177.3 .................
Purpose ............................................
Application of equipment rules ........
Definitions ........................................
10/1/97
10/1/97
11/22/03
6/17/99, 64 FR 32411 ....
6/17/99, 64 FR 32411 ....
10/6/05, 70 FR 58313.
(c)(139).
(c)(139).
Implementation of Emission Inspection Program
Section 177.22 ...............
Section 177.23 ...............
Section 177.24 ...............
Commencement of inspection .........
Notification of requirement for emission inspection.
Program evaluation ..........................
11/22/03
11/22/03
10/6/05, 70 FR 58313 ....
10/6/05, 70 FR 58313.
11/22/03
Retitled and revised.
10/6/05, 70 FR 58313.
PWALKER on PROD1PC71 with RULES2
I/M Program
Section 177.51 ...............
Program requirements .....................
11/22/03
10/6/05, 70 FR 58313 ....
Section 177.52 ...............
Section 177.53 ...............
Emission inspection prerequisites ...
Vehicle inspection process ..............
11/22/03
11/22/03
10/6/05, 70 FR 58313.
10/6/05, 70 FR 58313.
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00016
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
Excludes paragraphs (c)(1), (c)(2),
and (c)(3), and reference to those
paragraphs.
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13029
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Subchapter B—Subject Vehicles
Section 177.101 .............
Section 177.102 .............
Section 177.103 .............
Section 177.104 .............
Section 177.105 .............
Subject vehicles ...............................
Inspection of vehicles reentering
this Commonwealth.
Used vehicles after sale or resale ...
Vehicles registered in nondesignated areas or other states.
Vehicles requiring emission inspection due to change of address.
11/22/03
9/27/97
10/6/05, 70 FR 58313.
6/17/99, 64 FR 32411 ....
(c)(139).
9/27/97
9/27/97
6/17/99, 64 FR 32411 ....
6/17/99, 64 FR 32411 ....
(c)(139).
(c)(139).
11/22/03
10/6/05, 70 FR 58313.
Subchapter C—Emission Test Procedures and Emission Standards
General
Section
Section
Section
Section
177.201 .............
177.202 .............
177.202a ...........
177.202b ...........
Section 177.203 .............
Section 177.204 .............
General requirements ......................
Emission test equipment .................
OBD–I/M check equipment ..............
Equipment for gas cap test and visual inspection.
Test procedures ...............................
Basis for failure ................................
11/22/03
11/22/03
11/22/03
11/22/03
10/6/05,
10/6/05,
10/6/05,
10/6/05,
70
70
70
70
FR
FR
FR
FR
58313.
58313.
58313 ....
58313 ....
11/22/03
11/22/03
10/6/05, 70 FR 58313.
10/6/05, 70 FR 58313 ....
New section.
New section.
Retitled and revised.
Recall Provisions
Section 177.231 .............
Section 177.232 .............
Section 177.233 .............
Requirements regarding manufacturer recall notices.
Compliance with recall notices ........
Failure to comply .............................
9/27/97
6/17/99, 64 FR 32411 ....
(c)(139).
9/27/97
9/27/97
6/17/99, 64 FR 32411 ....
6/17/99, 64 FR 32411 ....
(c)(139).
(c)(139).
Emission Inspection Report
Section 177.251 .............
Section 177.252 .............
Section 177.253 .............
Record of test results ......................
Emission inspection report ..............
Responsibility of the station owner
for vehicles which fail the emission inspection.
9/27/97
11/22/03
11/22/03
6/17/99, 64 FR 32411 ....
10/6/05, 70 FR 58313 ....
10/6/05, 70 FR 58313 ....
(c)(139).
Retitled and revised.
Retitled and revised.
10/6/05,
10/6/05,
10/6/05,
10/6/05,
10/6/05,
New section.
Retest
Section
Section
Section
Section
Section
177.271
177.272
177.273
177.274
177.275
.............
.............
.............
.............
.............
Procedure ........................................
Prerequisites ....................................
Content of repair data form .............
Retest fees .......................................
Repair technician training and certification.
11/22/03
11/22/03
11/22/03
11/22/03
11/22/03
70
70
70
70
70
FR
FR
FR
FR
FR
58313.
58313.
58313.
58313.
58313 ....
Issuance of Waiver
Section 177.281 .............
Section 177.282 .............
Issuance of waiver ...........................
Annual adjustment of minimum
waiver expenditure for emission
inspection.
11/22/03
11/22/03
10/6/05, 70 FR 58313.
10/6/05, 70 FR 58313 ....
Excludes/removes the sentence and
partial sentence, ‘‘The minimum
expenditure for the first 2 years
after commencement of the program in an affected area is $150.
Beginning with the 3rd year of the
program in an affected area’’.
Procedures Relating to Certificates of Emission Inspection
Section 177.291 .............
PWALKER on PROD1PC71 with RULES2
Section 177.292 .............
Procedures relating to certificates of
emission inspection.
Recording inspection .......................
11/22/03
10/6/05, 70 FR 58313 ....
11/22/03
Retitled and revised.
10/6/05, 70 FR 58313.
On-Road Testing
Section 177.301 .............
Section 177.302 .............
Section 177.304 .............
VerDate Nov<24>2008
Authorization to conduct on-road
emission testing.
On-road testing devices ...................
Failure of on-road emission test ......
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00017
9/27/97
6/17/99, 64 FR 32411 ....
(c)(139).
9/27/97
11/22/03
6/17/99, 64 FR 32411 ....
10/6/05, 70 FR 58313.
(c)(139).
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
13030
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 177.305 .............
Failure to produce proof of correction of on-road emission test failure.
9/27/97
Additional explanation/
§ 52.2063 citation
EPA approval date
6/17/99, 64 FR 32411 ....
(c)(139).
Subchapter D—Official Emission Inspection Station Requirements
General
Section 177.401 .............
Section 177.402 .............
Section 177.403 .............
Section 177.404 .............
Section
Section
Section
Section
177.405
177.406
177.407
177.408
.............
.............
.............
.............
Appointment .....................................
Application .......................................
Approval of emission inspection station.
Required certificates and station
signs.
Emission inspection areas ...............
Equipment ........................................
Hours of operation ...........................
Certified emission inspectors ...........
11/22/03
9/27/97
9/27/97
10/6/05, 70 FR 58313.
6/17/99, 64 FR 32411 ....
6/17/99, 64 FR 32411 ....
11/22/03
10/6/05, 70 FR 58313.
11/22/03
11/22/03
11/22/03
11/22/03
10/6/05,
10/6/05,
10/6/05,
10/6/05,
70
70
70
70
FR
FR
FR
FR
58313.
58313 ....
58313.
58313.
(c)(139).
(c)(139).
Retitled and revised.
Obligations and Responsibilities of Station Owners/Agents
Section 177.421 .............
Section 177.422 .............
Section 177.423 .............
Section 177.424 .............
Section 177.425 .............
Section 177.426 .............
Section 177.427 .............
Obligations and responsibilities of
station owners/agents.
Commonwealth emission inspection
stations.
Fleet emission inspection stations ...
General emission inspection stations.
Security ............................................
Ordering certificates of emission inspection.
Violations of use of certificate of
emission inspection.
11/22/03
10/6/05, 70 FR 58313.
11/22/03
10/6/05, 70 FR 58313 ....
Retitled and revised.
11/22/03
11/22/03
10/6/05, 70 FR 58313 ....
10/6/05, 70 FR 58313.
Retitled and revised.
11/22/03
9/27/97
10/6/05, 70 FR 58313.
6/17/99, 64 FR 32411 ....
(c)(139).
9/27/97
6/17/99, 64 FR 32411 ....
(c)(139).
Quality Assurance
Section 177.431 .............
Quality assurance ............................
11/22/03
10/6/05, 70 FR 58313.
Subchapter E—Equipment Manufacturers’ and Contractors’ Requirements and Obligations
Equipment Manufacturers’ Requirements
Section
Section
Section
Section
177.501
177.502
177.503
177.504
.............
.............
.............
.............
Equipment approval procedures ......
Service commitment ........................
Performance commitment ................
Revocation of approval ....................
11/22/03
11/22/03
11/22/03
9/27/97
10/6/05,
10/6/05,
10/6/05,
6/17/99,
70
70
70
64
FR
FR
FR
FR
58313.
58313.
58313.
32411 ....
(c)(139).
Contractor Obligations
Section 177.521 .............
Contractor obligations and responsibilities.
11/22/03
10/6/05, 70 FR 58313.
Subchapter F—Schedule of Penalties and Hearing Procedure
Schedule of Penalties and Suspensions
Section 177.601 .............
Section 177.602 .............
Section 177.603 .............
Definitions ........................................
Schedule of penalties for emission
inspection stations.
Schedule of penalties for emission
inspectors.
11/22/03
11/22/03
10/6/05, 70 FR 58313 ....
10/6/05, 70 FR 58313.
11/22/03
New section.
10/6/05, 70 FR 58313.
PWALKER on PROD1PC71 with RULES2
Additional Violations
Section 177.605 .............
Section 177.606 .............
Subsequent violations ......................
Multiple violations ............................
11/22/03
9/27/97
10/6/05, 70 FR 58313.
6/17/99, 64 FR 32411 ....
(c)(139).
Departmental Hearing Procedure
Section 177.651 .............
VerDate Nov<24>2008
Notice of alleged violation and opportunity to be heard prior to immediate suspension.
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00018
11/22/03
Fmt 4701
10/6/05, 70 FR 58313 ....
Sfmt 4700
E:\FR\FM\25MRR2.SGM
Retitled and revised.
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13031
(1) EPA-APPROVED PENNSYLVANIA REGULATIONS—Continued
State effective date
State citation
Title/subject
Section 177.652 .............
Official documents ...........................
9/27/97
Additional explanation/
§ 52.2063 citation
EPA approval date
6/17/99, 64 FR 32411 ....
(c)(139).
Restoration After Suspension
Section 177.671 .............
Section 177.672 .............
Section 177.673 .............
Restoration of certification of an
emission inspector after suspension.
Restoration of certification of an
emission inspection station after
suspension.
Restoration of certification of certified repair technician after suspension.
9/27/97
6/17/99, 64 FR 32411 ....
(c)(139).
9/27/97
6/17/99, 64 FR 32411 ....
(c)(139).
9/27/97
6/17/99, 64 FR 32411 ....
(c)(139).
Registration Recall Procedure for Violation of §§ 177.301–177.305 (Relating Toon-Road Resting)
Section 177.691 .............
Appendix A .....................
Appendix B .....................
Registration Recall Committee ........
Acceleration
Simulation
Mode:
Pennsylvania Procedures, Standards, Equipment Specifications
and Quality Control Requirements.
Department Procedures and Specifications.
11/22/03
11/22/03
10/6/05, 70 FR 58313.
10/6/05, 70 FR 58313 ....
Replaces previous Appendix A.
11/22/03
10/6/05, 70 FR 58313 ....
Replaces previous Appendix B.
(2) EPA-APPROVED ALLEGHENY COUNTY HEALTH DEPARTMENT (ACHD) REGULATIONS
Article XX or XXI citation
State effective date
Title/subject
EPA approval date
Additional explanation/
§ 52.2063 citation
Part A—General
2101.01 ...........................
Short Titles .......................................
10/20/95
11/14/02, 67 FR 68935 ..
2101.02.a, .02.c ..............
2101.03 ...........................
Declaration of Policy and Purpose ..
Effective Date and Repealer ...........
10/20/95
10/20/95
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
2101.04 ...........................
2101.05 ...........................
2101.06 ...........................
2101.07 (Except paragraphs .07.c.2 and c.8).
2101.10 ...........................
Existing Orders ................................
Existing Permits and Licenses ........
Construction and Interpretation .......
Administration and Organization .....
10/20/95
3/31/98
10/20/95
10/20/95
11/14/02, 67 FR 68935 ..
8/30/04, 69 FR 52831 ....
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
In SIP at 52.2020(c)(92); citation
change only at(c)(192).
(c)(192).
In SIP at (c)(92); citation change
only at (c)(192).
(c)(192).
52.2420(c)(209).
(c)(192).
(c)(192).
Ambient Air Quality Standards (Except: PM10—County & Free silica
portion; Pb (1-hr & 8-hr avg.); settled particulates, beryllium, sulfates, fluorides, and hydrogen sulfide).
Prohibition of Air Pollution ...............
Interstate Air Pollution .....................
Nuisances ........................................
Circumvention ..................................
Definitions ........................................
Definitions related to gasoline volatility.
Definitions ........................................
10/20/95
11/14/02, 67 FR 68935 ..
(c)(192).
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
5/15/98,
9/1/99
7/10/03
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
4/17/01, 66 FR 19724 ....
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(151).
2101.11
2101.12
2101.13
2101.14
2101.20
2101.20
...........................
...........................
...........................
...........................
...........................
...........................
2101.20 ...........................
6/24/05, 70 FR 36511.
Part B—Permits Generally
PWALKER on PROD1PC71 with RULES2
2102.01 ...........................
2102.02 ...........................
2102.03.a through .k ......
2102.04 ...........................
2102.05 ...........................
2102.06 ...........................
2102.08 ...........................
2102.10 ...........................
VerDate Nov<24>2008
Certification ......................................
Applicability ......................................
Permits Generally ............................
Installation Permits ..........................
Installation Permits for New and
Modified Major Sources.
Major Sources Locating In or Impacting a Nonattainment Area.
Emission Offset Registration ...........
Installation Permit Application and
Administration Fees.
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00019
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
11/14/02,
11/14/02,
11/14/02,
11/14/02,
11/14/02,
..
..
..
..
..
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
10/20/95
11/14/02, 67 FR 68935 ..
(c)(192).
10/20/95
10/20/95
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
(c)(192).
(c)(192).
Fmt 4701
Sfmt 4700
67
67
67
67
67
FR
FR
FR
FR
FR
68935
68935
68935
68935
68935
E:\FR\FM\25MRR2.SGM
25MRR2
13032
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(2) EPA-APPROVED ALLEGHENY COUNTY HEALTH DEPARTMENT (ACHD) REGULATIONS—Continued
Article XX or XXI citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Part C—Operating Permits
2103.01 ...........................
Transition .........................................
10/20/95
8/30/04, 69 FR 52831 ....
(c)(209).
Subpart 1—Operating Permits (All Major and Minor Permits)
2103.10.a., b ..................
2103.11 ...........................
2103.12 ...........................
2103.13 ...........................
2103.14 ...........................
2103.15 ...........................
Applicability, Prohibitions, Records
Applications ......................................
Issuance, Standard Conditions ........
Expiration, Renewals, Reactivation
Revisions, Amendments, Modifications.
Reopenings, Revocations ................
10/20/95
10/20/95
3/31/98
10/20/95
1/12/01
11/14/02, 67 FR 68935 ..
8/30/04, 69 FR 52831 ....
8/30/04, 69 FR 52831 ....
8/30/04, 69 FR 52831 ....
8/30/04, 69 FR 52831 ....
(c)(192).
(c)(209).
(c)(209).
(c)(209).
(c)(209).
10/20/95
8/30/04, 69 FR 52831 ....
(c)(209).
Subpart 2—Additional Requirements for Major Permits
2103.20.b.4 .....................
Applicability, Prohibitions, Records
10/20/95
11/14/02, 67 FR 68935 ..
(c)(192).
Part D—Pollutant Emission Standards
2104.01 ...........................
2104.02 ...........................
Visible Emissions .............................
Particulate Mass Emissions .............
10/20/95
8/15/97
11/14/02, 67 FR 68935 ..
6/12/98, 63 FR 32126 ....
2104.03
2104.05
2104.06
2104.07
Sulfur Oxide Emissions ...................
Materials Handling ...........................
Violations .........................................
Stack Heights ...................................
7/10/03
10/20/95
10/20/95
10/20/95
7/21/04, 69 FR 43522 ....
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
...........................
...........................
...........................
...........................
(c)(192).
(c)(133)(i)(B)(1); Citation changes
approved on 11/12/02 (67 FR
68935) at (c)(192).
(c)(216)(i)(C).
(c)(192).
(c)(192).
(c)(192).
Part E—Source Emission and Operating Standards
2105.01
2105.02
2105.03
2105.04
...........................
...........................
...........................
...........................
2105.06 ...........................
Equivalent Compliance Techniques
Other Requirements Not Affected ...
Operation and Maintenance ............
Temporary Shutdown of Incineration
Equipment.
Major Sources of Nitrogen Oxides
and Volatile Organic Compounds.
7/10/03
10/20/95
10/20/95
10/20/95
6/24/05, 70 FR 36511.
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
(c)(192).
(c)(192).
(c)(192).
10/20/95
10/7/02, 67 FR 62389 ....
(c)(157).
Subpart 1—VOC Sources
2105.10 ...........................
2105.11 ...........................
2105.12 ...........................
2105.13 ...........................
2105.14 ...........................
2105.15
2105.16
2105.17
2105.19
...........................
...........................
...........................
...........................
Surface Coating Processes .............
Graphic Arts Systems ......................
Volatile Organic Compound Storage
Tanks.
Gasoline Loading Facilities ..............
Gasoline Dispensing Facilities—
Stage II Control.
Degreasing Operations ....................
Cutback Asphalt Paving ..................
Ethylene Production Processes .......
Synthetic Organic Chemical & Polymer
Manufacturing—Fugitive
Sources.
7/10/03
10/20/95
10/20/95
6/24/05, 70 FR 36511.
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
(c)(192).
(c)(192).
10/20/95
7/10/05
11/14/02, 67 FR 68935 ..
1/17/08, 73 FR 3190.
(c)(192).
10/20/95
10/20/95
10/20/95
10/20/95
11/14/02,
11/14/02,
11/14/02,
11/14/02,
(c)(192).
(c)(192).
(c)(192).
(c)(192).
67
67
67
67
FR
FR
FR
FR
68935
68935
68935
68935
..
..
..
..
Subpart 2—Stag, Coke, and Miscellaneous Sulfur Sources
PWALKER on PROD1PC71 with RULES2
2105.20 ...........................
2105.21 ...........................
Slag Quenching ...............................
Coke Ovens and Coke Oven Gas ...
10/20/95
8/15/97
11/14/02, 67 FR 68935 ..
6/12/98, 63 FR 32126 ....
2105.22 ...........................
Miscellaneous Sulfur Emitting Processes.
10/20/95
11/14/02, 67 FR 68935 ..
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00020
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
(c)(192).
(c)(133);
1. EPA approved revisions effective
7/11/95 on 9/8/98 (63 FR 47434)
at (c)(135).
2. EPA approved revisions effective
10/20/95 on 11/14/02 (67 FR
68935) at (c)(192).
(c)(192).
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13033
(2) EPA-APPROVED ALLEGHENY COUNTY HEALTH DEPARTMENT (ACHD) REGULATIONS—Continued
Article XX or XXI citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Subpart 3—Incineration and Combustion Sources
2105.30 (except paragraphs .b.3 and .f).
Incinerators ......................................
10/20/95
11/14/02, 67 FR 68935 ..
(c)(192); Section 2105.30.f. is federally enforceable as part of the applicable section 111(d) plan.
Subpart 4—Miscellaneous Fugitive Sources
2105.40
2105.41
2105.42
2105.43
2105.44
2105.45
2105.46
2105.47
2105.48
...........................
...........................
...........................
...........................
...........................
...........................
...........................
...........................
...........................
2105.49.a, .b ..................
Permit Source Premises ..................
Non-Permit Premises .......................
Parking Lots and Roadways ............
Permit Source Transport .................
Non-Permit Source Transport ..........
Construction and Land Clearing ......
Mining ..............................................
Demolition ........................................
Areas Subject to Sections 2105.40
Through 2105.47.
Fugitive Emissions ...........................
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
11/14/02,
11/14/02,
11/14/02,
11/14/02,
11/14/02,
11/14/02,
11/14/02,
11/14/02,
11/14/02,
67
67
67
67
67
67
67
67
67
FR
FR
FR
FR
FR
FR
FR
FR
FR
68935
68935
68935
68935
68935
68935
68935
68935
68935
..
..
..
..
..
..
..
..
..
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
10/20/95
11/14/02, 67 FR 68935 ..
(c)(192).
Subpart 5—Open Burning and Abrasive Blasting Sources
2105.50 (except paragraph .50.d).
Article XX, Section 533 ..
Open Burning ...................................
10/20/95
11/14/02, 67 FR 68935 ..
(c)(192).
Abrasive Blasting .............................
10/9/86
10/19/87, 51 FR 38758 ..
(c)(69).
Subpart 7—Miscellaneous VOC Sources
2105.70 ...........................
2105.71 ...........................
2105.72 ...........................
2105.74 ...........................
2105.75 ...........................
2105.76 ...........................
Petroleum Refineries .......................
Pharmaceutical Products .................
Manufacturer of Pneumatic Rubber
Tires.
Aerospace Manufacturing and Rework.
Mobile Equipment Repair and Refinishing.
Wood Furniture Manufacturing Operations.
10/20/95
10/20/95
10/20/95
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
7/10/03
6/24/05, 70 FR 36511.
7/10/03
6/24/05, 70 FR 36511.
7/10/03
(c)(192).
(c)(192).
(c)(192).
6/24/05, 70 FR 36511.
Subpart 9—Transportation Related Sources
2105.90 ...........................
Gasoline Volatility ............................
5/15/98
9/1/99
4/17/01, 66 FR 19724 ....
(c)(151).
Part F—Air Pollution Episodes
2106.01 ...........................
2106.02 ...........................
2106.03 ...........................
2106.04 ...........................
2106.05 ...........................
Air Pollution Episode System ..........
Air Pollution Source Curtailment
Plans.
Episode Criteria ...............................
Episode Actions ...............................
USX-Clairton Works PM–10 Self
Audit Emergency Action Plan.
10/20/95
10/20/95
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
(c)(192).
(c)(192).
10/20/95
10/20/95
8/15/97
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
6/12/98, 63 FR 32126 ....
(c)(192).
(c)(192).
(c)(133)(i)(B)(3).
PWALKER on PROD1PC71 with RULES2
Part G—Methods
2107.01 ...........................
2107.02 ...........................
2107.03 ...........................
2107.04 (except paragraph .04.h).
2107.05 ...........................
2107.06 ...........................
2107.07 ...........................
2107.08 ...........................
2107.10 ...........................
2107.11 ...........................
2107.15 ...........................
2107.20.c, .g through .j,
.m and .n.
VerDate Nov<24>2008
General ............................................
Particulate Matter .............................
Sulfur Oxides ...................................
Volatile Organic Compounds ...........
10/20/95
10/20/95
10/20/95
10/20/95
1/14/02, 67 FR 68935 ....
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
(c)(192).
(c)(192).
(c)(192).
(c)(192).
Nitrogen Oxides ...............................
Incinerator Temperatures ................
Coke Oven Emissions .....................
Coke Oven Gas ...............................
Sulfur Content of Coke ....................
Visible Emissions .............................
Gasoline Volatility and RFG ............
Ambient Measurements ...................
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
5/15/98
10/20/95
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
4/17/01, 66 FR 19724 ....
11/14/02, 67 FR 68935 ..
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(151).
(c)(192).
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00021
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
13034
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(2) EPA-APPROVED ALLEGHENY COUNTY HEALTH DEPARTMENT (ACHD) REGULATIONS—Continued
Article XX or XXI citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Part H—Reporting, Testing & Monitoring
2108.01 ...........................
2108.01.a. .......................
2108.01.b ........................
2108.01.c ........................
2108.01.d. .......................
2108.01.e (Except paragraphs e.1.A &.B).
2108.01.f .........................
2108.01.g ........................
2108.02 ...........................
2108.03 ...........................
2108.04 ...........................
Reports Required .............................
Termination of Operation .................
Shutdown of Control Equipment ......
Breakdowns .....................................
Cold Start .........................................
Emissions Inventory Statements .....
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
11/14/02,
11/14/02,
11/14/02,
11/14/02,
11/14/02,
11/14/02,
67
67
67
67
67
67
FR
FR
FR
FR
FR
FR
68935
68935
68935
68935
68935
68935
..
..
..
..
..
..
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
Orders ..............................................
Violations .........................................
Emissions Testing ............................
Continuous Emissions Monitoring ...
Ambient Monitoring ..........................
10/20/95
10/20/95
10/20/95
10/20/95
10/20/95
11/14/02,
11/14/02,
11/14/02,
11/14/02,
11/14/02,
67
67
67
67
67
FR
FR
FR
FR
FR
68935
68935
68935
68935
68935
..
..
..
..
..
(c)(192).
(c)(192).
(c)(192).
(c)(192).
(c)(192).
Part I—Enforcement
2109.01 ...........................
2109.02 (except paragraph.02.a.7).
2109.03a. (introductory
sentence), b. through f.
2109.04 ...........................
2109.05 ...........................
2109.06 (Except paragraphs .06.a.2, .a.3,
and .a.4).
2109.10 ...........................
2109.20 ...........................
Inspections .......................................
Remedies .........................................
10/20/95
10/20/95
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
(c)(192).
(c)(192).
Enforcement Orders ........................
10/20/95
11/14/02, 67 FR 68935 ..
(c)(192).
Orders Establishing an Additional or
More Restrictive Standard.
Emergency Orders ...........................
Civil Proceedings .............................
10/20/95
11/14/02, 67 FR 68935 ..
(c)(192).
10/20/95
10/20/95
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
(c)(192).
(c)(192).
Appeals ............................................
General Federal Conformity ............
10/20/95
10/20/95
11/14/02, 67 FR 68935 ..
11/14/02, 67 FR 68935 ..
(c)(192).
(c)(192).
(3) EPA-APPROVED PHILADELPHIA AMS REGULATIONS
Rule citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Title 3—Air Management Code
Chapter 3–100 ................
Chapter 3–200 (Except
§ 3–207(4)).
Chapter 3–300 ................
General Provisions ..........................
Prohibited Conduct ..........................
10/20/69
10/4/76
5/31/72, 37 FR 10842 ....
6/4/79, 44 FR 31980 ......
(c)(1).
(c)(18).
Administrative Provisions .................
9/21/72
3/12/79, 44 FR 13480 ....
(c)(15).
Regulation I—General Provisions
Section I .........................
Section II (Except portions of paragraph II.B).
Section III .......................
Section IV .......................
Section V ........................
Section VI .......................
Section VII ......................
Section VIII .....................
Section IX .......................
Section XI.D ...................
Definitions ........................................
Source Registration and Emission
Reporting.
Testing and Test Methods ...............
Availability of Technology ................
Improvement and Plan ....................
Pre-existing Regulations ..................
Circumvention ..................................
Severability ......................................
Effective Date ..................................
Compliance with Federal Regulations—Stack Height Regulations.
4/29/70
5/4/74
5/31/72, 37 FR 10842 ....
9/9/75, 40 FR 41787 ......
(c)(1).
(c)(12).
4/29/70
4/29/70
4/29/70
4/29/70
4/29/70
4/29/70
4/29/70
3/27/86
5/31/72,
5/31/72,
5/31/72,
5/31/72,
5/31/72,
5/31/72,
5/31/72,
1/23/89,
(c)(1).
(c)(1).
(c)(1).
(c)(1).
(c)(1).
(c)(1).
(c)(1).
(c)(70).
37
37
37
37
37
37
37
54
FR
FR
FR
FR
FR
FR
FR
FR
10842 ....
10842 ....
10842 ....
10842 ....
10842 ....
10842 ....
10842 ....
3029 ......
PWALKER on PROD1PC71 with RULES2
Regulation II—Air Contaminant and Particulate Matter Emissions
Section
Section
Section
Section
I .........................
II ........................
IV .......................
V ........................
Section VI .......................
Section VII ......................
VerDate Nov<24>2008
No Title [General Provisions] ...........
Open Fires .......................................
Visible Emissions .............................
Particulate Matter Emissions from
the Burning of Fuels.
Selection of Fuel for Particulate
Matter Emission Control.
Particulate Matter Emissions from
Chemical, Metallurgical, Mechanical and Other Processes.
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00022
4/29/70
4/29/70
5/4/74
8/27/81
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
9/9/75, 40 FR 41787 ......
4/16/82, 47 FR 16325 ....
(c)(1).
(c)(1).
(c)(12).
(c)(43).
4/29/70
5/31/72, 37 FR 10842 ....
(c)(1).
4/29/70
5/31/72, 37 FR 10842 ....
(c)(1).
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13035
(3) EPA-APPROVED PHILADELPHIA AMS REGULATIONS—Continued
State effective date
Additional explanation/
§ 52.2063 citation
Rule citation
Title/subject
EPA approval date
Section VIII .....................
Fugitive Dust ....................................
4/29/70
5/31/72, 37 FR 10842 ....
(c)(1).
Table 1 ...........................
No Title [Allowable Process Weight
Emissions].
4/29/70
5/31/72, 37 FR 10842 ....
(c)(1).
Regulation III—The Control of Emissions of Oxides and Sulfur Compounds
Section I .........................
Section II ........................
Section III .......................
No Title [General Provisions] ...........
Control of Emission of Sulfur Compounds.
Control of Sulfur in Fuels .................
4/29/70
5/10/80
5/31/72, 37 FR 10842 ....
9/17/81, 46 FR 46133 ....
(c)(1).
(c)(37).
8/27/81
4/16/82, 47 FR 16325 ....
(c)(43).
Regulation IV—Governing Air Pollution Control Measures During High Air Pollution Episodes
Section
Section
Section
Section
I .........................
II ........................
III .......................
IV .......................
Section V ........................
Section
Section
Section
Table I
VI .......................
VII ......................
VIII .....................
............................
Table II ...........................
Table III ..........................
Table IV ..........................
Definitions ........................................
Declaration of Conditions ................
Termination of Conditions ................
Alert and Notification System by the
Health Commissioner and the
Emergency Coordinator.
Advance Preparation for High Air
Pollution Episodes.
Actions and Restrictions ..................
Severability ......................................
Effective Date ..................................
Minimum Abatement Strategies for
Emission
Reduction
Plans—
Stage I Condition.
Minimum Abatement Strategies for
Emission
Reduction
Plans—
Stage II Condition.
Minimum Abatement Strategies for
Emission
Reduction
Plans—
Emergency Condition.
Emergency Business and Establishment List.
2/5/71
2/5/71
2/5/71
2/5/71
5/31/72,
5/31/72,
5/31/72,
5/31/72,
37
37
37
37
....
....
....
....
(c)(1).
(c)(1).
(c)(1).
(c)(1).
2/5/71
5/31/72, 37 FR 10842 ....
(c)(1)
2/5/71
2/5/71
2/5/71
2/5/71
5/31/72,
5/31/72,
5/31/72,
5/31/72,
....
....
....
....
(c)(1).
(c)(1).
(c)(1).
(c)(1).
2/5/71
5/31/72, 37 FR 10842 ....
(c)(1).
2/5/71
5/31/72, 37 FR 10842 ....
(c)(1).
2/5/71
5/31/72, 37 FR 10842 ....
(c)(1).
37
37
37
37
FR
FR
FR
FR
FR
FR
FR
FR
10842
10842
10842
10842
10842
10842
10842
10842
Regulation V—Control of Emissions of Organic Substances From Stationary Sources
Section I (Except for definitions related to paragraphs V.C.& V.D.).
Section I .........................
Section II ........................
Section III .......................
Section IV .......................
Section V (Except paragraphs V.C and V.D).
Section VI .......................
Section VII ......................
Section VIII .....................
Section IX .......................
Section X ........................
11/28/86
6/16/93, 58 FR 33200 ....
(c)(83).
Definitions ........................................
Storage Tanks .................................
Oil-Effluent Water Separator ...........
Pumps and Compressors ................
Organic Material Loading ................
5/23/88
7/10/71
7/10/71
7/10/71
7/10/71
4/6/93, 48 FR 17778 ......
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
(c)(78).
(c)(1).
(c)(1).
(c)(1).
(c)(1).
Solvents ...........................................
Processing of Photochemically Reactive Materials.
Architectural Coatings ......................
Disposal of Solvents ........................
7/10/71
7/10/71
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
(c)(1).
(c)(1).
7/10/71
7/10/71
5/31/72, 37 FR 10842 ....
5/31/72, 37 FR 10842 ....
(c)(1).
(c)(1).
11/28/86
6/16/93, 58 FR 33192 ....
(c)(82).
11/28/86
11/28/86
5/23/98
7/10/71
recodified
5/23/88
7/10/71
recodified
5/23/88
7/10/71
recodified
5/23/88
4/12/93, 58 FR 19066 ....
6/16/93, 58 FR 33200 ....
4/6/93, 58 FR 17778 ......
5/31/72, 37 FR 10842 ....
(c)(77).
(c)(83).
(c)(78).
(c)(1).
5/31/72, 37 FR 10842 ....
(c)(1).
5/31/72, 37 FR 10842 ....
(c)(1).
XI .......................
XII ......................
XIII .....................
XXII ....................
Compliance
with
Pennsylvania
Standards for Volatile Organic
Compounds (VOC).
Petroleum Solvent Dry Cleaning .....
Pharmaceutical Tablet Coating .......
Process Equipment Leaks ...............
Circumvention ..................................
Section XXIII ...................
Severability ......................................
Section XXIV ..................
Effective Date ..................................
Section
Section
Section
Section
PWALKER on PROD1PC71 with RULES2
Definitions ........................................
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00023
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
13036
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(3) EPA-APPROVED PHILADELPHIA AMS REGULATIONS—Continued
Rule citation
State effective date
Title/subject
Additional explanation/
§ 52.2063 citation
EPA approval date
Regulation VII—Control of Emissions of Nitrogen Oxides From Stationary Sources
Section
Section
Section
Section
Section
Section
Section
I .........................
II ........................
III .......................
IV .......................
V ........................
VI .......................
VII ......................
Definitions ........................................
Fuel Burning Equipment ..................
Nitric Acid Plants .............................
Emissions Monitoring .......................
Circumvention ..................................
Severability ......................................
Effective Date ..................................
7/1/72
11/20/85
7/1/72
7/1/72
7/1/72
7/1/72
7/1/72
5/14/73,
1/14/87,
5/14/73,
5/14/73,
5/14/73,
5/14/73,
5/14/73,
38
52
38
38
38
38
38
FR
FR
FR
FR
FR
FR
FR
12696 ....
1456 ......
12696 ....
12696 ....
12696 ....
12696 ....
12696 ....
(c)(7).
(c)(65).
(c)(7).
(c)(7).
(c)(7).
(c)(7).
(c)(7).
Regulation VIII—Control of Emissions of Carbon Monoxide From Stationary Sources
Section
Section
Section
Section
Section
Section
I .........................
II ........................
III .......................
IV .......................
V ........................
VI .......................
Definitions ........................................
General ............................................
Emissions Monitoring .......................
Circumvention ..................................
Severability ......................................
Effective Date ..................................
8/20/72
8/20/72
8/20/72
8/20/72
8/20/72
8/20/72
5/14/73,
5/14/73,
5/14/73,
5/14/73,
5/14/73,
5/14/73,
38
38
38
38
38
38
FR
FR
FR
FR
FR
FR
12696
12696
12696
12696
12696
12696
....
....
....
....
....
....
(c)(7).
(c)(7).
(c)(7).
(c)(7).
(c)(7).
(c)(7).
Regulation XI—Control of Emissions From Incinerators
Section I .........................
Section II ........................
Section III (Except paragraph III.E. (odors)).
Section IV .......................
Section V ........................
Section VI .......................
Section VII ......................
Section VIII .....................
Section IX .......................
Definitions ........................................
General Provisions ..........................
Emissions Limitations ......................
5/4/74
5/4/74
5/4/74
9/9/75, 40 FR 41787 ......
9/9/75, 40 FR 41787 ......
9/9/75, 40 FR 41787 ......
(c)(12).
(c)(12).
(c)(12).
Design ..............................................
Operation .........................................
Permits and Licenses ......................
Circumvention ..................................
Severability ......................................
Effective Date ..................................
5/4/74
5/4/74
5/4/74
5/4/74
5/4/74
5/4/74
9/9/75,
9/9/75,
9/9/75,
9/9/75,
9/9/75,
9/9/75,
(c)(12).
(c)(12).
(c)(12).
(c)(12).
(c)(12).
(c)(12).
40
40
40
40
40
40
FR
FR
FR
FR
FR
FR
41787
41787
41787
41787
41787
41787
......
......
......
......
......
......
Regulation XIII—Construction, Modification, Reactivation and Operation of Sources
Section I .........................
Section II ........................
Introduction ......................................
Program Adoption ............................
10/30/95
10/30/95
3/28/03, 68 FR 15059 ....
3/28/03, 68 FR 15059 ....
(c)(203).
(c)(203).
(d) EPA-approved source-specific
requirements
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)
Name of source
Permit No.
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
For exceptions, see the applicable paragraphs in 40 CFR § 52.2063(c)
PWALKER on PROD1PC71 with RULES2
ARCO Chemical Company ..........
IMC Chemical Group ...................
Aristech Chemical Corp ...............
04–313–052
39–313–014
86–I–0024–P
Beaver ..............
Lehigh ...............
Allegheny ..........
The Knoll Group ...........................
ESSROC Materials ......................
Pennsylvania Power and Light
Co. (PP&L)—Brunner Island.
PPG Industries, Inc.—South Middleton.
Stroehmann Bakeries—Dauphin
County.
General Electric Transportation
Systems—Erie.
J. E. Baker Co. (Refractories)—
York.
Lafarge Corp ................................
Lafarge Corp ................................
West Penn Power—Armstrong ....
West Penn Power—Armstrong ....
46–326–001A
PA–48–0004A
PA–67–2005
VerDate Nov<24>2008
01:40 Mar 25, 2009
5/16/90, 55 FR 20267 ........
5/16/90, 55 FR 20267 ........
6/16/93, 58 FR 33197 ........
(c)(71).
(c)(72).
(c)(80).
Montgomery ......
Northampton .....
York ..................
12/9/86
12/10/86
8/28/86
3/3/87
3/24/93
12/20/94
12/22/94
10/19/93, 58 FR 53885 ......
08/08/95, 60 FR 40292 ......
08/08/95, 60 FR 40292 ......
(c)(87).
(c)(98)(i)(B)(1).
(c)(98)(i)(B)(2).
OP–21–2002
Cumberland ......
12/22/94
08/08/95, 60 FR 40292 ......
(c)(98)(i)(B)(3).
PA–22–2003
Dauphin ............
12/22/94
08/08/95, 60 FR 40292 ......
(c)(98)(i)(B)(4).
OP–25–025
Erie ...................
12/21/94
08/08/95, 60 FR 40292 ......
(c)(98)(i)(B)(5).
OP–67–2001
York ..................
12/22/94
08/08/95, 60 FR 40292 ......
(c)(98)(i)(B)(6).
OP–39–0011
PA–39–0011A
PA–03–000–023
PA–03–306–004
Lehigh ...............
Lehigh ...............
Armstrong .........
Armstrong .........
12/23/94
12/23/94
12/29/94
3/28/94
08/08/95,
08/08/95,
08/08/95,
08/08/95,
(c)(98)(i)(B)(7).
(c)(98)(i)(B)(7).
(c)(98)(i)(B)(8).
(c)(98)(i)(B)(8).
Jkt 217001
PO 00000
Frm 00024
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
60
60
60
60
FR
FR
FR
FR
40292
40292
40292
40292
25MRR2
......
......
......
......
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13037
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
West Penn Power—Armstrong ....
Plain and Fancy Kitchens, Inc .....
Stroehmann Bakeries—Bradford
County.
Stroehmann Bakeries—Bradford
County.
Stroehmann Bakeries—Lycoming
County.
Stroehmann Bakeries—Lycoming
County.
Philadelphia
Electric
Co.
(PECO)—Eddystone.
Philadelphia
Electric
Co.
(PECO)—Eddystone.
Gilberton Power Co.—John Rich
Memorial.
Bethlehem
Steel—Coke
and
Chemical Production.
Bethlehem Steel—Foundry ..........
Bethlehem
Steel—Structural
Products.
Bethlehem Steel—Forging ...........
Westwood Energy Properties, Inc.
(CRS Sirrine, Inc.).
PECO Energy Co.—Front Street
Crawford Furniture Manufacturing
Corp.—Clarion County.
Schuylkill Energy Resources .......
Columbia
Gas
Transmission
Corp.—Milford
Compressor
Station.
Texas
Eastern
Transmission
Corp.—Entriken
Compressor
Station.
Columbia
Gas
Transmission
Corp.—Greencastle
Compressor Station.
Lord Corporation—Aerospace Div
Tennessee Gas Pipeline Co.
(TENNECO)—Station 313.
PWALKER on PROD1PC71 with RULES2
Corning Asahi Video Products—
State College.
Corning Asahi Video Products—
State College.
Corning Asahi Video Products—
State College.
Corning Asahi Video Products—
State College.
Columbia
Gas
Transmission
Corp.—Easton
Compressor
Station.
Texas
Eastern
Transmission
Corp.—Bedford
Compressor
Station.
Texas
Eastern
Transmission
Corp.—Marietta
Compressor
Station.
Hercules Cement Co ...................
ESSROC (formerly Lone Star Industries, Inc.).
Pennsylvania Power and Light
Co. (PP&L)—Montour.
Pennsylvania
Electric
Co.
(PENELEC)—Shawville.
Zinc Corp. of America—Potter
Twp.
VerDate Nov<24>2008
01:40 Mar 25, 2009
State
effective
date
County
EPA approval date
Additional
explanation/
§ 52.2063 citation
PA–03–306–006
PA–38–318–019C
PA–08–0001
Armstrong .........
Lebanon ...........
Bradford ............
11/22/94
12/23/94
2/9/95
08/08/95, 60 FR 40292 ......
08/08/95, 60 FR 40292 ......
08/10/95, 60 FR 40758 ......
(c)(98)(i)(B)(8).
(c)(98)(i)(B)(9).
(c)(101)(i)(B).
OP–08–0001A
Bradford ............
2/9/95
08/10/95, 60 FR 40758 ......
(c)(101)(i)(B).
PA–41–0001
Lycoming ..........
2/9/95
08/10/95, 60 FR 40758 ......
(c)(101)(i)(B).
OP–41–0001A
Lycoming ..........
2/9/95
08/10/95, 60 FR 40758 ......
(c)(101)(i)(B).
OP–23–0017
Delaware ..........
12/28/94
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(1).
PA–23–0017
Delaware ..........
12/28/94
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(1).
OP–54–0004
Schuylkill ...........
12/20/94
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(2).
OP–48–0013
Northampton .....
12/20/94
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(3).
OP–48–0014
OP–48–0010
Northampton .....
Northampton .....
12/20/94
12/20/94
09/08/95, 60 FR 46768 ......
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(3).
(c)(102)(i)(B)(3).
OP–48–0015
OP–54–000–6
Northampton .....
Schuylkill ...........
12/20/94
12/27/94
09/08/95, 60 FR 46768 ......
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(3).
(c)(102)(i)(B)(4).
OP–46–0045
OP–16–021
Montgomery ......
Clarion ..............
3/31/95
3/27/95
09/08/95, 60 FR 46768 ......
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(5).
(c)(102)(i)(B)(6).
OP–54–0003
OP–52–0001
Schuylkill ...........
Pike ..................
5/19/95
4/21/95
09/08/95, 60 FR 46768 ......
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(7).
(c)(102)(i)(B)(9).
OP–31–2003
Huntingdon .......
5/16/95
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(10).
OP–28–2003
Franklin .............
4/21/95
09/08/95, 60 FR 46768 ......
(c)(102)(i)(B)(11).
OP–25–095
PA–53–0001
OP–53–0001
CP–53–0001
OP–14–0003
Erie ...................
Potter ................
3/30/95
11/27/95
09/08/95, 60 FR 46768 ......
04/09/96, 61 FR 15709 ......
(c)(102)(i)(B)(12).
(c)(103)(i)(B)(1).
Centre ...............
12/27/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(2).
OP–14–309–009C
Centre ...............
5/5/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(2).
OP–14–309–010A
Centre ...............
8/18/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(2).
OP–14–309–037A
Centre ...............
5/5/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(2).
OP–48–0001
PA–48–0001A
Northampton .....
5/19/95
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(3).
OP–05–2007
Bedford .............
5/16/95
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(4).
PA–36–2025
Lancaster ..........
5/16/95
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(5).
OP–48–0005
PA–48–0005A
OP–48–0007
Northampton .....
12/23/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(6).
Northampton .....
12/29/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(7).
OP–47–0001
PA–47–0001A
PA–17–0001
Montour ............
12/27/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(8).
Clearfield ..........
12/27/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(9).
OP–04–000–044
Beaver ..............
12/29/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(10).
Jkt 217001
PO 00000
Frm 00025
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
13038
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
The Proctor and Gamble Paper
Products Company Mehoopany.
Columbia
Gas
Transmission
Corp.—Union City Compressor
Station.
James River Corp.—Chambersburg.
Appleton Papers, Inc.—Harrisburg.
Air Products and Chemicals,
Inc.—Corporate R & D.
Elf Atochem North America,
Inc.—King of Prussia.
York
City
Sewer
Authority
(Wastewater Treatment Plant).
Glasgow, Inc.—Ivy Rock ..............
Glasgow, Inc.—Spring House ......
Glasgow, Inc.—Catanach ............
Glasgow, Inc.—Freeborn .............
UGI Utilities—Hunlock Creek .......
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
OP–66–0001
PA–66–0001A
OP–25–892
Wyoming ...........
12/20/94
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(11).
Erie ...................
4/11/95
04/09/96, 61 FR 15709 ......
(c)(103)(i)(B)(12).
OP–28–2006
Franklin .............
6/14/95
02/12/96, 61 FR 05303 ......
(c)(104)(i)(C)(1).
OP–21–2004
Cumberland ......
5/24/95
02/12/96, 61 FR 05303 ......
(c)(104)(i)(C)(2).
OP–39–0008
Lehigh ...............
5/25/95
02/12/96, 61 FR 05303 ......
(c)(104)(i)(C)(3).
OP–46–0022
Montgomery ......
6/27/95
02/12/96, 61 FR 05303 ......
(c)(104)(i)(C)(4).
OP–67–2013
York ..................
3/1/95
02/12/96, 61 FR 05303 ......
(c)(104)(i)(C)(5).
OP–46–0043
OP–46–0029
OP–15–0021
OP–23–0026
OP–40–0005
PA–40–0005A
PA–67–2009
Montgomery ......
Montgomery ......
Chester .............
Delaware ..........
Luzerne ............
6/7/95
6/7/95
6/7/95
6/7/95
12/20/94
02/12/96,
02/12/96,
02/12/96,
02/12/96,
05/16/96,
......
......
......
......
......
(c)(104)(i)(C)(6).
(c)(104)(i)(C)(7).
(c)(104)(i)(C)(8).
(c)(104)(i)(C)(9).
(c)(108)(i)(B)(1).
York ..................
8/17/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(2).
CP–67–2009
York ..................
8/17/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(2).
OP–18–0001
PA–18–0001
Clinton ..............
7/18/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(3).
OP–53–0007
PA–53–0007A
PA–67–2006
Potter ................
7/17/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(4).
York ..................
8/25/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(5).
PA–06–1036
Berks ................
5/12/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(6).
PA–06–315–001
Berks ................
6/4/92
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(6).
PA–32–000–303
Indiana ..............
7/5/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(7).
OP–23–0007
Delaware ..........
6/8/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(8).
OP–67–2030
OP–32–000–100
York ..................
Indiana ..............
8/30/95
7/18/95
05/16/96, 61 FR 24706 ......
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(9).
(c)(108)(i)(B)(10).
OP–06–1001
Berks ................
4/4/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(11).
OP–06–1005
Berks ................
4/4/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(12).
OP–46–0044
Montgomery ......
6/7/95
05/16/96, 61 FR 24706 ......
(c)(108)(i)(B)(13).
OP–43–285
Mercer ..............
11/3/95
12/20/96, 61 FR 67229 ......
Sharon Steel Corp.—Farrell ........
OP–43–017
Mercer ..............
11/3/95
12/20/96, 61 FR 67229 ......
DMi Furniture, Inc.—Timely Plant
#7 (Gettysburg).
R. R. Donnelley and Sons Co.—
Lancaster West Plant.
International Paper Company—
Hammermill Papers Division.
Lucent
Technology
(formerly
AT&T Corp.)—Reading.
Garden State Tanning, Inc.—
Fleetwood Plant.
Glidden Co., The—Reading .........
Maier’s Bakery—Reading Plant ...
Morgan Corp.—Morgantown Plant
Allentown Cement Co., Inc.—
Evansville Plant.
OP–01–2001
Adams ..............
6/13/95
03/12/97, 62 FR 11079 ......
(c)(113)(i)(B)(1);
52.2037(g).
(c)(113)(i)(B)(2);
52.2036(f);
52.2037(e).
(c)(114)(i)(B)(1).
OP–36–2026
Lancaster ..........
7/14/95
03/12/97, 62 FR 11079 ......
(c)(114)(i)(B)(2).
OP–18–0005
Clinton ..............
12/27/94
01/29/97, 62 FR 04167 ......
(c)(115)(i)(B).
PA–06–1003
Berks ................
6/26/95
04/18/97, 62 FR 19051 ......
(c)(117)(i)(B)(1).
PA–06–1014
Berks ................
6/21/95
04/18/97, 62 FR 19051 ......
(c)(117)(i)(B)(2).
OP–06–1035
PA–06–1023
OP–06–1025
PA–06–1002
Berks
Berks
Berks
Berks
04/18/97,
04/18/97,
04/18/97,
04/18/97,
(c)(117)(i)(B)(3).
(c)(118)(i)(B)(1).
(c)(118)(i)(B)(2).
(c)(118)(i)(B)(3).
PWALKER on PROD1PC71 with RULES2
Solar Turbines, Inc. (York Cogeneration Facility).
Solar Turbines, Inc. (York Cogeneration Facility).
Columbia
Gas
Transmission
Corp.—Renovo
Compressor
Station.
National Fuel Gas Supply Corp.—
East Fork Compressor Station.
York County Solid Waste &
Refuse Authority (Y.C.R.R.C.).
W.
R.
Grace
and
Co.—
FORMPAC Div.
W. R. Grace and Co.—Reading
Plant.
CNG Transmission Corp.—Cherry
Tree Sta.
EPC Power Corp. of Bethlehem
(Crozer Chester CoGen).
C–P Converters, Inc.—York ........
Fisher
Scientific
Co.
International—Indiana.
Adelphi
Kitchens,
Inc.—
Robesonia Factory.
Birchcraft Kitchens, Inc.—Reading Factory.
Glasgow, Inc.—Bridgeport Asphalt Plant.
Caparo Steel Co.—Farrell ...........
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00026
................
................
................
................
Fmt 4701
Sfmt 4700
2/15/96
9/20/95
8/31/95
10/11/95
E:\FR\FM\25MRR2.SGM
61
61
61
61
61
62
62
62
62
FR
FR
FR
FR
FR
FR
FR
FR
FR
05303
05303
05303
05303
24706
19051
19047
19047
19047
25MRR2
......
......
......
......
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13039
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
PWALKER on PROD1PC71 with RULES2
Quaker Maid (Schrock Cabinet
Group)—Leesport.
Brentwood
Industries,
Inc.—
Reading Plant.
Metropolitan
Edison
Co.
(MetEd)—Titus Station.
ICI
Fluoropolymers—
Downingtown.
Synthetic Thread Co., Inc.—Bethlehem.
Bird-in-Hand
Woodwork,
Inc.
(Childcraft Education Corp.).
Heinz Pet Products—Bloomsburg
Graco Children’s Products, Inc.—
Elverson.
Texas
Eastern
Transmission
Corp.—Bernville.
Texas
Eastern
Transmission
Corp.—Bechtelsville.
Carpenter Technology Corp.—
Reading Plant.
North American Fluoropolymers
Co. (NAFCO).
CNG
Transmission
Corp.—
Ellisburg Compressor Station.
CNG
Transmission
Corp.—
Ellisburg Compressor Station.
CNG
Transmission
Corp.—
Ellisburg Compressor Station.
CNG
Transmission
Corp.—
Greenlick Compressor Station.
CNG
Transmission
Corp.—
Greenlick Station.
CNG
Transmission
Corp.—
Greenlick Compressor Station.
CNG
Transmission
Corp.—
Crayne Station.
CNG Transmission Corp.—State
Line Station.
CNG Transmission Corp.—Big
Run Station.
Medusa Cement Company ..........
Keystone Cement Co ...................
Lehigh Portland Cement Company.
Mercer Lime and Stone Company
Con-Lime, Inc ...............................
Pennzoil
Products
Co.—
Rouseville.
R. R. Donnelley & Sons Co.—
Lancaster East Plant.
Panther Creek Partners ...............
Allegro
Microsystems,
W.G.,
Inc.—Willow Grove.
Hale
Products,
Inc.—
Conshohocken.
Con-Lime, Inc.—Bellefonte ..........
Coastal Aluminum Rolling Mills,
Inc.—Williamsport.
ABP/International Envelope Co ...
Brown Printing Company .............
OP–06–1028
Berks ................
10/27/95
04/18/97, 62 FR 19047 ......
(c)(118)(i)(B)(4).
PA–06–1006
Berks ................
2/12/96
04/18/97, 62 FR 19047 ......
(c)(118)(i)(B)(5).
PA–06–1024
Berks ................
3/9/95
04/18/97, 62 FR 19047 ......
(c)(118)(i)(B)(6).
PA–15–0009
CP–15–0009
PA–39–0007A
Chester .............
10/3/95
04/18/97, 62 FR 19047 ......
(c)(118)(i)(B)(7).
Lehigh ...............
8/10/95
04/18/97, 62 FR 19047 ......
(c)(118)(i)(B)(8).
OP–36–2022
Lancaster ..........
9/27/95
04/18/97, 62 FR 19047 ......
(c)(118)(i)(B)(9).
OP–19–0003
OP–15–0006
Columbia ..........
Chester .............
11/27/95
11/30/95
08/21/97, 62 FR 44413 ......
08/21/97, 62 FR 44413 ......
(c)(119)(i)(B)(1).
(c)(119)(i)(B)(2).
OP–06–1033
Berks ................
1/31/97
04/18/97, 62 FR 19049 ......
(c)(120)(i)(B)(1).
OP–06–1034
Berks ................
1/31/97
04/18/97, 62 FR 19049 ......
(c)(120)(i)(B)(2).
OP–06–1007
Berks ................
9/27/96
04/18/97, 62 FR 19049 ......
06–1026, CP–06–
1026
PA–53–0004A
Berks ................
04/18/97, 62 FR 19049 ......
Potter ................
4/19/95
6/1/95
2/29/96
06/11/97, 62 FR 31732 ......
(c)(120)(i)(B)(3),
(ii)(B).
(c)(120)(i)(B)(4),
(ii)(B).
(c)(121)(i)(B)(1).
OP–53–0004
Potter ................
2/29/96
06/11/97, 62 FR 31732 ......
(c)(121)(i)(B)(1).
CP–53–0004A
Potter ................
2/29/96
06/11/97, 62 FR 31732 ......
(c)(121)(i)(B)(1).
PA–53–0003A
Potter ................
12/18/95
06/11/97, 62 FR 31732 ......
(c)(121)(i)(B)(2).
CP–53–0003A
Potter ................
12/18/95
06/11/97, 62 FR 31732 ......
(c)(121)(i)(B)(2).
OP–53–0003
Potter ................
2/18/95
06/11/97, 62 FR 31732 ......
(c)(121)(i)(B)(2).
30–000–089
Greene .............
2/22/95
06/11/97, 62 FR 31732 ......
(c)(121)(i)(B)(3).
OP–53–0008
Potter ................
1/10/96
06/11/97, 62 FR 31732 ......
(c)(121)(i)(B)(4).
PA–33–147
Jefferson ...........
6/27/95
06/11/97, 62 FR 31732 ......
(c)(121)(i)(B)(5).
OP–37–013
OP–48–0003
OP–67–2024
Lawrence ..........
Northampton .....
York ..................
7/27/95
5/25/95
5/26/95
06/03/97, 62 FR 30250 ......
06/03/97, 62 FR 30250 ......
06/03/97, 62 FR 30250 ......
(c)(122)(i)(B)(1).
(c)(122)(i)(B)(2).
(c)(122)(i)(B)(3).
OP–10–023
OP–14–0001
PA–61–016
Butler ................
Centre ...............
Venango ...........
5/31/95
6/30/95
9/8/95
06/03/97, 62 FR 30250 ......
06/03/97, 62 FR 30250 ......
06/11/97, 62 FR 31738 ......
(c)(122)(i)(B)(4).
(c)(122)(i)(B)(5).
(c)(124)(i)(B).
OP–36–2027
Lancaster ..........
7/14/95
07/21/97, 62 FR 33891 ......
OP–13–0003
OP–46–0006
Carbon ..............
Montgomery ......
12/2/96
12/19/97
09/29/97, 62 FR 50871 ......
03/09/98, 63 FR 11370 ......
(c)(125)(i)(B);
52.2036j.
(c)(128)(i)(B).
(c)(130)(i)(B)(1).
OP–46–0057
Montgomery ......
11/21/97
03/09/98, 63 FR 11370 ......
(c)(130)(i)(B)(2).
OP–14–0001
OP–41–0007
Centre ...............
Lycoming ..........
1/7/98
11/21/97
03/09/98, 63 FR 11370 ......
03/09/98, 63 FR 11370 ......
(c)(130)(i)(B)(3).
(c)(130)(i)(B)(4).
OP–15–0023
CP–46–0018
Chester .............
Montgomery ......
03/09/98, 63 FR 11370 ......
03/09/98, 63 FR 11370 ......
(c)(130)(i)(B)(5).
(c)(130)(i)(B)(6).
Fibre-Metal Products Company ...
Finnaren & Haley, Inc ..................
Fres-co System USA, Inc ............
Graphic Packaging Corporation ...
Montour Oil Service Company, a
division of Sun Company, Inc.
OP–23–0025
OP–46–0070
OP–09–0027
OP–15–0013
OP–41–0013
Delaware ..........
Montgomery ......
Bucks ................
Chester .............
Lycoming ..........
11/2/95
9/26/96
10/27/97
2/20/98
3/5/98
3/5/98
2/28/98
3/19/98
06/29/98,
06/29/98,
06/29/98,
06/29/98,
06/29/98,
(c)(132)(i)(B)(1).
(c)(132)(i)(B)(2).
(c)(132)(i)(B)(3).
(c)(132)(i)(B)(4).
(c)(132)(i)(B)(5).
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00027
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
63
63
63
63
63
FR
FR
FR
FR
FR
35145
35145
35145
35145
35145
25MRR2
......
......
......
......
......
13040
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
PWALKER on PROD1PC71 with RULES2
Name of source
Permit No.
Atlantic Refining and Marketing
Corp. (Sun Co., Inc. (R&M)).
Transwall Corporation ..................
Tavo Packaging (formerly Mead
Packaging Company).
CNG Transmission Corp.—Harrison Compressor Station.
CNG Transmission Corp.—Harrison Compressor Station.
CNG Transmission Corp.—Harrison Station.
CNG Transmission Corp.—Leidy
Station.
CNG Transmission Corp.—Leidy
Compressor Station.
CNG Transmission Corp.—Leidy
Station.
CNG
Transmission
Corp.—
Sabinsville Compressor Station.
CNG
Transmission
Corp.—
Sabinsville Compressor Station.
CNG
Transmission
Corp.—
Sabinsville Station.
CNG Transmission Corp.—Tioga
Station.
Eldorado
Properties
Corp.—
Northumberland Terminal.
Endura Products, Inc ...................
Ford Electronics & Refrigeration
Company.
H & N Packaging, Inc. (formerly
Paramount Packaging Corp.).
Lancaster County Solid Waste
Management Authority.
Monsey Products Co.—Kimberton
Ortho-McNeil Pharmaceutical—
Spring House.
Piccari Press, Inc .........................
Pierce and Stevens Corp.—
Kimberton.
PQ Corporation—Chester ............
Reynolds
Metals
Company
Downington.
Rhone-Poulenc Rorer Pharmaceutical, Inc.
Superior Tube Company ..............
Uniform Tubes Inc .......................
U.S. Air Force—Willow Grove Air
Reserve Station.
Naval Air Station, Joint Reserve
Base—Willow Grove.
Columbia
Gas
Transmission
Corp.—Artemas
Compressor
Station.
Columbia
Gas
Transmission
Corp.—Donegal
Compressor
Station.
Columbia
Gas
Transmission
Corp.—Gettysburg Compressor
Station.
Columbia
Gas
Transmission
Corp.—Eagle Compressor Station.
Columbia
Gas
Transmission
Corp.—Downingtown.
GKN Sinter Metals, Inc ................
Cabinet Industries, Inc.—Water
Street Plant.
VerDate Nov<24>2008
01:40 Mar 25, 2009
State
effective
date
County
EPA approval date
Additional
explanation/
§ 52.2063 citation
OP–49–0015
Northampton .....
3/19/98
06/29/98, 63 FR 35145 ......
(c)(132)(i)(B)(6).
OP–15–0025
OP–09–0008
Chester .............
Bucks ................
3/10/98
11/8/95
06/29/98, 63 FR 35145 ......
06/29/98, 63 FR 35145 ......
(c)(132)(i)(B)(7).
(c)(132)(i)(B)(8).
PA–53–0005A
Potter ................
4/16/96
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(1).
OP–53–0005
Potter ................
4/16/96
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(1).
CP–53–0005A
Potter ................
4/16/96
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(1).
PA–18–0004A
Clinton ..............
3/25/96
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(2).
OP–18–0004
Clinton ..............
2/29/96
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(2).
CP–18–0004A
Clinton ..............
3/25/96
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(2).
PA–59–0002A
Tioga ................
12/18/95
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(3).
OP–59–0002
Tioga ................
12/18/95
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(3).
CP–59–0002A
Tioga ................
12/18/95
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(3).
OP–59–0006
Tioga ................
1/16/96
10/08/98, 63 FR 54050 ......
(c)(134)(i)(B)(4).
OP–49–0016
Northumberland
5/1/98
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(1).
OP–09–0028
OP–46–0036
Bucks ................
Montgomery ......
5/13/98
4/30/98
11/06/98, 63 FR 59884 ......
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(2).
(c)(136)(i)(B)(3).
OP–09–0038
Bucks ................
6/8/98
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(4).
36–02013
Lancaster ..........
6/3/98
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(5).
OP–15–0031
OP–46–0027
Chester .............
Montgomery ......
6/4/98
6/4/98
11/06/98, 63 FR 59884 ......
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(6).
(c)(136)(i)(B)(7).
OP–09–0040
OP–15–0011
Bucks ................
Chester .............
4/29/98
3/27/98
11/06/98, 63 FR 59884 ......
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(8).
(c)(136)(i)(B)(9).
OP–23–0016
OP–15–0004
Delaware ..........
Chester .............
6/16/98
5/8/98
11/06/98, 63 FR 59884 ......
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(10).
(c)(136)(i)(B)(11).
OP–46–0048B
Montgomery ......
4/2/98
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(12).
OP–46–0020
OP–46–0046A
OP–46–0072
Montgomery ......
Montgomery ......
Montgomery ......
4/17/98
3/26/98
5/1/98
11/06/98, 63 FR 59884 ......
11/06/98, 63 FR 59884 ......
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(13).
(c)(136)(i)(B)(14).
(c)(136)(i)(B)(15).
OP–46–0079
Montgomery ......
5/4/98
11/06/98, 63 FR 59884 ......
(c)(136)(i)(B)(16).
05–2006
Bedford .............
4/19/95
12/03/98, 63 FR 66755 ......
(c)(137)(i)B)(1).
63–000–631
Washington ......
7/10/95
12/03/98, 63 FR 66755 ......
(c)(137)(i)B)(2).
01–2003
Adams ..............
4/21/95
12/03/98, 63 FR 66755 ......
(c)(137)(i)B)(3).
OP–15–0022
Chester .............
2/1/96
12/03/98, 63 FR 66755 ......
(c)(137)(i)B)(4).
CP–15–0020
Chester .............
9/15/95
12/03/98, 63 FR 66755 ......
(c)(137)(i)B)(5).
OP–12–0002
OP–47–0005
Cameron ...........
Montour ............
10/30/98
9/21/98
04/16/99, 64 FR 18821 ......
04/16/99, 64 FR 18821 ......
(c)(138)(i)(B)(1).
(c)(138)(i)(B)(2).
Jkt 217001
PO 00000
Frm 00028
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13041
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
EPA approval date
Additional
explanation/
§ 52.2063 citation
PWALKER on PROD1PC71 with RULES2
Springs Window Fashions Division, Inc.
Centennial Printing Corp ..............
OP–41–0014
Lycoming ..........
9/29/98
04/16/99, 64 FR 18821 ......
(c)(138)(i)(B)(3).
OP–46–0068
Montgomery ......
04/16/99, 64 FR 18821 ......
(c)(138)(i)(B)(4).
Strick Corp.—Danville ..................
Handy and Harmon Tube Co.—
Norristown.
Boeing
Defense
&
Space
Group—Helicopters Div.
Delaware
County
Regional
Authority’s Western Regional
Treatment Plant (DELCORA
WRTP).
Delbar Products, Inc.—Perkasie ..
Department of Public Welfare
(NSH)—Norristown.
Dopaco, Inc.—Downingtown ........
Garlock, Inc. (Plastomer Products).
Interstate Brands Corporation
(formerly, Continental Baking
Company).
J. B. Slevin Company Inc.—
Lansdowne.
Laclede Steel Co.—Fairless Hills
LNP Engineering Plastics, Inc.—
Thorndale.
Lukens Steel Co.—Coatesville ....
Nabisco Biscuit Co .......................
PECO Energy Co.—Croydon
Generating Station.
PECO Energy Co.—Limerick
Generating Station.
PECO Energy Co.—USX Fairless
Works Powerhouse.
PECO
Energy
Co.—West
Conshohocken Plant.
Pennsylvania Electric Co.—Front
Street Station.
American Inks and Coatings
Corp.—Valley Forge.
Avery Dennison Co. (Fasson Roll
Division)—Quakertown.
Cabot Performance Materials—
Boyertown.
Cleveland
Steel
Container
Corp.—Quakertown.
CMS Gilbreth Packaging Systems—Bristol.
CMS Gilbreth Packaging Systems—Bensalem.
Congoleum Corp.—Marcus Hook
Epsilon Products Co.—Marcus
Hook.
Foamex
International,
Inc.—
Eddystone.
Forms, Inc., Spectra Graphics—
Willow Grove.
Global Packaging, Inc. (formerly
BG Packaging)—Oaks.
Jefferson Smurfit Corp. (Container Corp. of Amer.)—Oaks.
Jefferson Smurfit Corp. (Container Corp. of Amer.)—North
Wales.
Lonza, Inc.—Conshohocken ........
OP–47–0002
OP–46–0016
Montour ............
Montgomery ......
10/31/96
5/11/98
8/28/96
9/25/95
04/16/99, 64 FR 18821 ......
04/16/99, 64 FR 18821 ......
(c)(138)(i)(B)(5).
(c)(138)(i)(B)(6).
CP–23–0009
Delaware ..........
9/3/97
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(1).
OP–23–0032
Delaware ..........
3/12/97
5/16/97
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(2).
OP–09–0025
OP–46–0060
Bucks ................
Montgomery ......
2/1/96
1/21/98
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(3).
(c)(143)(i)(B)(4).
CP–15–0029
PA–09–0035
Chester .............
Bucks ................
3/6/96
3/12/97
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(5).
(c)(143)(i)(B)(6).
PLID (51–) 5811
Philadelphia ......
4/10/95
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(7).
OP–23–0013
Delaware ..........
9/3/96
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(8).
OP–09–0023
OP–15–0035
Bucks ................
Chester .............
7/17/95
10/31/97
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(9).
(c)(143)(i)(B)(10).
OP–15–0010
PLID (51–) 3201
OP–09–0016A
Chester .............
Philadelphia ......
Bucks ................
5/6/99
4/10/95
12/20/96
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(11).
(c)(143)(i)(B)(12).
(c)(143)(i)(B)(13).
OP–46–0038
Montgomery ......
7/25/95
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(14).
OP–09–0066
Bucks ................
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(15).
OP–46–0045A
Montgomery ......
12/31/98
4/6/99
12/4/97
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(16).
25–0041
Erie ...................
2/25/99
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(17).
OP–15–0026A
Chester .............
1/10/97
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(18).
OP–09–0001A
Bucks ................
10/2/97
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(19).
OP–46–0037
Montgomery ......
4/13/99
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(20).
OP–09–0022
Bucks ................
9/30/96
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(21).
OP–09–0036
Bucks ................
1/7/97
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(22).
OP–09–0037
Bucks ................
4/10/97
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(23).
OP–23–0021
OP–23–0012
Delaware ..........
Delaware ..........
12/31/98
2/15/96
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(24).
(c)(143)(i)(B)(25).
OP–23–0006A
Delaware ..........
3/30/99
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(26).
OP–46–0023
Montgomery ......
12/15/00, 65 FR78418 .......
(c)(143)(i)(B)(27).
OP–46–0026
Montgomery ......
12/15/00, 65 FR78418 .......
(c)(143)(i)(B)(28).
OP–46–0041
Montgomery ......
11/9/95
3/25/98
8/30/96
12/24/97
4/18/97
12/15/00, 65 FR78418 .......
(c)(143)(i)(B)(29).
OP–46–0062
Montgomery ......
7/15/96
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(30).
OP–46–0025
Montgomery ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(31).
Markel Corporation ......................
OP–46–0081
Montgomery ......
4/22/97
6/16/98
4/9/99
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(32).
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00029
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
13042
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
OP–15–0037
Chester .............
9/3/96
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(33).
OP–09–0021
CP–09–0005
Bucks ................
Bucks ................
12/20/96
8/8/96
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(34).
(c)(143)(i)(B)(35).
CP–46–0067
Montgomery ......
10/31/97
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(36).
OP–15–0014A
Chester .............
(c)(143)(i)(B)(37).
OP–15–0030
OP–46–0015
Chester .............
Montgomery ......
12/20/96
12/2/99
4/13/99
11/7/96
12/15/00, 65 FR 78418 ......
NVF Company .............................
Occidental Chemical Corp. (Vinyls Div.)—Pottstown.
Philadelphia Newspapers, Inc.
(Schuylkill Printing Plant).
The Proctor and Gamble Paper
Products Co.
Quebecor Printing Atglen, Inc.—
Atglen.
Sartomer Company, Inc ...............
PWALKER on PROD1PC71 with RULES2
McCorquodale Security Cards,
Inc.—West Whiteland.
Mike-Rich, Inc. (MRI)—Newtown
Minnesota Mining and Manufacturing (3M) Company—Bristol.
MM Biogas Power LLC (formerly
O’Brien Environmental Energy,
Inc.).
Norwood Industries, Inc.—Frazer
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(38).
(c)(143)(i)(B)(39).
OP–46–0012
Montgomery ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(40).
OP–66–0001
Wyoming ...........
8/30/96
3/15/00
4/4/97
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(41).
OP–15–0002
Chester .............
12/10/96
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(42).
OP–15–0015
Chester .............
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(43).
Silberline Manufacturing Co .........
SmithKline Beecham Research
Co. (formerly Sterling Winthrop,
Inc.).
Sullivan Graphics, Inc.—York ......
Sun Company, Inc (R&M) (formerly Chevron USA)—Tinicum.
Sun Company, Inc (R&M) (formerly Chevron USA)—Darby.
Universal Packaging Corporation
Zenith Products Corp.—Aston .....
Budd Company ............................
Bellevue Cogeneration Plant .......
MSC Pre-Finish Metals, Inc.—
Morrisville.
Temple
University,
Health
Sciences Center.
TRIGEN—Schuylkill Station .........
TRIGEN—Edison Station .............
Advanced Glassfiber Yarns LLC
(formerly Owens Corning)—
Huntingdon.
Armstrong
World
Industries,
Inc.—Beech Creek.
Bemis Company, Film Division ....
Brentwood Industries, Inc ............
Certainteed Corp.—Mountaintop
CNG Transmission Corp.—Ardell
Station.
CNG
Transmission
Corp.—
Finnefrock Station.
Consol Pennsylvania Coal Company—Bailey Prep Plant.
Consolidated Rail Corp. (CONRAIL)—Hollidaysburg Car Shop.
Consolidated Rail Corp. (CONRAIL)—Juniata.
Containment Solutions, Inc. (formerly called Fluid Containment—Mt. Union).
Cooper Energy Systems, Grove
City.
Cyprus Cumberland Resources
Corp.
Defense
Distribution—Susquehanna.
EMI Company ..............................
Empire Sanitary Landfill, Inc ........
OP–54–0041
OP–46–0031
Schuylkill ...........
Montgomery ......
1/17/96
3/25/98
4/19/99
10/31/97
5/1/98
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(44).
(c)(143)(i)(B)(45).
OP–67–2023
OP–23–0010
York ..................
Delaware ..........
8/22/95
10/31/96
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(46).
(c)(143)(i)(B)(47).
OP–23–0011
Delaware ..........
10/31/96
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(48).
OP–46–0156
OP–23–0008
PLID 51–1564
PLID (51–) 6513
OP–09–0030
Montgomery ......
Delaware ..........
Philadelphia ......
Philadelphia ......
Bucks ................
12/15/00,
12/15/00,
12/15/00,
12/15/00,
12/15/00,
......
......
......
......
......
(c)(143)(i)(B)(49).
(c)(143)(i)(B)(50).
(c)(143)(i)(B)(51).
(c)(143)(i)(B)(52).
(c)(143)(i)(B)(53).
PLID (51–) 8906
Philadelphia ......
4/8/99
4/7/97
12/28/95
4/10/95
11/7/96
3/31/98
5/27/95
12/15/00, 65 FR 78418 ......
(c)(143)(i)(B)(54).
PLID (51–) 4942
PLID (51–) 4902
OP–31–02002
Philadelphia ......
Philadelphia ......
Huntingdon .......
5/29/95
5/29/95
4/13/99
12/15/00, 65 FR 78418 ......
12/15/00, 65 FR 78418 ......
08/06/01, 66 FR 40891 ......
(c)(143)(i)(B)(55).
(c)(143)(i)(B)(56).
(c)(149)(i)(B)(1).
OP–18–0002
Clinton ..............
7/6/95
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(2).
OP–40–0007A
PA–06–1006A
OP–40–0010
OP–24–120
Luzerne ............
Berks ................
Luzerne ............
Elk ....................
10/10/95
6/3/99
5/31/96
9/30/95
08/06/01,
08/06/01,
08/06/01,
08/06/01,
......
......
......
......
(c)(149)(i)(B)(3).
(c)(149)(i)(B)(4).
(c)(149)(i)(B)(5).
(c)(149)(i)(B)(6).
PA–18–0003A
Clinton ..............
2/29/96
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(7).
OP–30–000–072
Greene .............
3/23/99
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(8).
OP–07–2002
Blair ..................
8/29/95
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(9).
OP–07–2003
Blair ..................
8/29/95
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(10).
OP–31–02005
Huntingdon .......
4/9/99
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(11).
OP–43–003
Mercer ..............
7/25/96
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(12).
OP–30–000–040
Greene .............
3/26/99
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(13).
OP–67–02041
York ..................
2/1/00
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(14).
OP–25–070
OP–35–0009
Erie ...................
Lackawanna .....
10/24/96
10/17/96
08/06/01, 66 FR 40891 ......
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(15).
(c)(149)(i)(B)(16).
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00030
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
65
65
65
65
65
66
66
66
66
FR
FR
FR
FR
FR
FR
FR
FR
FR
78418
78418
78418
78418
78418
40891
40891
40891
40891
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13043
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
(OP)30–000–109
Greene .............
7/10/95
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(17).
(OP)30–000–110
OP–25–029
(OP)56–000–151
Greene .............
Erie ...................
Somerset ..........
7/10/95
6/27/95
2/28/96
08/06/01, 66 FR 40891 ......
08/06/01, 66 FR 40891 ......
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(18).
(c)(149)(i)(B)(19).
(c)(149)(i)(B)(20).
(OP)67–2033
(OP)40–0008
York ..................
Luzerne ............
8/5/97
4/16/99
08/06/01, 66 FR 40891 ......
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(21).
(c)(149)(i)(B)(22).
(OP)44–2011
Mifflin ................
6/4/97
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(23).
(OP)44–2003
Mifflin ................
6/30/95
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(24).
(OP)40–0014A
Luzerne ............
5/30/95
08/06/01, 66 FR 40891 ......
(c)(149)(i)(B)(25).
OP–46–0005
Montgomery ......
(c)(154)(i)(D).
10/31/01,
10/31/01,
10/31/01,
10/31/01,
10/31/01,
10/31/01,
......
......
......
......
......
......
(c)(156)(i)(B)(1).
(c)(156)(i)(B)(2).
(c)(156)(i)(B)(3).
(c)(156)(i)(B)(4).
(c)(156)(i)(B)(5).
(c)(156)(i)(B)(6).
10/31/01, 66 FR 54936 ......
10/31/01, 66 FR 54936 ......
(c)(156)(i)(B)(7).
(c)(156)(i)(B)(8).
PA–PLID
PA–PLID
PA–PLID
PA–PLID
1/13/97
6/23/00
5/29/95
5/29/95
4/9/99
5/29/95
5/29/95
1/9/97
10/1/98
4/16/99
8/3/98
4/15/99
5/29/95
6/11/97
4/10/95
5/29/95
04/18/01, 66 FR 19858 ......
Kurz Hastings, Inc ........................
Lawrence McFadden, Inc ............
Philadelphia Baking Company .....
Philadelphia
Gas
Works—
Passyunk.
PPG Industries, Inc. (BASF) ........
SmithKline Beecham Pharmaceuticals.
Teva Pharmaceuticals USA (formerly Lemmon company).
The Philadelphian Condominium
Building.
Warner Company .........................
Webcraft Technologies, Inc .........
PWALKER on PROD1PC71 with RULES2
Equitrans, Inc.—Rogersville Station.
Equitrans, Inc.—Pratt Station ......
Erie Coke Corporation—Erie .......
Fleetwood Folding Trailers, Inc.—
Somerset.
Gichner Systems Group, Inc .......
Offset Paperback Manufacturers,
Inc.—Dallas.
Overhead Door Corporation—
Mifflin County.
SANYO Audio Manufacturing
(USA) Corp.
Stroehmann
Bakeries
OP—
Luzerne County.
Merck and Co., Inc.—West Point
Facility.
Amerada Hess Corp ....................
Amoco Oil Company ....................
Cartex Corporation .......................
Exxon Company, USA .................
GATX Terminals Corporation ......
Hatfield Quality Meats, Inc.—Hatfield.
J. L. Clark, Inc ..............................
Johnson Matthey, Inc.—Wayne ...
10/31/01,
10/31/01,
10/31/01,
10/31/01,
......
......
......
......
(c)(156)(i)(B)(9).
(c)(156)(i)(B)(10).
(c)(156)(i)(B)(11).
(c)(156)(i)(B)(12).
10/31/01, 66 FR 54936 ......
10/31/01, 66 FR 54936 ......
(c)(156)(i)(B)(13).
(c)(156)(i)(B)(14).
10/31/01, 66 FR 54936 ......
(c)(156)(i)(B)(15).
Latrobe Steel Company—Latrobe
Allegheny Ludlum Corporation—
Brackenridge.
Kosmos Cement Co.—Neville Island Facility.
Armstrong Cement and Supply
Company—Cabot.
Duquesne
Light
Company—
Cheswick Power Station.
Duquesne
Light
Company—
Elrama Plant.
Pennsylvania
Electric
Co.
(PENELEC)—Keystone Generating Station.
IDL, Incorporated .........................
Oakmont Pharmaceutical, Inc ......
U.S. Air, Inc ..................................
Lukens Steel Corporation—Houston Plant.
Allegheny Ludlum Steel Corporation—West Leechburg Plant.
(Allegheny Ludlum Corporation)
Jessop Steel Company—Washington Plant.
Koppel
Steel
Corporation—
Koppel Plant.
VerDate Nov<24>2008
01:40 Mar 25, 2009
PA–PLID (51–)
PA–PLID (51–)
OP–09–0076
PA–PLID (51–)
PA–PLID (51–)
OP–46–0013A
5009
5011
5008
5003
OP–36–02009
OP–15–0027
(51–)
(51–)
(51–)
(51–)
Philadelphia ......
Philadelphia ......
Bucks ................
Philadelphia ......
Philadelphia ......
Montgomery ......
Lancaster ..........
Chester .............
1585
2074
3048
–4921
Philadelphia
Philadelphia
Philadelphia
Philadelphia
......
......
......
......
66
66
66
66
66
66
66
66
66
66
FR
FR
FR
FR
FR
FR
FR
FR
FR
FR
54936
54936
54936
54936
54936
54936
54936
54936
54936
54936
OP–23–0005
OP–46–0035
Delaware ..........
Montgomery ......
OP–09–0010
Bucks ................
6/4/97
3/27/97
10/20/98
4/9/99
PA–PLID (51–) 6512
Philadelphia ......
5/29/95
10/31/01, 66 FR 54936 ......
(c)(156)(i)(B)(16).
OP–15–0001
OP–09–0009
Chester .............
Bucks ................
10/31/01, 66 FR 54936 ......
10/31/01, 66 FR 54936 ......
(c)(156)(i)(B)(17).
(c)(156)(i)(B)(18).
OP–65–000–016
CO–260
Westmoreland ..
Allegheny ..........
7/17/95
4/18/96
10/15/98
12/22/95
12/19/96
10/16/01, 66 FR 52517 ......
10/18/01, 66 FR 52851 ......
(c)(158)(i)(B).
(c)(159)(i)(B).
EO–208
Allegheny ..........
12/19/96
10/18/01, 66 FR 52857 ......
(c)(160)(i)(B)(1).
OP–10–028
Butler ................
3/31/99
10/18/01, 66 FR 52857 ......
(c)(160)(i)(B)(2).
CO–217
Allegheny ..........
3/8/96
10/18/01, 66 FR 52867 ......
(c)(161)(i)(B)(1).
(PA)63–000–014
Washington ......
12/29/94
10/18/01, 66 FR 52867 ......
(c)(161)(i)(B)(2).
(PA–)03–000–027
Armstrong .........
12/29/94
10/18/01, 66 FR 52867 ......
(c)(161)(i)(B)(3).
CO–225
CO–252
CO–255
(OP)63–000–080
Allegheny ..........
Allegheny ..........
Allegheny ..........
Washington ......
7/18/96
12/19/96
1/14/97
2/22/99
10/18/01,
10/18/01,
10/18/01,
10/16/01,
......
......
......
......
(c)(162)(i)(B)(1).
(c)(162)(i)(B)(2).
(c)(162)(i)(B)(3).
(c)(163)(i)(B)(1).
(OP)65–000–183
Westmoreland ..
3/23/99
10/16/01, 66 FR 52522 ......
(c)(163)(i)(B)(2).
(OP)63–000–027
Washington ......
3/26/99
10/16/01, 66 FR 52522 ......
(c)(163)(i)(B)(3).
(OP)04–000–059
Beaver ..............
3/23/01
10/16/01, 66 FR 52522 ......
(c)(163)(i)(D).
Jkt 217001
PO 00000
Frm 00031
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
66
66
66
66
FR
FR
FR
FR
52862
52862
52862
52522
25MRR2
13044
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
PWALKER on PROD1PC71 with RULES2
Consolidated Natural Gas (CNG)
Transmission
Corp.—Beaver
Station.
Consolidated Natural Gas (CNG)
Transmission Corp.—Oakford
Compressor Station.
Consolidated Natural Gas (CNG)
Transmission
Corp.—South
Oakford Station.
Consolidated Natural Gas (CNG)
Transmission
Corp.—Tonkin
Compressor Station.
Consolidated Natural Gas (CNG)
Transmission Corp.—Jeannette
Station.
Carnegie Natural Gas Co.—
Creighton Station.
Texas
Eastern
Transmission
Corp.—Uniontown Station.
Consolidated Natural Gas (CNG)
Transmission
Corp.—South
Bend Station.
Pruett Schaffer Chemical Company.
PPG Industries, Inc.—Springdale
Reichhold
Chemicals,
Inc.—
Bridgeville.
Reichhold
Chemicals,
Inc.—
Bridgeville.
Valspar Corporation—Pittsburgh
Ashland Chemical Corporation ....
Hercules, Inc.—West Elizabeth ...
Hercules, Inc.—West Elizabeth ...
OP–04–000–490
Beaver ..............
6/23/95
10/12/01, 66 FR 52055 ......
(c)(164)(i)(B)(1).
OP–65–000–837
Westmoreland ..
10/13/95
10/12/01, 66 FR 52055 ......
(c)(164)(i)(B)(2).
(OP)65–000–840
Westmoreland ..
10/13/95
10/12/01, 66 FR 52055 ......
(c)(164)(i)(B)(3).
(OP)65–000–634
Westmoreland ..
10/13/95
10/12/01, 66 FR 52055 ......
(c)(164)(i)(B)(4).
(OP)65–000–852
Westmoreland ..
10/13/95
10/12/01, 66 FR 52055 ......
(c)(164)(i)(B)(5).
EO–213
Allegheny ..........
5/14/96
10/12/01, 66 FR 52055 ......
(c)(164)(i)(B)(6).
(OP)26–000–413
Fayette .............
12/20/96
10/12/01, 66 FR 52055 ......
(c)(164)(i)(B)(7).
OP–03–000–180
Armstrong .........
12/2/98
10/12/01, 66 FR 52055 ......
(c)(164)(i)(B)(8).
CO–266
Allegheny ..........
9/2/98
10/12/01, 66 FR 52050 ......
(c)(165)(i)(B)(1).
CO–254
CO–218
Allegheny ..........
Allegheny ..........
12/19/96
12/19/96
10/12/01, 66 FR 52050 ......
10/12/01, 66 FR 52050 ......
CO–219
Allegheny ..........
2/21/96
10/12/01, 66 FR 52050 ......
CO–209
CO–227
EO–216
CO–257
Allegheny
Allegheny
Allegheny
Allegheny
......
......
......
......
(c)(165)(i)(B)(2).
(c)(165)(i)(B)(3)
[NOX RACT].
(c)(165)(i)(B)(4)
[VOC RACT].
(c)(165)(i)(B)(5).
(c)(166)(i)(B)(1).
(c)(166)(i)(B)(2).
(c)(166)(i)(B)(3).
Neville Chemical Company ..........
Anchor Glass Container Corp.—
Plant 5.
Anchor Hocking Specialty Glass
Co.—Phoenix Glass Plant.
Corning
Consumer
Products
Co.—Charleroi Plant.
General Electric Company ...........
Glenshaw Glass Company, Inc ...
Guardian Industries Corp .............
Allegheny County Sanitary Authority.
Browning-Ferris Industries ...........
Chambers Development Company—Monroeville
Borough
Landfill.
Kelly Run Sanitation, Forward
Township Landfill.
Stroehmann
Bakeries—Montgomery County (Norristown).
Schlosser Steel, Inc .....................
Perkasie
Industries
Corp.—
Perkasie.
Quaker Chemical Corporation—
Conshohocken.
Worthington Steel Company ........
Transcontinental Gas Pipeline
Corp.—Sta. 200, Frazer.
Rohm and Haas Company, Bucks
County Plant.
SEPTA—Berridge/Courtland
Maintenance Shop.
Southwest Water Pollution Control Plant/Biosolids Recycling
Center.
CO–230
(PA)26–000–119
VerDate Nov<24>2008
01:40 Mar 25, 2009
10/12/01,
10/16/01,
10/16/01,
10/16/01,
Allegheny ..........
Fayette .............
3/8/96
12/30/96
3/8/96
1/14/97
11/1/99
12/13/96
12/20/96
10/16/01, 66 FR 52506 ......
10/16/01, 66 FR 52527 ......
(c)(166)(i)(B)(4).
(c)(167)(i)(B)(1).
(OP)04–000–084
Beaver ..............
10/13/95
10/16/01, 66 FR 52527 ......
(c)(167)(i)(B)(2).
(PA)63–000–110
Washington ......
1/4/96
10/16/01, 66 FR 52527 ......
(c)(167)(i)(B)(3).
CO–251
CO–270
CO–242
CO–222
Allegheny
Allegheny
Allegheny
Allegheny
..........
..........
..........
..........
12/19/96
3/10/00
8/27/96
5/14/96
10/16/01,
10/16/01,
10/16/01,
10/16/01,
......
......
......
......
(c)(167)(i)(B)(4).
(c)(167)(i)(B)(5).
(c)(167)(i)(B)(6).
(c)(167)(i)(B)(7).
CO–231A
CO–253
Allegheny ..........
Allegheny ..........
4/28/97
12/30/96
10/16/01, 66 FR 52527 ......
10/16/01, 66 FR 52527 ......
(c)(167)(i)(B)(8).
(c)(167)(i)(B)(9).
CO–236
Allegheny ..........
1/23/97
10/16/01, 66 FR 52527 ......
(c)(167)(i)(B)(10).
PA–46–0003
Montgomery ......
5/4/95
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(1).
OP–46–0051
OP–09–0011
Montgomery ......
Bucks ................
2/1/96
8/14/96
10/31/01, 66 FR 54942 ......
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(2).
(c)(169)(i)(B)(3).
OP–46–0071
Montgomery ......
9/26/96
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(4).
OP–15–0016
PA–15–0017
Chester .............
Chester .............
7/23/96
6/5/95
10/31/01, 66 FR 54942 ......
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(5).
(c)(169)(i)(B)(6).
OP–09–0015
Bucks ................
4/20/99
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(7).
PA–51–4172
Philadelphia ......
7/27/99
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(8).
PA–51–9515
Philadelphia ......
7/27/99
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(9).
Jkt 217001
PO 00000
Frm 00032
Fmt 4701
..........
..........
..........
..........
Sfmt 4700
E:\FR\FM\25MRR2.SGM
66
66
66
66
66
66
66
66
FR
FR
FR
FR
FR
FR
FR
FR
52050
52506
52506
52506
52527
52527
52527
52527
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13045
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
Rohm and Haas Company—
Philadelphia Plant.
Sunoco Inc. (R&M)—Philadelphia
PWALKER on PROD1PC71 with RULES2
SBF Communications (owned by
Avant Garde Ent.).
Smith-Edwards-Dunlap Company
Tasty Baking Co ..........................
Armstrong
World
Industries,
Inc.—Beaver Falls Plant.
Bacharach, Inc .............................
Bakerstown Container Corporation.
Chestnut Ridge Foam, Inc.—Latrobe.
Flexsys
America
LP,
Monongahela Plant.
Haskell of Pittsburgh, Inc .............
Three Rivers Aluminum Company
(TRACO).
Tuscarora Plastics, Inc ................
Witco Corporation ........................
GenCorp (Plastic Films Division)—Jeannette Plant.
CENTRIA—Ambridge Coil Coating Operations Plant.
J & L Structural, Inc.—Aliquippa ..
Universal Stainless & Alloy Products, Inc.
Shenango, Inc ..............................
LTV Steel Company .....................
U.S. Steel (USX Corporation.)—
Clairton Works.
USX Corporation—Edgar Thomson Works.
USX, Inc.—Irvin Works ................
Wheeling-Pittsburgh Steel Corporation—Allenport Plant.
Koppers—Monessen Coke Plant
J & L Specialty Steel, Inc.—Midland Facility.
Washington Steel Corp.—Washington Plant.
Equitrans, Inc.—Hartson ..............
Witco Corp.—Petrolia Facility ......
Ranbar Electrical Materials Inc.
(formerly Westinghouse Electric
Co. EMD)—Manor.
Nova Chemicals, Inc. (formerly
Arco Chemical Co.—Beaver
Valley).
BASF Corporation—Monaca Site
Cardone Industries—Rising Sun
Ave.
Cardone Industries—Chew St .....
U.S. Navy, Naval Surface Warfare Center—Carderock Division.
Wheelabrator Falls, Inc ................
US Steel Group/USX Corporation—Fairless Works.
Brown Printing Company .............
Sun Chemical—General Printing
Ink Division.
Sunoco Chemicals, Frankford
Plant.
Armco, Inc. Butler Operations
Main Plant.
VerDate Nov<24>2008
01:40 Mar 25, 2009
State
effective
date
County
EPA approval date
Additional
explanation/
§ 52.2063 citation
PA–51–1531
Philadelphia ......
7/27/99
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(10).
PA(51–)1501
PA(51–)1517
PA(51–)2197
Philadelphia ......
8/1/00
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(11).
Philadelphia ......
7/21/00
10/31/01, 66 FR 54942 ......
(c)(169)(i)(B)(12).
PA–(51–)2255
PLID (51–) 2054
(OP)04–000–108
Philadelphia ......
Philadelphia ......
Beaver ..............
7/14/00
4/9/95
5/29/96
10/31/01, 66 FR 54942 ......
10/31/01, 66 FR 54942 ......
10/17/01, 66 FR 52695 ......
(c)(169)(i)(B)(13).
(c)(169)(i)(B)(14).
(c)(170)(i)(B)(1).
CO–263
CO–221
Allegheny ..........
Allegheny ..........
10/10/97
5/14/96
10/17/01, 66 FR 52695 ......
10/17/01, 66 FR 52695 ......
(c)(170)(i)(B)(2).
(c)(170)(i)(B)(3).
(OP)65–000–181
Westmoreland ..
12/29/95
10/17/01, 66 FR 52695 ......
(c)(170)(i)(B)(4).
(OP)63–000–015
Washington ......
3/23/01
10/17/01, 66 FR 52695 ......
(c)(170)(i)(B)(5).
CO–224
OP–10–267
Allegheny ..........
Butler ................
12/19/96
3/1/01
10/17/01, 66 FR 52695 ......
10/17/01, 66 FR 52695 ......
(c)(170)(i)(B)(6).
(c)(170)(i)(B)(7).
(OP)04–000–497
CO–210
(OP)65–000–207
Beaver ..............
Allegheny ..........
Westmoreland ..
4/3/96
5/14/96
1/4/96
10/17/01, 66 FR 52695 ......
10/17/01, 66 FR 52695 ......
10/15/01, 66 FR 52322 ......
(c)(170)(i)(B)(8).
(c)(170)(i)(B)(9).
(c)(171)(i)(B).
(OP)04–000–043
Beaver ..............
5/17/99
10/15/01, 66 FR 52322 ......
(c)(171)(i)(D).
OP–04–000–467
CO–241
Beaver ..............
Allegheny ..........
6/23/95
12/19/96
10/16/01, 66 FR 52511 ......
10/16/01, 66 FR 52511 ......
(c)(172)(i)(B)(1).
(c)(172)(i)(B)(2).
CO–233
CO–259
CO–234
Allegheny ..........
Allegheny ..........
Allegheny ..........
12/30/96
12/30/96
12/30/96
10/16/01, 66 FR 52511 ......
10/16/01, 66 FR 52511 ......
10/16/01, 66 FR 52511 ......
(c)(172)(i)(B)(3).
(c)(172)(i)(B)(4).
(c)(172)(i)(B)(5).
CO–235
Allegheny ..........
12/30/96
10/16/01, 66 FR 52511 ......
(c)(172)(i)(B)(6).
CO–258
(OP)63–000–066
Allegheny ..........
Washington ......
12/30/96
2/8/99
10/16/01, 66 FR 52511 ......
10/16/01, 66 FR 52511 ......
(c)(172)(i)(B)(7).
(c)(172)(i)(B)(8).
(OP)65–000–853
(OP)04–000–013
Westmoreland ..
Beaver ..............
3/20/98
3/23/01
10/16/01, 66 FR 52511 ......
10/16/01, 66 FR 52511 ......
(c)(172)(i)(B)(9).
(c)(172)(i)(B)(10).
(OP)63–000–023
Washington ......
9/12/96
10/16/01, 66 FR 52511 ......
(c)(172)(i)(B)(11).
(OP)63–000–642
PA–10–037
(OP)65–000–042
Washington ......
Butler ................
Westmoreland ..
7/10/95
6/27/95
2/22/99
10/17/01, 66 FR 52705 ......
10/17/01, 66 FR 52705 ......
10/17/01, 66 FR 52705 ......
(c)(173)(i)(B)(1).
(c)(173)(i)(B)(2).
(c)(173)(i)(B)(3).
(OP)04–000–033
Beaver ..............
4/16/99
1/24/01
10/17/01, 66 FR 52705 ......
(c)(173)(i)(B)(4).
(OP)04–000–306
PA(51–) PLID 3887
Beaver ..............
Philadelphia ......
3/23/01
5/29/95
10/17/01, 66 FR 52705 ......
10/30/01, 66 FR 54710 ......
(c)(173)(i)(B)(5).
(c)(174)(i)(B)(1).
PA(51–) PLID 2237
PA(51–)9724
Philadelphia ......
Philadelphia ......
5/29/95
12/27/97
10/30/01, 66 FR 54710 ......
10/30/01, 66 FR 54710 ......
(c)(174)(i)(B)(2).
(c)(174)(i)(B)(3).
OP–09–0013
Bucks ................
10/30/01, 66 FR 54710 ......
(c)(174)(i)(B)(4).
OP–09–0006
Bucks ................
1/11/96
5/17/96
4/8/99
10/30/01, 66 FR 54710 ......
(c)(174)(i)(B)(5).
OP–46–0018A
PA(51–) 2052
Montgomery ......
Philadelphia ......
5/17/00
7/14/00
10/30/01, 66 FR 54710 ......
10/30/01, 66 FR 54710 ......
(c)(174)(i)(B)(6).
(c)(174)(i)(B)(7).
PA(51–) 1551
Philadelphia ......
7/27/99
10/30/01, 66 FR 54710 ......
(c)(174)(i)(B)(8).
PA–10–001M
Butler ................
2/23/96
10/15/01, 66 FR 52338 ......
(c)(175)(i)(B).
Jkt 217001
PO 00000
Frm 00033
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
13046
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
PWALKER on PROD1PC71 with RULES2
Armco, Inc. Butler Operations
Stainless Plant.
Pennsylvania Power Co.—Bruce
Mansfield Plant.
West Penn Power Co.—Mitchell
Station.
Carnegie Natural Gas Company—Fisher Station.
Apollo Gas Company—Shoemaker Station.
Texas
Eastern
Transmission
Corp.—Delmont Station.
The Peoples Natural Gas Co.—
Valley Station.
The Peoples Natural Gas Co.—
Girty Compressor Station.
AES Beaver Valley Partners—
Monaca Plant.
Penreco—Karns City ...................
Ashland Petroleum Company ......
Bellefield Boiler Plant—Pittsburgh
Gulf Oil, L.P .................................
PA Dept. of Corrections ...............
Pittsburgh Thermal Limited Partnership.
BP Exploration & Oil, Inc.—
Greensburg Terminal.
Pittsburgh
Allegheny
County
Thermal, Ltd.
Aristech Chemical Corporation ....
Heinz U.S.A.—Pittsburgh .............
Heinz U.S.A.—Pittsburgh .............
Koppers Industries, Inc. (Aristech
Chem. Corp).
Nabisco Biscuit Co .......................
Pressure Chemical Co .................
General Carbide Corp ..................
Fansteel Hydro Carbide ...............
Carbidie Corporation ....................
Dyno Nobel Inc—Donora .............
Newcomer Products, Inc ..............
PECO
Energy
Company—
Cromby Generating Station.
Waste Resource Energy, Inc.
(Operator); Shawmut Bank,
Conn. National Assoc. (Owner);
Delaware County Resource Recovery Facility.
G-Seven, Ltd ................................
Leonard Kunkin Associates .........
Kimberly-Clark Corporation ..........
PA–10–001S
Butler ................
2/23/96
10/15/01, 66 FR 52338 ......
(c)(175)(i)(C).
(PA)04–000–235
Beaver ..............
12/29/94
10/15/01, 66 FR 52333 ......
(c)(176)(i)(B)(1).
(PA)63–000–016
Washington ......
6/12/95
10/15/01, 66 FR 52333 ......
(c)(176)(i)(B)(2).
(OP)03–000–182
Armstrong .........
12/2/98
10/15/01, 66 FR 52333 ......
(c)(176)(i)(B)(3).
(OP)03–000–183
Armstrong .........
9/12/96
10/15/01, 66 FR 52333 ......
(c)(176)(i)(B)(4).
(OP)65–000–839
Westmoreland ..
1/9/97
10/15/01, 66 FR 52333 ......
(c)(176)(i)(B)(5).
(OP)03–000–125
Armstrong .........
10/31/94
10/15/01, 66 FR 52333 ......
(c)(176)(i)(B)(6).
(PA)03–000–076
Armstrong .........
10/27/95
10/15/01, 66 FR 52333 ......
(c)(176)(i)(B)(7).
(OP)04–000–446
Beaver ..............
3/23/01
10/15/01, 66 FR 52333 ......
(c)(176)(i)(B)(8).
OP–10–0027
CO–256
EO–248
CO–250
EO–244
CO–220
Butler ................
Allegheny ..........
Allegheny ..........
Allegheny ..........
Allegheny ..........
Allegheny ..........
5/31/95
12/19/96
12/19/96
12/19/96
1/23/97
3/4/96
10/12/01,
10/12/01,
10/12/01,
10/12/01,
10/12/01,
10/12/01,
......
......
......
......
......
......
(c)(177)(i)(B)(1).
(c)(177)(i)(B)(2).
(c)(177)(i)(B)(3).
(c)(177)(i)(B)(4).
(c)(177)(i)(B)(5).
(c)(177)(i)(B)(6).
(OP)65–000–378
Westmoreland ..
3/23/01
10/12/01, 66 FR 52044 ......
(c)(177)(i)(B)(7).
CO–265
Allegheny ..........
11/9/98
10/12/01, 66 FR 52044 ......
(c)(177)(i)(B)(8).
CO–232
EO–211
CO–247
CO–223
Allegheny
Allegheny
Allegheny
Allegheny
..........
..........
..........
..........
12/30/96
3/8/96
10/24/96
8/27/96
10/17/01,
10/17/01,
10/17/01,
10/17/01,
66
66
66
66
FR
FR
FR
FR
52700
52700
52700
52700
......
......
......
......
(c)(178)(i)(B)(1).
(c)(178)(i)(B)(2).
(c)(178)(i)(B)(2).
(c)(178)(i)(B)(3).
CO–246
CO–261
(OP)65–000–622
(OP)65–000–860
(OP)65–000–720
(OP)63–000–070
(OP)65–000–851
OP–15–0019
Allegheny ..........
Allegheny ..........
Westmoreland ..
Westmoreland ..
Westmoreland ..
Washington ......
Westmoreland ..
Chester .............
12/19/96
6/11/97
12/29/95
12/12/97
7/31/98
3/31/99
8/7/97
4/28/95
10/17/01,
10/17/01,
10/17/01,
10/17/01,
10/17/01,
10/17/01,
10/17/01,
10/30/01,
66
66
66
66
66
66
66
66
FR
FR
FR
FR
FR
FR
FR
FR
52700
52700
52700
52700
52700
52700
52700
54699
......
......
......
......
......
......
......
......
(c)(178)(i)(B)(4).
(c)(178)(i)(B)(5).
(c)(178)(i)(B)(6).
(c)(178)(i)(B)(7).
(c)(178)(i)(B)(8).
(c)(178)(i)(B)(9).
(c)(178)(i)(B)(10).
(c)(179)(i)(B)(1).
OP–23–0004
Delaware ..........
11/16/95
10/30/01, 66 FR 54699 ......
(c)(179)(i)(B)(2).
OP–46–0078
OP–09–0073
OP–23–0014A
Montgomery ......
Bucks ................
Delaware ..........
10/30/01, 66 FR 54699 ......
10/30/01, 66 FR 54699 ......
10/30/01, 66 FR 54699 ......
(c)(179)(i)(B)(3).
(c)(179)(i)(B)(4).
(c)(179)(i)(B)(5).
Sunoco, Inc. (R&M); Marcus
Hook Plant.
Waste Management Disposal
Services of Pennsylvania, Inc.
(GROWS Landfill).
Koppel
Steel
Corporation—
Ambridge Plant.
General Motors Corporation ........
Oakmont Steel, Inc ......................
The Peoples Natural Gas Co ......
U.S. Bureau of Mines ..................
Waste Management Disposal
Services
of
Pennsylvania
(Pottstown Landfill).
FPL Energy MH50, LP (Sunoco,
Inc. (R&M)).
CP–23–0001
Delaware ..........
10/30/01, 66 FR 54699 ......
(c)(179)(i)(B)(6).
OP–09–0007
Bucks ................
4/20/99
6/25/01
6/24/98
8/1/01
6/8/95
8/2/01
12/19/97
7/17/01
10/30/01, 66 FR 54699 ......
(c)(179)(i)(B)(7).
OP–04–000–227
Beaver ..............
10/12/00
10/15/01, 66 FR 52317 ......
(c)(180)(i)(B).
CO–243
CO–226
CO–240
EO–215
OP–46–0033
Allegheny ..........
Allegheny ..........
Allegheny ..........
Allegheny ..........
Montgomery ......
8/27/96
5/14/96
8/27/96
3/8/96
4/20/99
10/15/01,
10/15/01,
10/15/01,
10/15/01,
10/30/01,
......
......
......
......
......
(c)(181)(i)(B)(1).
(c)(181)(i)(B)(2).
(c)(181)(i)(B)(3).
(c)(181)(i)(B)(4).
(c)(182)(i)(B)(1).
PA–23–0084
Delaware ..........
7/26/99
10/30/01, 66 FR 54704 ......
(c)(182)(i)(B)(2).
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00034
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
66
66
66
66
66
66
66
66
66
66
66
FR
FR
FR
FR
FR
FR
FR
FR
FR
FR
FR
52044
52044
52044
52044
52044
52044
52327
52327
52327
52327
54704
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13047
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
PWALKER on PROD1PC71 with RULES2
Exelon Generation Company—
(PECO)—Richmond Generating
Station.
Jefferson Smurfit Corp./Container
Corp. of America.
Maritank Philadelphia, Inc ............
Moyer Packing Company .............
Tullytown Resource Recovery Facility (Waste Management of
Pa., Inc.).
SPS Technologies, Inc ................
PECO Energy Company ..............
Philadelphia Gas Works—Richmond Plant.
Exelon Generation Company—
Delaware Generating Station.
Exelon Generation Company—
Schuylkill Generating Station.
International Business Systems,
Inc.
Bethlehem Lukens Plate ..............
Montenay Montgomery Limited
Partnership.
Northeast Foods, Inc. (Bake Rite
Rolls).
Aldan Rubber Company ..............
Braceland Brothers, Inc ...............
Graphic Arts, Incorporated ...........
O’Brien (Philadelphia) Cogeneration, Inc.—Northeast Water Pollution Control Plant.
O’Brien (Philadelphia) Cogeneration, Inc.—Southwest Water
Pollution Control Plant.
Pearl Pressman Liberty ...............
Arbill Industries, Inc .....................
McWhorter Technologies, Inc ......
NortheastWater Pollution Control
Plant.
Newman and Company ...............
Allegheny Ludlum Steel Corporation.
INDSPEC Chemical Corporation
Stoney
Creek
Technologies,
L.L.C.
Superpac, Inc ...............................
Transit America, Inc .....................
American Bank Note Company ...
PA–51–4903
Philadelphia ......
7/11/01
10/30/01, 66 FR 54704 ......
(c)(182)(i)(B)(3).
PLID (PA–51–) 1566
Philadelphia ......
4/10/95
10/31/01, 66 FR 54947 ......
(c)(184)(i)(B)(1).
PLID (PA–51–) 5013
OP–46–0001
OP–09–0024
Philadelphia ......
Montgomery ......
Bucks ................
12/28/95
3/15/96
7/14/97
10/31/01, 66 FR 54947 ......
10/31/01, 66 FR 54947 ......
10/31/01, 66 FR 54947 ......
(c)(184)(i)(B)(2).
(c)(184)(i)(B)(3).
(c)(184)(i)(B)(4).
OP–46–0032
OP–09–0077
PA–51–4922
Montgomery ......
Bucks ................
Philadelphia ......
10/30/97
12/19/97
7/27/99
10/31/01, 66 FR 54947 ......
10/31/01, 66 FR 54947 ......
10/31/01, 66 FR 54947 ......
(c)(184)(i)(B)(5).
(c)(184)(i)(B)(6).
(c)(184)(i)(B)(7).
PA–51–4901
Philadelphia ......
7/11/01
10/31/01, 66 FR 54947 ......
(c)(184)(i)(B)(8).
PA–51–4904
Philadelphia ......
7/11/01
10/31/01, 66 FR 54947 ......
(c)(184)(i)(B)(9).
OP–46–0049
Montgomery ......
10/29/98
10/30/01, 66 FR 54691 ......
(c)(185)(i)(B)(1).
OP–46–0011
OP–46–0010A
Montgomery ......
Montgomery ......
10/30/01, 66 FR 54691 ......
10/30/01, 66 FR 54691 ......
(c)(185)(i)(B)(2).
(c)(185)(i)(B)(3).
OP–09–0014
Bucks ................
12/11/98
4/20/99
6/20/00
4/9/99
10/30/01, 66 FR 54691 ......
(c)(185)(i)(B)(4).
PA–(51–)1561
PA–(51–)3679
PA–(51–)2260
PA–(51–)1533
Philadelphia
Philadelphia
Philadelphia
Philadelphia
......
......
......
......
7/21/00
7/14/00
7/14/00
7/21/00
10/30/01,
10/30/01,
10/30/01,
10/30/01,
......
......
......
......
(c)(185)(i)(B)(5).
(c)(185)(i)(B)(6).
(c)(185)(i)(B)(7).
(c)(185)(i)(B)(8).
PA–(51–)1534
Philadelphia ......
7/21/00
10/30/01, 66 FR 54691 ......
(c)(185)(i)(B)(9).
PA–(51–)7721
PA–51–3811
PA–51–3542
PA–51–9513
Philadelphia
Philadelphia
Philadelphia
Philadelphia
......
......
......
......
7/24/00
7/27/99
7/27/99
7/27/99
10/30/01,
10/30/01,
10/30/01,
10/30/01,
FR 54691 ......
FR 54691 ......
FR 54691 ......
FR54691 .......
(c)(185)(i)(B)(10).
(c)(185)(i)(B)(11).
(c)(185)(i)(B)(12).
(c)(185)(i)(B)(13).
PLID (51–) 3489
(OP–)65–000–137
Philadelphia ......
Westmoreland ..
6/11/97
5/17/99
10/30/01, 66 FR 54691 ......
10/19/01, 66 FR 53090 ......
(c)(185)(i)(B)(14).
(c)(186)(i)(B)(1).
PA10–021
PA–23–0002
Butler ................
Delaware ..........
10/19/98
2/24/99
10/19/01, 66 FR 53090 ......
11/5/01, 66 FR 55880 ........
(c)(186)(i)(B)(2).
(c)(187)(i)(B)(1).
OP–09–0003
PLID (51–) 1563
OP–46–0075
Bucks ................
Philadelphia ......
Montgomery ......
11/5/01, 66 FR 55880 ........
11/5/01, 66 FR 55880 ........
11/5/01, 66 FR 55880 ........
(c)(187)(i)(B)(2).
(c)(187)(i)(B)(3).
(c)(187)(i)(B)(4).
Atlas
Roofing
Corporation—
Quakertown.
Beckett Corporation .....................
Klearfold, Inc ................................
National Label Company .............
Bethlehem Steel Corporation .......
Hershey Chocolate USA ..............
Pennsylvania Power Company
New Castle Plant.
Lafarge Corporation .....................
The Peoples Natural Gas Company.
Horsehead Resource Development Company, Inc.
Williams Generation Company—
Hazelton.
Pennsylvania Power and Light
Company, Holtwood Steam
Electric Station.
OP–09–0039
Bucks ................
3/25/99
6/11/97
5/19/97
8/10/98
3/10/99
11/5/01, 66 FR 55880 ........
(c)(187)(i)(B)(5).
OP–15–0040
OP–09–0012
OP–46–0040
OP–22–02012
OP–22–2004A
OP–37–0023
Chester .............
Bucks ................
Montgomery ......
Dauphin ............
Dauphin ............
Lawrence ..........
7/8/97
4/15/99
7/28/97
4/9/99
1/24/00
4/8/99
11/5/01,
11/5/01,
11/5/01,
5/23/02,
6/26/02,
6/26/02,
........
........
........
........
........
........
(c)(187)(i)(B)(6).
(c)(187)(i)(B)(7).
(c)(187)(i)(B)(8).
(c)(191).
(c)(194)(i)(B)(1).
(c)(194)(i)(B)(2).
OP–39–0011B
(OP–)11–000–356
Lehigh ...............
Cambria ............
5/19/97
11/23/94
4/1/03, 68 FR 15661 ..........
4/1/03, 68 FR 15661 ..........
(c)(196)(i)(B)(1).
(c)(196)(i)(B)(2).
OP–13–0001
Carbon ..............
5/16/95
4/1/03, 68 FR 15661 ..........
(c)(196)(i)(B)(3).
OP–40–0031A
Luzerne ............
3/10/00
4/1/03, 68 FR 15661 ..........
(c)(196)(i)(B)(4).
PA–36–2016
Lancaster ..........
5/25/95
4/1/03, 68 FR 15661 ..........
(c)(196)(i)(B)(5).
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00035
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
66
66
66
66
66
66
66
66
66
66
66
67
67
67
FR
FR
FR
FR
FR
FR
FR
FR
FR
FR
54691
54691
54691
54691
55880
55880
55880
36108
43002
43002
25MRR2
13048
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
PWALKER on PROD1PC71 with RULES2
Name of source
Permit No.
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
General Electric Transportation
Systems.
Bethlehem Structural Products
Corporation.
International Paper Company,
Erie Mill.
National Fuel Gas Supply—Heath
Compressor Station.
PPG Industries, Inc ......................
Dominion Trans., Inc.—Finnefrock
Station.
Textron Lycoming—Oliver Street
Plant.
Lafayette College, Easton Campus.
Keystone Carbon Company .........
Mack Trucks, Inc ..........................
Owens-Brockway Glass Container, Inc.
Resilite Sport Products, Inc .........
Westfield Tanning Company ........
Tarkett, Incorporated ....................
Hacros Pigments, Inc ...................
GPU Generation Corp., Homer
City Station.
GPU Generation Corp., Seward
Station.
Ebensburg
Power
Company,
Ebensburg Cogeneration Plant.
Sithe Pennsylvania Holdings,
LLC, Warren Station.
Pennsylvania Power & Light
Company, Sunbury SES.
Lakeview Landfill ..........................
National Fuel Gas Supply Corp.—
Roystone Compressor Station.
Crompton Corporation, Fairview
Township.
Andritz, Inc ...................................
Brodart Company .........................
Erie Sewer Authority ....................
Hercules Cement Company .........
Tennessee Gas Pipeline Company, Station 321.
Tennessee Gas Pipeline Company, Station 219.
Information Display Technology,
Inc.
Bedford Materials Co., Inc ...........
Bollman Hat Company .................
Armco Inc .....................................
Specialty Tires of America, Inc ....
Truck Accessories Group East ....
Jeraco Enterprises, Inc ................
Insulation Corporation of America
Pope & Talbot, Inc .......................
Universal Rundle Corporation ......
Clark Filter ....................................
The Pennsylvania State University—University Park.
Tennessee Gas Pipeline Company—Charleston Township.
Tennessee Gas Pipeline Company—Wyalusing Township.
Masland Industries .......................
ESSROC Cement Corp ...............
OP–25–025A
Erie ...................
8/26/02
4/7/03, 68 FR 16724 ..........
(c)(198)(i)(B).
OP–48–0013
Northampton .....
10/24/96
5/2/03, 68 FR 23404 ..........
(c)(200)(i)(B)(1).
PA–25–028
Erie ...................
12/21/94
5/2/03, 68 FR 23404 ..........
(c)(200)(i)(B)(2).
PA–33–144A
Jefferson ...........
10/5/98
5/2/03, 68 FR 23404 ..........
(c)(200)(i)(B)(3).
OP–20–145
Title V–18–00005
Crawford ...........
Clinton ..............
5/31/95
2/16/00
3/24/03, 68 FR14154 .........
5/7/03, 68 FR 24365 ..........
(c)(201)(i)(B).
(c)(202)(i)(B)(1).
Title V–41–00005
Lycoming ..........
1/12/01
5/7/03, 68 FR 24365 ..........
(c)(202)(i)(B)(2).
OP–48–0034
Northampton .....
8/18/97
5/20/03, 68 FR 27471 ........
(c)(205)(i)(B).
OP–24–016
OP–39–0004
OP–33–033
Elk .....................
Northampton .....
Jefferson ...........
5/15/95
5/31/95
3/27/95
10/17/03, 68 FR 59741 ......
10/17/03, 68 FR 59741 ......
10/17/03, 68 FR 59741 ......
(c)(207)(i)(B)(1).
(c)(207)(i)(B)(1).
(c)(207)(i)(B)(1).
OP–49–0003
OP–59–0008
OP–39–0002
OP–48–0018
(OP–)32–000–055
Northumberland
Tioga ................
Lehigh ...............
Northampton .....
Indiana ..............
12/3/96
11/27/96
5/31/95
7/31/96
10/29/98
10/17/03, 68 FR 59741 ......
10/17/03, 68 FR 59741 ......
8/6/03, 68 FR 46487 ..........
8/6/03, 68 FR 46487 ..........
10/15/03, 68 FR 59321 ......
(c)(207)(i)(B)(1).
(c)(207)(i)(B)(1).
(c)(208)(i)(B)(1).
(c)(208)(i)(B)(2).
(c)(212)(i)(B)(1).
(OP–)32–000–040
Indiana ..............
4/30/98
10/15/03, 68 FR 59321 ......
(c)(212)(i)(B)(2).
(OP–)11–000–318
Cambria ............
3/28/01
10/15/03, 68 FR 59321 ......
(c)(212)(i)(B)(3).
OP–62–012B
Warren ..............
1/20/00
10/15/03, 68 FR 59321 ......
(c)(212)(i)(B)(4).
OP–55–0001A
Snyder ..............
7/7/97
10/15/03, 68 FR 59321 ......
(c)(212)(i)(B)(5).
OP–25–920
OP–62–141F
Erie ...................
Warren ..............
5/29/97
4/1/03
10/15/03, 68 FR 59321 ......
10/27/04, 69 FR 62583 ......
(c)(212)(i)(B)(6).
(c)(213)(i)(B)(1).
OP–10–037
Butler ................
6/4/03
5/25/04, 69 FR 29444 ........
(c)(213)(i)(B)(2).
41–00010C
18–0007A
OP–25–179
OP–48–0005A
OP–58–00001A
Lycoming ..........
Clinton ..............
Erie ...................
Northampton .....
Susquehanna ...
4/30/03
4/8/03
6/5/03
4/16/99
4/16/98
10/15/03,
10/15/03,
10/15/03,
11/24/03,
10/27/04,
......
......
......
......
......
(c)(214)(i)(B)(1).
(c)(214)(i)(B)(2).
(c)(214)(i)(B)(3).
(c)(217)(i)(B).
(c)(218)(i)(B)(1).
OP–43–0272
Mercer ..............
4/7/99
10/27/04, 69 FR 62585 ......
(c)(218)(i)(B)(2).
32–000–085
Indiana ..............
1/11/96
03/29/05, 70 FR 15774 ......
52.2020(d)(1)(h).
05–02005
36–2031
OP–43–040
32–000–065
OP–49–0005
OP–49–0014
39–0012
40–0019
OP–37–059
36–02040
OP–14–0006
Bedford .............
Lancaster ..........
Mercer ..............
Indiana ..............
Northumberland
Northumberland
Lehigh ...............
Luzerne ............
Lawrence ..........
Lancaster ..........
Centre ...............
4/15/99
7/3/95
9/30/99
1/6/00
3/26/99
4/6/97
10/17/95
5/31/96
5/31/95
2/4/00
12/30/98
03/29/05, 70 FR 15774 ......
03/29/05, 70 FR 15774 ......
03/29/05, 70 FR 15774 ......
03/29/05, 70 FR 15774 ......
03/29/05, 70 FR 15774 ......
03/29/05, 70 FR 15774 ......
03/29/05, 70 FR 15774 ......
03/29/05, 70 FR 15774 ......
03/29/05, 70 FR 15774 ......
03/29/05, 70 FR 15774 ......
3/30/05, 70 FR 16118 ........
52.2020(d)(1)(h).
52.2020(d)(1)(h).
52.2020(d)(1)(h).
52.2020(d)(1)(h).
52.2020(d)(1)(h).
52.2020(d)(1)(h).
52.2020(d)(1)(h).
52.2020(d)(1)(h).
52.2020(d)(1)(h).
52.2020(d)(1)(h).
52.2020(d)(1)(c).
OP–59–0001
Tioga ................
5/31/95
3/30/05, 70 FR 16118 ........
52.2020(d)(1)(c).
OP–08–0002
Bradford ............
5/31/95
3/30/05, 70 FR 16118 ........
52.2020(d)(1)(c).
21–2001
OP–37–003
Cumberland ......
Lawrence ..........
3/30/05, 70 FR 16118 ........
3/30/05, 70 FR 16118 ........
52.2020(d)(1)(c).
52.2020(d)(1)(c).
The Magee Carpet Company ......
OP–19–0001
Columbia ..........
5/31/95
7/27/95
3/31/99
1/22/97
3/30/05, 70 FR 16118 ........
52.2020(d)(1)(c).
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00036
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
68
68
68
68
69
FR
FR
FR
FR
FR
59318
59318
59318
65846
62585
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13049
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
EPA approval date
Additional
explanation/
§ 52.2063 citation
OP–27–015
Forest ...............
7/27/00
3/30/05, 70 FR 16118 ........
52.2020(d)(1)(c).
40–0002
40–0002A
67–2012
Luzerne ............
5/31/95
3/30/05, 70 FR 16118 ........
52.2020(d)(1)(c).
York ..................
5/5/95
3/30/05, 70 FR 16118 ........
52.2020(d)(1)(c).
44–2001
Mifflin ................
5/31/95
3/30/05, 70 FR 16118 ........
52.2020(d)(1)(c).
35–0004
22–2011
Lackawanna .....
Dauphin ............
5/31/96
6/7/95
3/30/05, 70 FR 16124 ........
3/30/05, 70 FR 16124 ........
52.2020 (d)(1)(d).
52.2020 (d)(1)(d).
OP–37–313
53–0009A
53–0009
28–02002
67–2032
OP–43–196
67–2002
39–0031
67–2014
OP–19–0002
OP–41–0002
Lawrence ..........
Potter ................
1/31/01
8/5/96
3/30/05, 70 FR 16124 ........
3/30/05, 70 FR 16124 ........
52.2020 (d)(1)(d).
52.2020 (d)(1)(d).
Franklin .............
York ..................
Mercer ..............
York ..................
Lehigh ...............
York ..................
Columbia ..........
Lycoming ..........
2/3/00
4/9/97
5/16/01
9/3/96
6/12/98
7/3/95
6/6/97
9/25/97
3/31/05,
3/31/05,
3/31/05,
3/31/05,
3/31/05,
3/31/05,
3/31/05,
3/31/05,
70
70
70
70
70
70
70
70
FR
FR
FR
FR
FR
FR
FR
FR
16416
16416
16416
16416
16416
16416
16416
16416
........
........
........
........
........
........
........
........
52.2020(d)(1)(g).
52.2020(d)(1)(g).
52.2020(d)(1)(g).
52.2020(d)(1)(g).
52.2020(d)(1)(g).
52.2020(d)(1)(g).
52.2020(d)(1)(g).
52.2020(d)(1)(g).
39–0005
01–2007
OP–43–036
OP–10–266
Lehigh ...............
Adams ..............
Mercer ..............
Butler ................
70
70
70
70
FR
FR
FR
FR
16416
16416
16420
16420
........
........
........
........
52.2020(d)(1)(g).
52.2020(d)(1)(g).
52.2020(d)(1)(a).
52.2020(d)(1)(a).
30–000–063
Greene .............
5/26/95
5/24/95
3/31/99
10/15/99
2/18/00
5/17/99
3/31/05,
3/31/05,
3/31/05,
3/31/05,
Consolidation Coal Co.—Coal
Preparation Plant.
Urick Foundry ...............................
Keystone Sanitary Landfill, Inc ....
Grinnell Corporation .....................
Buck Company Inc .......................
Owens-Brockway Glass Container, Inc.
Alcoa Extrusion, Inc .....................
Pennsylvania Electric Company ..
National Gypsum Company .........
Stoney Creek Technologies, LLC
Northeastern Power Company ....
Texas Eastern Transmission Corporation.
The Miller Group ..........................
CNG Transmission Corporation ...
I.H.F.P., Inc ..................................
National Forge Company .............
United Refining Company ............
3/31/05, 70 FR 16420 ........
52.2020(d)(1)(a).
OP–25–053
35–0014
36–2019
36–2035
OP–16–010
Erie ...................
Lackawanna .....
Lancaster ..........
Lancaster ..........
Clarion ..............
3/31/05,
3/31/05,
3/31/05,
3/31/05,
3/31/05,
70
70
70
70
70
FR
FR
FR
FR
FR
16420
16420
16420
16420
16423
........
........
........
........
........
52.2020(d)(1)(a).
52.2020(d)(1)(a).
52.2020(d)(1)(a).
52.2020(d)(1)(a).
52.2020(d)(1)(f).
54–0022
32–000–059
OP–60–0003
OP–23–0002
54–0008
22–2010
Schuylkill ...........
Indiana ..............
Union ................
Delaware ..........
Schuylkill ...........
Dauphin ............
10/24/96
4/19/99
6/30/95
8/1/95
3/27/95
5/31/95
4/19/99
12/29/94
1/17/96
7/24/03
5/26/95
1/31/97
3/31/05,
3/31/05,
3/31/05,
3/31/05,
3/31/05,
3/31/05,
70
70
70
70
70
70
FR
FR
FR
FR
FR
FR
16423
16423
16423
16423
16423
16423
........
........
........
........
........
........
52.2020(d)(1)(f).
52.2020(d)(1)(f).
52.2020(d)(1)(f).
52.2020(d)(1)(f).
52.2020(d)(1)(f).
52.2020(d)(1)(f).
54–0024
32–000–129
OP–49–0010A
OP–62–032
OP–62–017
Schuykill ...........
Indiana ..............
Northumberland
Warren ..............
Warren ..............
70
70
70
70
70
FR
FR
FR
FR
FR
16423
16423
16423
16423
16423
........
........
........
........
........
52.2020(d)(1)(f).
52.2020(d)(1)(f).
52.2020(d)(1)(f).
52.2020(d)(1)(f).
52.2020(d)(1)(f).
OP–42–110
McKean ............
3/31/05, 70 FR 16423 ........
52.2020(d)(1)(f).
Westvaco Corporation .................
Naval Surface Warfare Center,
Caderock Division Ship Systems Engineering Station.
R.H. Sheppard Co., Inc ...............
Wheatland Tube Company ..........
Transcontinental Gas Pipeline
Corporation.
Transcontinental Gas Pipeline
Corporation.
Transcontinental Gas Pipeline
Corporation.
Molded Fiber Glass ......................
Erie Forge and Steel, Inc .............
OSRAM SYLVANIA Products, Inc
Owens-Brockway Glass Container.
07–2008
PA–04108
Blair ..................
Philadelphia ......
2/1/99
6/22/95
1/7/98
5/31/95
5/31/95
11/14/96
3/4/96
5/31/96
9/29/95
10/18/04
3/31/05,
3/31/05,
3/31/05,
3/31/05,
3/31/05,
Petrowax Refining ........................
PWALKER on PROD1PC71 with RULES2
Tennessee Gas Pipeline Company—Howe Township.
Transcontinental Gas Pipeline
Corporation—Buck Township.
Transcontinental Gas Pipe Line
Corporation—Peach
Bottom
Township.
Standard Steel Division of Freedom Forge Corp.
Pope and Talbot, Inc ...................
Pennsylvania Power and Light
Company.
Ellwood Group Inc .......................
National Fuel Gas Supply Corporation.
Department of the Army ..............
Harley-Davidson Motor Company
GE Transportation Systems .........
Stone Container Corporation .......
Stanley Storage Systems, Inc .....
York Group, Inc ............................
Strick Corporation ........................
Grumman Olson, Division of
Grumman Allied Industries.
Prior Coated Metals, Inc ..............
Schindler Elevator Corporation ....
Hodge Foundry ............................
Resolite, A United Dominion Co ..
3/31/05, 70 FR 16423 ........
4/29/05, 70 FR 22257 ........
52.2020(d)(1)(f).
52.2020(d)(1)(j).
67–2016
OP–43–182
OP–53–0006
York ..................
Mercer ..............
Potter ................
8/4/95
7/26/95
10/13/95
8/24/05, 70 FR 49496 ........
8/24/05, 70 FR 49496 ........
8/24/05, 70 FR 49496 ........
52.2020(d)(1)(i).
52.2020(d)(1)(i).
52.2020(d)(1)(i).
OP–19–0004
Columbia ..........
5/30/95
8/24/05, 70 FR 49496 ........
52.2020(d)(1)(i).
PA–41–0005A
Lycoming ..........
8/9/95
8/24/05, 70 FR 49496 ........
52.2020(d)(1)(i).
OP–25–035
OP–25–924
OP–59–0007
OP–33–002
Erie ...................
Erie ...................
Tioga ................
Jefferson ...........
7/30/99
2/10/00
1/22/98
11/23/98
11/1/05,
11/1/05,
11/1/05,
11/1/05,
52.2020(d)(1)(k).
52.2020(d)(1)(k).
52.2020(d)(1)(k).
52.2020(d)(1)(k).
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00037
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
70
70
70
70
FR
FR
FR
FR
65842
65842
65842
65842
25MRR2
........
........
........
........
13050
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
EPA approval date
Additional
explanation/
§ 52.2063 citation
32–000–230
Indiana ..............
9/25/95
11/1/05, 70 FR 65842 ........
52.2020(d)(1)(k).
67–02010A
11–000–288
OP–24–131
York ..................
Cambria ............
Elk ....................
52.2020(d)(1)(k).
52.2020(d)(1)(k).
52.2020(d)(1)(e).
OP–43–142
18–00006
Mercer ..............
Clinton ..............
11/1/05, 70 FR 65845 ........
11/1/05, 70 FR 65845 ........
52.2020(d)(1)(e).
52.2020(d)(1)(e).
Waste Management Disposal
Services
of
Pennsylvania
(Pottstown Landfill).
Waste Management Disposal
Services of PA, Inc.
Armstrong World Industries, Inc ..
Cogentrix of Pennsylvania Inc .....
OP–46–0033
Berks; Montgomery.
7/19/00
1/13/99
5/12/95
5/31/95
2/16/99
6/15/99
9/29/03
4/20/99
1/27/04
11/1/05, 70 FR 65842 ........
11/1/05, 70 FR 65842 ........
11/1/05, 70 FR 65845 ........
Salem Tube, Inc ...........................
Dominion Trans, Inc .....................
PWALKER on PROD1PC71 with RULES2
Texas Eastern Transmission Corporation.
SKF, USA, Incorporated ..............
Johnstown America Corporation ..
SGL Carbon Corporation .............
11/2/05, 70 FR 66261 ........
52.2020(d)(1)(b).
67–02047
York ..................
4/20/99
11/2/05, 70 FR 66261 ........
52.2020(d)(1)(b).
36–2001
OP–33–137, PA–33–
302–014, OP–33–
302–014, PA 33–
399–004, OP 33–
399–004
OP–61–0181
Lancaster ..........
Jefferson ...........
11/2/05, 70 FR 66261 ........
3/8/06, 71 FR 11514 ..........
52.2020(d)(1)(b).
52.2020(d)(1)(l).
Venango ...........
7/3/99
1/27/98
11/15/90
5/31/93
10/31/98
5/31/93
4/30/98
3/8/06, 71 FR 11514 ..........
52.2020(d)(1)(l).
OP–54–005
Schuylkill ...........
9/18/98
3/8/06, 71 FR 11514 ..........
52.2020(d)(1)(l).
OP–32–000–200
Indiana ..............
9/24/98
3/8/06, 71 FR 11514 ..........
52.2020(d)(1)(l).
OP–49–0011
OP–16–0127
OP–22–02015
OP–22–02005
OP–07–02028
OP–54–0011
OP–39–0009
OP–40–0016
OP–40–0017
OP–37–243
Northumberland
Clarion ..............
Dauphin ............
Dauphin ............
Blair ..................
Schuylkill ...........
Lehigh ...............
Luzerne ............
Luzerne ............
Lawrence ..........
10/30/98
12/18/98
6/30/99
3/23/99
4/7/99
6/1/99
6/1/99
6/1/99
6/1/99
8/9/00
3/8/06, 71 FR 11514 ..........
3/8/06, 71 FR 11514 ..........
3/8/06, 71 FR 11514 ..........
3/8/06, 71 FR 11514 ..........
3/8/06, 71 FR 11514 ..........
3/8/06, 71 FR 11514 ..........
3/8/06, 71 FR 11514 ..........
3/8/06, 71 FR 11514 ..........
3/8/06, 71 FR 11514 ..........
3/31/06, 71 FR 16235 ........
52.2020(d)(1)(l).
52.2020(d)(1)(l).
52.2020(d)(1)(l).
52.2020(d)(1)(l).
52.2020(d)(1)(l).
52.2020(d)(1)(l).
52.2020(d)(1)(l).
52.2020(d)(1)(l).
52.2020(d)(1)(l).
52.2020(d)(1)(m).
PA 61–020
OP–32–000–059
OP–22–2007
OP–50–02001
OP14–0004
OP–40–0009A
CO 211
CO220
Venango ...........
Indiana ..............
Dauphin ............
Perry .................
Centre ...............
Luzerne ............
Allegheny ..........
Allegheny ..........
1/2/96
12/29/94
1/02/95
4/12/99
4/16/99
1/29/99
3/8/96
3/4/96
3/31/06, 71 FR 16235 ........
04/28/06, 71 FR 25070 ......
04/28/06, 71 FR 25070 ......
04/28/06, 71 FR 25070 ......
04/28/06, 71 FR 25070 ......
04/28/06, 71 FR 25070 ......
05/11/06, 71 FR 27394 ......
05/11/06, 71 FR 27394 ......
52.2020(d)(1)(m).
52.2020(d)(1)(n).
52.2020(d)(1)(n).
52.2020(d)(1)(n).
52.2020(d)(1)(n).
52.2020(d)(1)(n).
52.2020(d)(1)(o).
52.2020(d)(1)(o).
OP–15–0104
OP–13–0014
Chester .............
Carbon ..............
5/12/04
4/19/99
05/11/06, 71 FR 27394 ......
05/11/06, 71 FR 27394 ......
52.2020(d)(1)(o).
52.2020(d)(1)(o).
OP–67–2007
OP–49–0001
36–2024
OP–23–0003
22–02004B
OP–20–123
York ..................
Northumberland
Lancaster ..........
Delaware ..........
Dauphin ............
Crawford ...........
7/1/95
1/20/99
7/7/95
4/29/04
12/23/05
7/27/95
05/11/06, 71 FR 27394 ......
05/11/06, 71 FR 27394 ......
6/13/06, 71 FR 34011 ........
6/13/06, 71 FR 34011 ........
6/13/06, 71 FR 34011 ........
6/13/06, 71 FR 34011 ........
52.2020(d)(1)(o).
52.2020(d)(1)(o).
52.2020(d)(1)(p).
52.2020(d)(1)(p).
52.2020(d)(1)(p).
52.2020(d)(1)(p).
PA–42–009
07–02010
30–000–077
McKean ............
Blair ..................
Greene .............
5/31/95
2/27/06
1/3/97
6/13/06, 71 FR 34011 ........
6/13/06, 71 FR 34011 ........
6/13/06, 71 FR 34011 ........
52.2020(d)(1)(p).
52.2020(d)(1)(p).
52.2020(d)(1)(p).
OP–24–009
Elk ....................
5/23/95
6/13/06, 71 FR 34011 ........
52.2020(d)(1)(p).
OP–42–004
OP–14–0002
OP–49–0006
30–000–106
McKean ............
Centre ...............
Northumberland
Greene .............
11/23/98
10/19/98
11/5/96
9/22/95
6/14/06,
6/14/06,
6/14/06,
6/14/06,
52.2020(d)(1)(q).
52.2020(d)(1)(q).
52.2020(d)(1)(q).
52.2020(d)(1)(q).
Scrubgrass Generating Company,
LP.
Wheelabrator Frackville Energy
Co.
Indiana University of Pennsylvania—S.W. Jack Cogeneration
Facility.
Fleetwood Motor Homes ..............
Piney Creek, LP ...........................
Statoil Energy Power Paxton, LP
Harrisburg Steamworks ...............
Cove Shoe Company ...................
PP&L—Fichbach C.T. Facility .....
PP&L—Allentown C.T. Facility ....
PP&L—Harwood C.T. Facility ......
PP&L—Jenkins C.T. Facility ........
The International Metals Reclamation Co.
Petrowax, PA, Inc ........................
Pennsylvania Electric Company ..
The Harrisburg Authority ..............
Texas Eastern Transmission Corp
Graybec Lime, Inc ........................
Techneglas, Inc ............................
DLM Foods (formerly Heinz USA)
NRG Energy Center (formerly
Pittsburgh Thermal Limited
Partnership).
Tasty Baking Oxford, Inc .............
Silberline Manufacturing Company.
Adhesives Research, Inc .............
Mohawk Flush Doors, Inc ............
Bigbee Steel and Tank Company
Conoco Phillips Company ............
The Hershey Company ................
LORD Corporation, Cambridge
Springs.
Pittsburgh Corning Corporation ...
Small Tube Manufacturing, LLC ..
Texas Eastern Transmission Corporation, Holbrook Compressor
Station.
Willamette
Industries,
Johnsonburgh Mill.
American Refining Group, Inc .....
Bellefonte Lime Company ............
Butter Krust Baking Company, Inc
Carnegie Natural Gas Company
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00038
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
71
71
71
71
FR
FR
FR
FR
34259
34259
34259
34259
25MRR2
........
........
........
........
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13051
(1) EPA-APPROVED SOURCE-SPECIFIC REASONABLY AVAILABLE CONTROL TECHNOLOGY (RACT) REQUIREMENTS FOR
VOLATILE ORGANIC COMPOUNDS (VOC) AND OXIDES OF NITROGEN (NOX)—Continued
Name of source
Permit No.
State
effective
date
County
Additional
explanation/
§ 52.2063 citation
EPA approval date
Caterpillar, Inc ..............................
Gencorp, Inc ................................
Harris Semiconductor ..................
Merisol Antioxidants LLC .............
Norcon Power Partners, L.P ........
Triangle Pacific Corp ...................
Viking Energy of Northumberland
Limited Partnership.
White Cap, Inc .............................
Carlisle Tire & Rubber Company
The Carbide/Graphite Group, Inc
Celotex Corporation .....................
American Railcar Industries, Inc.
Shippers Car Line Division.
ACF Industries, Inc ......................
New Holland North America, Inc
Allsteel, Inc ...................................
Ball-Foster Glass Container Co ...
67–2017
54–0009
OP–40–0001A
OP–61–00011
OP–25–923
34–2001
OP–49–0004
York ..................
Schuykill ...........
Luzerne ............
Venango ...........
Erie ...................
Juniata ..............
Northumberland
8/1/95
5/31/96
4/16/99
4/18/05
9/21/95
5/31/95
5/30/95
6/14/06,
6/14/06,
6/14/06,
6/14/06,
6/14/06,
6/14/06,
6/14/06,
71
71
71
71
71
71
71
FR
FR
FR
FR
FR
FR
FR
34259
34259
34259
34259
34259
34259
34259
........
........
........
........
........
........
........
52.2020(d)(1)(q).
52.2020(d)(1)(q).
52.2020(d)(1)(q).
52.2020(d)(1)(q).
52.2020(d)(1)(q).
52.2020(d)(1)(q).
52.2020(d)(1)(q).
40–0004
21–2003
OP–24–012
OP–49–0013
OP–49–0012
Luzerne ............
Cumberland ......
Elk ....................
Northumberland
Northumberland
7/20/95
3/10/95
5/12/95
6/18/99
11/29/95
6/14/06,
7/11/06,
7/11/06,
7/11/06,
7/11/06,
71
71
71
71
71
FR
FR
FR
FR
FR
34259
38993
38993
38993
38993
........
........
........
........
........
52.2020(d)(1)(q).
52.2020(d)(1)(t).
52.2020(d)(1)(t).
52.2020(d)(1)(t).
52.2020(d)(1)(t).
OP–49–0009
36–2028
40–001–5
OP–42–028
Northumberland
Lancaster ..........
Luzerne ............
McKean ............
7/11/06,
7/11/06,
7/11/06,
7/11/06,
71
71
71
71
FR
FR
FR
FR
38993
38993
38993
38993
........
........
........
........
52.2020(d)(1)(t).
52.2020(d)(1)(t).
52.2020(d)(1)(t).
52.2020(d)(1)(t).
Pennsylvania Power & Light
Company—West Shore.
Foster Wheeler Mt. Carmel, Inc ..
Metropolitan Edison Company—
Portland.
Pennsylvania Power & Light
Company.
Pennsylvania Power & Light
Company.
Texas Eastern Transmission Corporation.
Pennsylvania Power & Light
Company.
Johnstown Corporation ................
Koppers Industries, Inc ................
Armstrong World Industries, Inc ..
Peoples Natural Gas Company ...
Dart Container Corporation ..........
AT&T Microelectronics .................
West Penn Power Co ..................
Merck and Co., Inc ......................
OP–21–2009
Cumberland ......
12/12/96
10/17/95
5/26/95
7/7/95
3/31/99
6/7/95
7/11/06, 71 FR 38995 ........
52.2020(d)(1)(r).
OP–49–0002
OP–48–0006
Northumberland
Northampton .....
6/30/95
12/14/94
7/11/06, 71 FR 38995 ........
7/11/06, 71 FR 38995 ........
52.2020(d)(1)(r).
52.2020(d)(1)(r).
OP–41–0004
Lycoming ..........
6/13/95
7/11/06, 71 FR 38995 ........
52.2020(d)(1)(r).
OP–18–0006
Clinton ..............
6/13/95
7/11/06, 71 FR 38995 ........
52.2020(d)(1)(r).
OP–34–2002
Juniata ..............
1/31/97
7/11/06, 71 FR 38995 ........
52.2020(d)(1)(r).
OP–48–0011
Northampton .....
12/19/94
7/11/06, 71 FR 38995 ........
52.2020(d)(1)(r).
OP–11–000–034
OP–41–0008
OP–36–2002
OP–16–124
OP–36–2015
OP–39–0001
OP–30–000–099
OP–49–0007B
Cambria ............
Lycoming ..........
Lancaster ..........
Clarion ..............
Lancaster ..........
Lehigh ...............
Greene .............
Northumberland
6/23/95
3/30/99
10/31/96
8/11/99
8/31/95
5/19/95
5/17/99
5/16/01
7/11/06, 71 FR 38995 ........
7/13/06, 71 FR 39572 ........
6/8/07, 72 FR 31749 ..........
6/8/07, 72 FR 31749 ..........
6/8/07, 72 FR 31749 ..........
6/8/07, 72 FR 31749 ..........
6/8/07, 72 FR 31749 ..........
3/4/08, 73 FR 11553 ..........
52.2020(d)(1)(r).
52.2020(d)(1)(s).
52.2020(d)(1)(u).
52.2020(d)(1)(u).
52.2020(d)(1)(u).
52.2020(d)(1)(u).
52.2020(d)(1)(u).
52.2020(d)(1)(v).
(2) EPA-APPROVED VOLATILE ORGANIC COMPOUNDS (VOC) EMISSIONS TRADING PROGRAMS
State effective
date
Name of source
Permit No.
County
National Can Company
Fres-co Systems,
USA Inc. Paramount
Packaging Corp.
85–524 ........................
85–525 ........................
Bucks ..........................
3/1/85
EPA approval date
4/21/88, 53 FR 13121
Additional explanation/
§ 52.2063 citation
(c)(68); transfer of offsets from NCCo to
Fresco and Paramount.
(3) EPA-APPROVED SOURCE SPECIFIC SULFUR DIOXIDE (SO2) REQUIREMENTS
State effective
date
PWALKER on PROD1PC71 with RULES2
Permit No.
County
USX Corporation, Clairton Coke Works.
Reliant Energy Mid-Atlantic Power Holdings LLC, Warren
Generating Station.
United Refining Company.
Trigen-Philadelphia Energy Corporation.
200 ..............................
Allegheny ....................
11/17/94
8/18/95, 60 FR 43012
(c)(99).
SO2–62–00012 ...........
Warren ........................
11/21/01
1/17/03, 68 FR 2459 ..
(c)(190)(i)(C)(1).
SO2–62–017E ............
Warren ........................
6/11/01
1/17/03, 68 FR 2459 ..
(c)(190)(i)(C)(2).
SO2–95–002 ...............
Philadelphia ................
7/27/00
9/9/02, 67 FR 57155 ..
(c)(193)(i)(B)(1).
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00039
Fmt 4701
Sfmt 4700
EPA approval date
Additional explanation/
§ 52.2063 citation
Name of source
E:\FR\FM\25MRR2.SGM
25MRR2
13052
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(3) EPA-APPROVED SOURCE SPECIFIC SULFUR DIOXIDE (SO2) REQUIREMENTS—Continued
Name of source
Permit No.
State effective
date
County
Grays Ferry Cogenera- SO2–95–002A ............
tion Partnership.
PECO Energy ComSO2–95–006 ...............
pany, Schuylkill Generating Station.
Sunoco, Inc. (R&M)
SO2–95–039 ...............
Philadelphia Refinery.
Additional explanation/
§ 52.2063 citation
EPA approval date
Philadelphia ................
7/27/00
9/9/02, 67 FR 57155 ..
(c)(193)(i)(B)(2).
Philadelphia ................
7/27/00
9/9/02, 67 FR 57155 ..
(c)(193)(i)(B)(3).
Philadelphia ................
7/27/00
9/9/02, 67 FR 57155 ..
(c)(193)(i)(B)(4).
(4) EPA-APPROVED SOURCE SPECIFIC LEADE (PB) REQUIREMENTS
State effective
date
Additional explanation/
§ 52.2063 citation
Name of source
Permit No.
County
EPA approval date
East Penn Manufacturing Corp.
General Battery Corporation.
Tonolli Corporation
(Closed).
Franklin Smelting and
Refining Corporation.
MDC Industries, Inc .....
Anzon, Inc ...................
[None] .........................
Berks ...........................
5/29/84
7/27/84, 49 FR 30179
(c)(62).
[None] .........................
Berks ...........................
5/29/84
7/27/84, 49 FR 30179
(c)(62)
[None] .........................
Carbon ........................
5/29/84
7/27/84, 49 FR 30179
(c)(62).
[None] .........................
Philadelphia ................
9/21/94
12/20/96, 61 FR 67275
(c)(112).
[None] .........................
[None] .........................
Philadelphia ................
Philadelphia ................
9/21/94
9/21/94
12/20/96, 61 FR 67275
12/20/96, 61 FR 67275
(c)(112).
(c)(112).
(e) EPA-approved nonregulatory and
quasi-regulatory material
(1) EPA-APPROVED NONREGULATORY AND QUASI-REGULATORY MATERIAL
Name of non-regulatory SIP revision
Applicable geographic area
Sulfur Dioxide Attainment Demonstration.
Conewego, Pleasant, and Glade
Townships; City of Warren
(Warren Co.).
Allegheny County—sulfur dioxide area defined in 40 CFR
81.339.
Philadelphia-Wilmington-Trenton
Ozone Nonattainment Area.
8/20/01
1/17/03, 68 FR 2454 ......
52.2033(b).
8/15/03
7/21/04, 69 FR 43522 ....
52.2033(c).
9/23/94
9/11/95, 60 FR 47081 ....
52.2035.
Philadelphia County ...................
9/8/95
10/30/95
3/22/96
2/18/97
7/22/98
1/28/97
1/30/96, 61 FR 2982 ......
52.2036(a).
4/3/01, 66 FR 17634 ......
52.2036(d).
5/7/97, 62 FR 24846 ......
52.2036(e).
9/12/96
6/9/97, 62 FR 31343 ......
52.2036(i).
7/31/98
6/17/99, 64 FR 32422 ....
52.2036(l).
3/22/96
2/18/97
11/12/92
8/17/01
7/31/98
2/25/00
4/30/98
8/21/98
2/25/00
7/19/01
2/25/00
10/19/01, 66 FR 53094 ..
52.2036(m).
11/12/02, 67 FR 68521 ..
52.2036(n).
10/26/01, 66 FR 54143 ..
52.2037(i).
10/26/01, 66 FR 54143 ..
52.2037(j).
10/26/01, 66 FR 54143 ..
52.2037(k).
2/23/04
3/22/96
2/18/97
7/22/98
5/21/04, 69 FR 29238 ....
4/3/01, 66 FR 17634 ......
52.2037(k).
52.2038(a).
Sulfur Dioxide Attainment Demonstration.
Photochemical Assessment
Monitoring Stations (PAMS)
Program.
1990 Base Year Emission Inventory—Carbon Monoxide.
1990 Base Year Emission Inventory—VOC.
Pittsburgh-Beaver Valley Ozone
Nonattainment Area.
1990 Base Year Emission Inventory—VOC, CO, NOX.
1990 Base Year Emission Inventory—VOC.
1990 Base Year Emission Inventory—NOX.
1990 Base Year Emission Inventory—NOX.
1990 Base Year Emission Inventory—Carbon Monoxide.
Post 1996 Rate of Progress
Plan.
One-Hour Ozone Attainment
Demonstration.
PWALKER on PROD1PC71 with RULES2
State submittal date
Philadelphia-Wilmington-Trenton
Ozone Nonattainment Area.
Philadelphia-Wilmington-Trenton
Ozone Nonattainment Area.
Pittsburgh-Beaver Valley Ozone
Nonattainment Area.
City of Pittsburgh-CBD & Oakland.
Philadelphia-Wilmington-Trenton
Ozone Nonattainment Area.
Philadelphia-Wilmington-Trenton
Ozone Nonattainment Area.
Mobile Budgets for Post-1996
and 2005 attainment plans.
Philadelphia-Wilmington-Trenton
Ozone Nonattainment Area.
15% Rate of Progress Plan .......
Pittsburgh-Beaver Valley Ozone
Nonattainment Area.
VerDate Nov<24>2008
01:40 Mar 25, 2009
Reading Area (Berks County) ....
Jkt 217001
PO 00000
Frm 00040
Fmt 4701
Sfmt 4700
EPA approval date
E:\FR\FM\25MRR2.SGM
Additional explanation
25MRR2
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
13053
(1) EPA-APPROVED NONREGULATORY AND QUASI-REGULATORY MATERIAL—Continued
Name of non-regulatory SIP revision
Applicable geographic area
15% Rate of Progress Plan .......
Philadelphia-Wilmington-Trenton
Ozone Nonattainment Area.
Control of Asphalt Paving Material (Emission offset).
Particulate matter SIP ................
State submittal date
Defined 16-county area in Western PA and Southwestern PA.
Allegheny
County—Clairton
PM10 nonattainment area.
Statewide ...................................
EPA approval date
Additional explanation
Attainment plan for sulfur dioxide.
Air Quality Monitoring Network ..
Expanded Ridesharing Program
Lead (Pb) SIP ............................
Lead (Pb) SIP ............................
Lead (Pb) SIP ............................
Ozone and Carbon Monoxide
Plan.
Ozone and Carbon Monoxide
Plan.
Ozone and Carbon Monoxide
Plan.
Carbon Monoxide Maintenance
Plan.
8/24/01, 66 FR 44547 ....
52.2038(b).
10/6/77, 42 FR 54417 ....
52.1120(c)(15), 52.2054.
9/8/98, 63 FR 47434 ......
52.2059.
2/1/93
1/6/95, 60 FR 1738 ........
52.2060.
Allegheny County .......................
Statewide ...................................
Southwest Pa. AQCR ................
Statewide (except Allegheny
County).
Armstrong County ......................
9/10/79
4/24/79
9/17/79
1/25/80
10/21/81, 46 FR 51607 ..
5/20/80, 46 FR 33607 ....
5/20/80, 46 FR 33607 ....
8/5/81, 46 FR 39822 ......
52.2063(c)(4).
52.2063(c)(22).
52.2063(c)(30).
52.2063(c)(34).
4/9/81
8/18/81, 46 FR 43423 ....
52.2063(c)(36).
Allegheny County .......................
Metro. Philadelphia AQCR .........
Allegheny County .......................
Philadelphia ................................
12/24/80
12/9/81
9/6/83
8/29/83
5/15/84
9/30/82
6/8/84
6/30/82
10/24/83
6/30/82
10/24/83
6/30/82
10/24/83
9/8/95
10/30/95
9/3/04
9/15/81, 46 FR 45762 ....
10/7/82, 47 FR 44259 ....
2/6/84, 49 FR 4379 ........
8/1/84, 49 FR 30696 ......
52.2063(c)(38).
52.2063(c)(46).
52.2063(c)(59).
52.2063(c)(61).
7/27/84, 49 FR 30179 ....
52.2063(c)(62).
2/26/85, 45 FR 7772 ......
52.2063(c)(63).
2/26/85, 45 FR 7772 ......
52.2063(c)(63).
2/26/85, 45 FR 7772 ......
52.2063(c)(63).
1/30/96, 61 FR 2982 ......
52.2063(c)(105).
04/04/05, 70 FR 16958 ..
3/19/07
Small Business Assistance Program.
Source Testing Manual ..............
Ozone Nonattainment Plan ........
Non-regulatory measures ...........
Air Quality Monitoring Network ..
9/12/96
4/10/97
6/5/98
5/20/77
7/15/77
1/6/94
10/5/07, 72 FR 56911 ....
Statewide (except Philadelphia
and Allegheny Counties).
Metro. Philadelphia AQCR .........
Southwestern Pa AQCR ............
Allentown-Bethlehem-Easton Air
Basin.
Philadelphia County ...................
Source Testing Manual ..............
Statewide ...................................
11/26/94
7/30/96, 61 FR 39597 ....
Continuous Source Testing
Manual (OFR error).
Ozone Maintenance Plan ...........
Statewide (OFR error) ...............
11/26/94
7/30/96, 61 FR 39597 ....
Reading Area (Berks County) ....
Ozone Maintenance Plan ...........
Pittsburgh-Beaver Valley Ozone
Nonattainment Area.
1/28/97
12/09/03
5/21/01
5/7/97, 62 FR 24846 ......
2/26/04, 68 FR 8824 ......
10/19/01, 66 FR 53094 ..
Revised
Carbon
Monoxide
Maintenance Plan Base Year
Emissions Inventory using
MOBILE6.
Conversion of the Carbon Monoxide Maintenance Plan to a
Limited Maintenance Plan Option.
52.2063(c)(110)(i)(D); cross-referenced in Section 139.5.
52.2063(c)(110)(i)(D); cross-referenced in Section 139.5.
52.2063(c)(123).
52.2063(c)(222).
52.2063(c)(188).
4/11/03
4/22/04
8/17/01
8/5/03, 68 FR 46099 ......
12/10/04, 69 FR 71212 ..
11/12/02, 67 FR 68521 ..
52.2063(c)(210).
52.2063(c)(226).
52.2063(c)(189).
9/14/02
9/11/03, 68 FR 53515 ....
52.2063(c)(215).
8/15/03
7/21/04, 69 FR 43522 ....
52.2063(c)(216)(i)(B).
5/7/04
7/1/04, 69 FR 39860 ......
52.2063(c)(224).
Carbon Monoxide Maintenance
Plan.
PM10 Maintenance Plan .............
Sulfur Dioxide Maintenance Plan
PWALKER on PROD1PC71 with RULES2
Sulfur Dioxide Maintenance Plan
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
VerDate Nov<24>2008
01:40 Mar 25, 2009
City of Pittsburgh—CBD & Oakland.
Allegheny
County—Clairton
PM10 nonattainment area.
Allegheny County—sulfur dioxide area defined in 40 CFR
81.339.
Conewego, Pleasant, and Glade
Townships; City of Warren
(Warren Co.).
Lancaster
Area
(Lancaster
County).
9/20/06
11/08/06
7/6/07, 72 FR 36889.
Tioga County ..............................
09/28/06
11/14/06
7/6/07, 72 FR 36892.
Franklin County Area (Franklin
County).
9/20/06
11/08/06
7/25/07, 72 FR 40746.
Jkt 217001
PO 00000
Frm 00041
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
13054
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 / Rules and Regulations
(1) EPA-APPROVED NONREGULATORY AND QUASI-REGULATORY MATERIAL—Continued
Name of non-regulatory SIP revision
Applicable geographic area
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
Harrisburg-Lebanon-Carlisle,
PA: Cumberland County, Dauphin County, Lebanon County,
Perry County.
Johnstown (Cambria County) ....
3/27/07
7/25/07, 72 FR 40749.
3/27/07
8/1/07, 72 FR 41903 ......
Blair County ...............................
2/8/07
8/1/07, 72 FR 41906 ......
Reading Area (Berks County) ....
1/25/07
8/24/07, 72 FR 41906 ....
Correction Notice published 1/
14/08, 73 FR 2162.
Erie County ................................
4/24/07
10/9/07, 72 FR 57207 ....
Mercer County ...........................
3/27/07
10/19/07, 72 FR 59213 ..
Correction Notices published 1/
14/08, 73 FR 2162; and 3/4/
08, 73 FR 11560.
Correction Notices published 1/
14/08, 73 FR 2162; and 3/4/
08, 73 FR 11560.
State College (Centre County) ..
6/12/07
11/14/07, 72 FR 63990.
Scranton-Wilkes-Barre
Area:
Lackawanna, Luzerne, Monroe and Wyoming Counties.
York, PA: Adams County, York
County.
6/12/07
11/19/07, 72 FR 64948.
6/14/07
1/14/08, 73 FR 2163.
Allentown-Bethlehem-Easton
Area: Carbon, Lehigh and
Northampton Counties.
6/26/07
8/9/07
3/4/08, 73 FR 11557 ......
Wayne County ...........................
12/17/07
6/6/08, 73 FR 32238.
Warren County ...........................
12/17/07
6/30/08, 73 FR 36802 ....
Columbia County .......................
12/17/07
7/2/08, 73 FR 37840.
Susquehanna County ................
12/17/07
7/2/08, 73 FR 37841.
Crawford County ........................
12/17/07
7/2/08, 73 FR 37843.
Somerset County .......................
12/17/07
7/2/08, 73 FR 37844.
Snyder County ...........................
12/17/07
7/18/08, 73 FR 41271.
Juniata County ...........................
12/17/07
7/18/08, 73 FR 41272.
Lawrence County .......................
12/17/07
7/18/08, 73 FR 41274.
Northumberland County .............
12/17/07
7/18/08, 73 FR 41275.
Pike County ................................
12/17/07
7/21/08, 73 FR 42263.
Schuylkill County ........................
12/17/07
8/8/08, 73 FR 46200.
Pittsburgh-Beaver Valley Nonattainment Area: Allegheny,
Armstrong, Beaver, Butler,
Fayette, Washington, and
Westmoreland counties.
4/26/07
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base Year Emissions Inventory.
PWALKER on PROD1PC71 with RULES2
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
8-Hour Ozone Maintenance Plan
and 2002 Base-Year Inventory.
2002 Base-Year Inventory .........
*
*
*
*
State submittal date
EPA approval date
11/17/08, 73 FR 67776 ..
Additional explanation
Correction Notice published 3/4/
08, 73 FR 11560.
Technical correction dated 8/9/
07 addresses omitted emissions inventory information
from 6/26/07 submittals.
The SIP effective date is 12/17/
08.
*
[FR Doc. E9–6007 Filed 3–24–09; 8:45 am]
BILLING CODE 6560–50–P
VerDate Nov<24>2008
01:40 Mar 25, 2009
Jkt 217001
PO 00000
Frm 00042
Fmt 4701
Sfmt 4700
E:\FR\FM\25MRR2.SGM
25MRR2
Agencies
[Federal Register Volume 74, Number 56 (Wednesday, March 25, 2009)]
[Rules and Regulations]
[Pages 13014-13054]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-6007]
[[Page 13013]]
-----------------------------------------------------------------------
Part IV
Environmental Protection Agency
-----------------------------------------------------------------------
40 CFR Part 52
Approval and Promulgation of Air Quality Implementation Plans;
Pennsylvania; Update to Materials Incorporated by Reference; Final Rule
Federal Register / Vol. 74, No. 56 / Wednesday, March 25, 2009 /
Rules and Regulations
[[Page 13014]]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
40 CFR Part 52
[PA200-4202; FRL-8774-8]
Approval and Promulgation of Air Quality Implementation Plans;
Pennsylvania; Update to Materials Incorporated by Reference
AGENCY: Environmental Protection Agency (EPA).
ACTION: Final rule; administrative change.
-----------------------------------------------------------------------
SUMMARY: EPA is updating the materials submitted by Pennsylvania that
are incorporated by reference (IBR) into the State implementation plan
(SIP). The regulations affected by this update have been previously
submitted by the Pennsylvania Department of Environmental Protection
and approved by EPA. This update affects the SIP materials that are
available for public inspection at the National Archives and Records
Administration (NARA), the Air and Radiation Docket and Information
Center located at EPA Headquarters in Washington, D.C., and the
Regional Office.
DATES: Effective Date: This action is effective March 25, 2009.
ADDRESSES: SIP materials which are incorporated by reference into 40
CFR part 52 are available for inspection at the following locations:
Air Protection Division, U.S. Environmental Protection Agency, Region
III, 1650 Arch Street, Philadelphia, Pennsylvania 19103; the Air and
Radiation Docket and Information Center, EPA Headquarters Library, Room
Number 3334, EPA West Building, 1301 Constitution Ave., NW.,
Washington, DC 20460, and the National Archives and Records
Administration. If you wish to obtain materials from a docket in the
EPA Headquarters Library, please call the Office of Air and Radiation
(OAR) Docket/Telephone number: (202) 566-1742; or the National Archives
and Records Administration (NARA). For information on the availability
of this material at NARA, call 202-741-6030, or go to: https://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
FOR FURTHER INFORMATION CONTACT: Harold A. Frankford, (215) 814-2108 or
by e-mail at frankford.harold@epa.gov.
SUPPLEMENTARY INFORMATION:
I. Background
The SIP is a living document which the State revises as necessary
to address the unique air pollution problems. Therefore, EPA, from time
to time must take action on SIP revisions containing new and/or revised
regulations to make them part of the SIP. On May 22, 1997 (62 FR
27968), EPA revised the procedures for incorporating by reference
Federally-approved SIPs, as a result of consultations between EPA and
the Office of the Federal Register (OFR). The description of the
revised SIP document, IBR procedures and ``Identification of plan''
format are discussed in further detail in the May 22, 1997 Federal
Register document. On February 25, 2005 (70 FR 9450), EPA published a
document in the Federal Register beginning the new IBR procedure for
Pennsylvania, including Philadelphia and Allegheny Counties. On January
3, 2007 (72 FR 200), EPA published an update to the IBR materials for
Pennsylvania, as of November 1, 2006.
II. EPA Action
In this document, EPA is doing the following:
1. Announcing the update to the IBR material as of December 1,
2008. This update includes specifically-identified material which has
not been revised between November 1, 2006 and December 1, 2008.
2. Making corrections to the following entries listed in the
paragraph 52.2020(c)(1) table, as described below:
a. Restoring the entry for Section 129.51 (Sources of VOC's-
General). This rule, which is currently part of the Pennsylvania SIP,
was listed in the original version of the table published at 40 CFR
52.2020(c)(1) (See, 70 FR 9450 at 9457), but inadvertently removed in a
subsequent IBR update rulemaking action.
b. Correcting the Federal Register page citation in the ``EPA
approval date'' column for rules in Title 25, Chapter 127, subchapters
A, B, C, F, H, and I which EPA had approved on July 30, 1996 (61 FR
39594 and 61 FR 39597).
c. Correcting the Federal Register page citation in the ``EPA
approval date'' column for rules in Title 25, Sections 139.5, 139.13,
139.32, 139.102 and 139.103 which EPA had approved on July 30, 1996 (61
FR 39594 and 61 FR 39597).
d. Removing a duplicate and outdated entry for Title 67, Section
175.41.
3. Making corrections to the following entries listed in the
paragraph 52.2020(c)(2) table, as described below:
a. Removing the entry for Aricle XX, Section 532. EPA has
determined that this entry has been erroneously included because the
SIP approval action taken on January 21, 1983 (48 FR 2768) specifically
excluded EPA action on this Article XX rule (48 FR 2768 at 2769).
b. Correcting the Federal Register page citation in the ``EPA
approval date'' column for Article XXI, Regulation 2105.14.
4. In the 52.2020(d)(1) table, correcting text errors in the
``County'' and ``State effective date'' column in the entry for
Cogentrix of Pennsylvania Inc.
5. Making corrections to the following entries listed in the
paragraph 52.2020(e)(1) table, as described below:
a. Source Testing Manual--correcting the Federal Register page
citation in the ``EPA approval date'' column.
b. Continuous Source Testing Manual--correcting the text in
``Name'' and ``Geographic area'' columns and correcting the Federal
Register page citation in the ``EPA approval date'' column.
c. 8-hour Ozone Maintenance Plan and 2002 Base Year Emissions
Inventory, Erie County--relocating this entry within the chart so as to
be in its proper chronological order and adding a reference in the
``Additional explanation'' column regarding a related correction
Federal Register notice.
d. 8-hour Ozone Maintenance Plan and 2002 Base Year Emissions
Inventory, Reading Area (Berks County)--correcting the date format in
``State submittal date'' column and adding a reference in the
``Additional explanation'' column regarding a related correction
Federal Register notice.
e. 8-hour Ozone Maintenance Plan and 2002 Base Year Emissions
Inventory, Johnstown (Cambria County) and Mercer County--adding
reference in the ``Additional explanation'' column regarding related
correction Federal Register notices.
f. 8-hour Ozone Maintenance Plan and 2002 Base Year Emissions
Inventory, Wayne County--correcting the date format in ``State
submittal date'' column.
EPA has determined that today's rule falls under the ``good cause''
exemption in section 553(b)(3)(B) of the Administrative Procedures Act
(APA) which, upon finding ``good cause,'' authorizes agencies to
dispense with public participation, and section 553(d)(3) which allows
an agency to make a rule effective immediately (thereby avoiding the
30-day delayed effective date otherwise provided for in the APA).
Today's rule simply codifies provisions which are already in effect as
a matter of law in Federal and approved State programs. Under section
553 of the APA, an agency may find good cause where procedures are
``impractical,
[[Page 13015]]
unnecessary, or contrary to the public interest.'' Public comment is
``unnecessary'' and ``contrary to the public interest'' since the
codification only reflects existing law. Immediate notice in the CFR
benefits the public by removing outdated citations and incorrect chart
entries.
III. Statutory and Executive Order Reviews
A. General Requirements
Under the Clean Air Act, the Administrator is required to approve a
SIP submission that complies with the provisions of the Act and
applicable Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a).
Thus, in reviewing SIP submissions, EPA's role is to approve state
choices, provided that they meet the criteria of the Clean Air Act.
Accordingly, this action merely approves state law as meeting Federal
requirements and does not impose additional requirements beyond those
imposed by state law. For that reason, this action:
Is not a ``significant regulatory action'' subject to
review by the Office of Management and Budget under Executive Order
12866 (58 FR 51735, October 4, 1993);
Does not impose an information collection burden under the
provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
Is certified as not having a significant economic impact
on a substantial number of small entities under the Regulatory
Flexibility Act (5 U.S.C. 601 et seq.);
Does not contain any unfunded mandate or significantly or
uniquely affect small governments, as described in the Unfunded
Mandates Reform Act of 1995 (Pub. L. 104-4);
Does not have Federalism implications as specified in
Executive Order 13132 (64 FR 43255, August 10, 1999);
Is not an economically significant regulatory action based
on health or safety risks subject to Executive Order 13045 (62 FR
19885, April 23, 1997);
Is not a significant regulatory action subject to
Executive Order 13211 (66 FR 28355, May 22, 2001);
Is not subject to requirements of Section 12(d) of the
National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272
note) because application of those requirements would be inconsistent
with the Clean Air Act; and
Does not provide EPA with the discretionary authority to
address, as appropriate, disproportionate human health or environmental
effects, using practicable and legally permissible methods, under
Executive Order 12898 (59 FR 7629, February 16, 1994).
B. Submission to Congress and the Comptroller General
The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the
Small Business Regulatory Enforcement Fairness Act of 1996, generally
provides that before a rule may take effect, the agency promulgating
the rule must submit a rule report, which includes a copy of the rule,
to each House of the Congress and to the Comptroller General of the
United States. EPA will submit a report containing this rule and other
required information to the U.S. Senate, the U.S. House of
Representatives, and the Comptroller General of the United States prior
to publication of the rule in the Federal Register. This rule is not a
``major rule'' as defined by 5 U.S.C. 804(2).
C. Petitions for Judicial Review
EPA has also determined that the provisions of section 307(b)(1) of
the Clean Air Act pertaining to petitions for judicial review are not
applicable to this action. Prior EPA rulemaking actions for each
individual component of the Pennsylvania SIP compilations had
previously afforded interested parties the opportunity to file a
petition for judicial review in the United States Court of Appeals for
the appropriate circuit within 60 days of such rulemaking action. Thus,
EPA sees no need in this action to reopen the 60-day period for filing
such petitions for judicial review for this ``Identification of plan''
reorganization update action for Pennsylvania.
List of Subjects in 40 CFR Part 52
Environmental protection, Air pollution control, Carbon monoxide,
Incorporation by reference, Intergovernmental relations, Lead, Nitrogen
dioxide, Ozone, Particulate matter, Reporting and recordkeeping
requirements, Sulfur oxides, Volatile organic compounds.
Dated: February 2, 2009.
William T. Wisniewski,
Acting Regional Administrator, Region III.
0
40 CFR part 52 is amended as follows:
PART 52--[AMENDED]
0
1. The authority for citation for part 52 continues to read as follows:
Authority: 42 U.S.C. 7401 et seq.
Subpart NN--Pennsylvania
0
2. Section 52.2020 is amended by revising paragraphs (b), (c), (d), and
(e)(1) to read as follows:
Sec. 52.2020 Identification of plan.
* * * * *
(b) Incorporation by reference.
(1) Material listed as incorporated by reference in paragraphs (c)
and (d) of this section was approved for incorporation by reference by
the Director of the Federal Register in accordance with 5 U.S.C. 552(a)
and 1 CFR part 51. Material incorporated as it exists on the date of
the approval, and notice of any change in the material will be
published in the Federal Register. Entries in paragraphs (c) and (d) of
this section with EPA approval dates on or after December 1, 2008 will
be incorporated by reference in the next update to the SIP compilation.
(2)(i) EPA Region III certifies that the following rules/
regulations and source-specific requirements provided by EPA at the
addresses in paragraph (b)(3) of this section are an exact duplicate of
the officially promulgated State rules/regulations and source-specific
requirements which have been approved as part of the State
implementation plan as of December 1, 2008:
(A) Materials in Notebook ``1. 40 CFR 52.2020(c)(1)--Pa Department
of Transportation (Pa DOT); 2. 40 CFR 52.2020(c)(2)--Allegheny County
Health Department (ACHD); 3. 40 CFR 52.2020(c)(3)--Philadelphia Air
Management Services (AMS).''
(B) Materials in Notebook ``40 CFR 52.2020(d)(1)--Source-specific
Requirements--Volume 6.''
(ii) EPA Region III certifies that the following rules/regulations
and source specifc requirements provided by EPA at the addresses in
paragraph (b)(3) of this section are an exact duplicate of the
officially promulgated State rules/regulations which have been approved
as part of the State implementation plan as of November 1, 2006. No
additional revisions were made between November 1, 2006 and December 1,
2008:
(A) Materials in Notebook ``40 CFR 52.2020(c)(1)--Pa Department of
Environmental Protection (DEP).''
(B) Materials in Notebook ``40 CFR 52.2020(d)(1)--Source-specific
Requirements--Volume 1, Part 1.''
(C) Materials in Notebook ``40 CFR 52.2020(d)(1)--Source-specific
Requirements--Volume 1, Part 2.''
(D) Materials in Notebook ``40 CFR 52.2020(d)(1)--Source-specific
Requirements--Volume 2, Part 1.''
[[Page 13016]]
(E) Materials in Notebook ``40 CFR 52.2020(d)(1)--Source-specific
Requirements--Volume 2, Part 2.''
(F) Materials in Notebook ``40 CFR 52.2020(d)(1)--Source-specific
Requirements--Volume 3.''
(G) Materials in Notebook ``40 CFR 52.2020(d)(1)--Source-specific
Requirements--Volume 4.''
(H) Materials in Notebook ``40 CFR 52.2020(d)(1)--Source-specific
Requirements--Volume 5.''
(I) Materials in Notebook ``40 CFR 52.2020(d)(2)-(d)(4)--Source-
specific Requirements.''
(3) Copies of the materials incorporated by reference may be
inspected at the EPA Region III Office at 1650 Arch Street,
Philadelphia, PA 19103. For further information, call (215) 814-2108;
the EPA, Air and Radiation Docket and Information Center, Room Number
3334, EPA West Building, 1301Constitution Avenue NW., Washington, DC
20460. For further information, call (202) 566-1742; or at the National
Archives and Records Administration (NARA). For information on the
availability of this material at NARA, call 202-741-6030, or go to:
https://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
(c) EPA-Approved Regulations
(1) EPA-Approved Pennsylvania Regulations
----------------------------------------------------------------------------------------------------------------
Additional
State explanation/
State citation Title/subject effective EPA approval date Sec. 52.2063
date citation
----------------------------------------------------------------------------------------------------------------
Title 25--Environmental Protection
Article III--Air Resources
Chapter 121--General Provisions
----------------------------------------------------------------------------------------------------------------
Section 121.1.................. Definitions..... 12/11/04 9/29/06, 71 FR 57428........... Revised; SIP-
effective date
is 10/30/06.
Section 121.2.................. Purpose......... 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Section 121.3.................. Applicability... 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Section 121.4.................. Regional 5/23/92 12/22/94, 59 FR 65971.......... (c)(94).
Organization of
the Department.
Section 121.7.................. Prohibition of 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Air Pollution.
Section 121.8.................. Compliance 8/13/77 12/17/79, 44 FR 73031.......... (c)(21);
responsibilitie correction
s. published 8/22/
80 (45 FR
56060).
Section 121.9.................. Circumvention... 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Section 121.10................. Existing orders. 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Section 121.11................. Severability 3/20/72 5/31/72, 37 FR 10842........... (c)(1); no
clause. longer in PA
DEP rules.
----------------------------------------------------------------------------------------------------------------
Chapter 123--Standards for Contaminants
----------------------------------------------------------------------------------------------------------------
Fugitive Emissions
----------------------------------------------------------------------------------------------------------------
Section 123.1(a) through (c)... Prohibition of 8/29/77 12/17/79, 44 FR 73031.......... (c)(21);
certain Paragraph
fugitive 123.1(d) is
emissions. not in the
SIP.
Section 123.2.................. Fugitive 8/13/83 7/27/84, 49 FR 30183........... (c)(60).
particulate
matter.
----------------------------------------------------------------------------------------------------------------
Particulate Matter Emissions
----------------------------------------------------------------------------------------------------------------
Section 123.11................. Combustion units 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Appendix A [Graph]............. Particulate 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Matter--Combust
ion Units.
Section 123.12................. Incinerators.... 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Section 123.13(a) through (c).. Processes....... 8/27/80 11/13/81, 46 FR 55971.......... (c)(39);
paragraph
123.13(d) is
not in the
SIP.
Appendix B [Graph]............. Particulate 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Matter--Process
es Listed in
Table 1.
Appendix C [Graph]............. Particulate 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Matter--Process
es Not Listed
in Table 1.
----------------------------------------------------------------------------------------------------------------
Sulfur Compound Emissions
----------------------------------------------------------------------------------------------------------------
Section 123.21................. General......... 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Section 123.22................. Combustion 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
units. [General
provisions--air
basins and non-
air basins.
Section 123.22(a).............. Combustion 8/1/79 8/18/81, 46 FR 43423........... (c)(36);
units--non air approved as
basins. part of the
control
strategy for
the Armstrong
County sulfur
dioxide
nonattainment
area.
Section 123.22(b).............. Combustion 8/1/79 8/8/79, 44 FR 46465............ (c)(20);
units--Erie Air correction
Basin. published 1/23/
80 (45 FR
5303).
Section 123.22(c).............. Combustion 10/1/78 6/4/79, 44 FR 31980............ (c)(18).
units--Southeas
t PA Air Basin.
Section 123.22(c).............. Combustion 8/21/82 7/5/83, 48 FR 30630............ (c)(53).
units--Upper
Beaver Valley
Air Basin.
Section 123.22(d).............. Combustion 1/1/81 12/16/81, 46 FR 61267.......... (c)(40).
units--Lower
Beaver Valley
Air Basin.
Figure 4 [Graph]............... Sulfur Oxides-- 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Combustion
Units.
[[Page 13017]]
Section 123.24................. Primary zinc 8/11/75 4/30/76, 41 FR 18077........... (c)(14).
smelters.
Section 123.25................. Monitoring 10/27/90 6/30/93, 58 FR 34911........... (c)(81).
requirements.
----------------------------------------------------------------------------------------------------------------
Odor Emissions
----------------------------------------------------------------------------------------------------------------
Section 123.31................. Limitations..... 3/20/72 5/31/72, 37 FR 10842........... (c)(1); SIP
version of
Section 123.31
is different
from State
version.
----------------------------------------------------------------------------------------------------------------
Visible Emissions
----------------------------------------------------------------------------------------------------------------
Section 123.41................. Limitations..... 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Section 123.42 (Except Exceptions...... 3/20/72 5/31/72, 37 FR 10842........... (c)(1);
paragraph 123.42(4)). Paragraph
123.42(4) is
declared not
in SIP at
(c)(21).
Section 123.43................. Measuring 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
Techniques.
Section 123.44................. Limitations of 12/27/97 6/11/02, 67 FR 39854........... (c)(189).
visible
fugitive air
contaminants
from operation
of any coke
oven battery.
Section 123.45................. Alternative 6/20/81 1/19/83, 48 FR 2319............ (c)(48).
opacity
limitations.
Appendix D [Chart]............. Alternate 6/20/81 1/19/83, 48 FR 2319............ (c)(48).
Opacity
Limitation--App
lication.
Section 123.46................. Monitoring 6/20/81 1/19/83, 48 FR 2319............ (c)(48).
requirements.
----------------------------------------------------------------------------------------------------------------
Nitrogen Compound Emissions
----------------------------------------------------------------------------------------------------------------
Section 123.51................. Monitoring 10/20/90 9/23/92, 57 FR 43905........... (c)(74).
requirements.
----------------------------------------------------------------------------------------------------------------
NOX Allowance Requirements
----------------------------------------------------------------------------------------------------------------
Section 123.101................ Purpose......... 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
Section 123.102................ Source NOX 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
allowance
requirements
and NOX
allowance
control period.
Section 123.103................ General NOX 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
allowance
provisions.
Section 123.104................ Source 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
authorized
account
representative
requirements.
Section 123.105................ NATS provisions. 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
Section 123.106................ NOX allowance 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
transfer
protocol.
Section 123.107................ NOX allowance 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
transfer
procedures.
Section 123.108................ Source emissions 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
monitoring
requirements.
Section 123.109................ Source emissions 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
reporting
requirements.
Section 123.110................ Source 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
compliance
requirements.
Section 123.111................ Failure to meet 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
source
compliance
requirements.
Section 123.112................ Source operating 11/1/97 6/6/00, 65 FR 35840............ (c)(145)
permit
provision
requirements.
Section 123.113................ Source 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
recordkeeping
requirements.
Section 123.114................ General NOX 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
allocation
provisions.
Section 123.115................ Initial NOX 3/11/00 6/6/00, 65 FR 35840............ (c)(145).
allowance NOX
allocations.
Section 123.116................ Source opt-in 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
provisions.
Section 123.117................ New NOX affected 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
source
provisions.
Section 123.118................ Emission 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
reduction
credit
provisions.
Section 123.119................ Bonus NOX 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
allowance
awards.
Section 123.120................ Audit........... 11/1/97 6/6/00, 65 FR 35840............ (c)(145).
Appendix E [Chart]............. Appendix E [NOX 3/11/00 6/6/00, 65 FR 35840............ (c)(145).
Allowances
Chart].
----------------------------------------------------------------------------------------------------------------
Chapter 126--Standard for Motor Fuels
----------------------------------------------------------------------------------------------------------------
Subchapter A--Oxygenate Content of Gasoline
----------------------------------------------------------------------------------------------------------------
Section 126.101................ General......... 8/19/95 12/17/99, 64 FR 70589.......... (c)(142).
Section 126.102................ Sampling and 8/19/95 12/17/99, 64 FR 70589.......... (c)(142).
testing.
Section 126.103................ Recordkeeping 8/19/95 12/17/99, 64 FR 70589.......... (c)(142).
and reporting.
Section 126.104................ Labeling 8/19/95 12/17/99, 64 FR 70589.......... (c)(142).
requirements.
----------------------------------------------------------------------------------------------------------------
[[Page 13018]]
Subchapter C--Gasoline Volatility Requirements
----------------------------------------------------------------------------------------------------------------
Section 126.301 (a) through (c) Compliant fuel 11/1/97 6/8/98, 63 FR 31116............ (c)(131).
requirement.
Section 126.302 (Except Recordkeeping 11/1/97 6/8/98, 63 FR 31116............ (c)(131).
Paragraph (a)(6) pertaining to and reporting.
RFG).
Section 126.303(a)............. Compliance and 11/1/97 6/8/98, 63 FR 31116............ (c)(131).
test methods.
----------------------------------------------------------------------------------------------------------------
Subchapter D--Motor Vehicle Emissions Control Program
----------------------------------------------------------------------------------------------------------------
General Provisions
----------------------------------------------------------------------------------------------------------------
Section 126.401................ Purpose......... 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
Section 126.402................ NLEV scope and 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
applicability.
----------------------------------------------------------------------------------------------------------------
Pennsylvania Clean Vehicles Program
----------------------------------------------------------------------------------------------------------------
Section 126.411................ General 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
Requirements.
Section 126.412................ Emission 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
requirements.
Section 126.413................ Exemptions...... 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
----------------------------------------------------------------------------------------------------------------
Applicable Motor Vehicle Testing
----------------------------------------------------------------------------------------------------------------
Section 126.421................ New motor 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
vehicle
certification
testing.
Section 126.422................ New motor 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
vehicle
compliance
testing.
Section 126.423................ Assembly line 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
testing.
Section 126.424................ In-use motor 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
vehicle
enforcement
testing.
Section 126.425................ In-use 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
surveillance
testing.
----------------------------------------------------------------------------------------------------------------
Motor Vehicle Manufacturers' Obligations
----------------------------------------------------------------------------------------------------------------
Section 126.431................ Warranty and 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
recall.
Section 126.432................ Reporting 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
requirements.
----------------------------------------------------------------------------------------------------------------
Motor Vehicle Dealer Responsibilities
----------------------------------------------------------------------------------------------------------------
Section 126.441................ Responsibilities 12/5/98 12/28/99, 64 FR 72564.......... (c)(141)(i)(C).
of motor
vehicle dealers.
----------------------------------------------------------------------------------------------------------------
Chapter 127--Construction, Modification, Reactivation, and Operation of Sources
----------------------------------------------------------------------------------------------------------------
Subchapter A--General
----------------------------------------------------------------------------------------------------------------
Section 127.1.................. Purpose......... 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
Section 127.3.................. Operational 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
flexibility.
----------------------------------------------------------------------------------------------------------------
Subchapter B--Plan Approval Requirements
----------------------------------------------------------------------------------------------------------------
Section 127.11................. Plan approval 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
requirements.
Section 127.11a................ Reactivation of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
sources.
Section 127.12................. Content of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
applications.
Section 127.12a................ Compliance 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
review.
Section 127.12b................ Plan approval 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
terms and
conditions.
Section 127.12c................ Plan approval 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
reporting
requirements.
Section 127.13................. Extensions...... 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
Section 127.13a................ Plan approval 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
changes for
cause.
Section 127.13b................ Denial of Plan 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
approval
application.
Section 127.13c................ Notice of basis 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
for certain
plan approval
decisions.
Section 127.14................. Exemptions...... 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
Section 127.25................. Compliance 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
requirement.
Section 127.32................. Transfer of plan 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
approvals.
Section 127.35................. Maximum 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
achievable
control
technology
standards for
hazardous air
pollutants.
[[Page 13019]]
Section 127.36................. Health risk- 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
based emission
standards and
operating
practice
requirements.
Section 127.44................. Public Notice... 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
Section 127.45................. Contents of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
notice.
Section 127.46................. Filing protests. 8/13/83 7/27/84, 49 FR 30183........... (c)(60).
Section 127.47................. Consideration of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
protests.
Section 127.48................. Conferences and 8/13/83 7/27/84, 49 FR 30183........... (c)(60).
hearings.
Section 127.49................. Conference or 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
hearing
procedure.
Section 127.50................. Conference or 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
hearing record.
Section 127.51................. Plan approval 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
disposition.
----------------------------------------------------------------------------------------------------------------
Subchapter D--Prevention of Significant Deterioration of Air Quality
----------------------------------------------------------------------------------------------------------------
Section 127.81................. Purpose......... 6/18/83 8/21/84, 49 FR 33127........... (c)(57).
Section 127.82................. Scope........... 6/18/83 8/21/84, 49 FR 33127........... (c)(57).
Section 127.83................. Adoption of 6/18/83 8/21/84, 49 FR 33127........... (c)(57).
Program.
----------------------------------------------------------------------------------------------------------------
Subchapter E--New Source Review
----------------------------------------------------------------------------------------------------------------
Section 127.201................ General 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
requirements.
Section 127.202................ Effective date.. 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
Section 127.203................ Facilities 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
subject to
special permit
requirements.
Section 127.204................ Emissions 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
subject to this
subchapter.
Section 127.205................ Special permit 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
requirements.
Section 127.206................ ERC general 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
requirements.
Section 127.207................ ERC generation 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
and creation.
Section 127.208................ ERC use and 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
transfer
requirements.
Section 127.209................ ERC registry 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
system.
Section 127.210................ Offset ratios... 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
Section 127.211................ Applicability 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
determination.
Section 127.212................ Portable 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
facilities.
Section 127.213................ Construction and 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
demolition.
Section 127.214................ Exemption....... 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
Section 127.215................ Reactivation.... 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
Section 127.216................ Circumvention... 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
Section 127.217................ Clean Air Act 1/15/94 12/9/97, 62 FR 64722........... (c)(107).
Titles III-V
applicability.
----------------------------------------------------------------------------------------------------------------
Subchapter F--Operating Permit Requirements
----------------------------------------------------------------------------------------------------------------
General
----------------------------------------------------------------------------------------------------------------
Section 127.401................ Scope........... 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
Section 127.402................ General 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
provisions.
Section 127.403................ Permitting of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
sources
operating
lawfully
without a
permit.
Section 127.404................ Compliance 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
schedule for
repermitting.
----------------------------------------------------------------------------------------------------------------
Permit Applications
----------------------------------------------------------------------------------------------------------------
Section 127.411................ Content of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
applications..
Section 127.412................ Compliance 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
review forms.
Section 127.413................ Municipal 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
notification.
Section 127.414................ Supplemental 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
information.
----------------------------------------------------------------------------------------------------------------
Review of Applications
----------------------------------------------------------------------------------------------------------------
Section 127.421................ Review of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
Applications.
Section 127.422................ Denial of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
permits.
Section 127.423................ Notice of basis 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
for certain
operating
permit
decisions.
Section 127.424................ Public notice... 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
Section 127.425................ Contents of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
notice.
Section 127.426................ Filing protests. 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
Section 127.427................ Consideration of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
protest.
Section 127.428................ Conferences and 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
hearings.
Section 127.429................ Conference or 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
hearing
procedure.
Section 127.430................ Conference or 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
hearing record.
[[Page 13020]]
Section 127.431................ Operating permit 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
disposition.
----------------------------------------------------------------------------------------------------------------
Operating Permit Conditions
----------------------------------------------------------------------------------------------------------------
Section 127.441................ Operating permit 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
terms and
conditions.
Section 127.442................ Reporting 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
requirements.
Section 127.443................ Operating permit 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
requirements.
Section 127.444................ Compliance 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
requirements.
Section 127.445................ Operating permit 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
compliance
schedules.
Section 127.446................ Operating permit 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
duration.
Section 127.447................ Alternate 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
operating
scenarios.
Section 127.448................ Emissions 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
trading at
facilities with
Federally
enforceable
emissions cap.
Section 127.449................ De minimis 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
emission
increases.
Section 127.450................ Administrative 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
operating
permit
amendments.
----------------------------------------------------------------------------------------------------------------
Operating Permit Modifications
----------------------------------------------------------------------------------------------------------------
Section 127.461................ Operating permit 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
changes for
cause.
Section 127.462................ Minor operating 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
permit
modifications.
Section 127.463................ Operating permit 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
revisions to
incorporate
applicable
standards.
Section 127.464................ Transfer of 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
operating
permits.
----------------------------------------------------------------------------------------------------------------
Subchapter H--General Plan Approvals and Operating Permits
----------------------------------------------------------------------------------------------------------------
General
----------------------------------------------------------------------------------------------------------------
Section 127.601................ Scope........... 11/26/94 7/30/96, 61 FR 39594........... (c)(111).
----------------------------------------------------------------------------------------------------------------
Issuance of General Plan Approvals and General Operating Permits
----------------------------------------------------------------------------------------------------------------
Section 127.611................ General plan 11/26/94 7/30/96, 61 FR 39594........... (c)(111).
approvals and
general
operating
permits.
Section 127.612................ Public notice 11/26/94 7/30/96, 61 FR 39594........... (c)(111).
and review
period.
----------------------------------------------------------------------------------------------------------------
Use of General Plan Approvals and Permits
----------------------------------------------------------------------------------------------------------------
Section 127.621................ Application for 11/26/94 7/30/96, 61 FR 39594........... (c)(111).
use of general
plan approvals
and general
operating
permits.
Section 127.622................ Compliance with 11/26/94 7/30/96, 61 FR 39594........... (c)(111).
general plan
approvals and
general
operating
permits.
----------------------------------------------------------------------------------------------------------------
Subchapter I--Plan Approval and Operating Permit Fees
----------------------------------------------------------------------------------------------------------------
Section 127.701................ General 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
provisions.
Section 127.702................ Plan approval 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
fees.
Section 127.703................ Operating permit 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
fees under
Subchapter F.
Section 127.707................ Failure to pay 11/26/94 7/30/96, 61 FR 39597........... (c)(110)(i)(C).
fee.
----------------------------------------------------------------------------------------------------------------
Subchapter J--General Conformity
----------------------------------------------------------------------------------------------------------------
Section 127.801................ Purpose......... 11/9/96 9/29/97, 62 FR 50870........... (c)(126).
Section 127.802................ Adoption of 11/9/96 9/29/97, 62 FR 50870........... (c)(126).
Standards.
----------------------------------------------------------------------------------------------------------------
Chapter 129--Standards for Sources
----------------------------------------------------------------------------------------------------------------
Miscellaneous Sources
----------------------------------------------------------------------------------------------------------------
Section 129.11................. Nitric acid 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
plants.
Section 129.12................. Sulfuric acid 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
plants.
Section 129.13................. Sulfur recovery 3/20/72 5/31/72, 37 FR 10842........... (c)(1).
plants.
APPENDIX A..................... Allowable 4/23/94 3/23/98, 63 FR 13789........... (c)(129).
emissions,
sulfur oxides--
sulfur recovery
plants.
Section 129.14................. Open burning 8/9/76 8/19/80, 45 FR 55178........... (c)(33).
operations.
[[Page 13021]]
Section 129.15................. Coke pushing 8/29/77, 12/ 12/17/79, 44 FR 73031.......... (c)(21);
operations. 31/77 correction
published 8/22/
80, 45 FR
56060.
Section 129.16................. Door 12/12/77 7/17/79, 44 FR 41429........... (c)(19).
maintenance,
adjustment and
replacement
practices.
Section 129.18................. Municipal waste 10/27/90 6/30/93, 58 FR 34911........... (c)(81).
incinerators.
----------------------------------------------------------------------------------------------------------------
Sources of VOCs
----------------------------------------------------------------------------------------------------------------
Section 129.51................. General......... 4/10/99 6/25/01, 66 FR 33645........... (c)(155).
Section 129.52................. Surface coating 6/10/00 7/20/01, 66 FR 37908........... (c)(152).
processes.
Section 129.54................. Seasonal 8/3/91 5/13/93, 58 FR 28362........... (c)(79).
operation of
auxiliary
incineration
equipment.
Section 129.55................. Petroleum 6/20/81 1/19/83, 48 FR 2319............ (c)(48).
refineries--spe
cific sources.
Section 129.56................. Storage tanks 9/5/98 7/26/00, 65 FR 45920........... (c)(147).
greater than
40,000 gallons
capacity
containing VOCs.
Section 129.57................. Storage tanks 6/20/81 1/19/83, 48 FR 2319............ (c)(48).
less than or
equal to 40,000
gallons
capacity
containing VOCs.
Section 129.58................. Petroleum 8/13/83 7/27/84, 49 FR 30183........... (c)(60).
refineries--fug
itive sources.
Section 129.59................. Bulk gasoline 8/3/91 5/13/93, 58 FR 28362........... (c)(79).
terminals.
Section 129.60................. Bulk gasoline 8/3/91 5/13/93, 58 FR 28362........... (c)(79).
plants.
Section 129.61................. Small gasoline 8/3/91 5/13/93, 58 FR 28362........... (c)(79).
storage tank
control (Stage
I control).
Section 129.62................. General 5/23/94 12/22/94, 59 FR 65971.......... (c)(94).
standards for
bulk gasoline
terminals, bulk
gasoline
plants, and