Freeport LNG Development, LP; Notice of Availability of the Environmental Assessment for the Proposed Freeport LNG Export Project and Bog/Truck Project, 11931-11932 [E9-6075]
Download as PDF
Federal Register / Vol. 74, No. 53 / Friday, March 20, 2009 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP03–75–003, CP03–75–004,
CP05–361–001, and CP05–361–002]
Freeport LNG Development, LP; Notice
of Availability of the Environmental
Assessment for the Proposed Freeport
LNG Export Project and Bog/Truck
Project
March 13, 2009.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) and the Department of
Energy (DOE), Office of Fossil Fuels,
have prepared an environmental
assessment (EA) on the liquefied natural
gas (LNG) facilities proposed by
Freeport LNG Development, LP
(Freeport LNG) in the above-referenced
docket.
The EA was prepared to satisfy the
requirements of the National
Environmental Policy Act (NEPA). The
DOE is a cooperating agency for the
development of the EA. A cooperating
agency has jurisdiction by law or special
expertise with respect to potential
environmental impacts associated with
the proposal and is involved in the
NEPA analysis. The FERC staff
concludes that approval of the proposed
projects, with appropriate mitigating
measures, would not constitute a major
Federal action significantly affecting the
quality of the human environment.
In order to operate its facility for the
LNG Export Project, Freeport LNG
proposes equipment modification at the
Phase I unloading dock to allow shore
to ship LNG transfer. This would
include converting one 1 of the four
existing unloading arms on the Phase I
unloading dock to a loading line to
transfer export-bound LNG from the
terminal’s storage tanks to awaiting
ships. The conversion would involve
minor changes involving a check valve
and a control valve. The check valve
would be replaced with a short spool.
At any given time, the terminal would
operate either in the export mode or the
currently authorized import mode, but
not in both modes simultaneously, such
that ships visiting the terminal to load
LNG for export would operate instead
of, not in addition to, ships delivering
LNG for domestic use only.
Freeport LNG also applied to DOE on
August 1, 2008 in Docket No. FE–08–
70–LNG to export on a short-term or
1 Freeport LNG’s LNG Transfer System Startup/
Operation Procedure (Document No. FLNG–REC–
101XXX [Revision 1–09–04–08]) identifies the arm
as LA–1A.
VerDate Nov<24>2008
17:07 Mar 19, 2009
Jkt 217001
spot market basis up to 24 Bcf of
previously imported LNG cumulatively
over a two-year period from the United
States (U.S.) to the United Kingdom,
Belgium, Spain, France, Italy, Japan,
South Korea, India, China, and/or
Taiwan.
Freeport LNG also proposes to
construct and operate a boil-off gas
(BOG) liquefaction system and a LNG
truck delivery system at the company’s
existing import terminal.2 These
facilities would allow Freeport LNG to
(1) liquefy about 5 million cubic feet per
day of BOG and return it to the LNG
storage tanks and (2) receive the
delivery of LNG by truck in order to
keep the tanks in the necessary
cryogenic state. The BOG liquefaction
plant would also act as a back-up to the
existing BOG takeaway pipeline
compression. The location of BOG
liquefaction facilities would consist of:
• One BOG liquefaction heat
exchanger;
• One BOG liquefaction expandercompressor;
• Two BOG liquefaction compression
lube oil filters;
• Three BOG refrigeration compressor
units (approximately 1,380 horsepower
(hp) each);
• Natural gas piping, 4, 6, 8, and 12inch-diameter aboveground piping; and
• LNG piping, 4-inch-diameter
aboveground piping.
Freeport LNG is proposing certain
facility modifications to enable it to
undertake LNG truck unloading
activities in the event that the BOG
liquefaction facilities are not available.
The truck unloading facilities would
require the installation of a single 4inch-diameter inlet connection and
valves on one of the existing LNG
transfer lines and a 25 hp portable
electric pump, if needed. The LNG truck
would be connected to the valve via a
3-inch-diameter hose during unloading
of the LNG. Freeport LNG would use
these facilities to transfer the LNG from
the trucks to the existing tanks. Freeport
LNG anticipates that it would receive 5
to 6 truck deliveries per day, totaling
66,000 gallons or 4.96 million standard
cubic feet (MMscf) of LNG during the
periods when delivery by truck would
be required. The proposed LNG truck
delivery system is expected to operate
for about 60–90 days, generating traffic
of about 540 trucks annually.
The EA has been placed in the public
files of the FERC. A limited number of
2 During routine terminal operations, ambient
heat in the LNG storage tanks and piping causes
small amount of LNG to evaporate. The vaporizing
LNG is referred to as BOG or boil-off gas. The BOG
increases the storage tank pressure until a point
where it must be transferred, flared, or re-liquefied.
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
11931
copies of the EA are available for
distribution and public inspection at:
Federal Energy Regulatory Commission,
Public Reference Room, 888 First Street,
NE., Room 2A, Washington, DC 20426.
(202) 502–8371.
Copies of the EA have been mailed to
Federal, State, and local agencies;
public interest groups; interested
individuals and affected landowners;
Native American Tribes; newspapers
and libraries; and parties to this
proceeding.
Any person wishing to comment on
the EA may do so. To ensure
consideration prior to a Commission
decision on the proposal, it is important
that we receive your comments before
the date specified below.
You can make a difference by
providing us with your specific
comments or concerns about the Sabine
Export Project. Your comments should
focus on the potential environmental
effects, reasonable alternatives, and
measures to avoid or lessen
environmental impacts. The more
specific your comments, the more useful
they will be. To ensure that your
comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before April 13,
2009.
For your convenience, there are three
methods in which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket numbers CP03–75–003, CP03–
75–004, CP05–361–001, and CP05–361–
002 with your submission. The docket
number can be found on the front of this
notice. The Commission encourages
electronic filing of comments and has
dedicated eFiling expert staff available
to assist you at 202–502–8258 or
efiling@ferc.gov.
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located on
the Commission’s Internet Web site at
https://www.ferc.gov under the link to
Documents and Filings. A Quick
Comment is an easy method for
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Internet Web site at
https://www.ferc.gov under the link to
Documents and Filings. eFiling involves
preparing your submission in the same
manner as you would if filing on paper,
and then saving the file on your
computer’s hard drive. You will attach
that file as your submission. New
eFiling users must first create an
account by clicking on ‘‘Sign up’’ or
E:\FR\FM\20MRN1.SGM
20MRN1
11932
Federal Register / Vol. 74, No. 53 / Friday, March 20, 2009 / Notices
‘‘eRegister.’’ You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing;’’ or
(3) You may file your comments via
mail to the Commission by sending an
original and two copies of your letter to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First St., NE., Room 1A, Washington, DC
20426.
Label one copy of the comments for the
attention of Gas Branch 2, PJ11.2.
Comments will be considered by the
Commission but will not serve to make
the commentor a party to the
proceeding. Any person seeking to
become a party to the proceeding must
file a motion to intervene pursuant to
Rule 214 of the Commission’s Rules of
Practice and Procedures (18 CFR
385.214).3 Only intervenors have the
right to seek rehearing of the
Commission’s decision.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
comments considered.
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the eLibrary link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
3 Interventions may also be filed electronically via
the Internet in lieu of paper. See the previous
discussion on filing comments electronically.
VerDate Nov<24>2008
17:07 Mar 19, 2009
Jkt 217001
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
at 1–866–208–3676, or for TTY, (202)
502–8659.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–6075 Filed 3–19–09; 8:45 am]
Kimberly D. Bose,
Secretary.
[FR Doc. E9–6064 Filed 3–19–09; 8:45 am]
BILLING CODE
BILLING CODE
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Docket No. CP04–379–002]
[Project No 77–222]
Pacific Gas and Electric Company;
Notice of Availability of Environmental
Assessment
March 12, 2009.
In accordance with the National
Environmental Policy Act of 1969, as
amended, and the Federal Energy
Regulatory Commission’s regulations,
18 CFR part 380 (Order No. 486, 52 FR
47879), the Commission has reviewed
an application, filed March 6, 2008,
requesting approval to temporarily
amend article 52 of the Potter Valley
Project license. The project is located on
the Eel River and the East Branch
Russian River in Lake and Mendocino
Counties, California.
Pacific Gas and Electric Company
(licensee for the Potter Valley Project)
requested approval to divert additional
water from the Eel River to the East
Branch Russian River in the same
manner as authorized previously by the
Commission in an order titled, Order
Granting Temporary Amendment of
License Article 52, issued March 13,
2008. The request, if granted, would
provide frost protection from March 15–
April 14, 2009 while the Commission
continues its review of the licensee’s
long-term frost protection plan.
The attached environmental
assessment (EA), prepared by
Commission staff in the Office of Energy
Projects, analyzed the probable
environmental effects of the proposed
temporary amendment and has
concluded that approval would not
constitute a major Federal action
significantly affecting the quality of the
human environment.
A copy of the EA is available for
review at the Commission or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access
documents. For assistance, contact
FERC Online Support at
ferconlinesupport@ferc.gov or toll-free
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
Pine Prairie Energy Center, LLC;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Pine Prairie Energy Center
Supplemental Expansion Project and
Request for Comments on
Environmental Issues
March 13, 2009.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Pine Prairie Energy Center
Supplemental Expansion Project
(Expansion Project, or Project) involving
construction and operation of facilities
by Pine Prairie Energy Center, LLC (Pine
Prairie) in Evangeline and Acadia
Parishes, Louisiana.1 This EA will be
used by the Commission in its decisionmaking process to determine whether
the Expansion Project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process we will use to
gather input from the public and
interested agencies on the Expansion
Project. Your input will help the
Commission staff determine which
issues need to be evaluated in the EA.
Please note that the scoping period will
close on April 13, 2009.
This notice is being sent to affected
landowners; Federal, State, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. State and local
government representatives are asked to
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a Pine
Prairie representative about survey
permission and/or the acquisition of an
easement to construct, operate, and
1 Pine Prairie submitted an amendment
application on February 6, 2009 under Section 7 of
the Natural Gas Act.
E:\FR\FM\20MRN1.SGM
20MRN1
Agencies
[Federal Register Volume 74, Number 53 (Friday, March 20, 2009)]
[Notices]
[Pages 11931-11932]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-6075]
[[Page 11931]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP03-75-003, CP03-75-004, CP05-361-001, and CP05-361-002]
Freeport LNG Development, LP; Notice of Availability of the
Environmental Assessment for the Proposed Freeport LNG Export Project
and Bog/Truck Project
March 13, 2009.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) and the Department of Energy (DOE), Office of Fossil Fuels,
have prepared an environmental assessment (EA) on the liquefied natural
gas (LNG) facilities proposed by Freeport LNG Development, LP (Freeport
LNG) in the above-referenced docket.
The EA was prepared to satisfy the requirements of the National
Environmental Policy Act (NEPA). The DOE is a cooperating agency for
the development of the EA. A cooperating agency has jurisdiction by law
or special expertise with respect to potential environmental impacts
associated with the proposal and is involved in the NEPA analysis. The
FERC staff concludes that approval of the proposed projects, with
appropriate mitigating measures, would not constitute a major Federal
action significantly affecting the quality of the human environment.
In order to operate its facility for the LNG Export Project,
Freeport LNG proposes equipment modification at the Phase I unloading
dock to allow shore to ship LNG transfer. This would include converting
one \1\ of the four existing unloading arms on the Phase I unloading
dock to a loading line to transfer export-bound LNG from the terminal's
storage tanks to awaiting ships. The conversion would involve minor
changes involving a check valve and a control valve. The check valve
would be replaced with a short spool. At any given time, the terminal
would operate either in the export mode or the currently authorized
import mode, but not in both modes simultaneously, such that ships
visiting the terminal to load LNG for export would operate instead of,
not in addition to, ships delivering LNG for domestic use only.
---------------------------------------------------------------------------
\1\ Freeport LNG's LNG Transfer System Startup/Operation
Procedure (Document No. FLNG-REC-101XXX [Revision 1-09-04-08])
identifies the arm as LA-1A.
---------------------------------------------------------------------------
Freeport LNG also applied to DOE on August 1, 2008 in Docket No.
FE-08-70-LNG to export on a short-term or spot market basis up to 24
Bcf of previously imported LNG cumulatively over a two-year period from
the United States (U.S.) to the United Kingdom, Belgium, Spain, France,
Italy, Japan, South Korea, India, China, and/or Taiwan.
Freeport LNG also proposes to construct and operate a boil-off gas
(BOG) liquefaction system and a LNG truck delivery system at the
company's existing import terminal.\2\ These facilities would allow
Freeport LNG to (1) liquefy about 5 million cubic feet per day of BOG
and return it to the LNG storage tanks and (2) receive the delivery of
LNG by truck in order to keep the tanks in the necessary cryogenic
state. The BOG liquefaction plant would also act as a back-up to the
existing BOG takeaway pipeline compression. The location of BOG
liquefaction facilities would consist of:
---------------------------------------------------------------------------
\2\ During routine terminal operations, ambient heat in the LNG
storage tanks and piping causes small amount of LNG to evaporate.
The vaporizing LNG is referred to as BOG or boil-off gas. The BOG
increases the storage tank pressure until a point where it must be
transferred, flared, or re-liquefied.
---------------------------------------------------------------------------
One BOG liquefaction heat exchanger;
One BOG liquefaction expander-compressor;
Two BOG liquefaction compression lube oil filters;
Three BOG refrigeration compressor units (approximately
1,380 horsepower (hp) each);
Natural gas piping, 4, 6, 8, and 12-inch-diameter
aboveground piping; and
LNG piping, 4-inch-diameter aboveground piping.
Freeport LNG is proposing certain facility modifications to enable
it to undertake LNG truck unloading activities in the event that the
BOG liquefaction facilities are not available. The truck unloading
facilities would require the installation of a single 4-inch-diameter
inlet connection and valves on one of the existing LNG transfer lines
and a 25 hp portable electric pump, if needed. The LNG truck would be
connected to the valve via a 3-inch-diameter hose during unloading of
the LNG. Freeport LNG would use these facilities to transfer the LNG
from the trucks to the existing tanks. Freeport LNG anticipates that it
would receive 5 to 6 truck deliveries per day, totaling 66,000 gallons
or 4.96 million standard cubic feet (MMscf) of LNG during the periods
when delivery by truck would be required. The proposed LNG truck
delivery system is expected to operate for about 60-90 days, generating
traffic of about 540 trucks annually.
The EA has been placed in the public files of the FERC. A limited
number of copies of the EA are available for distribution and public
inspection at: Federal Energy Regulatory Commission, Public Reference
Room, 888 First Street, NE., Room 2A, Washington, DC 20426. (202) 502-
8371.
Copies of the EA have been mailed to Federal, State, and local
agencies; public interest groups; interested individuals and affected
landowners; Native American Tribes; newspapers and libraries; and
parties to this proceeding.
Any person wishing to comment on the EA may do so. To ensure
consideration prior to a Commission decision on the proposal, it is
important that we receive your comments before the date specified
below.
You can make a difference by providing us with your specific
comments or concerns about the Sabine Export Project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
The more specific your comments, the more useful they will be. To
ensure that your comments are timely and properly recorded, please send
in your comments so that they will be received in Washington, DC on or
before April 13, 2009.
For your convenience, there are three methods in which you can use
to submit your comments to the Commission. In all instances please
reference the project docket numbers CP03-75-003, CP03-75-004, CP05-
361-001, and CP05-361-002 with your submission. The docket number can
be found on the front of this notice. The Commission encourages
electronic filing of comments and has dedicated eFiling expert staff
available to assist you at 202-502-8258 or efiling@ferc.gov.
(1) You may file your comments electronically by using the Quick
Comment feature, which is located on the Commission's Internet Web site
at https://www.ferc.gov under the link to Documents and Filings. A Quick
Comment is an easy method for interested persons to submit text-only
comments on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Internet Web site at
https://www.ferc.gov under the link to Documents and Filings. eFiling
involves preparing your submission in the same manner as you would if
filing on paper, and then saving the file on your computer's hard
drive. You will attach that file as your submission. New eFiling users
must first create an account by clicking on ``Sign up'' or
[[Page 11932]]
``eRegister.'' You will be asked to select the type of filing you are
making. A comment on a particular project is considered a ``Comment on
a Filing;'' or
(3) You may file your comments via mail to the Commission by
sending an original and two copies of your letter to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First St., NE.,
Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas Branch 2,
PJ11.2.
Comments will be considered by the Commission but will not serve to
make the commentor a party to the proceeding. Any person seeking to
become a party to the proceeding must file a motion to intervene
pursuant to Rule 214 of the Commission's Rules of Practice and
Procedures (18 CFR 385.214).\3\ Only intervenors have the right to seek
rehearing of the Commission's decision.
---------------------------------------------------------------------------
\3\ Interventions may also be filed electronically via the
Internet in lieu of paper. See the previous discussion on filing
comments electronically.
---------------------------------------------------------------------------
Affected landowners and parties with environmental concerns may be
granted intervenor status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which would not be
adequately represented by any other parties. You do not need intervenor
status to have your comments considered.
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on ``General Search'' and enter the
docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-6075 Filed 3-19-09; 8:45 am]
BILLING CODE