Dominion Cove Point LNG, LP; Environmental Assessment for the Proposed Pipeline Compressor Addition Project and Request for Comments on Environmental Issues, 11094-11096 [E9-5559]
Download as PDF
11094
Federal Register / Vol. 74, No. 49 / Monday, March 16, 2009 / Notices
Filed Date: 03/02/2009.
Accession Number: 20090302–5184.
Comment Date: 5 p.m. Eastern Time
on Monday, March 23, 2009.
Docket Numbers: ER08–1317–003.
Applicants: California Independent
System Operator Corp.
Description: Quarterly Report on
Process in Processing Interconnection
Requests and Motion for Extension of
Time of the California Independent
System Operator Corporation.
Filed Date: 02/27/2009.
Accession Number: 20090227–5220.
Comment Date: 5 p.m. Eastern Time
on Friday, March 20, 2009.
Docket Numbers: ER09–369–000.
Applicants: PJM Interconnection
L.L.C.
Description: PJM Interconnection,
LLC submits response to FERC 1/3/09
deficiency notice requesting PJM to
provide additional information re its
proposed change to the PJM Open
Access Transmission Tariff, etc.
Filed Date: 03/02/2009.
Accession Number: 20090305–0052.
Comment Date: 5 p.m. Eastern Time
on Monday, March 23, 2009.
Any person desiring to intervene or to
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214) on or before 5 p.m. Eastern
time on the specified comment date. It
is not necessary to separately intervene
again in a subdocket related to a
compliance filing if you have previously
intervened in the same docket. Protests
will be considered by the Commission
in determining the appropriate action to
be taken, but will not serve to make
protestants parties to the proceeding.
Anyone filing a motion to intervene or
protest must serve a copy of that
document on the Applicant. In reference
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
not be served on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
VerDate Nov<24>2008
15:38 Mar 13, 2009
Jkt 217001
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please email FERCOnlineSupport@ferc.gov. or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. E9–5582 Filed 3–13–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP09–59–000]
Dominion Cove Point LNG, LP;
Environmental Assessment for the
Proposed Pipeline Compressor
Addition Project and Request for
Comments on Environmental Issues
March 9, 2009.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Pipeline Compressor Addition
Project (Project) involving construction
and operation of facilities by Dominion
Cove Point LNG, LP (Cove Point) in
Calvert County, Maryland.1 This EA
will be used by the Commission in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process we will use to
gather input from the public and
interested agencies on the project. Your
input will help the Commission staff
determine which issues need to be
evaluated in the EA. Please note that the
scoping period will close on April 8,
2009.
This notice is being sent to affected
landowners; Federal, State, and local
government representatives and
1 On February 3, 2009, Cove Point filed its
application with the Commission under section 7
of the Natural Gas Act and Part 157 of the
Commission’s regulations. The Commission issued
its Notice of Application on February 18, 2009.
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. State and local
government representatives are asked to
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
A brochure prepared by the FERC
entitled ‘‘A Guide to LNG—What All
Citizens Should Know’’ is available for
viewing on the FERC Internet Web site
(https://www.ferc.gov). This brochure
addresses a number of typically asked
questions, including what is LNG and
how is it transported.
Summary of the Proposed Project
Cove Point is proposing to construct,
install and operate on land owned by
Cove Point:
• One 3,500 horsepower (HP) electric
motor driven reciprocating compressor
unit;
• Associated compressor piping;
• Electrical connections for power;
• System controls;
• Approximately 900 feet of 6-inch
pipeline to replace existing 4-inch 108J
discharge pipeline;
• Coalescing separator to replace
existing coalescing separator; and
• Boil-off gas (BOG) turbine meter to
replace existing BOG turbine meter.
The general location of the project
facilities is shown in Appendix 1.2
If approved, Cove Point proposes to
commence construction of the proposed
facilities in the beginning of May 2009
in order to meet an in-service date of
early fourth quarter 2009.
Land Requirements for Construction
Construction of the project would
occur entirely on previously developed
property inside the existing 136 acre
fenced area for terminal operations and
within the existing 1,017 acre Cove
Point terminal site. The temporary
footprint of the project construction area
would take place on approximately 2
acres or less of previously disturbed
land. The permanent footprint of the
project area would affect less than 0.1
acre of previously disturbed land
currently covered in stone.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices are available on the Commission’s Web
site at the ‘‘eLibrary’’ link or from the Commission’s
Public Reference Room, 888 First Street, NE.,
Washington, DC 20426, or call (202) 502–8371. For
instructions on connecting to eLibrary, refer to the
last page of this notice. Copies of the appendices
were sent to all those receiving this notice in the
mail.
E:\FR\FM\16MRN1.SGM
16MRN1
Federal Register / Vol. 74, No. 49 / Monday, March 16, 2009 / Notices
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, the Commission staff
requests public comments on the scope
of the issues to address in the EA. All
comments received are considered
during the preparation of the EA. State
and local government representatives
are encouraged to notify their
constituents of this proposed action and
encourage them to comment on their
areas of concern.
In the EA we 3 will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils.
• Land use.
• Water resources, fisheries, and
wetlands.
• Cultural resources.
• Vegetation and wildlife.
• Air quality and noise.
• Endangered and threatened species.
• Public safety.
We will also evaluate possible
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to federal, state,
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission. To ensure your comments
are considered, please carefully follow
the instructions in the public
participation section below.
With this NOI, we are asking Federal,
state, and local agencies with
jurisdiction and/or special expertise
with respect to environmental issues to
formally cooperate with us in the
preparation of the EA. These agencies
3 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects
(OEP).
VerDate Nov<24>2008
15:38 Mar 13, 2009
Jkt 217001
may choose to participate once they
have evaluated the proposal relative to
their responsibilities. Additional
agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this NOI.
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
proposed facilities and the
environmental information provided by
Cove Point. This preliminary list of
issues may be changed based on your
comments and our analysis.
• The operation of the proposed
compressor would contribute to noise
generated by the existing Cove Point
facility.
• No impacts would occur to water
resources, fisheries, wetlands,
vegetation or wildlife. Other than air
quality and noise, all impacts would
occur within existing Cove Point
property.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before April 8,
2009.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number CP09–59–000 with your
submission. The Commission
encourages electronic filing of
comments and has dedicated eFiling
expert staff available to assist you at
202–502–8258 or efiling@ferc.gov.
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located on
the Commission’s internet Web site
at&fnl; https://www.ferc.gov under the
link to Documents and Filings. A Quick
Comment is an easy method for
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s internet Web site at
https://www.ferc.gov under the link to
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
11095
Documents and Filings. eFiling involves
preparing your submission in the same
manner as you would if filing on paper,
and then saving the file on your
computer’s hard drive. You will attach
that file as your submission. New
eFiling users must first create an
account by clicking on ‘‘Sign up’’ or
‘‘eRegister.’’ You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing’’; or
(3) You may file your comments via
mail to the Commission by sending an
original and two copies of your letter to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First St., NE., Room 1A, Washington, DC
20426. Label one copy of the comments
for the attention of Gas Branch 3, PJ11.3.
Environmental Mailing List
An effort is being made to send this
notice to all individuals, organizations,
and government entities interested in
and/or potentially affected by the
proposed project. This includes all
landowners who are potential right-ofway grantors, whose property may be
used temporarily for project purposes,
or who own homes within distances
defined in the Commission’s regulations
of certain aboveground facilities.
If you do not want to send comments
at this time but still want to remain on
our mailing list, please return the
Information Request (Appendix 2). If
you do not return the Information
Request, you will be taken off the
mailing list.
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor,’’ which is an
official party to the proceeding.
Intervenors play a more formal role in
the process and are able to file briefs,
appear at hearings, and be heard by the
courts if they choose to appeal the
Commission’s final ruling. An
intervenor formally participates in a
Commission proceeding by filing a
request to intervene. Instructions for
becoming an intervenor are included in
the User’s Guide under the ‘‘e-filing’’
link on the Commission’s Web site.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the eLibrary link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
E:\FR\FM\16MRN1.SGM
16MRN1
11096
Federal Register / Vol. 74, No. 49 / Monday, March 16, 2009 / Notices
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–5559 Filed 3–13–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. RP08–591–002]
Equitrans LP; Notice of Filing
March 9, 2009.
Take notice that on March 5, 2009,
Equitrans, L.P. filed an offer of
settlement in the form of a Stipulation
and Agreement resolving all issues
concerning Equitrans’ Tennessee
Capacity Surcharge Tracker.
Any person desiring to intervene or to
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214) on or before 5 p.m. Eastern
time on the date as indicated below. It
is not necessary to separately intervene
again in a subdocket related to a
compliance filing if you have previously
intervened in the same docket. Protests
will be considered by the Commission
in determining the appropriate action to
be taken, but will not serve to make
protestants parties to the proceeding.
Anyone filing a motion to intervene or
protest must serve a copy of that
document on the Applicant. In reference
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
VerDate Nov<24>2008
15:38 Mar 13, 2009
Jkt 217001
not be served on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please email FERCOnlineSupport@ferc.gov. or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on Friday, March 13, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–5551 Filed 3–13–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
withdrawal of Northern Virginia Electric
Cooperative from ODEC.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time on
March 17, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–5555 Filed 3–13–09; 8:45 am]
[Docket No. ER09–804–000]
BILLING CODE 6717–01–P
PJM Interconnection, LLC; Notice of
Filing
DEPARTMENT OF ENERGY
March 9, 2009.
Take notice that on March 6, 2009,
pursuant to Rule 207(a)(5) of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure, 18 CFR 385.207(a)(5), PJM
Interconnection, LLC filed a request for
limited tariff waiver as may be
necessary to implement the allocation of
Auction Revenue Rights pursuant to the
Notice of Cancellation of the Amended
and Restated Wholesale Power Contract
filed with the Commission on
September 8, 2008, by Old Dominion
Electric Cooperative (ODEC) to effect the
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[Docket No. ER09–779–000]
Nordic Energy Services, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
March 9, 2009.
This is a supplemental notice in the
above-referenced proceeding of Nordic
Energy Services, LLC’s application for
E:\FR\FM\16MRN1.SGM
16MRN1
Agencies
[Federal Register Volume 74, Number 49 (Monday, March 16, 2009)]
[Notices]
[Pages 11094-11096]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-5559]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP09-59-000]
Dominion Cove Point LNG, LP; Environmental Assessment for the
Proposed Pipeline Compressor Addition Project and Request for Comments
on Environmental Issues
March 9, 2009.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Pipeline Compressor Addition
Project (Project) involving construction and operation of facilities by
Dominion Cove Point LNG, LP (Cove Point) in Calvert County,
Maryland.\1\ This EA will be used by the Commission in its decision-
making process to determine whether the project is in the public
convenience and necessity.
---------------------------------------------------------------------------
\1\ On February 3, 2009, Cove Point filed its application with
the Commission under section 7 of the Natural Gas Act and Part 157
of the Commission's regulations. The Commission issued its Notice of
Application on February 18, 2009.
---------------------------------------------------------------------------
This notice announces the opening of the scoping process we will
use to gather input from the public and interested agencies on the
project. Your input will help the Commission staff determine which
issues need to be evaluated in the EA. Please note that the scoping
period will close on April 8, 2009.
This notice is being sent to affected landowners; Federal, State,
and local government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. State and local
government representatives are asked to notify their constituents of
this planned project and encourage them to comment on their areas of
concern.
A brochure prepared by the FERC entitled ``A Guide to LNG--What All
Citizens Should Know'' is available for viewing on the FERC Internet
Web site (https://www.ferc.gov). This brochure addresses a number of
typically asked questions, including what is LNG and how is it
transported.
Summary of the Proposed Project
Cove Point is proposing to construct, install and operate on land
owned by Cove Point:
One 3,500 horsepower (HP) electric motor driven
reciprocating compressor unit;
Associated compressor piping;
Electrical connections for power;
System controls;
Approximately 900 feet of 6-inch pipeline to replace
existing 4-inch 108J discharge pipeline;
Coalescing separator to replace existing coalescing
separator; and
Boil-off gas (BOG) turbine meter to replace existing BOG
turbine meter.
The general location of the project facilities is shown in Appendix
1.\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of all appendices are
available on the Commission's Web site at the ``eLibrary'' link or
from the Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
Copies of the appendices were sent to all those receiving this
notice in the mail.
---------------------------------------------------------------------------
If approved, Cove Point proposes to commence construction of the
proposed facilities in the beginning of May 2009 in order to meet an
in-service date of early fourth quarter 2009.
Land Requirements for Construction
Construction of the project would occur entirely on previously
developed property inside the existing 136 acre fenced area for
terminal operations and within the existing 1,017 acre Cove Point
terminal site. The temporary footprint of the project construction area
would take place on approximately 2 acres or less of previously
disturbed land. The permanent footprint of the project area would
affect less than 0.1 acre of previously disturbed land currently
covered in stone.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to
[[Page 11095]]
take into account the environmental impacts that could result from an
action whenever it considers the issuance of a Certificate of Public
Convenience and Necessity. NEPA also requires us to discover and
address concerns the public may have about proposals. This process is
referred to as ``scoping.'' The main goal of the scoping process is to
focus the analysis in the EA on the important environmental issues. By
this Notice of Intent, the Commission staff requests public comments on
the scope of the issues to address in the EA. All comments received are
considered during the preparation of the EA. State and local government
representatives are encouraged to notify their constituents of this
proposed action and encourage them to comment on their areas of
concern.
In the EA we \3\ will discuss impacts that could occur as a result
of the construction and operation of the proposed project under these
general headings:
---------------------------------------------------------------------------
\3\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
Geology and soils.
Land use.
Water resources, fisheries, and wetlands.
Cultural resources.
Vegetation and wildlife.
Air quality and noise.
Endangered and threatened species.
Public safety.
We will also evaluate possible alternatives to the proposed project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to federal, state, and local agencies, public
interest groups, interested individuals, affected landowners,
newspapers, libraries, and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission. To ensure your comments are
considered, please carefully follow the instructions in the public
participation section below.
With this NOI, we are asking Federal, state, and local agencies
with jurisdiction and/or special expertise with respect to
environmental issues to formally cooperate with us in the preparation
of the EA. These agencies may choose to participate once they have
evaluated the proposal relative to their responsibilities. Additional
agencies that would like to request cooperating agency status should
follow the instructions for filing comments provided under the Public
Participation section of this NOI.
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the proposed facilities and
the environmental information provided by Cove Point. This preliminary
list of issues may be changed based on your comments and our analysis.
The operation of the proposed compressor would contribute
to noise generated by the existing Cove Point facility.
No impacts would occur to water resources, fisheries,
wetlands, vegetation or wildlife. Other than air quality and noise, all
impacts would occur within existing Cove Point property.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send in your comments
so that they will be received in Washington, DC on or before April 8,
2009.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the project docket number CP09-59-000 with your submission.
The Commission encourages electronic filing of comments and has
dedicated eFiling expert staff available to assist you at 202-502-8258
or efiling@ferc.gov.
(1) You may file your comments electronically by using the Quick
Comment feature, which is located on the Commission's internet Web site
at&fnl; https://www.ferc.gov under the link to Documents and Filings. A
Quick Comment is an easy method for interested persons to submit text-
only comments on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's internet Web site at
https://www.ferc.gov under the link to Documents and Filings. eFiling
involves preparing your submission in the same manner as you would if
filing on paper, and then saving the file on your computer's hard
drive. You will attach that file as your submission. New eFiling users
must first create an account by clicking on ``Sign up'' or
``eRegister.'' You will be asked to select the type of filing you are
making. A comment on a particular project is considered a ``Comment on
a Filing''; or
(3) You may file your comments via mail to the Commission by
sending an original and two copies of your letter to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First St., NE.,
Room 1A, Washington, DC 20426. Label one copy of the comments for the
attention of Gas Branch 3, PJ11.3.
Environmental Mailing List
An effort is being made to send this notice to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project. This includes all landowners who are
potential right-of-way grantors, whose property may be used temporarily
for project purposes, or who own homes within distances defined in the
Commission's regulations of certain aboveground facilities.
If you do not want to send comments at this time but still want to
remain on our mailing list, please return the Information Request
(Appendix 2). If you do not return the Information Request, you will be
taken off the mailing list.
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor,'' which is an official party to the
proceeding. Intervenors play a more formal role in the process and are
able to file briefs, appear at hearings, and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in a Commission proceeding by filing a request to
intervene. Instructions for becoming an intervenor are included in the
User's Guide under the ``e-filing'' link on the Commission's Web site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on ``General Search'' and enter the
docket number excluding the last three digits in the Docket Number
field. Be sure you have selected
[[Page 11096]]
an appropriate date range. For assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676,
or for TTY, contact (202) 502-8659. The eLibrary link also provides
access to the texts of formal documents issued by the Commission, such
as orders, notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/
EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-5559 Filed 3-13-09; 8:45 am]
BILLING CODE 6717-01-P