Atmos Pipeline and Storage, LLC; Notice of Availability of the Environmental Assessment for the Proposed Fort Necessity Gas Storage Project, 10729-10730 [E9-5247]
Download as PDF
Federal Register / Vol. 74, No. 47 / Thursday, March 12, 2009 / Notices
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on March 16, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–5260 Filed 3–11–09; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP09–22–000]
Atmos Pipeline and Storage, LLC;
Notice of Availability of the
Environmental Assessment for the
Proposed Fort Necessity Gas Storage
Project
cprice-sewell on PRODPC61 with NOTICES
March 4, 2009.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared an
environmental assessment (EA) on the
natural gas pipeline facilities proposed
by Atmos Pipeline and Storage, LLC
(Atmos) in the above-referenced docket.
The EA was prepared to satisfy the
requirements of the National
Environmental Policy Act. The staff
concludes that approval of the proposed
project, with appropriate mitigating
measures, would not constitute a major
federal action significantly affecting the
quality of the human environment.
The EA assesses the potential
environmental effects of the
construction and operation of the
proposed natural gas storage and
pipeline facilities including:
Storage facilities:
• Three 8.25 billion cubic feet (Bcf)
salt dome storage caverns (24.75 Bcf
total) with a total working capacity of
15.0 Bcf of natural gas, each with a well
and well pad for solution mining and
subsequent gas injection/withdrawal;
• One leaching plant with associated
pumps, tanks, and piping;
• Nine water supply wells;
• Nine brine disposal wells;
• Two collocated 0.9-mile-long, 30inch-diameter gas pipelines from the
compressor station to the three cavern
wells;
• 0.4 mile of 2-inch-diameter diesel
injection pipeline extending from the
leaching plant to the three cavern wells;
• 0.4 mile of 2-inch-diameter
instrument air pipeline extending from
the leaching plant to the three cavern
wells;
• 1.7 miles of varying diameter high
density polyethylene (HDPE) water
supply pipeline extending from the
VerDate Nov<24>2008
14:56 Mar 11, 2009
Jkt 217001
water supply wells to the leaching
plant;
• 0.4 mile of 20-inch-diameter steel
pipeline feeding high pressure water
extending from the leaching plant to the
three cavern wells;
• 0.4 mile of 22-inch-diameter HDPE
pipeline to return brine from the three
cavern wells to the leaching plant;
• 5.5 miles of varying diameter steel
brine disposal pipeline extending from
the leaching plant to the brine disposal;
• Related delivery piping, line
heaters, pressure vessels, and valves
along with other appurtenant facilities;
and
• One electrical substation consisting
of two 15/20 mega volt ampere
transformers.
Interconnect pipeline facilities:
• One compressor station with nine
4,700 horsepower (hp)-rated natural gas
driven reciprocating compressors,
totaling 42,300 hp;
• One dehydration facility;
• Four meter stations;
• Two collocated 0.01-mile-long (70foot-long), 36-inch-diameter
interconnect gas pipelines with one
metering station to tie in to Tennessee
Gas Pipeline’s (TGP) existing 30-inchdiameter pipeline;
• Two collocated 0.8-mile-long, 36inch-diameter interconnect gas
pipelines with one metering station to
tie into Columbia Gulf Transmission’s
(CGT) existing 30- and 36-inch-diameter
pipelines, continuing northwest from
the proposed TGP metering station site;
• Two collocated 6.5-mile-long 30inch-diameter interconnect gas
pipelines with two metering stations
collocated within the same fenced area
to tie into ANR Pipeline Company’s
(ANR) existing 30- and 36-inch-diameter
pipelines and to the existing 30-inchdiameter Winnsboro Extension of the
Regency Energy Partners’ (Regency)
pipeline, continuing north from the
proposed CGT metering station site; and
• All related facilities.
Atmos states that the project would
provide new storage. It would
interconnect with the existing interstate
pipelines operated by TGP, CGT, and
ANR, and the intrastate pipeline
operated by Regency. All proposed
facilities would be constructed and
operated in Franklin Parish, Louisiana.
Atmos proposes beginning construction
in 2009 and to have Cavern No. 1 in
service by 2011, Cavern No. 2 in service
by 2013, and Cavern No. 3 in service by
2015.
The EA has been placed in the public
files of the FERC. A limited number of
copies of the EA are available for
distribution and public inspection at:
Federal Energy Regulatory Commission,
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
10729
Public Reference Room, 888 First Street,
NE., Room 2A, Washington, DC 20426,
(202) 502–8371.
Copies of the EA have been mailed to
federal, state, and local agencies; public
interest groups; interested individuals
and affected landowners; Native
American tribes; newspapers and
libraries; and parties to this proceeding.
Any person wishing to comment on
the EA may do so. To ensure
consideration prior to a Commission
decision on the proposal, it is important
that we receive your comments before
the date specified below.
You can make a difference by
providing us with your specific
comments or concerns about the Fort
Necessity Gas Storage Project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. The more
specific your comments, the more useful
they will be. To ensure that your
comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before April 3,
2009.
For your convenience, there are three
methods in which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number CP09–22–000 with your
submission. The docket number can be
found on the front of this notice. The
Commission encourages electronic filing
of comments and has dedicated eFiling
expert staff available to assist you at
202–502–8258 or efiling@ferc.gov.
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located on
the Commission’s internet Web site at
https://www.ferc.gov under the link to
Documents and Filings. A Quick
Comment is an easy method for
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s internet Web site at
https://www.ferc.gov under the link to
Documents and Filings. eFiling involves
preparing your submission in the same
manner as you would if filing on paper,
and then saving the file on your
computer’s hard drive. You will attach
that file as your submission. New
eFiling users must first create an
account by clicking on ‘‘Sign up’’ or
‘‘eRegister.’’ You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing;’’ or
(3) You may file your comments via
mail to the Commission by sending an
E:\FR\FM\12MRN1.SGM
12MRN1
10730
Federal Register / Vol. 74, No. 47 / Thursday, March 12, 2009 / Notices
cprice-sewell on PRODPC61 with NOTICES
original and two copies of your letter to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First St., NE, Room 1A, Washington, DC
20426.
Label one copy of the comments for
the attention of Gas Branch 2, PJ11.2.
Comments will be considered by the
Commission but will not serve to make
the commentor a party to the
proceeding. Any person seeking to
become a party to the proceeding must
file a motion to intervene pursuant to
Rule 214 of the Commission’s Rules of
Practice and Procedures (18 CFR
385.214).1 Only intervenors have the
right to seek rehearing of the
Commission’s decision.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
comments considered.
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208-FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the eLibrary link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–5247 Filed 3–11–09; 8:45 am]
BILLING CODE 6717–01–P
1 Interventions may also be filed electronically via
the Internet in lieu of paper. See the previous
discussion on filing comments electronically.
VerDate Nov<24>2008
14:56 Mar 11, 2009
Jkt 217001
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Docket Nos. CP07–406–003]
[Docket No. QF08–564–000]
Georgia Pacific Toledo LLC; Notice of
Filing of Notice of Self-Certification of
Qualifying Status of a Cogeneration
Facility
March 5, 2009.
Take notice that on May 15, 2008,
Georgia Pacific Toledo LLC (‘‘GP’’),
1400 SE. Butler Bridge Road, Toledo,
Oregon 97391, filed with the Federal
Energy Regulatory Commission a notice
of self-certification of a facility as a
qualifying cogeneration facility
pursuant to 18 CFR 292.207(a) of the
Commission’s regulations.
GP states that the facility in question
is a topping-cycle cogeneration facility
with a primary energy source of natural
gas. The cogeneration facility consists of
two black liquor recovery boilers, three
power boilers, and one hog fuel (bark)
boiler to generate electricity and process
heat to serve the resident paper mill.
The facility is located in Toledo,
Oregon.
GP further states that the facility is
interconnected to Central Lincoln PUD
(‘‘Lincoln’’), and expects from time-totime to sell energy to or purchase
supplementary, standby, back-up, and
maintenance power from Lincoln.
A notice of self-certification does not
institute a proceeding regarding
qualifying facility status; a notice of selfcertification provides notice that the
entity making filing has determined the
Facility meets the applicable criteria to
be a qualifying facility. Any person
seeking to challenge such qualifying
facility status may do so by filing a
motion pursuant to 18 CFR
292.207(d)(iii).
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–5262 Filed 3–11–09; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
Monroe Gas Storage Company, LLC;
Notice of Filing
March 4, 2009.
Take notice that on February 23, 2009,
Monroe Gas Storage Company, LLC
(Monroe Gas), 1200 17th Street, Suite
2100, Denver, CO 80202, filed an
application, pursuant to section 7 of the
Natural Gas Act (NGA) and Part 157 of
the Commission’s Rules and
Regulations, for limited amendment to
its certificate of public convenience and
necessity issued on December 21, 2007
under Docket No. CP07–406–000.
Monroe Gas seeks authorization to
implement its Revised Well Plan Project
at the certificated gas storage field
currently under construction in Monroe
County, Mississippi (Project). The
application is on file with the
Commission and open for public
inspection. This filing is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or toll
free at (866)208–3676, or for TTY,
contact (202) 502–8659.
The Project will involve the relocation
of two wells, the addition of eight new
wells, and related changes to ancillary
facilities, including well pads, gathering
pipelines and access roads. There will
be no changes to the certificated
compression and control facilities.
Monroe Gas does not seek to change the
overall physical capabilities of the
certificated gas storage field. The Project
will affect a total of approximately 33.41
acres of land which located within the
boundaries of the storage field as
previously certificated.
Any questions regarding the
application are to be directed to William
B. Mathews, Monroe Gas Storage
Company, LLC, 1200 17th Street, Suite
2100, Denver, CO 80202, (303) 951–
4282.
Any person wishing to obtain legal
status by becoming a party to the
proceedings for this project should, on
or before the below listed comment
date, file with the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426, a
motion to intervene in accordance with
E:\FR\FM\12MRN1.SGM
12MRN1
Agencies
[Federal Register Volume 74, Number 47 (Thursday, March 12, 2009)]
[Notices]
[Pages 10729-10730]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-5247]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP09-22-000]
Atmos Pipeline and Storage, LLC; Notice of Availability of the
Environmental Assessment for the Proposed Fort Necessity Gas Storage
Project
March 4, 2009.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared an environmental assessment (EA) on the
natural gas pipeline facilities proposed by Atmos Pipeline and Storage,
LLC (Atmos) in the above-referenced docket.
The EA was prepared to satisfy the requirements of the National
Environmental Policy Act. The staff concludes that approval of the
proposed project, with appropriate mitigating measures, would not
constitute a major federal action significantly affecting the quality
of the human environment.
The EA assesses the potential environmental effects of the
construction and operation of the proposed natural gas storage and
pipeline facilities including:
Storage facilities:
Three 8.25 billion cubic feet (Bcf) salt dome storage
caverns (24.75 Bcf total) with a total working capacity of 15.0 Bcf of
natural gas, each with a well and well pad for solution mining and
subsequent gas injection/withdrawal;
One leaching plant with associated pumps, tanks, and
piping;
Nine water supply wells;
Nine brine disposal wells;
Two collocated 0.9-mile-long, 30-inch-diameter gas
pipelines from the compressor station to the three cavern wells;
0.4 mile of 2-inch-diameter diesel injection pipeline
extending from the leaching plant to the three cavern wells;
0.4 mile of 2-inch-diameter instrument air pipeline
extending from the leaching plant to the three cavern wells;
1.7 miles of varying diameter high density polyethylene
(HDPE) water supply pipeline extending from the water supply wells to
the leaching plant;
0.4 mile of 20-inch-diameter steel pipeline feeding high
pressure water extending from the leaching plant to the three cavern
wells;
0.4 mile of 22-inch-diameter HDPE pipeline to return brine
from the three cavern wells to the leaching plant;
5.5 miles of varying diameter steel brine disposal
pipeline extending from the leaching plant to the brine disposal;
Related delivery piping, line heaters, pressure vessels,
and valves along with other appurtenant facilities; and
One electrical substation consisting of two 15/20 mega
volt ampere transformers.
Interconnect pipeline facilities:
One compressor station with nine 4,700 horsepower (hp)-
rated natural gas driven reciprocating compressors, totaling 42,300 hp;
One dehydration facility;
Four meter stations;
Two collocated 0.01-mile-long (70-foot-long), 36-inch-
diameter interconnect gas pipelines with one metering station to tie in
to Tennessee Gas Pipeline's (TGP) existing 30-inch-diameter pipeline;
Two collocated 0.8-mile-long, 36-inch-diameter
interconnect gas pipelines with one metering station to tie into
Columbia Gulf Transmission's (CGT) existing 30- and 36-inch-diameter
pipelines, continuing northwest from the proposed TGP metering station
site;
Two collocated 6.5-mile-long 30-inch-diameter interconnect
gas pipelines with two metering stations collocated within the same
fenced area to tie into ANR Pipeline Company's (ANR) existing 30- and
36-inch-diameter pipelines and to the existing 30-inch-diameter
Winnsboro Extension of the Regency Energy Partners' (Regency) pipeline,
continuing north from the proposed CGT metering station site; and
All related facilities.
Atmos states that the project would provide new storage. It would
interconnect with the existing interstate pipelines operated by TGP,
CGT, and ANR, and the intrastate pipeline operated by Regency. All
proposed facilities would be constructed and operated in Franklin
Parish, Louisiana. Atmos proposes beginning construction in 2009 and to
have Cavern No. 1 in service by 2011, Cavern No. 2 in service by 2013,
and Cavern No. 3 in service by 2015.
The EA has been placed in the public files of the FERC. A limited
number of copies of the EA are available for distribution and public
inspection at: Federal Energy Regulatory Commission, Public Reference
Room, 888 First Street, NE., Room 2A, Washington, DC 20426, (202) 502-
8371.
Copies of the EA have been mailed to federal, state, and local
agencies; public interest groups; interested individuals and affected
landowners; Native American tribes; newspapers and libraries; and
parties to this proceeding.
Any person wishing to comment on the EA may do so. To ensure
consideration prior to a Commission decision on the proposal, it is
important that we receive your comments before the date specified
below.
You can make a difference by providing us with your specific
comments or concerns about the Fort Necessity Gas Storage Project. Your
comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. The more specific your comments, the more useful they will be.
To ensure that your comments are timely and properly recorded, please
send in your comments so that they will be received in Washington, DC
on or before April 3, 2009.
For your convenience, there are three methods in which you can use
to submit your comments to the Commission. In all instances please
reference the project docket number CP09-22-000 with your submission.
The docket number can be found on the front of this notice. The
Commission encourages electronic filing of comments and has dedicated
eFiling expert staff available to assist you at 202-502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the Quick
Comment feature, which is located on the Commission's internet Web site
at https://www.ferc.gov under the link to Documents and Filings. A Quick
Comment is an easy method for interested persons to submit text-only
comments on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's internet Web site at
https://www.ferc.gov under the link to Documents and Filings. eFiling
involves preparing your submission in the same manner as you would if
filing on paper, and then saving the file on your computer's hard
drive. You will attach that file as your submission. New eFiling users
must first create an account by clicking on ``Sign up'' or
``eRegister.'' You will be asked to select the type of filing you are
making. A comment on a particular project is considered a ``Comment on
a Filing;'' or
(3) You may file your comments via mail to the Commission by
sending an
[[Page 10730]]
original and two copies of your letter to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First St., NE, Room 1A,
Washington, DC 20426.
Label one copy of the comments for the attention of Gas Branch 2,
PJ11.2.
Comments will be considered by the Commission but will not serve to
make the commentor a party to the proceeding. Any person seeking to
become a party to the proceeding must file a motion to intervene
pursuant to Rule 214 of the Commission's Rules of Practice and
Procedures (18 CFR 385.214).\1\ Only intervenors have the right to seek
rehearing of the Commission's decision.
---------------------------------------------------------------------------
\1\ Interventions may also be filed electronically via the
Internet in lieu of paper. See the previous discussion on filing
comments electronically.
---------------------------------------------------------------------------
Affected landowners and parties with environmental concerns may be
granted intervenor status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which would not be
adequately represented by any other parties. You do not need intervenor
status to have your comments considered.
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on ``General Search'' and enter the
docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-5247 Filed 3-11-09; 8:45 am]
BILLING CODE 6717-01-P