Download as PDF Federal Register / Vol. 74, No. 42 / Thursday, March 5, 2009 / Notices AGENDA: The Commission will receive presentations on the following topic: Voter Registration Databases: Initial Discussion on Reviewing HAVA Mandated Guidance. This hearing will be open to the public. PERSON TO CONTACT FOR INFORMATION: Bryan Whitener. Telephone: (202) 566– 3100. Alice Miller, Chief Operating Officer, U.S. Election Assistance Commission. [FR Doc. E9–4760 Filed 3–3–09; 11:15 am] BILLING CODE 6820–KF–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13345–000] Shearwater Design Inc.; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13345–000) in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3372. Kimberly D. Bose, Secretary. [FR Doc. E9–4716 Filed 3–4–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY jlentini on PROD1PC65 with NOTICES February 26, 2009. On December 15, 2008, and supplemented on February 5, 2009, and February 24, 2009, Shearwater Design Inc. filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Homeowner Tidal Power Electric Generation Project located on the Kennebec River in Sagadahoc County, Maine. The project uses no dam or impoundment. The proposed project would consist of: (1) 6 hydrokinetic turbine units that would be directly connected to individual homes, with a total installed capacity of 60-kilowatts, and (2) appurtenant facilities. The project is estimated to have an annual generation of 150,000-kilowatt-hours, which would be used by the homeowners and net metered back into the electricity power grid. Applicant Contact: Ms. Dot Kelly, Shearwater Design Inc., 83 Captain Perry Drive, Phippsburg, Maine 04562, phone: (207) 443–4787. FERC Contact: Kelly T. Houff (202) 502–6393. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions VerDate Nov<24>2008 16:49 Mar 04, 2009 Jkt 217001 Federal Energy Regulatory Commission [Project No. 13347–000] Wells Rural Electric Company; Notice of Application for Preliminary Permit Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests 9605 Suite A, Reno, NV 89511, (775) 852– 1440. FERC Contact: Jake Tung, (202) 502– 8757. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket number (P–13347) in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3372. Kimberly D. Bose, Secretary. [FR Doc. E9–4705 Filed 3–4–09; 8:45 am] BILLING CODE 6717–01–P February 25, 2009. On December 18, 2008, Wells Rural Electric Company filed an application, pursuant to section 4(f) of the Federal Power Act (FPA), to study the proposed Bishop Creek Dam Water Power Project. The proposed project would be located on Bishop Creek or Bishop Creek Reservoir in Elko, Nevada. The existing Bishop Dam is federally owned and/or operated by the Bureau of Land Management. The proposed project would consist of: (1) A new dam of 79-foot high and crest of 408.7-foot long; (2) a reservoir holding 17,167-acre-foot of water at normal pool elevation at 5,923 feet; (3) a new 4 mile-long, 25-kilovolt transmission line; (4) a powerhouse containing one generating unit with one megawatts (MW) capacity; and (5) appurtenant facilities. The proposed project would have the potential for annual generation of 8.766 gigawatthours (GWh). Applicant Contact: Mr. Dan Dyer or Andrew Hammond, Dyer Engineering Consultants Inc., 5442 Longley Lane, PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Attendance at Nepool Meetings February 26, 2009. The Federal Energy Regulatory Commission hereby gives notice that members of the Commission and Commission staff may attend the following upcoming NEPOOL meetings: • NEPOOL Participants Committee; • March 6 (Manchester, VT); • April 3 (Boston, MA); • May 1 (Location TBD); • June 5 (Location TBD); • June 23 (Location TBD); • NEPOOL Markets Committee Meeting; • March 10–11 (Marlborough, MA); • March 25–26 (Location TBD); • April 6–7 (Westborough, MA); • May 12–13 (Marlborough, MA); • June 9–10 (Marlborough, MA). E:\FR\FM\05MRN1.SGM 05MRN1

Agencies

[Federal Register Volume 74, Number 42 (Thursday, March 5, 2009)]
[Notices]
[Page 9605]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-4705]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13347-000]


Wells Rural Electric Company; Notice of Application for 
Preliminary Permit Accepted for Filing and Soliciting Comments, Motions 
To Intervene, and Protests

February 25, 2009.
    On December 18, 2008, Wells Rural Electric Company filed an 
application, pursuant to section 4(f) of the Federal Power Act (FPA), 
to study the proposed Bishop Creek Dam Water Power Project. The 
proposed project would be located on Bishop Creek or Bishop Creek 
Reservoir in Elko, Nevada. The existing Bishop Dam is federally owned 
and/or operated by the Bureau of Land Management.
    The proposed project would consist of: (1) A new dam of 79-foot 
high and crest of 408.7-foot long; (2) a reservoir holding 17,167-acre-
foot of water at normal pool elevation at 5,923 feet; (3) a new 4 mile-
long, 25-kilovolt transmission line; (4) a powerhouse containing one 
generating unit with one megawatts (MW) capacity; and (5) appurtenant 
facilities. The proposed project would have the potential for annual 
generation of 8.766 gigawatt-hours (GWh).
    Applicant Contact: Mr. Dan Dyer or Andrew Hammond, Dyer Engineering 
Consultants Inc., 5442 Longley Lane, Suite A, Reno, NV 89511, (775) 
852-1440.
    FERC Contact: Jake Tung, (202) 502-8757.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Comments, motions to intervene, notices of intent, and competing 
applications may be filed electronically via the Internet. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original and eight 
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For 
more information on how to submit these types of filings please go to 
the Commission's Web site located at https://www.ferc.gov/filing-
comments.asp. More information about this project can be viewed or 
printed on the ``eLibrary'' link of the Commission's Web site at http:/
/www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P-
13347) in the docket number field to access the document. For 
assistance, call toll-free 1-866-208-3372.

Kimberly D. Bose,
Secretary.
 [FR Doc. E9-4705 Filed 3-4-09; 8:45 am]