Progress Energy Florida, Inc.; Establishment of Atomic Safety and Licensing Board, 9113 [E9-4338]
Download as PDF
Federal Register / Vol. 74, No. 39 / Monday, March 2, 2009 / Notices
South Carolina (located approximately 2
miles from the proposed VCSNS Units
2 and 3) requested an extension of the
scoping period. NRC staff has concluded
that Mayor Ginyard’s reasonable
request, coupled with comments
provided during the scoping meetings,
amounts to a special circumstance that
warrants an extension of the scoping
period.
The purpose of this notice is to inform
the public that the NRC is extending the
current scoping period by 30 days.
Members of the public may send written
comments on the scope of the VCSNS
COLs environmental review to the
Chief, Rulemaking, Directives and
Editing Branch, Office of
Administration, Mailstop TWB–05–
B01M, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, and should cite the publication
date and page number of this Federal
Register notice. To ensure that
comments will be considered, written
comments must be postmarked by April
6, 2009. Electronic comments may be
sent by e-mail to the NRC at
Summer.COLEIS@nrc.gov. Electronic
submissions must be sent no later than
April 6, 2009, to ensure that they will
be considered.
Information about the proposed
action, the EIS, and the scoping process
may be obtained from Ms. Patricia
Vokoun or Mr. Paul Michalak at 1–800–
368–5642, extensions 3470 or 7612,
respectively; at the U.S. Nuclear
Regulatory Commission, Mailstop T–
6D32, Washington, DC 20555–0001; or
via e-mail at Patricia.Vokoun@nrc.gov
or Paul.Michalak@nrc.gov.
Dated at Rockville, Maryland, this 24th day
of February 2009.
For the Nuclear Regulatory Commission.
Nilesh Chokshi,
Deputy Director, Division of Site and
Environmental Reviews, Office of New
Reactors.
[FR Doc. E9–4336 Filed 2–27–09; 8:45 am]
BILLING CODE 7590–01–P
notice is hereby given that an Atomic
Safety and Licensing Board (Board) is
being established to preside over the
following proceeding:
Progress Energy Florida, Inc.
Levy County Nuclear Power Plant, Units
1 and 2
This proceeding concerns a Petition to
Intervene and Request for Hearing from
the Green Party of Florida, the Ecology
Party of Florida, and Nuclear
Information and Resource Service,
which was submitted in response to a
December 8, 2008 Notice of Order,
Hearing, and Opportunity to Petition for
Leave to Intervene on a Combined
License for the Levy County Nuclear
Power Plant, Units 1 and 2 (73 FR
74,532). The petitioners challenge the
application filed by Progress Energy
Florida, Inc. pursuant to Subpart C of 10
CFR Part 52 for a combined license for
Levy County Nuclear Power Plant, Units
1 and 2, which would be located in
Levy County, Florida.
The Board is comprised of the
following administrative judges:
Alex S. Karlin, Chair, Atomic Safety and
Licensing Board Panel, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
Anthony J. Baratta, Atomic Safety and
Licensing Board Panel, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
William H. Murphy, Atomic Safety and
Licensing Board Panel, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
All correspondence, documents, and
other materials shall be filed in
accordance with the NRC E-Filing rule,
which the NRC promulgated in August
2007 (72 FR 49,139).
Issued at Rockville, Maryland, this 23rd
day of February 2009.
E. Roy Hawkens,
Chief Administrative Judge, Atomic Safety
and Licensing Board Panel.
[FR Doc. E9–4338 Filed 2–27–09; 8:45 am]
9113
Week of March 2, 2009
Wednesday, March 4, 2009
2:45 p.m. Discussion of Security
Issues (Closed—Ex. 1).
*
*
*
*
*
* The schedule for Commission
meetings is subject to change on short
notice. To verify the status of meetings,
call (recording)—(301) 415–1292.
Contact person for more information:
Rochelle Bavol, (301) 415–1651.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the Internet
at: https://www.nrc.gov/about-nrc/policymaking/schedule.html.
*
*
*
*
*
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.
braille, large print), please notify the
NRC’s Disability Program Coordinator,
Rohn Brown, at 301–492–2279, TDD:
301–415–2100, or by e-mail at
rohn.brown@nrc.gov. Determinations on
requests for reasonable accommodation
will be made on a case-by-case basis.
*
*
*
*
*
This notice is distributed by mail to
several hundred subscribers; if you no
longer wish to receive it, or would like
to be added to the distribution, please
contact the Office of the Secretary,
Washington, DC 20555 (301–415–1969).
In addition, distribution of this meeting
notice over the Internet system is
available. If you are interested in
receiving this Commission meeting
schedule electronically, please send an
electronic message to
darlene.wright@nrc.gov.
Dated: February 25, 2009.
Rochelle C. Bavol,
Office of the Secretary.
[FR Doc. E9–4436 Filed 2–26–09; 11:15 am]
BILLING CODE 7590–01–P
erowe on PROD1PC63 with NOTICES
Progress Energy Florida, Inc.;
Establishment of Atomic Safety and
Licensing Board
Pursuant to delegation by the
Commission dated December 29, 1972,
published in the Federal Register, 37 FR
28,710 (1972), and the Commission’s
regulations, see 10 CFR 2.104, 2.300,
2.303, 2.309, 2.311, 2.318, and 2.321,
VerDate Nov<24>2008
12:24 Feb 27, 2009
Jkt 217001
NUCLEAR REGULATORY
COMMISSION
Sunshine Federal Register Notice
[Docket Nos. 52–029–COL, 52–030–COL;
ASLBP No. 09–879–04–COL–BD01]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
NUCLEAR REGULATORY
COMMISSION
[NRC–2009–00]
AGENCY HOLDING THE MEETINGS: Nuclear
Regulatory Commission.
DATES: Week of March 2, 2009.
PLACE: Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public and Closed.
ADDITIONAL ITEMS TO BE CONSIDERED:
Office of Federal and State Materials
and Environmental Management
Programs, Annual Decommissioning
Report; Notice of Availability
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
AGENCY: Nuclear Regulatory
Commission.
ACTION: Notice of availability.
E:\FR\FM\02MRN1.SGM
02MRN1
Agencies
[Federal Register Volume 74, Number 39 (Monday, March 2, 2009)]
[Notices]
[Page 9113]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-4338]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 52-029-COL, 52-030-COL; ASLBP No. 09-879-04-COL-BD01]
Progress Energy Florida, Inc.; Establishment of Atomic Safety and
Licensing Board
Pursuant to delegation by the Commission dated December 29, 1972,
published in the Federal Register, 37 FR 28,710 (1972), and the
Commission's regulations, see 10 CFR 2.104, 2.300, 2.303, 2.309, 2.311,
2.318, and 2.321, notice is hereby given that an Atomic Safety and
Licensing Board (Board) is being established to preside over the
following proceeding:
Progress Energy Florida, Inc.
Levy County Nuclear Power Plant, Units 1 and 2
This proceeding concerns a Petition to Intervene and Request for
Hearing from the Green Party of Florida, the Ecology Party of Florida,
and Nuclear Information and Resource Service, which was submitted in
response to a December 8, 2008 Notice of Order, Hearing, and
Opportunity to Petition for Leave to Intervene on a Combined License
for the Levy County Nuclear Power Plant, Units 1 and 2 (73 FR 74,532).
The petitioners challenge the application filed by Progress Energy
Florida, Inc. pursuant to Subpart C of 10 CFR Part 52 for a combined
license for Levy County Nuclear Power Plant, Units 1 and 2, which would
be located in Levy County, Florida.
The Board is comprised of the following administrative judges:
Alex S. Karlin, Chair, Atomic Safety and Licensing Board Panel, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001.
Anthony J. Baratta, Atomic Safety and Licensing Board Panel, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001.
William H. Murphy, Atomic Safety and Licensing Board Panel, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001.
All correspondence, documents, and other materials shall be filed
in accordance with the NRC E-Filing rule, which the NRC promulgated in
August 2007 (72 FR 49,139).
Issued at Rockville, Maryland, this 23rd day of February 2009.
E. Roy Hawkens,
Chief Administrative Judge, Atomic Safety and Licensing Board Panel.
[FR Doc. E9-4338 Filed 2-27-09; 8:45 am]