Pacific Gas and Electric Company; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Fishway Prescriptions, 4954 [E9-1757]

Download as PDF 4954 Federal Register / Vol. 74, No. 17 / Wednesday, January 28, 2009 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 233–161] Pacific Gas and Electric Company; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Fishway Prescriptions sroberts on PROD1PC70 with NOTICES January 21, 2009. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Amendment of License. b. Project No.: 233–161. c. Date filed: December 5, 2008. d. Applicant: Pacific Gas and Electric Company. e. Name of Project: Pit 3, 4 & 5 Hydroelectric Project. f. Location: The project is located on the Pit River in Shasta County, California. The project occupies federal lands administered by the U.S. Forest Service. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a–825r. h. David Moller, Director, Hydro Licensing, Pacific Gas and Electric Company, P.O. Box 7770000, N11C– 1147, San Francisco, CA 94177–0001, telephone (415) 973–4696, Fax (415) 973–5121, DXMa@pge.com. i. FERC Contact: Anumzziatta Purchiaroni, Telephone (202) 502–6191, and e-mail anumzziatta.purchiaroni@FERC.gov. j. Deadline for filing motions to intervene and protests, comments, recommendations, preliminary terms and conditions, and preliminary fishway prescriptions is 60 days from the issuance of this notice; reply comments are due 105 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. k. Description of Request: The applicant proposes to amend the license for Pit 3, 4 & 5 Hydroelectric Project to construct a new powerhouse at the Pit 3 Dam, containing a single 2.8 MW turbine/generator unit with a hydraulic capacity of 370 cfs. The proposed Britton Powerhouse will be constructed within the existing project boundary, and would use the power potential of increased minimum instream flows VerDate Nov<24>2008 17:30 Jan 27, 2009 Jkt 217001 released as required under Article 401 of the license. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or e-mail FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210,.211,.214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: All filings must (1) bear in all capital letters the title ‘‘PROTEST’’, ‘‘MOTION TO INTERVENE’’, ‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’ ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘ FISHWAY PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, recommendations, terms and conditions or prescriptions should relate to project PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 works which are the subject of the license amendment. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. p. As provided for in 18 CFR 4.34(b)(5)(i), a license applicant must file, no later than 60 days following the date of issuance of this notice of acceptance and ready for environmental analysis: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. q. e-Filing: Motions to intervene, protests, comments, recommendations, terms and conditions, and fishway prescriptions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘e-Filing’’ link. Kimberly D. Bose, Secretary. [FR Doc. E9–1757 Filed 1–27–09; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EF09–4011–000] Southwestern Power Administration; Notice of Filing January 21, 2009. Take notice that on January 12, 2009, the Acting Deputy Secretary, U.S. Department of Energy, pursuant to the authority vested on the Deputy Secretary by the Department of Energy’s Delegation Order Nos. 00–001.00 (2001) and 00–001.00C (2007), and by sections 301(b), 302(a), 402(e), 641, 642, 643, and 644, of the Department of Energy Organization Act (Pub. L. 95–91), submitted final confirmation, approval, E:\FR\FM\28JAN1.SGM 28JAN1

Agencies

[Federal Register Volume 74, Number 17 (Wednesday, January 28, 2009)]
[Notices]
[Page 4954]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-1757]



[[Page 4954]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 233-161]


Pacific Gas and Electric Company; Notice of Application Accepted 
for Filing, Soliciting Motions To Intervene and Protests, Ready for 
Environmental Analysis, and Soliciting Comments, Recommendations, Terms 
and Conditions, and Fishway Prescriptions

January 21, 2009.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Amendment of License.
    b. Project No.: 233-161.
    c. Date filed: December 5, 2008.
    d. Applicant: Pacific Gas and Electric Company.
    e. Name of Project: Pit 3, 4 & 5 Hydroelectric Project.
    f. Location: The project is located on the Pit River in Shasta 
County, California. The project occupies federal lands administered by 
the U.S. Forest Service.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a-825r.
    h. David Moller, Director, Hydro Licensing, Pacific Gas and 
Electric Company, P.O. Box 7770000, N11C-1147, San Francisco, CA 94177-
0001, telephone (415) 973-4696, Fax (415) 973-5121, DXMa@pge.com.
    i. FERC Contact: Anumzziatta Purchiaroni, Telephone (202) 502-6191, 
and e-mail anumzziatta.purchiaroni@FERC.gov.
    j. Deadline for filing motions to intervene and protests, comments, 
recommendations, preliminary terms and conditions, and preliminary 
fishway prescriptions is 60 days from the issuance of this notice; 
reply comments are due 105 days from the issuance date of this notice. 
All documents (original and eight copies) should be filed with: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426.
    k. Description of Request: The applicant proposes to amend the 
license for Pit 3, 4 & 5 Hydroelectric Project to construct a new 
powerhouse at the Pit 3 Dam, containing a single 2.8 MW turbine/
generator unit with a hydraulic capacity of 370 cfs. The proposed 
Britton Powerhouse will be constructed within the existing project 
boundary, and would use the power potential of increased minimum 
instream flows released as required under Article 401 of the license.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street, NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. This filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. You may also 
register online at https://www.ferc.gov/docs-filing/esubscription.asp to 
be notified via e-mail of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or e-mail 
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 
385.210,.211,.214. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the title ``PROTEST'', ``MOTION TO 
INTERVENE'', ``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' 
``TERMS AND CONDITIONS,'' or `` FISHWAY PRESCRIPTIONS;'' (2) set forth 
in the heading the name of the applicant and the project number of the 
application to which the filing responds; (3) furnish the name, 
address, and telephone number of the person protesting or intervening; 
and (4) otherwise comply with the requirements of 18 CFR 385.2001 
through 385.2005. All comments, recommendations, terms and conditions 
or prescriptions must set forth their evidentiary basis and otherwise 
comply with the requirements of 18 CFR 4.34(b). All comments, 
recommendations, terms and conditions or prescriptions should relate to 
project works which are the subject of the license amendment. Agencies 
may obtain copies of the application directly from the applicant. A 
copy of any protest or motion to intervene must be served upon each 
representative of the applicant specified in the particular 
application. If an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency. A copy of all other 
filings in reference to this application must be accompanied by proof 
of service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 
385.2010.
    p. As provided for in 18 CFR 4.34(b)(5)(i), a license applicant 
must file, no later than 60 days following the date of issuance of this 
notice of acceptance and ready for environmental analysis: (1) A copy 
of the water quality certification; (2) a copy of the request for 
certification, including proof of the date on which the certifying 
agency received the request; or (3) evidence of waiver of water quality 
certification.
    q. e-Filing: Motions to intervene, protests, comments, 
recommendations, terms and conditions, and fishway prescriptions may be 
filed electronically via the Internet in lieu of paper. See, 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
at https://www.ferc.gov under the ``e-Filing'' link.

Kimberly D. Bose,
Secretary.