Detroit Edison Company; Notice of Hearing, and Opportunity To Petition for Leave To Intervene and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information and Safeguards Information for Contention Preparation on a Combined License for Fermi 3, 836-840 [E9-111]

Download as PDF 836 Federal Register / Vol. 74, No. 5 / Thursday, January 8, 2009 / Notices denying the amendment request would result in no change in current environmental impacts. The environmental impacts of the proposed action and the no-action alternative are therefore similar, and the no-action alternative is accordingly not further considered. Conclusion The NRC staff has concluded that the proposed action is consistent with the NRC’s unrestricted release criteria specified in 10 CFR 20.1402. Because the proposed action will not significantly impact the quality of the human environment, the NRC staff concludes that the proposed action is the preferred alternative. Agencies and Persons Consulted NRC provided a draft of this EA to the Commonwealth of Puerto Rico, Department of Health for review on October 29, 2008. On December 8, 2008, Commonwealth of Puerto Rico, Department of Health responded by email. The State agreed with the conclusions of the EA, and otherwise had no comments. The NRC staff has determined that the proposed action is of a procedural nature, and will not affect listed species or critical habitat. Therefore, no further consultation is required under Section 7 of the Endangered Species Act. The NRC staff has also determined that the proposed action is not the type of activity that has the potential to cause effects on historic properties. Therefore, no further consultation is required under Section 106 of the National Historic Preservation Act. erowe on PROD1PC63 with NOTICES III. Finding of No Significant Impact The NRC staff has prepared this EA in support of the proposed action. On the basis of this EA, the NRC finds that there are no significant environmental impacts from the proposed action, and that preparation of an environmental impact statement is not warranted. Accordingly, the NRC has determined that a Finding of No Significant Impact is appropriate. IV. Further Information Documents related to this action, including the application for license amendment and supporting documentation, are available electronically at the NRC’s Electronic Reading Room at https://www.nrc.gov/ reading-rm/adams.html. From this site, you can access the NRC’s Agencywide Document Access and Management System (ADAMS), which provides text and image files of NRC’s public documents. The documents related to VerDate Nov<24>2008 13:57 Jan 07, 2009 Jkt 217001 this action are listed below, along with their ADAMS accession numbers. 1. NUREG–1757, ‘‘Consolidated NMSS Decommissioning Guidance;’’ 2. Title 10 Code of Federal Regulations, Part 20, Subpart E, ‘‘Radiological Criteria for License Termination;’’ 3. Title 10, Code of Federal Regulations, Part 51, ‘‘Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions;’’ and 4. NUREG–1496, ‘‘Generic Environmental Impact Statement in Support of Rulemaking on Radiological Criteria for License Termination of NRCLicensed Nuclear Facilities.’’ 5. Termination request letter dated May 19, 2008, with the ‘‘Radiological Final Status Survey Report’’ [ML081690148] 6. Deficiency response letter dated October 3, 2008 [ML082840721] 7. E-mail dated October 17, 2008 re: MDC calculations [ML082940566] with attachment spreadsheet [ML082940570] If you do not have access to ADAMS, or if there are problems in accessing the documents located in ADAMS, contact the NRC Public Document Room (PDR) Reference staff at 1–800–397–4209, 301– 415–4737, or by e-mail to pdr@nrc.gov. These documents may also be viewed electronically on the public computers located at the NRC’s PDR, O 1 F21, One White Flint North, 11555 Rockville Pike, Rockville, MD 20852. The PDR reproduction contractor will copy documents for a fee. Dated at Region I at 475 Allendale Road, King of Prussia, PA this 30th day of December 2008. For the Nuclear Regulatory Commission. Pamela Henderson, Chief, Medical Branch, Division of Nuclear Materials Safety, Region I. [FR Doc. E9–94 Filed 1–7–09; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [DOCKET NO. 52–033] Detroit Edison Company; Notice of Hearing, and Opportunity To Petition for Leave To Intervene and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information and Safeguards Information for Contention Preparation on a Combined License for Fermi 3 Pursuant to the Atomic Energy Act of 1954, as amended, and the regulations in Title 10 of the Code of Federal Regulations (10 CFR) Part 2, ‘‘Rules of Practice for Domestic Licensing PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 Proceedings and Issuance of Orders,’’ 10 CFR Part 50, ‘‘Domestic Licensing of Production and Utilization Facilities,’’ and 10 CFR Part 52, ‘‘Licenses, Certifications, and Approvals for Nuclear Power Plants,’’ notice is hereby given that a hearing will be held, at a time and place to be set in the future by the U.S. Nuclear Regulatory Commission (NRC, the Commission) or designated by the Atomic Safety and Licensing Board (Board). The hearing will consider the application dated September 18, 2008, filed by Detroit Edison Company, pursuant to Subpart C of 10 CFR Part 52, for a combined license (COL). The application, which was supplemented by letters dated October 27, 2008, November 11, 2008, and November 20, 2008, requests approval of a COL for the Fermi Nuclear Power Plant, Unit 3, to be located in Monroe County, Michigan. The application was accepted for docketing on November 25, 2008. The docket number established for this COL application is 52–033. The Fermi COL application references the application for certification of the Economic Simplified Boiling Water Reactor (ESBWR) design, which was initially submitted on August 24, 2005. The ESBWR design is the subject of an ongoing rulemaking under Docket Number 52–010. The hearing will be conducted by a Board that will be designated by the Chairman of the Atomic Safety and Licensing Board Panel or will be conducted by the Commission. Notice as to the membership of the Board will be published in the Federal Register at a later date. The NRC staff will complete a detailed technical review of the COL application and will document its findings in a safety evaluation report. The Commission will refer a copy of the application to the Advisory Committee on Reactor Safeguards (ACRS) in accordance with 10 CFR 52.87, ‘‘Referral to the ACRS,’’ and the ACRS will report on those portions of the application that concern safety. The NRC staff will also prepare an Environmental Impact Statement, as required by 10 CFR 51.20(b)(2). Any person whose interest may be affected by this proceeding and who desires to participate as a party to this proceeding must file a written petition for leave to intervene in accordance with 10 CFR 2.309. Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing. A petition for leave to intervene must be filed no later than 60 days from the E:\FR\FM\08JAN1.SGM 08JAN1 erowe on PROD1PC63 with NOTICES Federal Register / Vol. 74, No. 5 / Thursday, January 8, 2009 / Notices date of publication of this notice in the Federal Register. Non-timely filings will not be entertained absent a determination by the Commission or presiding officer designated to rule on the petition, pursuant to the requirements of 10 CFR 2.309(c)(1)(i)– (viii). All documents filed in NRC adjudicatory proceedings, including petitions to intervene and requests to participate as an interested government entity under 10 CFR 2.315(c), must be filed in accordance with the NRC EFiling rule, which was promulgated by the NRC on August 28, 2007 (72 FR 49139). The E-Filing process requires participants to submit and serve documents over the internet or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings unless they seek a waiver in accordance with the procedures described below. To comply with the procedural requirements of E-Filing, at least 10 days prior to the filing deadline, the petitioner must contact the Office of the Secretary by e-mail at HearingDocket@nrc.gov, or by calling (301) 415–1677, to request (1) a digital ID certificate, which allows the participant (or its counsel or representative) to digitally sign documents and access the E-Submittal server for any proceeding in which it is participating; and/or (2) creation of an electronic docket for the proceeding (even in instances in which the petitioner (or its counsel or representative) already holds an NRCissued digital ID certificate). Each participant will need to download the Workplace Forms Viewer TM to access the Electronic Information Exchange (EIE), a component of the E-Filing system. The Workplace Forms Viewer TM is free and is available at https://www.nrc.gov/site-help/esubmittals/install-viewer.html. Information about applying for a digital ID certificate is available on NRC’s public Web site at https://www.nrc.gov/ site-help/e-submittals/applycertificates.html. Once a participant has obtained a digital ID certificate, had a docket created, and downloaded the EIE viewer, it can then submit a petition for leave to intervene. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public Web site at https://www.nrc.gov/site-help/esubmittals.html. A filing is considered complete at the time the filer submits its documents through EIE. To be timely, an electronic filing must be submitted to the EIE system no later than 11:59 p.m. VerDate Nov<24>2008 13:57 Jan 07, 2009 Jkt 217001 Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an e-mail notice confirming receipt of the document. The EIE system also distributes an e-mail notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before a petition to intervene is filed so that they can obtain access to the document via the E-Filing system. A person filing electronically using the agency’s adjudicatory E-filing system may seek assistance through the ‘‘Contact Us’’ link located on the NRC Web site at https://www.nrc.gov/sitehelp/e-submittals.html or by calling the NRC Meta-System Help Desk, which is available between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday, excluding government holidays. The toll-free help line number is 1–866– 672–7640. A person filing electronically may also seek assistance by sending an e-mail to MSHD.Resource@nrc.gov. Participants who believe that they have a good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) First class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland, 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by firstclass mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service. Non-timely requests and/or petitions and contentions will not be entertained absent a determination by the Commission, the presiding officer, or the Atomic Safety and Licensing Board that the petition should be granted and/ PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 837 or the contentions should be admitted based on a balancing of the factors specified in 10 CFR 2.309(c)(1)(i)–(viii). To be timely, filings must be submitted no later than 11:59 p.m. Eastern Standard Time on the due date. Documents submitted in adjudicatory proceedings will appear in the NRC’s electronic hearing docket which is available to the public at https:// ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant to an order of the Commission, an Atomic Safety and Licensing Board, or a Presiding Officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home telephone numbers in their filings. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submission. Any person who files a motion pursuant to 10 CFR 2.323 must consult with counsel for the applicant and counsel for the NRC staff who are listed below. Counsel for the applicant is Bruce R. Maters, 313–235–7481, Matersb@dteenergy.com. Counsel for the NRC staff in this proceeding is Marcia Carpentier, (301) 415–4126, Marcia.Carpentier@nrc.gov. A person who is not a party may be permitted to make a limited appearance by making an oral or written statement of his or her position on the issues at any session of the hearing or any prehearing conference within the limits and conditions fixed by the presiding officer, but may not otherwise participate in the proceeding. These limited appearance statements need not be submitted using the E-filing process. Documents may be examined, and/or copied for a fee, at the NRC’s Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland, and will be accessible electronically through the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room link at the NRC Web site https://www.nrc.gov/ reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1–800–397–4209, 301– 415–4737, or by e-mail to pdr.resource@nrc.gov. The application is available at https://www.nrc.gov/ reactors/new-reactors/col/Fermi.html. The ADAMS accession number for the E:\FR\FM\08JAN1.SGM 08JAN1 838 Federal Register / Vol. 74, No. 5 / Thursday, January 8, 2009 / Notices application cover letter is ML081300460. The ADAMS accession numbers for supplemental letters are ML0831203285, ML083190539, and ML083530798. To search for documents in ADAMS using the Fermi COL application docket numbers, 52–033, enter the term ‘‘05200033’’ in the ‘‘Docket Number’’ field when using either the web-based search (advanced search) engine or the ADAMS find tool in Citrix. The ESBWR design certification can be found by going to https://www.nrc.gov/reactors/newlicensing/design-cert/esbwr.html or by accessing our ADAMS Advanced Web Search and entering ‘‘05200010’’ in the ‘‘Docket Number’’ field to search for documents linked to the ESBWR design certification application. erowe on PROD1PC63 with NOTICES Order Imposing Procedures for Access to Sensitive Unclassified NonSafeguards Information and Safeguards Information for Contention Preparation 1. This order contains instructions regarding how potential parties to this proceeding may request access to documents containing sensitive unclassified information (including Sensitive Unclassified Non-Safeguards Information (SUNSI) and Safeguards Information (SGI)). 2. Within 10 days after publication of this notice of hearing and opportunity to petition for leave to intervene, any potential party as defined in 10 CFR 2.4 who believes access to SUNSI or SGI is necessary for a response to the notice may request access to SUNSI or SGI. A ‘‘potential party’’ is any person who intends or may intend to participate as a party by demonstrating standing and the filing of an admissible contention under 10 CFR 2.309. Requests submitted later than 10 days will not be considered absent a showing of good cause for the late filing, addressing why the request could not have been filed earlier. 3. The requester shall submit a letter requesting permission to access SUNSI and/or SGI to the Office of the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, Attention: Rulemakings and Adjudications Staff, and provide a copy to the Associate General Counsel for Hearings, Enforcement and Administration, Office of the General Counsel, Washington, DC 20555–0001. The expedited delivery or courier mail address for both offices is U.S. Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The e-mail address for the Office of the Secretary and the Office of the General Counsel are HearingDocket@nrc.gov and VerDate Nov<24>2008 13:57 Jan 07, 2009 Jkt 217001 OGCmail@nrc.gov, respectively.1 The request must include the following information: a. A description of the licensing action with a citation to this Federal Register notice of hearing and opportunity to petition for leave to intervene; b. The name and address of the potential party and a description of the potential party’s particularized interest that could be harmed by the action identified in (a); c. If the request is for SUNSI, the identity of the individual requesting access to SUNSI and the requester’s need for the information in order to meaningfully participate in this adjudicatory proceeding, particularly why publicly available versions of the application would not be sufficient to provide the basis and specificity for a proffered contention; d. If the request is for SGI, the identity of the individual requesting access to SGI and the identity of any expert, consultant or assistant who will aid the requester in evaluating the SGI, and information that shows: (i) Why the information is indispensable to meaningful participation in this licensing proceeding; and (ii) The technical competence (demonstrable knowledge, skill, experience, training or education) of the requester to understand and use (or evaluate) the requested information to provide the basis and specificity for a proffered contention. The technical competence of a potential party or its counsel may be shown by reliance on a qualified expert, consultant or assistant who demonstrates technical competence as well as trustworthiness and reliability, and who agrees to sign a nondisclosure affidavit and be bound by the terms of a protective order; and e. If the request is for SGI, Form SF– 85, ‘‘Questionnaire for Non-Sensitive Positions,’’ Form FD–258 (fingerprint card), and a credit check release form completed by the individual who seeks access to SGI and each individual who will aid the requester in evaluating the SGI. For security reasons, Form SF–85 can only be submitted electronically, through a restricted-access database. To obtain online access to the form, the requester should contact the NRC’s Office of Administration at 301–415– 1 While a request for hearing or petition to intervene in this proceeding must comply with the filing requirements of the NRC’s ‘‘E-Filing Rule,’’ the initial request to access SUNSI and/or SGI under these procedures should be submitted as described in this paragraph. PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 0320.2 The other completed forms must be signed in original ink, accompanied by a check or money order payable in the amount of $191.00 to the U.S. Nuclear Regulatory Commission for each individual, and mailed to the U.S. Nuclear Regulatory Commission, Office of Administration, Security Processing Unit, Mail Stop TWB–05 B32M, Washington, DC 20555–0012. These forms will be used to initiate the background check, which includes fingerprinting as part of a criminal history records check. Note: copies of these forms do not need to be included with the request letter to the Office of the Secretary, but the request letter should state that the forms and fees have been submitted as described above. 4. To avoid delays in processing requests for access to SGI, all forms should be reviewed for completeness and accuracy (including legibility) before submitting them to the NRC. Incomplete packages will be returned to the sender and will not be processed. 5. Based on an evaluation of the information submitted under items 2 and 3.a through 3.d, above, the NRC staff will determine within 10 days of receipt of the written access request whether (1) there is a reasonable basis to believe the petitioner is likely to establish standing to participate in this NRC proceeding, and (2) there is a legitimate need for access to SUNSI or need to know the SGI requested. For SGI, the need to know determination is made based on whether the information requested is necessary (i.e., indispensable) for the proposed recipient to proffer and litigate a specific contention in this NRC proceeding 3 and whether the proposed recipient has the technical competence (demonstrable knowledge, skill, training, education, or experience) to evaluate and use the specific SGI requested in this proceeding. 6. If standing and need to know SGI are shown, the NRC staff will further determine based upon completion of the background check whether the proposed recipient is trustworthy and reliable. The NRC staff will conduct (as 2 The requester will be asked to provide his or her full name, social security number, date and place of birth, telephone number, and email address. After providing this information, the requester usually should be able to obtain access to the online form within one business day. 3 Broad SGI requests under these procedures are thus highly unlikely to meet the standard for need to know; furthermore, staff redaction of information from requested documents before their release may be appropriate to comport with this requirement. These procedures do not authorize unrestricted disclosure or less scrutiny of a requester’s need to know than ordinarily would be applied in connection with an already-admitted contention. E:\FR\FM\08JAN1.SGM 08JAN1 839 Federal Register / Vol. 74, No. 5 / Thursday, January 8, 2009 / Notices erowe on PROD1PC63 with NOTICES necessary) an inspection to confirm that the recipient’s information protection systems are sufficient to protect SGI from inadvertent release or disclosure. Recipients may opt to view SGI at the NRC’s facility rather than establish their own SGI protection program to meet SGI protection requirements. 7. A request for access to SUNSI or SGI will be granted if: a. The request has demonstrated that there is a reasonable basis to believe that a potential party is likely to establish standing to intervene or to otherwise participate as a party in this proceeding; b. The proposed recipient of the information has demonstrated a need for SUNSI or a need to know for SGI, and that the proposed recipient of SGI is trustworthy and reliable; c. The proposed recipient of the information has executed a NonDisclosure Agreement or Affidavit and agrees to be bound by the terms of a Protective Order setting forth terms and conditions to prevent the unauthorized or inadvertent disclosure of SUNSI and/ or SGI; and d. The presiding officer has issued a protective order concerning the information or documents requested.4 Any protective order issued shall provide that the petitioner must file SUNSI or SGI contentions 25 days after receipt of (or access to) that information. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI or SGI contentions by that later deadline. 8. If the request for access to SUNSI or SGI is granted, the terms and conditions for access to sensitive unclassified information will be set forth in a draft protective order and affidavit of non-disclosure appended to a joint motion by the NRC staff, any other affected parties to this proceeding,5 and the petitioner(s). If the diligent efforts by the relevant parties or petitioner(s) fail to result in an agreement on the terms and conditions for a draft protective order or nondisclosure affidavit, the relevant parties to the proceeding or the petitioner(s) 4 If a presiding officer has not yet been designated, the Chief Administrative Judge will issue such orders, or will appoint a presiding officer to do so. 5 Parties/persons other than the requester and the NRC staff will be notified by the NRC staff of a favorable access determination (and may participate in the development of such a motion and protective order) if it concerns SUNSI and if the party/person’s interest independent of the proceeding would be harmed by the release of the information (e.g., as with proprietary information). VerDate Nov<24>2008 13:57 Jan 07, 2009 Jkt 217001 should notify the presiding officer within 5 days, describing the obstacles to the agreement. 9. If the request for access to SUNSI is denied by the NRC staff or a request for access to SGI is denied by NRC staff either after a determination on standing and need to know or, later, after a determination on trustworthiness and reliability, the NRC staff shall briefly state the reasons for the denial. Before the Office of Administration makes an adverse determination regarding access, the proposed recipient must be provided an opportunity to correct or explain information. The requester may challenge the NRC staff’s adverse determination with respect to access to SUNSI or with respect to standing or need to know for SGI by filing a challenge within 5 days of receipt of that determination with (a) the presiding officer designated in this proceeding; (b) if no presiding officer has been appointed, the Chief Administrative Judge, or if he or she is unavailable, another administrative judge, or an administrative law judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another officer has been designated to rule on information access issues, with that officer. In the same manner, an SGI requester may challenge an adverse determination on trustworthiness and reliability by filing a challenge within 15 days of receipt of that determination. In the same manner, a party other than the requester may challenge an NRC staff determination granting access to SUNSI whose release would harm that party’s interest independent of the proceeding. Such a challenge must be filed within 5 days of the notification by the NRC staff of its grant of such a request. If challenges to the NRC staff determinations are filed, these procedures give way to the normal process for litigating disputes concerning access to information. The availability of interlocutory review by the Commission of orders ruling on such NRC staff determinations (whether granting or denying access) is governed by 10 CFR 2.311.6 10. The Commission expects that the NRC staff and presiding officers (and any other reviewing officers) will consider and resolve requests for access to SUNSI and/or SGI, and motions for protective orders, in a timely fashion in order to minimize any unnecessary delays in identifying those petitioners who have standing and who have propounded contentions meeting the specificity and basis requirements in 10 CFR Part 2. Attachment 1 to this Order summarizes the general target schedule for processing and resolving requests under these procedures. Dated at Rockville, Maryland, this 2nd day of January 2009. For the Nuclear Regulatory Commission. J. Samuel Walker, Acting Secretary of the Commission. Attachment 1—General Target Schedule for Processing and Resolving Requests for Access to Sensitive Unclassified Non-Safeguards Information and Safeguards Information in This Proceeding Day Event/activity 0 ............... Publication of FEDERAL REGISTER notice of hearing and opportunity to petition for leave to intervene, including order with instructions for access requests. Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) and/or Safeguards Information (SGI) with information: supporting the standing of a potential party identified by name and address; describing the need for the information in order for the potential party to participate meaningfully in an adjudicatory proceeding; demonstrating that access should be granted (e.g., showing technical competence for access to SGI); and, for SGI, including application fee for fingerprint/background check. Deadline for submitting petition for intervention containing: (i) Demonstration of standing; (ii) all contentions whose formulation does not require access to SUNSI and/or SGI (+25 Answers to petition for intervention; +7 petitioner/requestor reply). 10 ............. 60 ............. 6 As of October 15, 2007, the NRC’s final ‘‘EFiling Rule’’ became effective. See Use of Electronic Submissions in Agency Hearings (72 FR 49139; August 28, 2007). Requesters should note that the filing requirements of that rule apply to appeals of NRC staff determinations (because they must be served on a presiding officer or the Commission, as applicable), but not to the initial SUNSI/SGI requests submitted to the NRC staff under these procedures. PO 00000 Frm 00047 Fmt 4703 Sfmt 4703 E:\FR\FM\08JAN1.SGM 08JAN1 840 Federal Register / Vol. 74, No. 5 / Thursday, January 8, 2009 / Notices Day Event/activity Day Event/activity 20 ............. Nuclear Regulatory Commission (NRC) staff informs the requester of the staff’s determination whether the request for access provides a reasonable basis to believe standing can be established and shows (1) need for SUNSI or (2) need to know for SGI. (For SUNSI, NRC staff also informs any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation of redactions or review of redacted documents). If NRC staff makes the finding of need to know for SGI and likelihood of standing, NRC staff begins background check (including fingerprinting for a criminal history records check), information processing (preparation of redactions or review of redacted documents), and readiness inspections. If NRC staff finds no ‘‘need,’’ ‘‘need to know,’’ or likelihood of standing, the deadline for petitioner/requester to file a motion seeking a ruling to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a motion seeking a ruling to reverse the NRC staff’s grant of access. Deadline for NRC staff reply to motions to reverse NRC staff determination(s). (Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file NonDisclosure Agreement for SUNSI. 190 ........... (Receipt +180) If NRC staff finds standing, need to know for SGI, and trustworthiness and reliability, deadline for NRC staff to file motion for Protective Order and draft Non-disclosure Affidavit (or to make a determination that the proposed recipient of SGI is not trustworthy or reliable). NOTE: Before the Office of Administration makes an adverse determination regarding access, the proposed recipient must be provided an opportunity to correct or explain information. Deadline for petitioner to seek reversal of a final adverse NRC staff determination either before the presiding officer or another designated officer. If access granted: Issuance of presiding officer or other designated officer decision on motion for protective order for access to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final adverse determination by the NRC staff. Deadline for filing executed NonDisclosure Affidavits. Access provided to SUNSI and/or SGI consistent with decision issuing the protective order. Deadline for submission of contentions whose development depends upon access to SUNSI and/or SGI. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI or SGI contentions by that later deadline. (Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI and/or SGI. (Answer receipt +7) Petitioner/Intervenor reply to answers. Decision on contention admission. 25 ............. 30 ............. erowe on PROD1PC63 with NOTICES 40 ............. 205 ........... A .............. A + 3 ........ A + 28 ...... A + 53 ...... A + 60 ...... B .............. [FR Doc. E9–111 Filed 1–7–09; 8:45 am] BILLING CODE 7590–01–P SECURITIES AND EXCHANGE COMMISSION [Release No. 34–59175; File No. SR–FINRA– 2008–066] Self-Regulatory Organizations; Financial Industry Regulatory Authority, Inc.; Notice of Filing and Immediate Effectiveness of Proposed Rule Change To Reflect the Closing of the FINRA/NSX Trade Reporting Facility on December 31, 2008 December 30, 2008. Pursuant to Section 19(b)(1) of the Securities Exchange Act of 1934 (‘‘Act’’) 1 and Rule 19b–4 thereunder,2 notice is hereby given that on December 23, 2008, Financial Industry Regulatory Authority, Inc. (‘‘FINRA’’) (f/k/a National Association of Securities Dealers, Inc. (‘‘NASD’’)) filed with the Securities and Exchange Commission (‘‘SEC’’ or ‘‘Commission’’) the proposed rule change as described in Items I and II below, which Items have been prepared by FINRA. FINRA submitted the proposed rule change under Section 19(b)(3)(A) of the Act and Rule 19b– 4(f)(6) 3 thereunder, which renders the proposal effective upon filing with the Commission. The Commission is publishing this notice to solicit comments on the proposed rule change from interested persons. I. Self-Regulatory Organization’s Statement of the Terms of Substance of the Proposed Rule Change FINRA’s proposed rule change reflects the closing of the FINRA/NSX Trade Reporting Facility (the ‘‘FINRA/NSX TRF’’) as of the close of business on December 31, 2008. The text of the proposed rule change is attached as Exhibit 5.4 II. Self-Regulatory Organization’s Statement of the Purpose of, and Statutory Basis for, the Proposed Rule Change In its filing with the Commission, FINRA included statements concerning the purpose of and basis for the proposed rule change and discussed any comments it received on the proposed rule change. The text of these statements may be examined at the places specified in Item IV below. FINRA has prepared summaries, set forth in sections A, B, 1 15 U.S.C. 78s(b)(1). CFR 240.19b–4. 3 17 CFR 240.19b–4(f)(6). 4 The Commission notes that while provided in Exhibit 5 to the filing, the text of the proposed rule change is not attached to this notice but is available at FINRA, the Commission’s Public Reference Room, and at https://www.finra.org. 2 17 VerDate Nov<24>2008 13:57 Jan 07, 2009 Jkt 217001 PO 00000 Frm 00048 Fmt 4703 Sfmt 4703 E:\FR\FM\08JAN1.SGM 08JAN1

Agencies

[Federal Register Volume 74, Number 5 (Thursday, January 8, 2009)]
[NOT]
[Pages 836-840]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-111]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[DOCKET NO. 52-033]


Detroit Edison Company; Notice of Hearing, and Opportunity To 
Petition for Leave To Intervene and Order Imposing Procedures for 
Access to Sensitive Unclassified Non-Safeguards Information and 
Safeguards Information for Contention Preparation on a Combined License 
for Fermi 3

    Pursuant to the Atomic Energy Act of 1954, as amended, and the 
regulations in Title 10 of the Code of Federal Regulations (10 CFR) 
Part 2, ``Rules of Practice for Domestic Licensing Proceedings and 
Issuance of Orders,'' 10 CFR Part 50, ``Domestic Licensing of 
Production and Utilization Facilities,'' and 10 CFR Part 52, 
``Licenses, Certifications, and Approvals for Nuclear Power Plants,'' 
notice is hereby given that a hearing will be held, at a time and place 
to be set in the future by the U.S. Nuclear Regulatory Commission (NRC, 
the Commission) or designated by the Atomic Safety and Licensing Board 
(Board). The hearing will consider the application dated September 18, 
2008, filed by Detroit Edison Company, pursuant to Subpart C of 10 CFR 
Part 52, for a combined license (COL). The application, which was 
supplemented by letters dated October 27, 2008, November 11, 2008, and 
November 20, 2008, requests approval of a COL for the Fermi Nuclear 
Power Plant, Unit 3, to be located in Monroe County, Michigan. The 
application was accepted for docketing on November 25, 2008. The docket 
number established for this COL application is 52-033. The Fermi COL 
application references the application for certification of the 
Economic Simplified Boiling Water Reactor (ESBWR) design, which was 
initially submitted on August 24, 2005. The ESBWR design is the subject 
of an ongoing rulemaking under Docket Number 52-010.
    The hearing will be conducted by a Board that will be designated by 
the Chairman of the Atomic Safety and Licensing Board Panel or will be 
conducted by the Commission. Notice as to the membership of the Board 
will be published in the Federal Register at a later date. The NRC 
staff will complete a detailed technical review of the COL application 
and will document its findings in a safety evaluation report. The 
Commission will refer a copy of the application to the Advisory 
Committee on Reactor Safeguards (ACRS) in accordance with 10 CFR 52.87, 
``Referral to the ACRS,'' and the ACRS will report on those portions of 
the application that concern safety. The NRC staff will also prepare an 
Environmental Impact Statement, as required by 10 CFR 51.20(b)(2).
    Any person whose interest may be affected by this proceeding and 
who desires to participate as a party to this proceeding must file a 
written petition for leave to intervene in accordance with 10 CFR 
2.309. Those permitted to intervene become parties to the proceeding, 
subject to any limitations in the order granting leave to intervene, 
and have the opportunity to participate fully in the conduct of the 
hearing.
    A petition for leave to intervene must be filed no later than 60 
days from the

[[Page 837]]

date of publication of this notice in the Federal Register. Non-timely 
filings will not be entertained absent a determination by the 
Commission or presiding officer designated to rule on the petition, 
pursuant to the requirements of 10 CFR 2.309(c)(1)(i)-(viii).
    All documents filed in NRC adjudicatory proceedings, including 
petitions to intervene and requests to participate as an interested 
government entity under 10 CFR 2.315(c), must be filed in accordance 
with the NRC E-Filing rule, which was promulgated by the NRC on August 
28, 2007 (72 FR 49139). The E-Filing process requires participants to 
submit and serve documents over the internet or in some cases to mail 
copies on electronic storage media. Participants may not submit paper 
copies of their filings unless they seek a waiver in accordance with 
the procedures described below.
    To comply with the procedural requirements of E-Filing, at least 10 
days prior to the filing deadline, the petitioner must contact the 
Office of the Secretary by e-mail at HearingDocket@nrc.gov, or by 
calling (301) 415-1677, to request (1) a digital ID certificate, which 
allows the participant (or its counsel or representative) to digitally 
sign documents and access the E-Submittal server for any proceeding in 
which it is participating; and/or (2) creation of an electronic docket 
for the proceeding (even in instances in which the petitioner (or its 
counsel or representative) already holds an NRC-issued digital ID 
certificate). Each participant will need to download the Workplace 
Forms Viewer \TM\ to access the Electronic Information Exchange (EIE), 
a component of the E-Filing system. The Workplace Forms Viewer \TM\ is 
free and is available at https://www.nrc.gov/site-help/e-submittals/
install-viewer.html. Information about applying for a digital ID 
certificate is available on NRC's public Web site at https://
www.nrc.gov/site-help/e-submittals/apply-certificates.html.
    Once a participant has obtained a digital ID certificate, had a 
docket created, and downloaded the EIE viewer, it can then submit a 
petition for leave to intervene. Submissions should be in Portable 
Document Format (PDF) in accordance with NRC guidance available on the 
NRC public Web site at https://www.nrc.gov/site-help/e-submittals.html. 
A filing is considered complete at the time the filer submits its 
documents through EIE. To be timely, an electronic filing must be 
submitted to the EIE system no later than 11:59 p.m. Eastern Time on 
the due date. Upon receipt of a transmission, the E-Filing system time-
stamps the document and sends the submitter an e-mail notice confirming 
receipt of the document. The EIE system also distributes an e-mail 
notice that provides access to the document to the NRC Office of the 
General Counsel and any others who have advised the Office of the 
Secretary that they wish to participate in the proceeding, so that the 
filer need not serve the documents on those participants separately. 
Therefore, applicants and other participants (or their counsel or 
representative) must apply for and receive a digital ID certificate 
before a petition to intervene is filed so that they can obtain access 
to the document via the E-Filing system.
    A person filing electronically using the agency's adjudicatory E-
filing system may seek assistance through the ``Contact Us'' link 
located on the NRC Web site at https://www.nrc.gov/site-help/e-
submittals.html or by calling the NRC Meta-System Help Desk, which is 
available between 8 a.m. and 8 p.m., Eastern Time, Monday through 
Friday, excluding government holidays. The toll-free help line number 
is 1-866-672-7640. A person filing electronically may also seek 
assistance by sending an e-mail to MSHD.Resource@nrc.gov.
    Participants who believe that they have a good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted by: (1) First class mail 
addressed to the Office of the Secretary of the Commission, U.S. 
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: 
Rulemaking and Adjudications Staff; or (2) courier, express mail, or 
expedited delivery service to the Office of the Secretary, Sixteenth 
Floor, One White Flint North, 11555 Rockville Pike, Rockville, 
Maryland, 20852, Attention: Rulemaking and Adjudications Staff. 
Participants filing a document in this manner are responsible for 
serving the document on all other participants. Filing is considered 
complete by first-class mail as of the time of deposit in the mail, or 
by courier, express mail, or expedited delivery service upon depositing 
the document with the provider of the service.
    Non-timely requests and/or petitions and contentions will not be 
entertained absent a determination by the Commission, the presiding 
officer, or the Atomic Safety and Licensing Board that the petition 
should be granted and/or the contentions should be admitted based on a 
balancing of the factors specified in 10 CFR 2.309(c)(1)(i)-(viii). To 
be timely, filings must be submitted no later than 11:59 p.m. Eastern 
Standard Time on the due date.
    Documents submitted in adjudicatory proceedings will appear in the 
NRC's electronic hearing docket which is available to the public at 
https://ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant 
to an order of the Commission, an Atomic Safety and Licensing Board, or 
a Presiding Officer. Participants are requested not to include personal 
privacy information, such as social security numbers, home addresses, 
or home telephone numbers in their filings. With respect to copyrighted 
works, except for limited excerpts that serve the purpose of the 
adjudicatory filings and would constitute a Fair Use application, 
participants are requested not to include copyrighted materials in 
their submission.
    Any person who files a motion pursuant to 10 CFR 2.323 must consult 
with counsel for the applicant and counsel for the NRC staff who are 
listed below. Counsel for the applicant is Bruce R. Maters, 313-235-
7481, Matersb@dteenergy.com. Counsel for the NRC staff in this 
proceeding is Marcia Carpentier, (301) 415-4126, 
Marcia.Carpentier@nrc.gov.
    A person who is not a party may be permitted to make a limited 
appearance by making an oral or written statement of his or her 
position on the issues at any session of the hearing or any pre-hearing 
conference within the limits and conditions fixed by the presiding 
officer, but may not otherwise participate in the proceeding. These 
limited appearance statements need not be submitted using the E-filing 
process.
    Documents may be examined, and/or copied for a fee, at the NRC's 
Public Document Room (PDR), located at One White Flint North, Public 
File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, 
Maryland, and will be accessible electronically through the Agencywide 
Documents Access and Management System (ADAMS) Public Electronic 
Reading Room link at the NRC Web site https://www.nrc.gov/reading-rm/
adams.html. Persons who do not have access to ADAMS or who encounter 
problems in accessing documents located in ADAMS should contact the NRC 
PDR Reference staff by telephone at 1-800-397-4209, 301-415-4737, or by 
e-mail to pdr.resource@nrc.gov. The application is available at https://
www.nrc.gov/reactors/new-reactors/col/Fermi.html. The ADAMS accession 
number for the

[[Page 838]]

application cover letter is ML081300460. The ADAMS accession numbers 
for supplemental letters are ML0831203285, ML083190539, and 
ML083530798. To search for documents in ADAMS using the Fermi COL 
application docket numbers, 52-033, enter the term ``05200033'' in the 
``Docket Number'' field when using either the web-based search 
(advanced search) engine or the ADAMS find tool in Citrix. The ESBWR 
design certification can be found by going to https://www.nrc.gov/
reactors/new-licensing/design-cert/esbwr.html or by accessing our ADAMS 
Advanced Web Search and entering ``05200010'' in the ``Docket Number'' 
field to search for documents linked to the ESBWR design certification 
application.

Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information and Safeguards Information for Contention 
Preparation

    1. This order contains instructions regarding how potential parties 
to this proceeding may request access to documents containing sensitive 
unclassified information (including Sensitive Unclassified Non-
Safeguards Information (SUNSI) and Safeguards Information (SGI)).
    2. Within 10 days after publication of this notice of hearing and 
opportunity to petition for leave to intervene, any potential party as 
defined in 10 CFR 2.4 who believes access to SUNSI or SGI is necessary 
for a response to the notice may request access to SUNSI or SGI. A 
``potential party'' is any person who intends or may intend to 
participate as a party by demonstrating standing and the filing of an 
admissible contention under 10 CFR 2.309. Requests submitted later than 
10 days will not be considered absent a showing of good cause for the 
late filing, addressing why the request could not have been filed 
earlier.
    3. The requester shall submit a letter requesting permission to 
access SUNSI and/or SGI to the Office of the Secretary, U.S. Nuclear 
Regulatory Commission, Washington, DC 20555-0001, Attention: 
Rulemakings and Adjudications Staff, and provide a copy to the 
Associate General Counsel for Hearings, Enforcement and Administration, 
Office of the General Counsel, Washington, DC 20555-0001. The expedited 
delivery or courier mail address for both offices is U.S. Nuclear 
Regulatory Commission, 11555 Rockville Pike, Rockville, Maryland 20852. 
The e-mail address for the Office of the Secretary and the Office of 
the General Counsel are HearingDocket@nrc.gov and OGCmail@nrc.gov, 
respectively.\1\ The request must include the following information:
---------------------------------------------------------------------------

    \1\ While a request for hearing or petition to intervene in this 
proceeding must comply with the filing requirements of the NRC's 
``E-Filing Rule,'' the initial request to access SUNSI and/or SGI 
under these procedures should be submitted as described in this 
paragraph.
---------------------------------------------------------------------------

    a. A description of the licensing action with a citation to this 
Federal Register notice of hearing and opportunity to petition for 
leave to intervene;
    b. The name and address of the potential party and a description of 
the potential party's particularized interest that could be harmed by 
the action identified in (a);
    c. If the request is for SUNSI, the identity of the individual 
requesting access to SUNSI and the requester's need for the information 
in order to meaningfully participate in this adjudicatory proceeding, 
particularly why publicly available versions of the application would 
not be sufficient to provide the basis and specificity for a proffered 
contention;
    d. If the request is for SGI, the identity of the individual 
requesting access to SGI and the identity of any expert, consultant or 
assistant who will aid the requester in evaluating the SGI, and 
information that shows:
    (i) Why the information is indispensable to meaningful 
participation in this licensing proceeding; and
    (ii) The technical competence (demonstrable knowledge, skill, 
experience, training or education) of the requester to understand and 
use (or evaluate) the requested information to provide the basis and 
specificity for a proffered contention. The technical competence of a 
potential party or its counsel may be shown by reliance on a qualified 
expert, consultant or assistant who demonstrates technical competence 
as well as trustworthiness and reliability, and who agrees to sign a 
non-disclosure affidavit and be bound by the terms of a protective 
order; and
    e. If the request is for SGI, Form SF-85, ``Questionnaire for Non-
Sensitive Positions,'' Form FD-258 (fingerprint card), and a credit 
check release form completed by the individual who seeks access to SGI 
and each individual who will aid the requester in evaluating the SGI. 
For security reasons, Form SF-85 can only be submitted electronically, 
through a restricted-access database. To obtain online access to the 
form, the requester should contact the NRC's Office of Administration 
at 301-415-0320.\2\ The other completed forms must be signed in 
original ink, accompanied by a check or money order payable in the 
amount of $191.00 to the U.S. Nuclear Regulatory Commission for each 
individual, and mailed to the U.S. Nuclear Regulatory Commission, 
Office of Administration, Security Processing Unit, Mail Stop TWB-05 
B32M, Washington, DC 20555-0012.
---------------------------------------------------------------------------

    \2\ The requester will be asked to provide his or her full name, 
social security number, date and place of birth, telephone number, 
and email address. After providing this information, the requester 
usually should be able to obtain access to the online form within 
one business day.
---------------------------------------------------------------------------

    These forms will be used to initiate the background check, which 
includes fingerprinting as part of a criminal history records check. 
Note: copies of these forms do not need to be included with the request 
letter to the Office of the Secretary, but the request letter should 
state that the forms and fees have been submitted as described above.
    4. To avoid delays in processing requests for access to SGI, all 
forms should be reviewed for completeness and accuracy (including 
legibility) before submitting them to the NRC. Incomplete packages will 
be returned to the sender and will not be processed.
    5. Based on an evaluation of the information submitted under items 
2 and 3.a through 3.d, above, the NRC staff will determine within 10 
days of receipt of the written access request whether (1) there is a 
reasonable basis to believe the petitioner is likely to establish 
standing to participate in this NRC proceeding, and (2) there is a 
legitimate need for access to SUNSI or need to know the SGI requested. 
For SGI, the need to know determination is made based on whether the 
information requested is necessary (i.e., indispensable) for the 
proposed recipient to proffer and litigate a specific contention in 
this NRC proceeding \3\ and whether the proposed recipient has the 
technical competence (demonstrable knowledge, skill, training, 
education, or experience) to evaluate and use the specific SGI 
requested in this proceeding.
---------------------------------------------------------------------------

    \3\ Broad SGI requests under these procedures are thus highly 
unlikely to meet the standard for need to know; furthermore, staff 
redaction of information from requested documents before their 
release may be appropriate to comport with this requirement. These 
procedures do not authorize unrestricted disclosure or less scrutiny 
of a requester's need to know than ordinarily would be applied in 
connection with an already-admitted contention.
---------------------------------------------------------------------------

    6. If standing and need to know SGI are shown, the NRC staff will 
further determine based upon completion of the background check whether 
the proposed recipient is trustworthy and reliable. The NRC staff will 
conduct (as

[[Page 839]]

necessary) an inspection to confirm that the recipient's information 
protection systems are sufficient to protect SGI from inadvertent 
release or disclosure. Recipients may opt to view SGI at the NRC's 
facility rather than establish their own SGI protection program to meet 
SGI protection requirements.
    7. A request for access to SUNSI or SGI will be granted if:
    a. The request has demonstrated that there is a reasonable basis to 
believe that a potential party is likely to establish standing to 
intervene or to otherwise participate as a party in this proceeding;
    b. The proposed recipient of the information has demonstrated a 
need for SUNSI or a need to know for SGI, and that the proposed 
recipient of SGI is trustworthy and reliable;
    c. The proposed recipient of the information has executed a Non-
Disclosure Agreement or Affidavit and agrees to be bound by the terms 
of a Protective Order setting forth terms and conditions to prevent the 
unauthorized or inadvertent disclosure of SUNSI and/or SGI; and
    d. The presiding officer has issued a protective order concerning 
the information or documents requested.\4\ Any protective order issued 
shall provide that the petitioner must file SUNSI or SGI contentions 25 
days after receipt of (or access to) that information. However, if more 
than 25 days remain between the petitioner's receipt of (or access to) 
the information and the deadline for filing all other contentions (as 
established in the notice of hearing or opportunity for hearing), the 
petitioner may file its SUNSI or SGI contentions by that later 
deadline.
---------------------------------------------------------------------------

    \4\ If a presiding officer has not yet been designated, the 
Chief Administrative Judge will issue such orders, or will appoint a 
presiding officer to do so.
---------------------------------------------------------------------------

    8. If the request for access to SUNSI or SGI is granted, the terms 
and conditions for access to sensitive unclassified information will be 
set forth in a draft protective order and affidavit of non-disclosure 
appended to a joint motion by the NRC staff, any other affected parties 
to this proceeding,\5\ and the petitioner(s). If the diligent efforts 
by the relevant parties or petitioner(s) fail to result in an agreement 
on the terms and conditions for a draft protective order or non-
disclosure affidavit, the relevant parties to the proceeding or the 
petitioner(s) should notify the presiding officer within 5 days, 
describing the obstacles to the agreement.
---------------------------------------------------------------------------

    \5\ Parties/persons other than the requester and the NRC staff 
will be notified by the NRC staff of a favorable access 
determination (and may participate in the development of such a 
motion and protective order) if it concerns SUNSI and if the party/
person's interest independent of the proceeding would be harmed by 
the release of the information (e.g., as with proprietary 
information).
---------------------------------------------------------------------------

    9. If the request for access to SUNSI is denied by the NRC staff or 
a request for access to SGI is denied by NRC staff either after a 
determination on standing and need to know or, later, after a 
determination on trustworthiness and reliability, the NRC staff shall 
briefly state the reasons for the denial. Before the Office of 
Administration makes an adverse determination regarding access, the 
proposed recipient must be provided an opportunity to correct or 
explain information. The requester may challenge the NRC staff's 
adverse determination with respect to access to SUNSI or with respect 
to standing or need to know for SGI by filing a challenge within 5 days 
of receipt of that determination with (a) the presiding officer 
designated in this proceeding; (b) if no presiding officer has been 
appointed, the Chief Administrative Judge, or if he or she is 
unavailable, another administrative judge, or an administrative law 
judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another 
officer has been designated to rule on information access issues, with 
that officer. In the same manner, an SGI requester may challenge an 
adverse determination on trustworthiness and reliability by filing a 
challenge within 15 days of receipt of that determination.
    In the same manner, a party other than the requester may challenge 
an NRC staff determination granting access to SUNSI whose release would 
harm that party's interest independent of the proceeding. Such a 
challenge must be filed within 5 days of the notification by the NRC 
staff of its grant of such a request.
    If challenges to the NRC staff determinations are filed, these 
procedures give way to the normal process for litigating disputes 
concerning access to information. The availability of interlocutory 
review by the Commission of orders ruling on such NRC staff 
determinations (whether granting or denying access) is governed by 10 
CFR 2.311.\6\
---------------------------------------------------------------------------

    \6\ As of October 15, 2007, the NRC's final ``E-Filing Rule'' 
became effective. See Use of Electronic Submissions in Agency 
Hearings (72 FR 49139; August 28, 2007). Requesters should note that 
the filing requirements of that rule apply to appeals of NRC staff 
determinations (because they must be served on a presiding officer 
or the Commission, as applicable), but not to the initial SUNSI/SGI 
requests submitted to the NRC staff under these procedures.
---------------------------------------------------------------------------

    10. The Commission expects that the NRC staff and presiding 
officers (and any other reviewing officers) will consider and resolve 
requests for access to SUNSI and/or SGI, and motions for protective 
orders, in a timely fashion in order to minimize any unnecessary delays 
in identifying those petitioners who have standing and who have 
propounded contentions meeting the specificity and basis requirements 
in 10 CFR Part 2. Attachment 1 to this Order summarizes the general 
target schedule for processing and resolving requests under these 
procedures.

    Dated at Rockville, Maryland, this 2nd day of January 2009.

    For the Nuclear Regulatory Commission.
J. Samuel Walker,
Acting Secretary of the Commission.

Attachment 1--General Target Schedule for Processing and Resolving 
Requests for Access to Sensitive Unclassified Non-Safeguards 
Information and Safeguards Information in This Proceeding

------------------------------------------------------------------------
                Day                            Event/activity
------------------------------------------------------------------------
0.................................  Publication of Federal Register
                                     notice of hearing and opportunity
                                     to petition for leave to intervene,
                                     including order with instructions
                                     for access requests.
10................................  Deadline for submitting requests for
                                     access to Sensitive Unclassified
                                     Non-Safeguards Information (SUNSI)
                                     and/or Safeguards Information (SGI)
                                     with information: supporting the
                                     standing of a potential party
                                     identified by name and address;
                                     describing the need for the
                                     information in order for the
                                     potential party to participate
                                     meaningfully in an adjudicatory
                                     proceeding; demonstrating that
                                     access should be granted (e.g.,
                                     showing technical competence for
                                     access to SGI); and, for SGI,
                                     including application fee for
                                     fingerprint/background check.
60................................  Deadline for submitting petition for
                                     intervention containing: (i)
                                     Demonstration of standing; (ii) all
                                     contentions whose formulation does
                                     not require access to SUNSI and/or
                                     SGI (+25 Answers to petition for
                                     intervention; +7 petitioner/
                                     requestor reply).

[[Page 840]]

 
20................................  Nuclear Regulatory Commission (NRC)
                                     staff informs the requester of the
                                     staff's determination whether the
                                     request for access provides a
                                     reasonable basis to believe
                                     standing can be established and
                                     shows (1) need for SUNSI or (2)
                                     need to know for SGI. (For SUNSI,
                                     NRC staff also informs any party to
                                     the proceeding whose interest
                                     independent of the proceeding would
                                     be harmed by the release of the
                                     information.) If NRC staff makes
                                     the finding of need for SUNSI and
                                     likelihood of standing, NRC staff
                                     begins document processing
                                     (preparation of redactions or
                                     review of redacted documents). If
                                     NRC staff makes the finding of need
                                     to know for SGI and likelihood of
                                     standing, NRC staff begins
                                     background check (including
                                     fingerprinting for a criminal
                                     history records check), information
                                     processing (preparation of
                                     redactions or review of redacted
                                     documents), and readiness
                                     inspections.
25................................  If NRC staff finds no ``need,''
                                     ``need to know,'' or likelihood of
                                     standing, the deadline for
                                     petitioner/requester to file a
                                     motion seeking a ruling to reverse
                                     the NRC staff's denial of access;
                                     NRC staff files copy of access
                                     determination with the presiding
                                     officer (or Chief Administrative
                                     Judge or other designated officer,
                                     as appropriate). If NRC staff finds
                                     ``need'' for SUNSI, the deadline
                                     for any party to the proceeding
                                     whose interest independent of the
                                     proceeding would be harmed by the
                                     release of the information to file
                                     a motion seeking a ruling to
                                     reverse the NRC staff's grant of
                                     access.
30................................  Deadline for NRC staff reply to
                                     motions to reverse NRC staff
                                     determination(s).
40................................  (Receipt +30) If NRC staff finds
                                     standing and need for SUNSI,
                                     deadline for NRC staff to complete
                                     information processing and file
                                     motion for Protective Order and
                                     draft Non-Disclosure Affidavit.
                                     Deadline for applicant/licensee to
                                     file Non-Disclosure Agreement for
                                     SUNSI.
190...............................  (Receipt +180) If NRC staff finds
                                     standing, need to know for SGI, and
                                     trustworthiness and reliability,
                                     deadline for NRC staff to file
                                     motion for Protective Order and
                                     draft Non-disclosure Affidavit (or
                                     to make a determination that the
                                     proposed recipient of SGI is not
                                     trustworthy or reliable). Note:
                                     Before the Office of Administration
                                     makes an adverse determination
                                     regarding access, the proposed
                                     recipient must be provided an
                                     opportunity to correct or explain
                                     information.
205...............................  Deadline for petitioner to seek
                                     reversal of a final adverse NRC
                                     staff determination either before
                                     the presiding officer or another
                                     designated officer.
A.................................  If access granted: Issuance of
                                     presiding officer or other
                                     designated officer decision on
                                     motion for protective order for
                                     access to sensitive information
                                     (including schedule for providing
                                     access and submission of
                                     contentions) or decision reversing
                                     a final adverse determination by
                                     the NRC staff.
A + 3.............................  Deadline for filing executed Non-
                                     Disclosure Affidavits. Access
                                     provided to SUNSI and/or SGI
                                     consistent with decision issuing
                                     the protective order.
A + 28............................  Deadline for submission of
                                     contentions whose development
                                     depends upon access to SUNSI and/or
                                     SGI. However, if more than 25 days
                                     remain between the petitioner's
                                     receipt of (or access to) the
                                     information and the deadline for
                                     filing all other contentions (as
                                     established in the notice of
                                     hearing or opportunity for
                                     hearing), the petitioner may file
                                     its SUNSI or SGI contentions by
                                     that later deadline.
A + 53............................  (Contention receipt +25) Answers to
                                     contentions whose development
                                     depends upon access to SUNSI and/or
                                     SGI.
A + 60............................  (Answer receipt +7) Petitioner/
                                     Intervenor reply to answers.
B.................................  Decision on contention admission.
------------------------------------------------------------------------

 [FR Doc. E9-111 Filed 1-7-09; 8:45 am]
BILLING CODE 7590-01-P