Termination of an Environmental Impact Statement for the Construction and Operation of a 300-MW Coal-Fired Electric Generating Unit Proposed by Wisconsin Power and Light Company Near Cassville in Grant County, WI, 701 [E9-36]
Download as PDF
Federal Register / Vol. 74, No. 4 / Wednesday, January 7, 2009 / Notices
Department of the Army; Corps of
Engineers
Termination of an Environmental
Impact Statement for the Construction
and Operation of a 300–MW Coal-Fired
Electric Generating Unit Proposed by
Wisconsin Power and Light Company
Near Cassville in Grant County, WI
would evaluate the application under
the terms of a Nationwide Permit, as
applicable, or prepare an Environmental
Assessment as part of its standard
permit application review.
Dated: December 22, 2008.
Jon L. Christensen,
Colonel, Corps of Engineers, District Engineer.
[FR Doc. E9–36 Filed 1–6–09; 8:45 am]
DEPARTMENT OF DEFENSE
AGENCY: Department of the Army, U.S.
Army Corps of Engineers, DoD.
ACTION: Notice of Termination.
SUMMARY: The St. Paul District, Corps of
Engineers (Corps) is canceling the
preparation of a federal Environmental
Impact Statement (EIS) for the proposal
by Wisconsin Power and Light
Company (WPL) to conduct work below
the ordinary high water mark of the
Mississippi River, a navigable water of
the U.S., and to discharge dredged or fill
material into waters of the U.S. to
facilitate the construction and operation
of a 300 megawatt (MW) baseload coalfired electric generating unit, referred to
as NED 3, near Cassville in Grant
County, WI. The Corps has terminated
its review of the WPL permit
application due to WPL’s withdrawal of
their permit application on November
21, 2008.
ADDRESSES: Questions concerning this
termination notice can be addressed to
Ms. Tamara Cameron, Regulatory
Branch by letter at U.S. Army Corps of
Engineers, 190 Fifth Street East, Suite
401, St. Paul, MN 55101–1638, by
telephone or by e-mail at
tamara.e.cameron@usace.army.mil.
FOR FURTHER INFORMATION CONTACT: Ms.
Tamara Cameron, (651) 290–5197.
SUPPLEMENTARY INFORMATION: On
January 17, 2008 the Corps published in
the Federal Register (73 FR 3241) a
notice of intent to prepare an EIS jointly
with the Public Service Commission of
Wisconsin (PSCW). Scoping meetings
were held in January and March, 2008
and a notice of availability of the draft
EIS was published in the Federal
Register (73 FR 30099) on May 23, 2008.
In July 2008, WPL modified their
proposal so that work would be done
under and over the Mississippi River,
but not in the River, and there would be
no discharges of dredged or fill material
into any waters of the U.S. On
November 21, 2008, WPL withdrew
their permit application, and
consequently the Corps has decided to
terminate the EIS.
If WPL submits a subsequent permit
application for work over and/or under
the Mississippi River, as detailed in
their most recent proposal, the Corps
VerDate Nov<24>2008
16:10 Jan 06, 2009
Jkt 217001
BILLING CODE 3720–58–P
DEPARTMENT OF EDUCATION
Submission for OMB Review;
Comment Request
Department of Education.
The Director, Information
Collection Clearance Division,
Regulatory Information Management
Services, Office of Management invites
comments on the submission for OMB
review as required by the Paperwork
Reduction Act of 1995.
DATES: Interested persons are invited to
submit comments on or before February
6, 2009.
ADDRESSES: Written comments should
be addressed to the Office of
Information and Regulatory Affairs,
Attention: Education Desk Officer,
Office of Management and Budget, 725
17th Street, NW., Room 10222, New
Executive Office Building, Washington,
DC 20503 or faxed to (202) 395–6974.
SUPPLEMENTARY INFORMATION: Section
3506 of the Paperwork Reduction Act of
1995 (44 U.S.C. Chapter 35) requires
that the Office of Management and
Budget (OMB) provide interested
Federal agencies and the public an early
opportunity to comment on information
collection requests. OMB may amend or
waive the requirement for public
consultation to the extent that public
participation in the approval process
would defeat the purpose of the
information collection, violate State or
Federal law, or substantially interfere
with any agency’s ability to perform its
statutory obligations. The Acting IC
Clearance Official, Regulatory
Information Management Services,
Office of Management, publishes that
notice containing proposed information
collection requests prior to submission
of these requests to OMB. Each
proposed information collection,
grouped by office, contains the
following: (1) Type of review requested,
e.g. new, revision, extension, existing or
reinstatement; (2) Title; (3) Summary of
the collection; (4) Description of the
need for, and proposed use of, the
information; (5) Respondents and
frequency of collection; and (6)
AGENCY:
SUMMARY:
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
701
Reporting and/or Recordkeeping
burden. OMB invites public comment.
Dated: January 2, 2009.
Stephanie Valentine,
Acting IC Clearance Official, Regulatory
Information Management Services, Office of
Management.
Federal Student Aid
Type of Review: Extension.
Title: Teacher Education Assistance
for College and Higher Education Grant
Eligibility Regulations.
Frequency: On Occasion; Annually.
Affected Public: Individuals or
household; Businesses or other forprofit; Not-for-profit institutions; State,
Local, or Tribal Gov’t, SEAs or LEAs.
Reporting and Recordkeeping Hour
Burden:
Responses: 211,097.
Burden Hours: 35,695.
Abstract: Eligible and participating
institutions of higher education who
participate in the TEACH Grant program
operate the program consistent with
these regulations. Information is
necessary to make determinations
regarding program compliance with the
implementing regulations. This request
is for approval of reporting and
recordkeeping requirements contained
in the attached proposed regulations
related to the TEACH Grant
administrative requirements for the
Title IV, HEA programs. The
information collection requirements in
these proposed regulations are
necessary to determine eligibility to
receive program benefits and to prevent
fraud and abuse of program funds.
Requests for copies of the information
collection submission for OMB review
may be accessed from https://
edicsweb.ed.gov, by selecting the
‘‘Browse Pending Collections’’ link and
by clicking on link number 3901. When
you access the information collection,
click on ‘‘Download Attachments’’ to
view. Written requests for information
should be addressed to U.S. Department
of Education, 400 Maryland Avenue,
SW., LBJ, Washington, DC 20202–4537.
Requests may also be electronically
mailed to the Internet address
ICDocketMgr@ed.gov or faxed to 202–
401–0920. Please specify the complete
title of the information collection when
making your request.
Comments regarding burden and/or
the collection activity requirements
should be electronically mailed to
ICDocketMgr@ed.gov. Individuals who
use a telecommunications device for the
deaf (TDD) may call the Federal
E:\FR\FM\07JAN1.SGM
07JAN1
Agencies
[Federal Register Volume 74, Number 4 (Wednesday, January 7, 2009)]
[Notices]
[Page 701]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-36]
[[Page 701]]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army; Corps of Engineers
Termination of an Environmental Impact Statement for the
Construction and Operation of a 300-MW Coal-Fired Electric Generating
Unit Proposed by Wisconsin Power and Light Company Near Cassville in
Grant County, WI
AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.
ACTION: Notice of Termination.
-----------------------------------------------------------------------
SUMMARY: The St. Paul District, Corps of Engineers (Corps) is canceling
the preparation of a federal Environmental Impact Statement (EIS) for
the proposal by Wisconsin Power and Light Company (WPL) to conduct work
below the ordinary high water mark of the Mississippi River, a
navigable water of the U.S., and to discharge dredged or fill material
into waters of the U.S. to facilitate the construction and operation of
a 300 megawatt (MW) baseload coal-fired electric generating unit,
referred to as NED 3, near Cassville in Grant County, WI. The Corps has
terminated its review of the WPL permit application due to WPL's
withdrawal of their permit application on November 21, 2008.
ADDRESSES: Questions concerning this termination notice can be
addressed to Ms. Tamara Cameron, Regulatory Branch by letter at U.S.
Army Corps of Engineers, 190 Fifth Street East, Suite 401, St. Paul, MN
55101-1638, by telephone or by e-mail at
tamara.e.cameron@usace.army.mil.
FOR FURTHER INFORMATION CONTACT: Ms. Tamara Cameron, (651) 290-5197.
SUPPLEMENTARY INFORMATION: On January 17, 2008 the Corps published in
the Federal Register (73 FR 3241) a notice of intent to prepare an EIS
jointly with the Public Service Commission of Wisconsin (PSCW). Scoping
meetings were held in January and March, 2008 and a notice of
availability of the draft EIS was published in the Federal Register (73
FR 30099) on May 23, 2008.
In July 2008, WPL modified their proposal so that work would be
done under and over the Mississippi River, but not in the River, and
there would be no discharges of dredged or fill material into any
waters of the U.S. On November 21, 2008, WPL withdrew their permit
application, and consequently the Corps has decided to terminate the
EIS.
If WPL submits a subsequent permit application for work over and/or
under the Mississippi River, as detailed in their most recent proposal,
the Corps would evaluate the application under the terms of a
Nationwide Permit, as applicable, or prepare an Environmental
Assessment as part of its standard permit application review.
Dated: December 22, 2008.
Jon L. Christensen,
Colonel, Corps of Engineers, District Engineer.
[FR Doc. E9-36 Filed 1-6-09; 8:45 am]