Termination of an Environmental Impact Statement for the Construction and Operation of a 300-MW Coal-Fired Electric Generating Unit Proposed by Wisconsin Power and Light Company Near Cassville in Grant County, WI, 701 [E9-36]

Download as PDF Federal Register / Vol. 74, No. 4 / Wednesday, January 7, 2009 / Notices Department of the Army; Corps of Engineers Termination of an Environmental Impact Statement for the Construction and Operation of a 300–MW Coal-Fired Electric Generating Unit Proposed by Wisconsin Power and Light Company Near Cassville in Grant County, WI would evaluate the application under the terms of a Nationwide Permit, as applicable, or prepare an Environmental Assessment as part of its standard permit application review. Dated: December 22, 2008. Jon L. Christensen, Colonel, Corps of Engineers, District Engineer. [FR Doc. E9–36 Filed 1–6–09; 8:45 am] DEPARTMENT OF DEFENSE AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD. ACTION: Notice of Termination. SUMMARY: The St. Paul District, Corps of Engineers (Corps) is canceling the preparation of a federal Environmental Impact Statement (EIS) for the proposal by Wisconsin Power and Light Company (WPL) to conduct work below the ordinary high water mark of the Mississippi River, a navigable water of the U.S., and to discharge dredged or fill material into waters of the U.S. to facilitate the construction and operation of a 300 megawatt (MW) baseload coalfired electric generating unit, referred to as NED 3, near Cassville in Grant County, WI. The Corps has terminated its review of the WPL permit application due to WPL’s withdrawal of their permit application on November 21, 2008. ADDRESSES: Questions concerning this termination notice can be addressed to Ms. Tamara Cameron, Regulatory Branch by letter at U.S. Army Corps of Engineers, 190 Fifth Street East, Suite 401, St. Paul, MN 55101–1638, by telephone or by e-mail at tamara.e.cameron@usace.army.mil. FOR FURTHER INFORMATION CONTACT: Ms. Tamara Cameron, (651) 290–5197. SUPPLEMENTARY INFORMATION: On January 17, 2008 the Corps published in the Federal Register (73 FR 3241) a notice of intent to prepare an EIS jointly with the Public Service Commission of Wisconsin (PSCW). Scoping meetings were held in January and March, 2008 and a notice of availability of the draft EIS was published in the Federal Register (73 FR 30099) on May 23, 2008. In July 2008, WPL modified their proposal so that work would be done under and over the Mississippi River, but not in the River, and there would be no discharges of dredged or fill material into any waters of the U.S. On November 21, 2008, WPL withdrew their permit application, and consequently the Corps has decided to terminate the EIS. If WPL submits a subsequent permit application for work over and/or under the Mississippi River, as detailed in their most recent proposal, the Corps VerDate Nov<24>2008 16:10 Jan 06, 2009 Jkt 217001 BILLING CODE 3720–58–P DEPARTMENT OF EDUCATION Submission for OMB Review; Comment Request Department of Education. The Director, Information Collection Clearance Division, Regulatory Information Management Services, Office of Management invites comments on the submission for OMB review as required by the Paperwork Reduction Act of 1995. DATES: Interested persons are invited to submit comments on or before February 6, 2009. ADDRESSES: Written comments should be addressed to the Office of Information and Regulatory Affairs, Attention: Education Desk Officer, Office of Management and Budget, 725 17th Street, NW., Room 10222, New Executive Office Building, Washington, DC 20503 or faxed to (202) 395–6974. SUPPLEMENTARY INFORMATION: Section 3506 of the Paperwork Reduction Act of 1995 (44 U.S.C. Chapter 35) requires that the Office of Management and Budget (OMB) provide interested Federal agencies and the public an early opportunity to comment on information collection requests. OMB may amend or waive the requirement for public consultation to the extent that public participation in the approval process would defeat the purpose of the information collection, violate State or Federal law, or substantially interfere with any agency’s ability to perform its statutory obligations. The Acting IC Clearance Official, Regulatory Information Management Services, Office of Management, publishes that notice containing proposed information collection requests prior to submission of these requests to OMB. Each proposed information collection, grouped by office, contains the following: (1) Type of review requested, e.g. new, revision, extension, existing or reinstatement; (2) Title; (3) Summary of the collection; (4) Description of the need for, and proposed use of, the information; (5) Respondents and frequency of collection; and (6) AGENCY: SUMMARY: PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 701 Reporting and/or Recordkeeping burden. OMB invites public comment. Dated: January 2, 2009. Stephanie Valentine, Acting IC Clearance Official, Regulatory Information Management Services, Office of Management. Federal Student Aid Type of Review: Extension. Title: Teacher Education Assistance for College and Higher Education Grant Eligibility Regulations. Frequency: On Occasion; Annually. Affected Public: Individuals or household; Businesses or other forprofit; Not-for-profit institutions; State, Local, or Tribal Gov’t, SEAs or LEAs. Reporting and Recordkeeping Hour Burden: Responses: 211,097. Burden Hours: 35,695. Abstract: Eligible and participating institutions of higher education who participate in the TEACH Grant program operate the program consistent with these regulations. Information is necessary to make determinations regarding program compliance with the implementing regulations. This request is for approval of reporting and recordkeeping requirements contained in the attached proposed regulations related to the TEACH Grant administrative requirements for the Title IV, HEA programs. The information collection requirements in these proposed regulations are necessary to determine eligibility to receive program benefits and to prevent fraud and abuse of program funds. Requests for copies of the information collection submission for OMB review may be accessed from https:// edicsweb.ed.gov, by selecting the ‘‘Browse Pending Collections’’ link and by clicking on link number 3901. When you access the information collection, click on ‘‘Download Attachments’’ to view. Written requests for information should be addressed to U.S. Department of Education, 400 Maryland Avenue, SW., LBJ, Washington, DC 20202–4537. Requests may also be electronically mailed to the Internet address ICDocketMgr@ed.gov or faxed to 202– 401–0920. Please specify the complete title of the information collection when making your request. Comments regarding burden and/or the collection activity requirements should be electronically mailed to ICDocketMgr@ed.gov. Individuals who use a telecommunications device for the deaf (TDD) may call the Federal E:\FR\FM\07JAN1.SGM 07JAN1

Agencies

[Federal Register Volume 74, Number 4 (Wednesday, January 7, 2009)]
[Notices]
[Page 701]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-36]



[[Page 701]]

-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army; Corps of Engineers


Termination of an Environmental Impact Statement for the 
Construction and Operation of a 300-MW Coal-Fired Electric Generating 
Unit Proposed by Wisconsin Power and Light Company Near Cassville in 
Grant County, WI

AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.

ACTION: Notice of Termination.

-----------------------------------------------------------------------

SUMMARY: The St. Paul District, Corps of Engineers (Corps) is canceling 
the preparation of a federal Environmental Impact Statement (EIS) for 
the proposal by Wisconsin Power and Light Company (WPL) to conduct work 
below the ordinary high water mark of the Mississippi River, a 
navigable water of the U.S., and to discharge dredged or fill material 
into waters of the U.S. to facilitate the construction and operation of 
a 300 megawatt (MW) baseload coal-fired electric generating unit, 
referred to as NED 3, near Cassville in Grant County, WI. The Corps has 
terminated its review of the WPL permit application due to WPL's 
withdrawal of their permit application on November 21, 2008.

ADDRESSES: Questions concerning this termination notice can be 
addressed to Ms. Tamara Cameron, Regulatory Branch by letter at U.S. 
Army Corps of Engineers, 190 Fifth Street East, Suite 401, St. Paul, MN 
55101-1638, by telephone or by e-mail at 
tamara.e.cameron@usace.army.mil.

FOR FURTHER INFORMATION CONTACT: Ms. Tamara Cameron, (651) 290-5197.

SUPPLEMENTARY INFORMATION: On January 17, 2008 the Corps published in 
the Federal Register (73 FR 3241) a notice of intent to prepare an EIS 
jointly with the Public Service Commission of Wisconsin (PSCW). Scoping 
meetings were held in January and March, 2008 and a notice of 
availability of the draft EIS was published in the Federal Register (73 
FR 30099) on May 23, 2008.
    In July 2008, WPL modified their proposal so that work would be 
done under and over the Mississippi River, but not in the River, and 
there would be no discharges of dredged or fill material into any 
waters of the U.S. On November 21, 2008, WPL withdrew their permit 
application, and consequently the Corps has decided to terminate the 
EIS.
    If WPL submits a subsequent permit application for work over and/or 
under the Mississippi River, as detailed in their most recent proposal, 
the Corps would evaluate the application under the terms of a 
Nationwide Permit, as applicable, or prepare an Environmental 
Assessment as part of its standard permit application review.

    Dated: December 22, 2008.
Jon L. Christensen,
Colonel, Corps of Engineers, District Engineer.
[FR Doc. E9-36 Filed 1-6-09; 8:45 am]
BILLING CODE 3720-58-P