Carolina Power & Light Company; Shearon Harris Nuclear Power Plant, Unit 1; Notice of Issuance of Renewed Facility Operating License No. NPF-63 for an Additional 20-Year Period; Record of Decision, 78857-78858 [E8-30477]
Download as PDF
Federal Register / Vol. 73, No. 247 / Tuesday, December 23, 2008 / Notices
ACTION: Notice of Granting of Request to
Extend the Comment Period of Draft
Regulatory Guides, DG–1186 and DG–
4013.
FOR FURTHER INFORMATION CONTACT:
Steve Garry, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, telephone: (301) 415–2766 or email to Steve.Garry@nrc.gov.
SUPPLEMENTARY INFORMATION:
Response to Request
I. Introduction
The U.S. Nuclear Regulatory
Commission (NRC) issued for public
comment DG–1186, ‘‘Measuring,
Evaluating, and Reporting Radioactive
Materials in Liquid and Gaseous
Effluents and Solid Wastes,’’ which was
published in the Federal Register, 73 FR
65705, on November 4, 2008. DG–1186
is proposed Revision 2 of Regulatory
Guide 1.21.
NRC also issued for public comment
DG–4013, ‘‘Environmental Monitoring
for Nuclear Power Plants,’’ which was
published in the Federal Register, 73 FR
66685, on November 10, 2008. DG–4013
is proposed Revision 2 of Regulatory
Guide 4.1.
The DGs are in the agency’s
‘‘Regulatory Guide’’ series. This series
has been developed to describe and
make available to the public such
information as methods that are
acceptable to the NRC staff for
implementing specific parts of the
NRC’s regulations, techniques that the
staff uses in evaluating specific
problems or postulated accidents, and
data that the staff needs in its review of
applications for permits and licenses.
II. Further Information
The NRC staff requested receipt of
comments on DG–1186 by December 30,
2008, and the receipt of comments on
DG–4013 by January 9, 2009. By this
action, the NRC staff is extending the
comment period until January 30, 2009,
for DG–1186 and DG–4013. Comments
received after January 30, 2009 for DG–
1186 and DG–4013, would be
considered if practical to do so, but the
NRC is able to ensure consideration
only for comments received on or before
January 30, 2009. Although a time limit
is given, comments and suggestions in
connection with items for inclusion in
guides currently being developed or
improvements in all published guides
are encouraged at any time.
III. Request To Extend the Comment
Period
Basis for the Request
The NRC received the following
extension request:
VerDate Aug<31>2005
16:29 Dec 22, 2008
Jkt 217001
In a letter, the Nuclear Energy
Institute requested that the public
review and comment period on DG–
1186 and DG–4013 be extended to
January 30, 2009. This will allow the
public an opportunity to formulate
comments because there is an NRC
public meeting on the two draft guides
scheduled for January 15, 2009.
The request for an extension to the
comment period is approved until
January 30, 2009.
Requests for technical information
about DG–1186 and DG–4013 may be
directed to the NRC contact, Steve Garry
at (301) 415–2766 or e-mail to
Steve.Garry@nrc.gov.
Electronic copies of DG–1186 are
available through the NRC’s public Web
site under Draft Regulatory Guides in
the ‘‘Regulatory Guides’’ collection of
the NRC’s Electronic Reading Room at
https://www.nrc.gov/reading-rm/doccollections/. Electronic copies are also
available in ADAMS (https://
www.nrc.gov/reading-rm/adams.html),
under Accession No. ML080660617.
Electronic copies of DG–4013 are also
available through the NRC’s public Web
site under Draft Regulatory Guides in
the ‘‘Regulatory Guides’’ collection of
the NRC’s Electronic Reading Room at
https://www.nrc.gov/reading-rm/doccollections/. Electronic copies are also
available in ADAMS (https://
www.nrc.gov/reading-rm/adams.html),
under Accession No. ML080660608.
In addition, regulatory guides are
available for inspection at the NRC’s
Public Document Room (PDR), which is
located at 11555 Rockville Pike,
Rockville, Maryland. The PDR’s mailing
address is USNRC PDR, Washington, DC
20555–0001. The PDR can also be
reached by telephone at (301) 415–4737
or (800) 397–4205, by fax at (301) 415–
3548, and by e-mail to
pdr.resource@nrc.gov.
Regulatory guides are not
copyrighted, and Commission approval
is not required to reproduce them.
Dated at Rockville, Maryland, this 17th day
of December, 2008.
For the Nuclear Regulatory Commission.
Andrea D. Valentin,
Chief, Regulatory Guide Development Branch,
Division of Engineering, Office of Nuclear
Regulatory Research.
[FR Doc. E8–30476 Filed 12–22–08; 8:45 am]
BILLING CODE 7590–01–P
PO 00000
Frm 00137
Fmt 4703
Sfmt 4703
78857
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–400]
Carolina Power & Light Company;
Shearon Harris Nuclear Power Plant,
Unit 1; Notice of Issuance of Renewed
Facility Operating License No. NPF–63
for an Additional 20-Year Period;
Record of Decision
Notice is hereby given that the U.S.
Nuclear Regulatory Commission (the
Commission or NRC) has issued
Renewed Facility Operating License No.
NPF–63 to the Carolina Power & Light
Company (the licensee), now doing
business as Progress Energy Carolinas,
Inc., the operator of the Shearon Harris
Nuclear Power Plant (HNP), Unit 1.
Renewed Facility Operating License No.
NPF–63 authorizes operation of HNP by
the licensee at reactor core power levels
not in excess of 2900 megawatts thermal
(900 megawatts electric), in accordance
with the provisions of the HNP renewed
license and its Technical Specifications.
This notice also serves as the record
of decision for the renewal of Facility
Operating License No. NPF–63 for HNP,
consistent with Title 10 of the Code of
Federal Regulations (10 CFR) Section
51.103. As discussed in the Final
Supplemental Environmental Impact
Statement (FSEIS) for HNP, dated
August 2008, the Commission
considered a range of reasonable
alternatives that included generation
from coal, natural gas, oil, wind, solar,
hydropower, geothermal, wood waste,
municipal solid waste, other biomassderived fuels, delayed retirement,
utility-sponsored conservation, a
combination of alternatives, and a noaction alternative. The factors
considered in the record of decision can
be found in the supplemental
environmental impact statement for
License Renewal, Supplement 33
regarding HNP, Unit 1.
HNP is a pressurized-water reactor
designed by the Westinghouse Electric
Corporation that is located in Wake
County, North Carolina, approximately
twenty miles southwest of Raleigh,
North Carolina. The application for the
renewed license complied with the
standards and requirements of the
Atomic Energy Act of 1954, as amended
(the Act), and the Commission’s
regulations. As required by the Act and
the Commission’s regulations in 10 CFR
Chapter I, the Commission has made
appropriate findings, which are set forth
in the license.
Prior public notice of the action
involving the proposed issuance of the
renewed license and of an opportunity
for a hearing regarding the proposed
E:\FR\FM\23DEN1.SGM
23DEN1
78858
Federal Register / Vol. 73, No. 247 / Tuesday, December 23, 2008 / Notices
issuance of the renewed license was
published in the Federal Register on
March 20, 2007 (72 FR 13139). For
further details with respect to this
action, see (1) The Carolina Power &
Light Company, license renewal
application for HNP, dated November
14, 2006, as supplemented by letters
dated through July 21, 2008; (2) the
Commission’s Safety Evaluation Report
(NUREG–1916 Volumes 1 and 2),
published in December 2008; (3) the
licensee’s updated safety analysis
report; and (4) the Commission’s FSEIS
(NUREG–1437, Supplement 33),
published in August 2008. These
documents are available at the NRC
Public Document Room, One White
Flint North, 11555 Rockville Pike,
Rockville, Maryland 20852, and can be
viewed from the NRC Public Electronic
Reading Room at https://www.nrc.gov/
reading-rm/adams.html.
Copies of the Renewed Facility
Operating License No. NPF–63 may be
obtained by writing to the U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001, Attention: Director,
Division of License Renewal. Copies of
the HNP, Unit 1, Safety Evaluation
Report (NUREG–1916 Volumes 1 and 2)
and the FSEIS (NUREG–1437,
Supplement 33) may be purchased from
the National Technical Information
Service, U.S. Department of Commerce,
Springfield, Virginia 22161–0002
(https://www.ntis.gov), 703–605–6000, or
the Superintendent of Documents, U.S.
Government Printing Office, P.O. Box
371954, Pittsburgh, Pennsylvania
15250–7954, (https://
www.gpoaccess.gov), 202–512–1800. All
orders should clearly identify the NRC
publication number and the requester’s
Government Printing Office deposit
account number or a VISA or
MasterCard number and expiration date.
Dated at Rockville, Maryland, this 17th day
of December 2008.
For the Nuclear Regulatory Commission.
Brian E. Holian,
Director, Division of License Renewal, Office
of Nuclear Reactor Regulation.
[FR Doc. E8–30477 Filed 12–22–08; 8:45 am]
BILLING CODE 7590–01–P
VerDate Aug<31>2005
16:29 Dec 22, 2008
Jkt 217001
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–483]
Union Electric Company; Notice of
Consideration of Issuance of
Amendment to Facility Operating
License, Proposed No Significant
Hazards Consideration Determination,
and Opportunity for a Hearing
The U.S. Nuclear Regulatory
Commission (the Commission) is
considering issuance of an amendment
to Facility Operating License No. NPF–
30 issued to Union Electric Company
(the licensee) for operation of the
Callaway Plant, Unit 1 located in
Callaway County, Missouri.
By letter dated October 31, 2008, the
Nuclear Regulatory Commission issued
Amendment No. 186, to Callaway Plant,
Unit 1, Facility Operating License No.
NPF–30. The amendment allowed a
one-time extension of the allowed
outage time (completion time) for each
of the two essential service water (ESW)
trains (ESW Train A and Train B) from
72 hours to 14 days. The extended
completion time was requested to
support planned replacement of the
underground carbon steel piping with
new high density polyethylene (HDPE)
piping for ESW Train A and ESW Train
B during plant operation. The
amendment was issued with a
requirement to complete the
replacement of carbon steel piping with
HDPE for both ESW trains by December
31, 2008. By its application dated
December 1, 2008, the licensee informed
NRC that it had experienced significant
delays in completing the replacement of
underground piping/conduit of ESW
Train A, due, in part, to underground
obstructions during excavation, a longer
refueling outage (Refuel 16) than
anticipated, a forced outage at the
beginning of Cycle 17, switchyard
maintenance, and other equipment and
personnel issues. Therefore, the licensee
proposed a change in plant modification
dates for replacement of ESW Train B
carbon steel piping. The present plan
calls for completing the modification of
ESW Train A by December 31, 2008, as
approved by Amendment No. 186.
Consequently, the proposed amendment
would extend the implementation date
for completion of replacement of carbon
steel piping for ESW Train B from
December 31, 2008, to April 30, 2009.
Before issuance of the proposed
license amendment, the Commission
will have made findings required by the
Atomic Energy Act of 1954, as amended
(the Act), and the Commission’s
regulations.
PO 00000
Frm 00138
Fmt 4703
Sfmt 4703
The Commission has made a
proposed determination that the
amendment request involves no
significant hazards consideration. Under
the Commission’s regulations in Title 10
of the Code of Federal Regulations (10
CFR), Section 50.92, this means that
operation of the facility in accordance
with the proposed amendment would
not (1) Involve a significant increase in
the probability or consequences of an
accident previously evaluated; or (2)
create the possibility of a new or
different kind of accident from any
accident previously evaluated; or (3)
involve a significant reduction in a
margin of safety. As required by 10 CFR
50.91(a), the licensee has provided its
analysis of the issue of no significant
hazards consideration, which is
presented below:
1. Does the proposed change involve a
significant increase in the probability or
consequences of an accident previously
evaluated?
Response: No.
Overall protection system performance will
remain within the bounds of the previously
performed accident analyses since no
hardware changes are proposed to the
protection systems. The same reactor trip
system (RTS) and engineered safety feature
actuation system (ESFAS) instrumentation
will continue to be used. The protection
systems will continue to function in a
manner consistent with the plant design
basis. The use of polyethylene (PE) piping in
the ESW system will result in improved
system performance and enhanced system
reliability, and will provide an acceptable
level of quality and safety. There will be no
changes to the essential service water (ESW)
system or ultimate heat sink (UHS)
surveillance and operating limits.
The proposed changes will not adversely
affect accident initiators or precursors nor
alter the design assumptions, conditions, and
configuration of the facility or the manner in
which the plant is operated and maintained.
The proposed changes will not alter or
prevent the ability of structures, systems, and
components (SSCs) from performing their
intended functions to mitigate the
consequences of an initiating event within
the assumed acceptance limits.
The proposed changes do not affect the
way in which safety-related systems perform
their functions.
All accident analysis acceptance criteria
will continue to be met with the proposed
changes. The proposed changes will not
affect the source term, containment isolation,
or radiological release assumptions used in
evaluating the radiological consequences of
an accident previously evaluated. The
proposed changes will not alter any
assumptions or change any mitigation actions
in the radiological consequence evaluations
in the FSAR. The applicable radiological
dose acceptance criteria will continue to be
met.
Therefore, the proposed changes do not
involve a significant increase in the
E:\FR\FM\23DEN1.SGM
23DEN1
Agencies
[Federal Register Volume 73, Number 247 (Tuesday, December 23, 2008)]
[Notices]
[Pages 78857-78858]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-30477]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-400]
Carolina Power & Light Company; Shearon Harris Nuclear Power
Plant, Unit 1; Notice of Issuance of Renewed Facility Operating License
No. NPF-63 for an Additional 20-Year Period; Record of Decision
Notice is hereby given that the U.S. Nuclear Regulatory Commission
(the Commission or NRC) has issued Renewed Facility Operating License
No. NPF-63 to the Carolina Power & Light Company (the licensee), now
doing business as Progress Energy Carolinas, Inc., the operator of the
Shearon Harris Nuclear Power Plant (HNP), Unit 1. Renewed Facility
Operating License No. NPF-63 authorizes operation of HNP by the
licensee at reactor core power levels not in excess of 2900 megawatts
thermal (900 megawatts electric), in accordance with the provisions of
the HNP renewed license and its Technical Specifications.
This notice also serves as the record of decision for the renewal
of Facility Operating License No. NPF-63 for HNP, consistent with Title
10 of the Code of Federal Regulations (10 CFR) Section 51.103. As
discussed in the Final Supplemental Environmental Impact Statement
(FSEIS) for HNP, dated August 2008, the Commission considered a range
of reasonable alternatives that included generation from coal, natural
gas, oil, wind, solar, hydropower, geothermal, wood waste, municipal
solid waste, other biomass-derived fuels, delayed retirement, utility-
sponsored conservation, a combination of alternatives, and a no-action
alternative. The factors considered in the record of decision can be
found in the supplemental environmental impact statement for License
Renewal, Supplement 33 regarding HNP, Unit 1.
HNP is a pressurized-water reactor designed by the Westinghouse
Electric Corporation that is located in Wake County, North Carolina,
approximately twenty miles southwest of Raleigh, North Carolina. The
application for the renewed license complied with the standards and
requirements of the Atomic Energy Act of 1954, as amended (the Act),
and the Commission's regulations. As required by the Act and the
Commission's regulations in 10 CFR Chapter I, the Commission has made
appropriate findings, which are set forth in the license.
Prior public notice of the action involving the proposed issuance
of the renewed license and of an opportunity for a hearing regarding
the proposed
[[Page 78858]]
issuance of the renewed license was published in the Federal Register
on March 20, 2007 (72 FR 13139). For further details with respect to
this action, see (1) The Carolina Power & Light Company, license
renewal application for HNP, dated November 14, 2006, as supplemented
by letters dated through July 21, 2008; (2) the Commission's Safety
Evaluation Report (NUREG-1916 Volumes 1 and 2), published in December
2008; (3) the licensee's updated safety analysis report; and (4) the
Commission's FSEIS (NUREG-1437, Supplement 33), published in August
2008. These documents are available at the NRC Public Document Room,
One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852,
and can be viewed from the NRC Public Electronic Reading Room at http:/
/www.nrc.gov/reading-rm/adams.html.
Copies of the Renewed Facility Operating License No. NPF-63 may be
obtained by writing to the U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, Attention: Director, Division of License
Renewal. Copies of the HNP, Unit 1, Safety Evaluation Report (NUREG-
1916 Volumes 1 and 2) and the FSEIS (NUREG-1437, Supplement 33) may be
purchased from the National Technical Information Service, U.S.
Department of Commerce, Springfield, Virginia 22161-0002 (https://
www.ntis.gov), 703-605-6000, or the Superintendent of Documents, U.S.
Government Printing Office, P.O. Box 371954, Pittsburgh, Pennsylvania
15250-7954, (https://www.gpoaccess.gov), 202-512-1800. All orders should
clearly identify the NRC publication number and the requester's
Government Printing Office deposit account number or a VISA or
MasterCard number and expiration date.
Dated at Rockville, Maryland, this 17th day of December 2008.
For the Nuclear Regulatory Commission.
Brian E. Holian,
Director, Division of License Renewal, Office of Nuclear Reactor
Regulation.
[FR Doc. E8-30477 Filed 12-22-08; 8:45 am]
BILLING CODE 7590-01-P