City of Spearfish, SD; Notice of Scoping Meetings and Site Visit and Soliciting Scoping Comments, 74480-74481 [E8-28923]
Download as PDF
74480
Federal Register / Vol. 73, No. 236 / Monday, December 8, 2008 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12775–001]
City of Spearfish, SD; Notice of
Scoping Meetings and Site Visit and
Soliciting Scoping Comments
mstockstill on PROD1PC66 with NOTICES
December 2, 2008.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Major Project.
b. Project No.: P–12775–001.
c. Date filed: September 10, 2008.
d. Applicant: City of Spearfish, South
Dakota.
e. Name of Project: Spearfish
Hydroelectric Project.
f. Location: On Spearfish Creek in
Lawrence County, South Dakota. The
project occupies about 57.3 acres of
United States lands within the Black
Hills National Forest administered by
the U.S. Forest Service.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Ms. Cheryl
Johnson, Public Works Administrator,
City of Spearfish, 625 Fifth Street,
Spearfish, SD 57783; (605) 642–1333; or
e-mail at cherylj@city.spearfish.sd.us.
i. FERC Contact: Steve Hocking at
(202) 502–8753; or e-mail at
steve.hocking@ferc.gov.
j. Deadline for filing scoping
comments: February 13, 2009.
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedures require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
Scoping comments may be filed
electronically via the Internet in lieu of
paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov) under the ‘‘eFiling’’ link.
k. This application is not ready for
environmental analysis at this time.
l. The existing Spearfish Project
consists of: (1) A 130-foot-long, 4-foot-
VerDate Aug<31>2005
16:32 Dec 05, 2008
Jkt 217001
high concrete gravity dam; (2) a 0.32acre reservoir; (3) a gatehouse next to
the dam that contains four 2-foot-high,
4-foot-wide steel intake gates; (4) a 4.5mile-long, 6.5-foot-wide, 9-foot-high
concrete-lined rock tunnel; (5) a forebay
pond; (6) two 1,200-foot-long, 48-inch
diameter, wood stave pipelines; (7) four
36-inch-diameter, 54-foot-high
standpipe surge towers; (8) two 4,700foot-long, 30-to 34-inch diameter steel
penstocks; (9) a reinforced concrete
powerhouse containing two Pelton
turbines and two, 2,000-kilowatt
generators; and (10) appurtenant
facilities.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202)
502–8659. A copy is also available for
inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
e-mail of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Scoping Process
The Commission intends to prepare a
single (no draft) environmental
assessment (EA) for the project in
accordance with the National
Environmental Policy Act. The EA will
consider both site-specific and
cumulative environmental impacts and
reasonable alternatives to the proposed
action.
Scoping Meetings
Commission staff will conduct one
agency scoping meeting and one public
meeting. The agency scoping meeting
will focus on resource agency and nongovernmental organization (NGO)
concerns, while the public scoping
meeting is primarily for public input.
All interested individuals,
organizations, and agencies are invited
to attend one or both of the meetings,
and to assist the staff in identifying the
scope of the environmental issues that
should be analyzed in the EA. The times
and locations of these meetings are as
follows:
Evening Scoping Meeting
Date and Time: January 13, 2009,
from 7 p.m. to 10 p.m.
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
Location: City of Spearfish Council
Center, 625 Fifth Street, Spearfish, SD
57783.
Daytime Scoping Meeting
Date and Time: January 14, 2009,
from 10 a.m. to 2 p.m.
Location: City of Spearfish Council
Center, 625 Fifth Street, Spearfish, SD
57783.
Copies of the Scoping Document
(SD1) outlining the subject areas to be
addressed in the EA were distributed to
the parties on the Commission’s mailing
list for this project. Copes of SD1 will
be available at the scoping meeting or
may be viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link
(see item m above).
Site Visit
Commission staff will hold a site visit
to the project on January 13, 2009, from
9 a.m. to about 12 noon. Anyone
wishing to attend the site visit should
meet at the Spearfish Project
powerhouse at 9 a.m. located at 520 S.
Canyon, Spearfish, South Dakota 57783.
We will drive to the dam and stop along
the way to view Spearfish Creek; drive
to the project’s forebay and standpipe
facilities; then drive back to the project’s
powerhouse and take a tour of the
powerhouse. All participants are
responsible for their own transportation.
The site visit scheduled for January
13, 2009, is weather dependent. If the
site visit is cancelled, notice will be
placed on the Commission’s January 13,
2009, calendar which can be found on
the Commission’s Web site (https://
www.ferc.gov). Please check the
Commission’s January 13, 2009,
calendar before leaving in the morning
to attend the site visit.
Objectives
At the scoping meetings, the staff will:
(1) Summarize the environmental issues
tentatively identified for analysis in the
EA; (2) solicit from the meeting
participants all available information,
especially quantifiable data, on the
resources at issue; (3) encourage
statements from experts and the public
on issues that should be analyzed in the
EA, including viewpoints in opposition
to, or in support of, the staff’s
preliminary views; (4) determine the
resource issues to be addressed in the
EA; and (5) identify those issues that
require a detailed analysis, as well as
those issues that do not require a
detailed analysis.
Procedures
Scoping meetings will be recorded by
a stenographer and will become part of
E:\FR\FM\08DEN1.SGM
08DEN1
74481
Federal Register / Vol. 73, No. 236 / Monday, December 8, 2008 / Notices
the Commission’s formal record for this
proceeding.
Individuals, organizations, and
agencies with environmental expertise
and concerns are encouraged to attend
the meeting and to assist the staff in
defining and clarifying the issues to be
addressed in the EA.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–28923 Filed 12–5–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12611–003]
Verdant Power, LLC; Notice of Intent
To File License Application, Filing of
Draft Application, Request for Waivers
of Integrated Licensing Process
Regulations Necessary for Expedited
Processing of a Hydrokinetic Pilot
Project License Application, Extending
the Comment Period, and Soliciting
Comments
December 1, 2008.
a. Type of Filing: Notice of Intent to
File a License Application for an
Original License for a Hydrokinetic Pilot
Project.
b. Project No.: 12611–003.
c. Date Filed: November 25, 2008.
d. Submitted By: Verdant Power, LLC.
e. Name of Project: Roosevelt Island
Tidal Energy Project.
f. Location: In the east channel of the
East River, in New York City, New York.
The project would not occupy federal
lands.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Applicant Contact: Ronald F.
Smith, Verdant Power, LLC, The
Octagon, 888 Main Street, New York,
NY 10044 (212) 888–8887 ext 601.
i. FERC Contact: Tom Dean (202) 502–
6041.
j. Verdant Power, LLC (Verdant
Power) has filed with the Commission:
(1) A notice of intent (NOI) to file an
application for an original license for a
kinetic hydropower pilot project and a
draft license application with
monitoring plans; (2) a request for
waivers of the integrated licensing
process regulations necessary for
expedited processing of a hydrokinetic
pilot project license application,
including extending the period to file
comments on the draft license
application and monitoring plans; (3) a
proposed process plan and schedule; (4)
a request to be designated as the nonfederal representative for section 7 of
the Endangered Species Act
consultation; and (5) a request to be
designated as the non-federal
representative for section 106
consultation under the National Historic
Preservation Act (collectively the prefiling materials).
k. With this notice, we are soliciting
comments on the pre-filing materials
listed in paragraph j above, including
the draft license application and
monitoring plans. All comments should
be sent to the address above in
paragraph h. The comment period has
been extended 45 days at the request of
Verdant Power to take into
consideration the holiday season. In
addition, all comments (original and
eight copies) must be filed with the
Commission at the following address:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
All filings with the Commission must
include on the first page, the project
name (Roosevelt Island Tidal Energy
Project) and number (P–12611–003),
and bear the heading ‘‘Comments on the
proposed Roosevelt Island Tidal Energy
Project.’’ Any individual or entity
interested in submitting comments on
the pre-filing materials must do so by
January 9, 2009.
Comments may be filed electronically
via the Internet in lieu of paper. The
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-filing’’ link.
l. With this notice, we are approving
Verdant Power’s request to be
designated as the non-federal
representative for section 7 of the
Endangered Species Act (ESA) and its
request to initiate consultation under
section 106 of the National Historic
Preservation Act; and recommending
that it begin informal consultation with:
(a) the U.S. Fish and Wildlife Service
and the National Marine Fisheries
Service as required by section 7 of ESA;
and (b) the New York State Historic
Preservation Officer, as required by
section 106, National Historical
Preservation Act, and the implementing
regulations of the Advisory Council on
Historic Preservation at 36 CFR 800.2.
m. This notice does not constitute the
Commission’s approval of Verdant
Power’s request to use the Pilot Project
Licensing Procedures. Upon its review
of the project’s overall characteristics
relative to the pilot project criteria, the
draft license application contents, and
any comments filed, the Commission
will determine whether there is
adequate information to conclude the
pre-filing process.
n. The proposed Roosevelt Island
Tidal Energy Project would consist of:
(1) A field array of thirty 35-kilowatt, 5meter-diameter axial flow Kinetic
Hydropower System (KHPS) turbinegenerator units mounted on ten triframe
mounts, with a total capacity of about 1
megawatt; (2) underwater cables from
each turbine to five shoreline switchgear
vaults, that would interconnect to a
control room and interconnection
points; and (3) appurtenant facilities for
navigation safety and operation. The
estimated annual generation of the
proposed project would be between
1,680 and 2,400 megawatt-hours.
o. A copy of the draft license
application and all pre-filing materials
are available for review at the
Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCONlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in paragraph h.
p. Pre-filing process schedule. The
pre-filing process will be conducted
pursuant to the following tentative
schedule. Revisions to the schedule may
be made as appropriate.
mstockstill on PROD1PC66 with NOTICES
Milestone
Date
Comments on pre-filing materials due .......................................................................................................
Issuance of meeting notice (if needed) ......................................................................................................
Public meeting/technical conference (if needed) .......................................................................................
Issuance of notice concluding pre-filing process and ILP waiver request determination ..........................
January 9, 2009.
January 26, 2009.
February 25, 2009.
February 9, 2009 (if no meeting is needed).
March 12, 2009 (if meeting is needed).
VerDate Aug<31>2005
16:32 Dec 05, 2008
Jkt 217001
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
E:\FR\FM\08DEN1.SGM
08DEN1
Agencies
[Federal Register Volume 73, Number 236 (Monday, December 8, 2008)]
[Notices]
[Pages 74480-74481]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-28923]
[[Page 74480]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12775-001]
City of Spearfish, SD; Notice of Scoping Meetings and Site Visit
and Soliciting Scoping Comments
December 2, 2008.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Major Project.
b. Project No.: P-12775-001.
c. Date filed: September 10, 2008.
d. Applicant: City of Spearfish, South Dakota.
e. Name of Project: Spearfish Hydroelectric Project.
f. Location: On Spearfish Creek in Lawrence County, South Dakota.
The project occupies about 57.3 acres of United States lands within the
Black Hills National Forest administered by the U.S. Forest Service.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Ms. Cheryl Johnson, Public Works
Administrator, City of Spearfish, 625 Fifth Street, Spearfish, SD
57783; (605) 642-1333; or e-mail at cherylj@city.spearfish.sd.us.
i. FERC Contact: Steve Hocking at (202) 502-8753; or e-mail at
steve.hocking@ferc.gov.
j. Deadline for filing scoping comments: February 13, 2009.
All documents (original and eight copies) should be filed with:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice and Procedures require all
intervenors filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
Scoping comments may be filed electronically via the Internet in
lieu of paper. The Commission strongly encourages electronic filings.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site (https://www.ferc.gov) under the ``e-Filing'' link.
k. This application is not ready for environmental analysis at this
time.
l. The existing Spearfish Project consists of: (1) A 130-foot-long,
4-foot-high concrete gravity dam; (2) a 0.32-acre reservoir; (3) a
gatehouse next to the dam that contains four 2-foot-high, 4-foot-wide
steel intake gates; (4) a 4.5-mile-long, 6.5-foot-wide, 9-foot-high
concrete-lined rock tunnel; (5) a forebay pond; (6) two 1,200-foot-
long, 48-inch diameter, wood stave pipelines; (7) four 36-inch-
diameter, 54-foot-high standpipe surge towers; (8) two 4,700-foot-long,
30-to 34-inch diameter steel penstocks; (9) a reinforced concrete
powerhouse containing two Pelton turbines and two, 2,000-kilowatt
generators; and (10) appurtenant facilities.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at (866)
208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Scoping Process
The Commission intends to prepare a single (no draft) environmental
assessment (EA) for the project in accordance with the National
Environmental Policy Act. The EA will consider both site-specific and
cumulative environmental impacts and reasonable alternatives to the
proposed action.
Scoping Meetings
Commission staff will conduct one agency scoping meeting and one
public meeting. The agency scoping meeting will focus on resource
agency and non-governmental organization (NGO) concerns, while the
public scoping meeting is primarily for public input. All interested
individuals, organizations, and agencies are invited to attend one or
both of the meetings, and to assist the staff in identifying the scope
of the environmental issues that should be analyzed in the EA. The
times and locations of these meetings are as follows:
Evening Scoping Meeting
Date and Time: January 13, 2009, from 7 p.m. to 10 p.m.
Location: City of Spearfish Council Center, 625 Fifth Street,
Spearfish, SD 57783.
Daytime Scoping Meeting
Date and Time: January 14, 2009, from 10 a.m. to 2 p.m.
Location: City of Spearfish Council Center, 625 Fifth Street,
Spearfish, SD 57783.
Copies of the Scoping Document (SD1) outlining the subject areas to
be addressed in the EA were distributed to the parties on the
Commission's mailing list for this project. Copes of SD1 will be
available at the scoping meeting or may be viewed on the Web at https://
www.ferc.gov using the ``eLibrary'' link (see item m above).
Site Visit
Commission staff will hold a site visit to the project on January
13, 2009, from 9 a.m. to about 12 noon. Anyone wishing to attend the
site visit should meet at the Spearfish Project powerhouse at 9 a.m.
located at 520 S. Canyon, Spearfish, South Dakota 57783. We will drive
to the dam and stop along the way to view Spearfish Creek; drive to the
project's forebay and standpipe facilities; then drive back to the
project's powerhouse and take a tour of the powerhouse. All
participants are responsible for their own transportation.
The site visit scheduled for January 13, 2009, is weather
dependent. If the site visit is cancelled, notice will be placed on the
Commission's January 13, 2009, calendar which can be found on the
Commission's Web site (https://www.ferc.gov). Please check the
Commission's January 13, 2009, calendar before leaving in the morning
to attend the site visit.
Objectives
At the scoping meetings, the staff will: (1) Summarize the
environmental issues tentatively identified for analysis in the EA; (2)
solicit from the meeting participants all available information,
especially quantifiable data, on the resources at issue; (3) encourage
statements from experts and the public on issues that should be
analyzed in the EA, including viewpoints in opposition to, or in
support of, the staff's preliminary views; (4) determine the resource
issues to be addressed in the EA; and (5) identify those issues that
require a detailed analysis, as well as those issues that do not
require a detailed analysis.
Procedures
Scoping meetings will be recorded by a stenographer and will become
part of
[[Page 74481]]
the Commission's formal record for this proceeding.
Individuals, organizations, and agencies with environmental
expertise and concerns are encouraged to attend the meeting and to
assist the staff in defining and clarifying the issues to be addressed
in the EA.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-28923 Filed 12-5-08; 8:45 am]
BILLING CODE 6717-01-P