Proposed Phase 1 Decommissioning Plan for the West Valley Demonstration Project, West Valley, NY, 74162-74163 [E8-28807]
Download as PDF
dwashington3 on PROD1PC60 with NOTICES
74162
Federal Register / Vol. 73, No. 235 / Friday, December 5, 2008 / Notices
NYSERDA needs to determine what
material or structures for which it is
responsible will remain on site, and
what institutional controls, engineered
barriers, or stewardship provisions
would be needed.
This Draft EIS is intended to support
DOE and NYSERDA decisions regarding
the Proposed Action, which is the
completion of the WVDP and the
decommissioning and/or long-term
management or stewardship of the
WNYNSC. This would include the
disposition of the high-level radioactive
waste storage tanks, the former spent
fuel reprocessing plant, the North
Plateau Groundwater Plume, the Cesium
Prong, the NRC-licensed Disposal Area
(NDA), and the State-licensed Disposal
Area (SDA). The three action
alternatives evaluated for the Proposed
Action are as follows:
Sitewide Removal: Under this
alternative, all site facilities as outlined
in this Draft EIS would be removed; all
environmental media would be
decontaminated; and all radioactive,
hazardous, and mixed waste would be
characterized, packaged as necessary,
and shipped off site for disposal.
Completion of these activities would
allow unrestricted use of the site (i.e.,
the site could be made available for any
public or private use). This alternative
includes temporary onsite storage of
vitrified high-level radioactive waste
canisters pending the availability of a
Federal repository.
Sitewide Close-In-Place: Under this
alternative, most facilities would be
closed in place. Residual radioactivity
in facilities with larger inventories of
long-lived radionuclides would be
isolated by specially designed closure
structures and engineered barriers.
Major facilities and sources of
contamination, such as the Waste Tank
Farm and burial grounds, would be
managed at their current locations. This
would allow large areas of the site to be
released for unrestricted use. The
license for remaining portions of the
WNYNSC could be terminated under
restricted conditions, or those portions
could remain under long-term NRC
license or permit. Facilities that are
closed in-place, and any buffer areas
around them, would require long-term
stewardship.
Phased Decisionmaking: Under this
alternative, decommissioning would be
completed in two phases. This
alternative involves near-term removal
actions where there is agency consensus
and characterization studies to facilitate
decisionmaking for the remaining
facilities or areas.
Phase 1 would include removal of the
Main Plant Process Building, the source
VerDate Aug<31>2005
15:27 Dec 04, 2008
Jkt 217001
of the North Plateau Groundwater
Plume, and the lagoons on the WVDP
premises. All facilities and the lagoons
would be removed, except for the
permeable treatment wall (an in-situ
groundwater mitigation technology).
Phase 1 decisions would also include
removal of a number of other facilities
on the WVDP premises. No
decommissioning or long-term
management activities would be
conducted for the Waste Tank Farm and
its support facilities, the construction
and demolition debris landfill, the nonsource area of the North Plateau
Groundwater Plume, or the NDA. The
SDA would continue under active
management, consistent with its permit
and license requirements. Phase 1
activities would make use of proven
technologies and available waste
disposal sites to reduce the potential
near-term health and safety risks from
residual radioactivity and hazardous
contaminants at the site. Phase 1 would
also include an ongoing assessment
period during which DOE and
NYSERDA would conduct additional
studies, evaluations, and
characterization of site contamination.
The studies and evaluations would be
conducted to clarify and possibly
reduce technical uncertainties related to
the decision on final decommissioning
and long-term management of the site,
particularly uncertainties associated
with the long-term performance models,
the performance of engineered barriers
and other technologies for in-place
containment, the viability and cost of
technology for exhuming buried waste,
and the availability of waste disposal
sites. In consultation with NYSERDA
and the cooperating and involved
agencies on this Draft EIS, DOE would
determine whether the new information
warrants a new or supplemental EIS.
NYSERDA also would assess the results
of site-specific studies and other
information during Phase 1 to determine
the need for additional SEQRA
documentation.
According to the approach
determined most appropriate during the
additional Phase 1 studies and
evaluations, Phase 2 would complete
decommissioning or long-term
management decisionmaking. Under the
Phased Decisionmaking Alternative, the
Phase 2 decision would be made within
30 years.
No Action Alternative: Under this
alternative, no actions toward
decommissioning would be taken. This
alternative would involve the continued
management and oversight of all
facilities located on the WNYNSC
property as of the Starting Point for this
EIS in 2011. The No Action Alternative
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
does not meet the Purpose and Need for
agency action, but analysis of the No
Action Alternative is required under
NEPA and SEQRA as a basis of
comparison.
Preferred Alternative: The Phased
Decisionmaking Alternative is DOE’s
and NYSERDA’s Preferred Alternative.
Combination Alternatives: DOE and
NYSERDA recognize that, after
consideration of public comments, some
combination of alternatives analyzed in
the Draft EIS may be identified as the
best way to meet agency goals and
protect human health and safety and the
environment. If a specific combination
alternative is identified as preferred
between the Draft and Final EISs, DOE
would present the combination
alternative and its potential impacts in
the Final EIS. If a combination
alternative is ultimately selected for
implementation, the Record of Decision
and Findings Statement (under SEQRA)
would explain the reasons DOE and
NYSERDA made that decision.
Following the end of the public
comment period, DOE will consider and
respond to the comments received, and
issue the Final Decommissioning and/or
Long-Term Stewardship EIS, including
a Comment Response Document. DOE
will issue a Record of Decision no
sooner than 30 days after EPA issues a
Notice of Availability of the final EIS in
the Federal Register.
Signed in Washington, DC, November 25,
2008.
Ines R. Triay,
Acting Assistant Secretary for Environmental
Management.
[FR Doc. E8–28806 Filed 12–4–08; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Proposed Phase 1 Decommissioning
Plan for the West Valley Demonstration
Project, West Valley, NY
AGENCY: Department of Energy.
ACTION: Notice of availability.
SUMMARY: The U.S. Department of
Energy (DOE) announces the availability
of the proposed Phase 1
Decommissioning Plan for the West
Valley Demonstration Project (WVDP) at
the Western New York Nuclear Service
Center in West Valley, New York
(WNYNSC). The proposed Phase 1
Decommissioning Plan is consistent
with DOE’s preferred alternative in the
Revised Draft Environmental Impact
Statement for the Decommissioning
and/or Long-Term Stewardship at the
West Valley Demonstration Project and
Western New York Nuclear Service
E:\FR\FM\05DEN1.SGM
05DEN1
dwashington3 on PROD1PC60 with NOTICES
Federal Register / Vol. 73, No. 235 / Friday, December 5, 2008 / Notices
Center (Draft EIS, DOE/EIS–02260). DOE
intends, at a future date, to issue a
Record of Decision pursuant to the Final
EIS. The proposed Phase 1
Decommissioning Plan is being
reviewed by the U.S. Nuclear Regulatory
Commission (NRC). The Department
will consider NRC comments prior to
the initiation of decontamination and
decommissioning operations, and
should DOE during the course of the
National Environmental Policy Act
process or as a result of comments from
the NRC ultimately decide upon an
approach that differs from the current
preferred alternative in the Draft
Decommissioning EIS, or adopt changes
that affect the proposed Phase 1
Decommissioning Plan, then DOE will
revise the Phase 1 Decommissioning
Plan as necessary to reflect the changes.
ADDRESSES: Copies of the proposed
Phase 1 Decommissioning Plan for the
West Valley Demonstration Project are
available for public inspection at the
following locations:
U.S. Department of Energy, FOIA
Reading Room, Room 1E–190,
Forrestal Building, 1000
Independence Avenue, SW.,
Washington, DC 20585–0001;
Hulbert Library, DOE–WVDP Public
Reading Room, 18 Chapel St.,
Springville, NY 14141. 716–592–
7742; and
Ashford Office Complex Public Reading
Room, 9030 Route 219, West Valley,
NY 14171–0191. (716) 942–4679.
The proposed Phase 1
Decommissioning Plan is also available
at:
The U.S. Department of Energy West
Valley Demonstration Project Web
site, at https://www.wv.doe.gov; and
The U.S. Nuclear Regulatory
Commission Electronic Reading Room
Web site, at https://www.nrc.gov/
reading-rm/adams.html.
FOR FURTHER INFORMATION CONTACT:
Ms. Moira N. Maloney,
Decommissioning Plan Project
Manager, West Valley Demonstration
Project, U.S. Department of Energy,
10282 Rock Springs Road, West
Valley, NY 14171–0191;
Mr. Bryan C. Bower, Director, West
Valley Demonstration Project, U.S.
Department of Energy, 10282 Rock
Springs Road, West Valley, NY
14171–0191; and
Mr. Desi Crouther, Director, Office of
Small Sites Projects, Office of
Environmental Management, U.S.
Department of Energy, 1000
Independence Avenue, SW.,
Washington, DC 20585–0001.
SUPPLEMENTARY INFORMATION: The West
Valley Demonstration Project Act (the
VerDate Aug<31>2005
15:27 Dec 04, 2008
Jkt 217001
Act), Public Law 96–368 of October 1,
1980, directed the Department of Energy
to carry out a high-level radioactive
waste management demonstration
project at the WNYNSC. The purpose of
the project was to demonstrate the
solidification of high-level radioactive
waste for disposal in a Federal
repository. The Act also requires the
Department to decontaminate and
decommission the underground highlevel waste storage tanks and other
facilities where the solidified high-level
radioactive waste was stored, the
facilities used in the solidification of the
waste, and any material and hardware
used in connection with the project, in
accordance with such requirements as
the NRC may prescribe.
In accordance with the Act, DOE
entered into an agreement with the NRC
to establish arrangements for review and
consultation by the NRC for the Project.
The procedures for NRC review and
consultation were established in the
September 23, 1981 Memorandum of
Understanding and section 2(c)(1) of the
Act between DOE and NRC.
Accordingly, DOE is to submit to NRC,
for its review and comment, a Project
Decommissioning Plan for the facilities
that were used in solidifying the waste,
which includes a description of
engineering and operating activities to
be performed. The plan is to be
reviewed by the NRC and comments
provided to DOE. DOE is to review and
consider the comments provided prior
to the initiation of decontamination and
decommissioning operations.
The decommissioning activities
described in the proposed Phase 1
Decommissioning Plan for the West
Valley Demonstration Project are
consistent with the Phased Decisionmaking Alternative, the preferred
alternative described in the Revised
Draft Environmental Impact Statement
for Decommissioning and/or Long-Term
Stewardship at the West Valley
Demonstration Project and Western New
York Nuclear Service Center. Under the
Phased Decision-making Alternative,
the decommissioning of the Project and
WNYNSC would be completed in two
phases. Phase 1 decommissioning
activities within the Project premises,
which are described in the proposed
Phase 1 Decommissioning Plan, are
near-term removal actions that include
removal of the Main Plant Process
Building, Vitrification Facility, source
area of the North Plateau Groundwater
Plume, wastewater treatment facility
lagoons, and certain ancillary buildings,
foundations, slabs, and pads on the
WVDP premises. The Phase 2 decisions
on the decommissioning of the
remainder of the Project and WNYNSC,
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
74163
or its long-term management, would be
made in the future and is not part of the
proposed Phase 1 Decommissioning
Plan.
DOE will issue a Record of Decision
pursuant to section III.B.1 of the final
EIS no sooner than 30 days after the
U.S. Environmental Protection Agency
has published its Notice of Availability
in the Federal Register. DOE will revise
the proposed Phase 1 Decommissioning
Plan to be consistent with the Record of
Decision as necessary.
Issued in Washington, DC, on December 1,
2008.
Cynthia Anderson,
Deputy Chief Operations Officer.
[FR Doc. E8–28807 Filed 12–4–08; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. IC09–567–000, FERC–567]
Commission Information Collection
Activities, Proposed Collection;
Comment Request; Extension
November 28, 2008.
AGENCY: Federal Energy Regulatory
Commission.
ACTION: Notice of proposed information
collection and request for comments.
SUMMARY: In compliance with the
requirements of section 3506(c)(2)(a) of
the Paperwork Reduction Act of 1995
(Pub. L. 104–13), the Federal Energy
Regulatory Commission (Commission) is
soliciting public comment on the
specific aspects of the information
collection described below.
DATES: Comments in consideration of
the collection of information are due
January 30, 2009.
ADDRESSES: An example of this
collection of information may be
obtained from the Commission’s Web
site (at https://www.ferc.gov/docs-filing/
elibrary.asp). Comments may be filed
either electronically or in paper format,
and should refer to Docket No. IC09–
567–000. Documents must be prepared
in an acceptable filing format and in
compliance with the Federal Energy
Regulatory Commission submission
guidelines at https://www.ferc.gov/help/
submission-guide.asp.
Comments may be filed electronically
via the eFiling link on the Commission’s
Web site at www.ferc.gov. First time
users will have to establish a user name
and password (https://www.ferc.gov/
docs-filing/eregistration.asp) before
eFiling. The Commission will send an
E:\FR\FM\05DEN1.SGM
05DEN1
Agencies
[Federal Register Volume 73, Number 235 (Friday, December 5, 2008)]
[Notices]
[Pages 74162-74163]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-28807]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Proposed Phase 1 Decommissioning Plan for the West Valley
Demonstration Project, West Valley, NY
AGENCY: Department of Energy.
ACTION: Notice of availability.
-----------------------------------------------------------------------
SUMMARY: The U.S. Department of Energy (DOE) announces the availability
of the proposed Phase 1 Decommissioning Plan for the West Valley
Demonstration Project (WVDP) at the Western New York Nuclear Service
Center in West Valley, New York (WNYNSC). The proposed Phase 1
Decommissioning Plan is consistent with DOE's preferred alternative in
the Revised Draft Environmental Impact Statement for the
Decommissioning and/or Long-Term Stewardship at the West Valley
Demonstration Project and Western New York Nuclear Service
[[Page 74163]]
Center (Draft EIS, DOE/EIS-02260). DOE intends, at a future date, to
issue a Record of Decision pursuant to the Final EIS. The proposed
Phase 1 Decommissioning Plan is being reviewed by the U.S. Nuclear
Regulatory Commission (NRC). The Department will consider NRC comments
prior to the initiation of decontamination and decommissioning
operations, and should DOE during the course of the National
Environmental Policy Act process or as a result of comments from the
NRC ultimately decide upon an approach that differs from the current
preferred alternative in the Draft Decommissioning EIS, or adopt
changes that affect the proposed Phase 1 Decommissioning Plan, then DOE
will revise the Phase 1 Decommissioning Plan as necessary to reflect
the changes.
ADDRESSES: Copies of the proposed Phase 1 Decommissioning Plan for the
West Valley Demonstration Project are available for public inspection
at the following locations:
U.S. Department of Energy, FOIA Reading Room, Room 1E-190, Forrestal
Building, 1000 Independence Avenue, SW., Washington, DC 20585-0001;
Hulbert Library, DOE-WVDP Public Reading Room, 18 Chapel St.,
Springville, NY 14141. 716-592-7742; and
Ashford Office Complex Public Reading Room, 9030 Route 219, West
Valley, NY 14171-0191. (716) 942-4679.
The proposed Phase 1 Decommissioning Plan is also available at:
The U.S. Department of Energy West Valley Demonstration Project Web
site, at https://www.wv.doe.gov; and
The U.S. Nuclear Regulatory Commission Electronic Reading Room Web
site, at https://www.nrc.gov/reading-rm/adams.html.
FOR FURTHER INFORMATION CONTACT:
Ms. Moira N. Maloney, Decommissioning Plan Project Manager, West Valley
Demonstration Project, U.S. Department of Energy, 10282 Rock Springs
Road, West Valley, NY 14171-0191;
Mr. Bryan C. Bower, Director, West Valley Demonstration Project, U.S.
Department of Energy, 10282 Rock Springs Road, West Valley, NY 14171-
0191; and
Mr. Desi Crouther, Director, Office of Small Sites Projects, Office of
Environmental Management, U.S. Department of Energy, 1000 Independence
Avenue, SW., Washington, DC 20585-0001.
SUPPLEMENTARY INFORMATION: The West Valley Demonstration Project Act
(the Act), Public Law 96-368 of October 1, 1980, directed the
Department of Energy to carry out a high-level radioactive waste
management demonstration project at the WNYNSC. The purpose of the
project was to demonstrate the solidification of high-level radioactive
waste for disposal in a Federal repository. The Act also requires the
Department to decontaminate and decommission the underground high-level
waste storage tanks and other facilities where the solidified high-
level radioactive waste was stored, the facilities used in the
solidification of the waste, and any material and hardware used in
connection with the project, in accordance with such requirements as
the NRC may prescribe.
In accordance with the Act, DOE entered into an agreement with the
NRC to establish arrangements for review and consultation by the NRC
for the Project. The procedures for NRC review and consultation were
established in the September 23, 1981 Memorandum of Understanding and
section 2(c)(1) of the Act between DOE and NRC. Accordingly, DOE is to
submit to NRC, for its review and comment, a Project Decommissioning
Plan for the facilities that were used in solidifying the waste, which
includes a description of engineering and operating activities to be
performed. The plan is to be reviewed by the NRC and comments provided
to DOE. DOE is to review and consider the comments provided prior to
the initiation of decontamination and decommissioning operations.
The decommissioning activities described in the proposed Phase 1
Decommissioning Plan for the West Valley Demonstration Project are
consistent with the Phased Decision-making Alternative, the preferred
alternative described in the Revised Draft Environmental Impact
Statement for Decommissioning and/or Long-Term Stewardship at the West
Valley Demonstration Project and Western New York Nuclear Service
Center. Under the Phased Decision-making Alternative, the
decommissioning of the Project and WNYNSC would be completed in two
phases. Phase 1 decommissioning activities within the Project premises,
which are described in the proposed Phase 1 Decommissioning Plan, are
near-term removal actions that include removal of the Main Plant
Process Building, Vitrification Facility, source area of the North
Plateau Groundwater Plume, wastewater treatment facility lagoons, and
certain ancillary buildings, foundations, slabs, and pads on the WVDP
premises. The Phase 2 decisions on the decommissioning of the remainder
of the Project and WNYNSC, or its long-term management, would be made
in the future and is not part of the proposed Phase 1 Decommissioning
Plan.
DOE will issue a Record of Decision pursuant to section III.B.1 of
the final EIS no sooner than 30 days after the U.S. Environmental
Protection Agency has published its Notice of Availability in the
Federal Register. DOE will revise the proposed Phase 1 Decommissioning
Plan to be consistent with the Record of Decision as necessary.
Issued in Washington, DC, on December 1, 2008.
Cynthia Anderson,
Deputy Chief Operations Officer.
[FR Doc. E8-28807 Filed 12-4-08; 8:45 am]
BILLING CODE 6450-01-P