Littleville Power Company, Inc.; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Fishway Prescriptions, 66032-66033 [E8-26450]
Download as PDF
66032
Federal Register / Vol. 73, No. 216 / Thursday, November 6, 2008 / Notices
mechanisms, or any other natural or
human factors; and (5) efforts being
made to protect the species.
The Lynn Canal Pacific herring status
review is available at: https://
alaskafisheries.noaa.gov/
protectedresources/herring/.
Dated: October 27, 2008.
James H. Lecky,
Director, Office of Protected Resources,
National Marine Fisheries Service.
[FR Doc. E8–26543 Filed 11–5–08; 8:45 am]
more information on how to submit
these types of filings please go to the
Commission’s Web site located at https://
www.ferc.gov/filing-comments.asp.
More information about this project can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13203) in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3372.
BILLING CODE 3510–22–S
Kimberly D. Bose,
Secretary.
[FR Doc. E8–26452 Filed 11–5–08; 8:45 am]
DEPARTMENT OF ENERGY
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Project No. 13164–000]
Bangor Water District; Notice of
Conduit Exemption Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
sroberts on PROD1PC70 with NOTICES
October 30, 2008.
On April 11, 2008, Bangor Water
District filed an application, pursuant to
16 U.S.C. 791a–825r of the Federal
Power Act, for conduit exemption of the
Veazie Energy Recovery Project, to be
located on the water supply pipeline in
Penobscot County, Maine.
The proposed Veazie Energy Recovery
Project consists of: (1) A proposed
powerhouse containing one generating
unit having an installed capacity of 75
kilowatts, and (2) appurtenant facilities.
Bangor Water District estimates the
project would have an average annual
generation of 590 megawatt-hours,
which would be sold to a local utility.
Applicant Contact: Mrs. Kathy
Moriarity, General Manager, Bangor
Water District, P.O. Box 1129, Bangor,
ME 04402–1129, phone (207) 947–4516.
FERC Contact: Robert Bell, (202) 502–
6062.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and eight
copies should be mailed to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. For
VerDate Aug<31>2005
19:11 Nov 05, 2008
Jkt 217001
Federal Energy Regulatory
Commission
[Project No. 2801–027]
Littleville Power Company, Inc.; Notice
of Application Accepted for Filing,
Soliciting Motions To Intervene and
Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, Terms and
Conditions, and Fishway Prescriptions
October 30, 2008.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
License.
b. Project No.: P–2801–027.
c. Date filed: October 31, 2007.
d. Applicant: Littleville Power
Company, Inc.
e. Name of Project: Glendale
Hydroelectric Project.
f. Location: On the Housatonic River
in the Town of Stockbridge, Berkshire
County. The project does not affect
federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Kevin M. Webb,
Environmental Affairs Coordinator,
Littleville Power Company, Inc., One
Tech Drive, Suite 220, Andover, MA
01810, (978) 681–1900 ext. 809,
kevin.webb@northamerica.enel.it
i. FERC Contact: Kristen Murphy,
(202) 502–6236 or
kristen.murphy@ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments,
recommendations, terms and
conditions, and fishway prescriptions
is, December 30, 2008, 60 days from the
issuance of this notice; reply comments
are due, February 12, 2009, 105 days
from the issuance date of this notice.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Motions to intervene and protests may
be filed electronically via the Internet in
lieu of paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov) under the
‘‘eFiling’’ link.
k. This application has been accepted
for filing and is now is ready for
environmental analysis.
l. As licensed, the existing Glendale
Project consists of: (1) A 250-foot-long,
30-foot-high concrete gravity dam with
a 182-foot-long spillway; (2) a 23-acre
reservoir; (3) two manually-operated 10
by 10-foot intake gates; (4) a 1,500-footlong, 40-foot-wide intake canal; (5) a
forebay structure and a 250-foot-long,
12-foot-diameter steel penstock; (6) a
powerhouse with four turbine
generating units with a combined
installed capacity of 1,140-kilowatts; (7)
a 300-foot-long tailrace channel; (8) a
step-up transformer and an 83-foot-long,
13.8 kilovolt transmission line; and (9)
appurtenant facilities. The Housatonic
River reach that is bypassed by the
project (measured from the gatehouse to
the tailrace channel) is about 2,500 feet
long.
The proposed project would include a
new 165-kW turbine unit in the waste
gate slot located at the gatehouse
adjacent to the project dam. This unit
would operate off of a proposed
minimum bypassed reach flow of 90
cubic feet per second (cfs) or inflow. In
addition, the proposed project would
provide additional recreational access
through formal canoe portage facilities
and parking.
The applicant estimates that the total
average annual generation, with the
proposed additional turbine, would be
5,800 megawatt-hours. The applicant
proposes to continue to operate the
project in run-of-river mode with an
increase in minimum flow in the bypass
reach from 10 cfs to 90 cfs or inflow,
whichever is less. The purpose of the
E:\FR\FM\06NON1.SGM
06NON1
sroberts on PROD1PC70 with NOTICES
Federal Register / Vol. 73, No. 216 / Thursday, November 6, 2008 / Notices
project is to produce electrical power for
sale.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210,.211,.214. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’, ‘‘MOTION
TO INTERVENE’’, ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or ‘‘ FISHWAY
PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. Agencies
may obtain copies of the application
directly from the applicant. A copy of
any protest or motion to intervene must
be served upon each representative of
the applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. Procedural Schedule: The
application will be processed according
to the following revised Hydro
VerDate Aug<31>2005
19:11 Nov 05, 2008
Jkt 217001
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target Date
Commission issues EA ............
Comments on EA .....................
March 2009.
April 2009.
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–26450 Filed 11–5–08; 8:45 am]
BILLING CODE 6717–01–P
66033
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. For
more information on how to submit
these types of filings please go to the
Commission’s Web site located at
https://www.ferc.gov/filingcomments.asp. More information about
this project can be viewed or printed on
the ‘‘eLibrary’’ link of Commission’s
Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13203) in the docket number field to
access the document. For assistance,
call toll-free 1–866–208–3372.
Kimberly D. Bose,
Secretary.
DEPARTMENT OF ENERGY
[FR Doc. E8–26456 Filed 11–5–08; 8:45 am]
Federal Energy Regulatory
Commission
BILLING CODE 6717–01–P
[Project No. 3041–004]
DEPARTMENT OF ENERGY
Mackay Bar Corporation; Notice of
Conduit Exemption Application
Accepted for Filing and Soliciting
Comment, Motions To Intervene, and
Competing Applications
October 30, 2008.
On April 28, 2008, Mackay Bar
Corporation filed an application,
pursuant to section 16U.S.C. 791a—825r
of the Federal Power Act, for conduit
exemption of the Hettinger Project, to be
located on an irrigation system in Idaho
County, Idaho.
The proposed Hettinger Project
consists of: (1) A proposed powerhouse
containing one generating unit having
an installed capacity of 17.9 kilowatts,
and (2) appurtenant facilities. Mackay
Bar Corporation, estimates the project
would have an average annual
generation of 140 megawatt-hours and
be sold to a local utility.
Applicant Contact: Mrs. Yvonne
Goundry, General Manager, Mackay Bar
Corporation, P.O. Box 7968, Boise, ID
83707, phone (208) 344–9904.
FERC Contact: Robert Bell, (202) 502–
6062.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and eight
copies should be mailed to: Kimberly D.
Bose, Secretary, Federal Energy
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[Project No. 13269–000]
Town of Bennington, Vermont; Notice
of Conduit Exemption Application
Accepted for Filing and Soliciting
Comment, Motions To Intervene, and
Competing Applications
October 30, 2008.
On July 23, 2008, Town of
Bennington, Vermont filed an
application, pursuant to section 16
U.S.C. 791a—825r of the Federal Power
Act, for conduit exemption of the
Bennington Water Treatment Project, to
be located on the water treatment
pipeline in Bennington County,
Vermont.
The proposed Bennington Water
Treatment Project consists of: (1) A
proposed powerhouse containing one
generating unit having an installed
capacity of 17 kilowatts, and (2)
appurtenant facilities. The Town of
Bennington, Vermont, estimates the
project would have an average annual
generation of 140 megawatt-hours and
be sold to a local utility.
Applicant Contact: Mr. Stuart A.
Huard, Town Manager, Town of
Bennington, Vermont, P.O. Box 469,
Bennington, VT 05201, phone (802)
442–1037.
FERC Contact: Robert Bell, (202) 502–
6062.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
E:\FR\FM\06NON1.SGM
06NON1
Agencies
[Federal Register Volume 73, Number 216 (Thursday, November 6, 2008)]
[Notices]
[Pages 66032-66033]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-26450]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2801-027]
Littleville Power Company, Inc.; Notice of Application Accepted
for Filing, Soliciting Motions To Intervene and Protests, Ready for
Environmental Analysis, and Soliciting Comments, Recommendations, Terms
and Conditions, and Fishway Prescriptions
October 30, 2008.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent License.
b. Project No.: P-2801-027.
c. Date filed: October 31, 2007.
d. Applicant: Littleville Power Company, Inc.
e. Name of Project: Glendale Hydroelectric Project.
f. Location: On the Housatonic River in the Town of Stockbridge,
Berkshire County. The project does not affect federal lands.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Kevin M. Webb, Environmental Affairs
Coordinator, Littleville Power Company, Inc., One Tech Drive, Suite
220, Andover, MA 01810, (978) 681-1900 ext. 809,
kevin.webb@northamerica.enel.it
i. FERC Contact: Kristen Murphy, (202) 502-6236 or
kristen.murphy@ferc.gov.
j. Deadline for filing motions to intervene and protests, comments,
recommendations, terms and conditions, and fishway prescriptions is,
December 30, 2008, 60 days from the issuance of this notice; reply
comments are due, February 12, 2009, 105 days from the issuance date of
this notice.
All documents (original and eight copies) should be filed with:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
Motions to intervene and protests may be filed electronically via
the Internet in lieu of paper. The Commission strongly encourages
electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions
on the Commission's Web site (https://www.ferc.gov) under the
``eFiling'' link.
k. This application has been accepted for filing and is now is
ready for environmental analysis.
l. As licensed, the existing Glendale Project consists of: (1) A
250-foot-long, 30-foot-high concrete gravity dam with a 182-foot-long
spillway; (2) a 23-acre reservoir; (3) two manually-operated 10 by 10-
foot intake gates; (4) a 1,500-foot-long, 40-foot-wide intake canal;
(5) a forebay structure and a 250-foot-long, 12-foot-diameter steel
penstock; (6) a powerhouse with four turbine generating units with a
combined installed capacity of 1,140-kilowatts; (7) a 300-foot-long
tailrace channel; (8) a step-up transformer and an 83-foot-long, 13.8
kilovolt transmission line; and (9) appurtenant facilities. The
Housatonic River reach that is bypassed by the project (measured from
the gatehouse to the tailrace channel) is about 2,500 feet long.
The proposed project would include a new 165-kW turbine unit in the
waste gate slot located at the gatehouse adjacent to the project dam.
This unit would operate off of a proposed minimum bypassed reach flow
of 90 cubic feet per second (cfs) or inflow. In addition, the proposed
project would provide additional recreational access through formal
canoe portage facilities and parking.
The applicant estimates that the total average annual generation,
with the proposed additional turbine, would be 5,800 megawatt-hours.
The applicant proposes to continue to operate the project in run-of-
river mode with an increase in minimum flow in the bypass reach from 10
cfs to 90 cfs or inflow, whichever is less. The purpose of the
[[Page 66033]]
project is to produce electrical power for sale.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Anyone may submit comments, a protest, or a motion to intervene
in accordance with the requirements of Rules of Practice and Procedure,
18 CFR 385.210,.211,.214. In determining the appropriate action to
take, the Commission will consider all protests or other comments
filed, but only those who file a motion to intervene in accordance with
the Commission's Rules may become a party to the proceeding. Any
comments, protests, or motions to intervene must be received on or
before the specified comment date for the particular application.
All filings must (1) bear in all capital letters the title
``PROTEST'', ``MOTION TO INTERVENE'', ``COMMENTS,'' ``REPLY COMMENTS,''
``RECOMMENDATIONS,'' ``TERMS AND CONDITIONS,'' or `` FISHWAY
PRESCRIPTIONS;'' (2) set forth in the heading the name of the applicant
and the project number of the application to which the filing responds;
(3) furnish the name, address, and telephone number of the person
protesting or intervening; and (4) otherwise comply with the
requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain
copies of the application directly from the applicant. A copy of any
protest or motion to intervene must be served upon each representative
of the applicant specified in the particular application. A copy of all
other filings in reference to this application must be accompanied by
proof of service on all persons listed in the service list prepared by
the Commission in this proceeding, in accordance with 18 CFR 4.34(b)
and 385.2010.
o. Procedural Schedule: The application will be processed according
to the following revised Hydro Licensing Schedule. Revisions to the
schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target Date
------------------------------------------------------------------------
Commission issues EA...................... March 2009.
Comments on EA............................ April 2009.
------------------------------------------------------------------------
p. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-26450 Filed 11-5-08; 8:45 am]