Sabine Pipe Line LLC; Notice of Request Under Blanket Authorization, 63956 [E8-25684]

Download as PDF 63956 Federal Register / Vol. 73, No. 209 / Tuesday, October 28, 2008 / Notices INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. p. Agency Comments: Federal, State, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. q. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘eFiling’’ link. Kimberly D. Bose, Secretary. [FR Doc. E8–25623 Filed 10–27–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP09–4–000] Sabine Pipe Line LLC; Notice of Request Under Blanket Authorization ebenthall on PROD1PC60 with NOTICES October 22, 2008. Take notice that on October 8, 2008, Sabine Pipe Line LLC (Sabine), 2400 Fournace Place, Bellaire, Texas 77401, filed in Docket No. CP09–4–000, a prior notice request pursuant to sections 157.205, 157.208, and 157.212 of the Federal Energy Regulatory Commission’s regulations under the Natural Gas Act for authorization to construct, own, and operate certain facilities located at a proposed point of interconnection between Sabine and Kinder Morgan Louisiana Pipeline Company LLC (KMLP) in Calcasieu Parish, Louisiana, all as more fully set forth in the application, which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Specifically, Sabine proposes to design, construct, own, and operate all of the facilities necessary to receive up to 200 MMcf/d of revaporized liquefied VerDate Aug<31>2005 15:28 Oct 27, 2008 Jkt 217001 natural gas (LNG) from the Cheniere Sabine Pass LNG import terminal by way of a 20-inch pipeline owned and operated by KMLP. Sabine states that these facilities proposed include a 16inch valve, 16-inch flanges, 16-inch pipe and related fittings, miscellaneous bolts, gaskets, over-pressure protection valve(s)/device(s), electronic flow measurement instrumentation, and all necessary and related telemetry devices. Sabine estimates the cost of construction to be $293,000, with all such costs to be reimbursed by KMLP. Any questions regarding the application should be directed to Jeffrey L. Kirk, Chevron Pipe Line, 4800 Fournace Place, Bellaire, Texas 77401, at (713) 432–6753. Any person may, within 60 days after the issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention. Any person filing to intervene or the Commission’s staff may, pursuant to section 157.205 of the Commission’s Regulations under the Natural Gas Act (NGA) (18 CFR 157.205) file a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. The Commission strongly encourages electronic filings of comments, protests, and interventions via the Internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https:// www.ferc.gov) under the ‘‘e-Filing’’ link. Kimberly D. Bose, Secretary. [FR Doc. E8–25684 Filed 10–27–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings, #1 October 21, 2008. Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC09–7–000. Applicants: Bank of America Corporation, Bank of America, N.A., Merrill Lynch & Co., Inc., Merrill Lynch Commodities, Inc. PO 00000 Frm 00015 Fmt 4703 Sfmt 4703 Description: Application of Bank of America Corp, Bank of America, N.A. et al. for authorization to sell securities and request for expedited treatment. Filed Date: 10/17/2008. Accession Number: 20081020–0219. Comment Date: 5 p.m. Eastern Time on Friday, November 7, 2008. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER96–1361–013; ER99–2781–011; ER98–4138–009; ER00–1770–019; ER02–453–010; ER98– 3096–015; ER07–903–002; ER05–1054– 003; ER01–202–008; ER04–472–007. Applicants: Atlantic City Electric Company, Delmarva Power & Light Company, Potomac Electric Power Company, Conectiv Energy Supply, Inc., Conectiv Atlantic Generation, LLC, Conectiv Delmarva Generation, LLC, Conectiv Bethlehem LLC, Pepco Energy Services, Inc., Bethlehem Renewable Energy, LLC, Eastern Landfill Gas, LLC, Potomac Power Resources, LLC, Fauquier Landfill Gas, LLC. Description: Atlantic City Electric Co et al. amends the Market Based Rate Tariffs submitted with their 4/8/08 filing and amends Appendix B–2 to the Revised Updated Market Power Study to conform to Order 697–A etc. Filed Date: 10/14/2008. Accession Number: 20081016–0217. Comment Date: 5 p.m. Eastern Time on Tuesday, November 4, 2008. Docket Numbers: ER99–2156–016; ER96–719–023; ER97–2801–024; ER07– 1236–003. Applicants: Cordova Energy Company LLC, MidAmerican Energy Company, PacifiCorp, Yuma Cogeneration Associates. Description: Cordova Energy Co LLC et al. submits a notice of change in status. Filed Date: 10/15/2008. Accession Number: 20081017–0001. Comment Date: 5 p.m. Eastern Time on Wednesday, November 5, 2008. Docket Numbers: ER06–1291–002; ER07–565–001; ER07–566–001; ER07– 412–002. Applicants: MT. Tom Generating Company LLC, FirstLight Hydro Generating Company, FirstLight Power Resources Management, LLC, ECP Energy I, LLC. Description: Mt Tom Generation Co, LLC et al. (FirstLight Sellers) submits revised market-based rate tariff to replace the tariffs that were filed on 6/ 30/08 in connection with their Order 697 Updated Market Power Analysis. Filed Date: 10/14/2008. Accession Number: 20081016–0218. Comment Date: 5 p.m. Eastern Time on Tuesday, November 4, 2008. E:\FR\FM\28OCN1.SGM 28OCN1

Agencies

[Federal Register Volume 73, Number 209 (Tuesday, October 28, 2008)]
[Notices]
[Page 63956]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-25684]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP09-4-000]


Sabine Pipe Line LLC; Notice of Request Under Blanket 
Authorization

October 22, 2008.
    Take notice that on October 8, 2008, Sabine Pipe Line LLC (Sabine), 
2400 Fournace Place, Bellaire, Texas 77401, filed in Docket No. CP09-4-
000, a prior notice request pursuant to sections 157.205, 157.208, and 
157.212 of the Federal Energy Regulatory Commission's regulations under 
the Natural Gas Act for authorization to construct, own, and operate 
certain facilities located at a proposed point of interconnection 
between Sabine and Kinder Morgan Louisiana Pipeline Company LLC (KMLP) 
in Calcasieu Parish, Louisiana, all as more fully set forth in the 
application, which is on file with the Commission and open to public 
inspection. The filing may also be viewed on the web at https://
www.ferc.gov using the ``eLibrary'' link. Enter the docket number 
excluding the last three digits in the docket number field to access 
the document. For assistance, contact FERC at 
FERCOnlineSupport@ferc.gov or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Specifically, Sabine proposes to design, construct, own, and 
operate all of the facilities necessary to receive up to 200 MMcf/d of 
revaporized liquefied natural gas (LNG) from the Cheniere Sabine Pass 
LNG import terminal by way of a 20-inch pipeline owned and operated by 
KMLP. Sabine states that these facilities proposed include a 16-inch 
valve, 16-inch flanges, 16-inch pipe and related fittings, 
miscellaneous bolts, gaskets, over-pressure protection valve(s)/
device(s), electronic flow measurement instrumentation, and all 
necessary and related telemetry devices. Sabine estimates the cost of 
construction to be $293,000, with all such costs to be reimbursed by 
KMLP.
    Any questions regarding the application should be directed to 
Jeffrey L. Kirk, Chevron Pipe Line, 4800 Fournace Place, Bellaire, 
Texas 77401, at (713) 432-6753.
    Any person may, within 60 days after the issuance of the instant 
notice by the Commission, file pursuant to Rule 214 of the Commission's 
Procedural Rules (18 CFR 385.214) a motion to intervene or notice of 
intervention. Any person filing to intervene or the Commission's staff 
may, pursuant to section 157.205 of the Commission's Regulations under 
the Natural Gas Act (NGA) (18 CFR 157.205) file a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for protest. If a protest is filed and not 
withdrawn within 30 days after the time allowed for filing a protest, 
the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions via the Internet in lieu of paper. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site (https://www.ferc.gov) under the ``e-Filing'' link.

Kimberly D. Bose,
Secretary.
 [FR Doc. E8-25684 Filed 10-27-08; 8:45 am]
BILLING CODE 6717-01-P