Transcontinental Gas Pipe Line Corporation; Notice of Intent To Prepare an Environmental Assessment for the Proposed Mobile Bay South Expansion Project and Request for Comments on Environmental Issues, 63964-63966 [E8-25617]
Download as PDF
ebenthall on PROD1PC60 with NOTICES
63964
Federal Register / Vol. 73, No. 209 / Tuesday, October 28, 2008 / Notices
• A new electrical substation; and
• The New Hamilton Meter Station
and interconnect.
The purpose of this project is to
provide 24.7 billion cubic feet of
working gas capacity to customers in the
region by converting a nearly depleted
oil and gas reservoir into a highdeliverability natural gas storage facility
located approximately 3.5 miles
northwest of Caledonia in Monroe and
Lowndes Counties, Mississippi.
The EA has been placed in the public
files of the FERC. A limited number of
copies of the EA are available for
distribution and public inspection at:
Federal Energy Regulatory Commission,
Public Reference Room, 888 First Street,
NE., Room 2A, Washington, DC 20426,
(202) 502–8371.
Copies of the EA have been mailed to
Federal, State, and local agencies,
interested individuals, affected
landowners, newspapers, libraries, and
parties to this proceeding. Any person
wishing to comment on the EA may do
so. To ensure consideration prior to a
Commission decision on the proposal, it
is important that we receive your
comments before the date specified
below.
You can make a difference by
providing us with your specific
comments or concerns about the Project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before November
21, 2008.
For your convenience, there are three
methods in which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number CP08–418–000 with
your submission. The Commission
encourages electronic filing of
comments and has dedicated eFiling
expert staff available to assist you at
202–502–8258 or efiling@ferc.gov.
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located on
the Commission’s Internet Web site at
https://www.ferc.gov under the link to
Documents and Filings. A Quick
Comment is an easy method for
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Internet Web site at
https://www.ferc.gov under the link to
VerDate Aug<31>2005
15:28 Oct 27, 2008
Jkt 217001
Documents and Filings. eFiling involves
preparing your submission in the same
manner as you would if filing on paper,
and then saving the file on your
computer’s hard drive. You will attach
that file as your submission. New
eFiling users must first create an
account by clicking on ‘‘Sign up’’ or
‘‘eRegister’’. You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing;’’ or
(3) You may file your comments via
mail to the Commission by sending an
original and two copies of your letter to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First St., NE., Room 1A, Washington, DC
20426.
Label one copy of the comments for
the attention of Gas Branch 2, PJ11.2.
Comments will be considered by the
Commission but will not serve to make
the commentor a party to the
proceeding. Any person seeking to
become a party to the proceeding must
file a motion to intervene pursuant to
Rule 214 of the Commission’s Rules of
Practice and Procedures (18 CFR
385.214).1 Only intervenors have the
right to seek rehearing of the
Commission’s decision.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
comments considered.
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the eLibrary link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
1 Interventions may also be filed electronically via
the Internet in lieu of paper. See the previous
discussion on filing comments electronically.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries and direct links to the
documents. Go to https://www.ferc.gov/
esubscribenow.htm.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–25615 Filed 10–27–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP08–476–000]
Transcontinental Gas Pipe Line
Corporation; Notice of Intent To
Prepare an Environmental Assessment
for the Proposed Mobile Bay South
Expansion Project and Request for
Comments on Environmental Issues
October 21, 2008.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the construction and operation of
facilities proposed by Transcontinental
Gas Pipe Line Corporation (Transco) in
Choctaw County, Alabama.
This notice announces the opening of
the scoping process we will use to
gather input from the public and
interested agencies on the project. Your
input will help the Commission staff
determine which issues need to be
evaluated in the EA. Please note that the
scoping period will close on November
20, 2008.
This notice is being sent to affected
landowners; federal, state, and local
government representatives and
agencies; environmental and public
interest groups; Native American tribes;
other interested parties in this
proceeding; and local libraries and
newspapers. We encourage government
representatives to notify their
constituents of this planned project and
encourage them to comment on their
areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The pipeline
company would seek to negotiate a
mutually acceptable agreement.
However, if the project is approved by
the Commission, that approval conveys
with it the right of eminent domain.
Therefore, if easement negotiations fail
E:\FR\FM\28OCN1.SGM
28OCN1
Federal Register / Vol. 73, No. 209 / Tuesday, October 28, 2008 / Notices
to produce an agreement, the pipeline
company could initiate condemnation
proceedings in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ was attached to the project
notice Transco provided to landowners.
This fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is available for viewing
on the FERC Internet Web site (https://
www.ferc.gov).
Summary of the Proposed Project
The proposed Mobile Bay South
Expansion Project would involve the
construction and operation of
Compressor Station 85, a new 9,470
horsepower (hp) compressor station to
be located at the interconnection of the
Mobile Bay Lateral and Transco’s main
line in Choctaw County, Alabama.
Specifically, the Project will include all
necessary piping, auxiliary systems, and
appurtenant facilities, including:
• Two 4,735 hp Caterpillar 3636;
internal combustion engine-driven
compressor units;
• Approximately 2,400 feet of 30-inch
diameter piping extending from
Transco’s mainline to the compressor
station and from the compressor station
to the Mobile Bay Lateral; and
• Station yard piping and
appurtenances.
Construction of the project facilities
would enable Transco to provide firm
transportation service from Compressor
Station 85 and interconnects with party
pipelines at Station 85 southward to
delivery points located on the Mobile
Bay Lateral.
The location of the project facilities is
shown in Appendix 1.1
Nonjurisdictional Facilities
ebenthall on PROD1PC60 with NOTICES
Non-jurisdictional facilities associated
with this project would include
electrical service provided to the
compressor station from the local
utility, Black Warrior Electrical
Membership Cooperative. A water
pipeline would also be constructed by
North Choctaw Water to supply water to
the station.
1 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices, other than Appendix 1 (maps), are
available on the Commission’s website at the
‘‘eLibrary’’ link or from the Commission’s Public
Reference Room, 888 First Street, NE., Washington,
DC 20426, or call (202) 502–8371. For instructions
on connecting to eLibrary refer to the last page of
this notice. Copies of the appendices were sent to
all those receiving this notice in the mail.
VerDate Aug<31>2005
15:28 Oct 27, 2008
Jkt 217001
63965
Land Requirements for Construction
Transco would purchase a 126.8-acre
parcel of land to site the facilities.
Construction of the proposed facilities
would require about 32.9 acres of land
including aboveground facilities, outlet
pipeline, and access roads. Following
construction, about 10 acres would be
used for operation of the project’s
facilities. The remaining 22.9 acres of
land would be restored within the
existing compressor station property or
allowed to revert to former use along the
pipeline right-of-way.
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the public participation
section below.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, the Commission staff
requests public comments on the scope
of the issues to address in the EA. All
comments received are considered
during the preparation of the EA. State
and local government representatives
are encouraged to notify their
constituents of this proposed action and
encourage them to comment on their
areas of concern.
In the EA we 2 will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils.
• Land use.
• Water resources, fisheries, and
wetlands.
• Cultural resources.
• Vegetation and wildlife.
• Air quality and noise.
• Endangered and threatened species.
• Hazardous waste.
• Public safety.
We will also evaluate possible
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to federal, state,
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
proposed facilities and the
environmental information provided by
Transco. This preliminary list of issues
may be changed based on your
comments and our analysis.
• Cultural resources may be affected
by the project.
• The project may have air emissions
and noise impacts.
• The new compressor station may
have visual impacts on the surrounding
area.
• The federally listed gopher tortoise
habitat may be affected.
2 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects
(OEP).
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the Mobile
Bay South Expansion Project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. The more
specific your comments, the more useful
they will be. To ensure that your
comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before November
20, 2008.
For your convenience, there are three
methods in which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number CP08–476–000 with
your submission. The docket number
can be found on the front of this notice.
The Commission encourages electronic
filing of comments and has dedicated
eFiling expert staff available to assist
you at 202–502–8258 or
efiling@ferc.gov.
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located on
the Commission’s internet Web site at
https://www.ferc.gov under the link to
Documents and Filings. A Quick
E:\FR\FM\28OCN1.SGM
28OCN1
63966
Federal Register / Vol. 73, No. 209 / Tuesday, October 28, 2008 / Notices
Comment is an easy method for
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Internet Web site at
https://www.ferc.gov under the link to
Documents and Filings. eFiling involves
preparing your submission in the same
manner as you would if filing on paper,
and then saving the file on your
computer’s hard drive. You will attach
that file as your submission. New
eFiling users must first create an
account by clicking on ‘‘Sign up’’ or
‘‘eRegister.’’ You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing;’’ or
(3) You may file your comments via
mail to the Commission by sending an
original and two copies of your letter to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First St., NE., Room 1A, Washington, DC
20426.
Label one copy of the comments for
the attention of Gas Branch 2, PJ11.2.
ebenthall on PROD1PC60 with NOTICES
Environmental Mailing List
An effort is being made to send this
notice to all individuals, organizations,
and government entities interested in
and/or potentially affected by the
proposed project. This includes all
landowners who are potential right-ofway grantors, whose property may be
used temporarily for project purposes,
or who own homes within distances
defined in the Commission’s regulations
of certain aboveground facilities. By this
notice we are also asking governmental
agencies, especially those in Appendix
2, to express their interest in becoming
cooperating agencies for the preparation
of the EA.
If you do not want to send comments
at this time but still want to remain on
our mailing list, please return the
Information Request (Appendix 3). If
you do not return the Information
Request, you will be taken off the
mailing list.
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an official party to the
proceeding known as an ‘‘intervenor.’’
Intervenors play a more formal role in
the process. Among other things,
intervenors have the right to receive
copies of case-related Commission
documents and filings by other
intervenors. Likewise, each intervenor
must send one electronic copy (using
the Commission’s eFiling system) or 14
paper copies of its filings to the
VerDate Aug<31>2005
15:28 Oct 27, 2008
Jkt 217001
Secretary of the Commission and must
send a copy of its filings to all other
parties on the Commission’s service list
for this proceeding.
If you want to become an intervenor
you must file a motion to intervene
according to Rule 214 of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214). Only
intervenors have the right to seek
rehearing of the Commission’s decision.
The Notice of Application for this
proposed project issued on September
29, 2008 identified the date for the filing
of interventions as October 20, 2008.
However, affected landowners and
parties with environmental concerns
may be granted late intervenor status
upon showing good cause by stating that
they have a clear and direct interest in
this proceeding which would not be
adequately represented by any other
parties. You do not need intervenor
status to have your environmental
comments considered.
Availability of Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208-FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the eLibrary link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202)502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–25617 Filed 10–27–08; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. NJ08–5–001]
United States Department of Energy,
Bonneville Power Administration,
Transmission Service Terms and
Conditions; Notice of Filing
October 21, 2008.
Take notice that on October 15, 2008,
Bonneville Power Administration filed
certain attachments to Attachment K to
its Open Access Transmission Tariff in
response to the Commission’s July 17,
2008 Order and request for declaratory
order accepting their proposed
Attachment K as revised and finding
that the Commission’s standards for
reciprocity, pursuant to 18 CFR 35.28(e)
and 18 CFR 385.207.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all the parties in this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
E:\FR\FM\28OCN1.SGM
28OCN1
Agencies
[Federal Register Volume 73, Number 209 (Tuesday, October 28, 2008)]
[Notices]
[Pages 63964-63966]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-25617]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP08-476-000]
Transcontinental Gas Pipe Line Corporation; Notice of Intent To
Prepare an Environmental Assessment for the Proposed Mobile Bay South
Expansion Project and Request for Comments on Environmental Issues
October 21, 2008.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the construction and operation of
facilities proposed by Transcontinental Gas Pipe Line Corporation
(Transco) in Choctaw County, Alabama.
This notice announces the opening of the scoping process we will
use to gather input from the public and interested agencies on the
project. Your input will help the Commission staff determine which
issues need to be evaluated in the EA. Please note that the scoping
period will close on November 20, 2008.
This notice is being sent to affected landowners; federal, state,
and local government representatives and agencies; environmental and
public interest groups; Native American tribes; other interested
parties in this proceeding; and local libraries and newspapers. We
encourage government representatives to notify their constituents of
this planned project and encourage them to comment on their areas of
concern.
If you are a landowner receiving this notice, you may be contacted
by a pipeline company representative about the acquisition of an
easement to construct, operate, and maintain the proposed facilities.
The pipeline company would seek to negotiate a mutually acceptable
agreement. However, if the project is approved by the Commission, that
approval conveys with it the right of eminent domain. Therefore, if
easement negotiations fail
[[Page 63965]]
to produce an agreement, the pipeline company could initiate
condemnation proceedings in accordance with state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' was attached to the
project notice Transco provided to landowners. This fact sheet
addresses a number of typically asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
It is available for viewing on the FERC Internet Web site (https://
www.ferc.gov).
Summary of the Proposed Project
The proposed Mobile Bay South Expansion Project would involve the
construction and operation of Compressor Station 85, a new 9,470
horsepower (hp) compressor station to be located at the interconnection
of the Mobile Bay Lateral and Transco's main line in Choctaw County,
Alabama. Specifically, the Project will include all necessary piping,
auxiliary systems, and appurtenant facilities, including:
Two 4,735 hp Caterpillar 3636; internal combustion engine-
driven compressor units;
Approximately 2,400 feet of 30-inch diameter piping
extending from Transco's mainline to the compressor station and from
the compressor station to the Mobile Bay Lateral; and
Station yard piping and appurtenances.
Construction of the project facilities would enable Transco to
provide firm transportation service from Compressor Station 85 and
interconnects with party pipelines at Station 85 southward to delivery
points located on the Mobile Bay Lateral.
The location of the project facilities is shown in Appendix 1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of all appendices, other
than Appendix 1 (maps), are available on the Commission's website at
the ``eLibrary'' link or from the Commission's Public Reference
Room, 888 First Street, NE., Washington, DC 20426, or call (202)
502-8371. For instructions on connecting to eLibrary refer to the
last page of this notice. Copies of the appendices were sent to all
those receiving this notice in the mail.
---------------------------------------------------------------------------
Nonjurisdictional Facilities
Non-jurisdictional facilities associated with this project would
include electrical service provided to the compressor station from the
local utility, Black Warrior Electrical Membership Cooperative. A water
pipeline would also be constructed by North Choctaw Water to supply
water to the station.
Land Requirements for Construction
Transco would purchase a 126.8-acre parcel of land to site the
facilities. Construction of the proposed facilities would require about
32.9 acres of land including aboveground facilities, outlet pipeline,
and access roads. Following construction, about 10 acres would be used
for operation of the project's facilities. The remaining 22.9 acres of
land would be restored within the existing compressor station property
or allowed to revert to former use along the pipeline right-of-way.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
to discover and address concerns the public may have about proposals.
This process is referred to as ``scoping.'' The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this Notice of Intent, the Commission staff
requests public comments on the scope of the issues to address in the
EA. All comments received are considered during the preparation of the
EA. State and local government representatives are encouraged to notify
their constituents of this proposed action and encourage them to
comment on their areas of concern.
In the EA we \2\ will discuss impacts that could occur as a result
of the construction and operation of the proposed project under these
general headings:
---------------------------------------------------------------------------
\2\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
Geology and soils.
Land use.
Water resources, fisheries, and wetlands.
Cultural resources.
Vegetation and wildlife.
Air quality and noise.
Endangered and threatened species.
Hazardous waste.
Public safety.
We will also evaluate possible alternatives to the proposed project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to federal, state, and local agencies, public
interest groups, interested individuals, affected landowners,
newspapers, libraries, and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission.
To ensure your comments are considered, please carefully follow the
instructions in the public participation section below.
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the proposed facilities and
the environmental information provided by Transco. This preliminary
list of issues may be changed based on your comments and our analysis.
Cultural resources may be affected by the project.
The project may have air emissions and noise impacts.
The new compressor station may have visual impacts on the
surrounding area.
The federally listed gopher tortoise habitat may be
affected.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the Mobile Bay South Expansion Project. Your
comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. The more specific your comments, the more useful they will be.
To ensure that your comments are timely and properly recorded, please
send in your comments so that they will be received in Washington, DC
on or before November 20, 2008.
For your convenience, there are three methods in which you can use
to submit your comments to the Commission. In all instances please
reference the project docket number CP08-476-000 with your submission.
The docket number can be found on the front of this notice. The
Commission encourages electronic filing of comments and has dedicated
eFiling expert staff available to assist you at 202-502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the Quick
Comment feature, which is located on the Commission's internet Web site
at https://www.ferc.gov under the link to Documents and Filings. A Quick
[[Page 63966]]
Comment is an easy method for interested persons to submit text-only
comments on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Internet Web site at
https://www.ferc.gov under the link to Documents and Filings. eFiling
involves preparing your submission in the same manner as you would if
filing on paper, and then saving the file on your computer's hard
drive. You will attach that file as your submission. New eFiling users
must first create an account by clicking on ``Sign up'' or
``eRegister.'' You will be asked to select the type of filing you are
making. A comment on a particular project is considered a ``Comment on
a Filing;'' or
(3) You may file your comments via mail to the Commission by
sending an original and two copies of your letter to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First St., NE.,
Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas Branch 2,
PJ11.2.
Environmental Mailing List
An effort is being made to send this notice to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project. This includes all landowners who are
potential right-of-way grantors, whose property may be used temporarily
for project purposes, or who own homes within distances defined in the
Commission's regulations of certain aboveground facilities. By this
notice we are also asking governmental agencies, especially those in
Appendix 2, to express their interest in becoming cooperating agencies
for the preparation of the EA.
If you do not want to send comments at this time but still want to
remain on our mailing list, please return the Information Request
(Appendix 3). If you do not return the Information Request, you will be
taken off the mailing list.
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an official party to the proceeding known as an
``intervenor.'' Intervenors play a more formal role in the process.
Among other things, intervenors have the right to receive copies of
case-related Commission documents and filings by other intervenors.
Likewise, each intervenor must send one electronic copy (using the
Commission's eFiling system) or 14 paper copies of its filings to the
Secretary of the Commission and must send a copy of its filings to all
other parties on the Commission's service list for this proceeding.
If you want to become an intervenor you must file a motion to
intervene according to Rule 214 of the Commission's Rules of Practice
and Procedure (18 CFR 385.214). Only intervenors have the right to seek
rehearing of the Commission's decision.
The Notice of Application for this proposed project issued on
September 29, 2008 identified the date for the filing of interventions
as October 20, 2008. However, affected landowners and parties with
environmental concerns may be granted late intervenor status upon
showing good cause by stating that they have a clear and direct
interest in this proceeding which would not be adequately represented
by any other parties. You do not need intervenor status to have your
environmental comments considered.
Availability of Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on ``General Search'' and enter the
docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202)502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/
EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.