Haida Corporation; Notice of Request for Extension of Time To Commence and Complete Project Construction and Soliciting Comments, Motions To Intervene, and Protests, 62976 [E8-25087]

Download as PDF 62976 Federal Register / Vol. 73, No. 205 / Wednesday, October 22, 2008 / Notices last three digits in the docket number field to access the document. For assistance, call 1–866–208–3676, or for TTY, (202) 502–8659. Kimberly D. Bose, Secretary. [FR Doc. E8–25089 Filed 10–21–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 11480–010] Haida Corporation; Notice of Request for Extension of Time To Commence and Complete Project Construction and Soliciting Comments, Motions To Intervene, and Protests sroberts on PROD1PC70 with NOTICES October 15, 2008. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Request for Extension of Time. b. Project No.: 11480–010. c. Date Filed: July 23, 2008. d. Applicant: Haida Corporation. e. Name of Project: Upper Reynolds Creek Hydroelectric Project. f. Location: On Reynolds Creek, near the town of Hydaburg, Copper River Meridian, Prince of Wales, in the Ketchikan Borough recording district, Alaska. g. Pursuant to: Public Law 109–297, 120 STAT. 1471. h. Applicant Contact: Donald H. Clarke, Law Offices of GKRSE, 1500 K Street, NW., Suite 330, Washington, DC 20005; (202) 408–5400. i. FERC Contact: Diane M. Murray, Telephone: (202) 502–8838 and e-mail: diane.murray@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: November 17, 2008. All documents (original and eight copies) should be filed with: Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Please include the project number (P–11480–010) on any comments. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a VerDate Aug<31>2005 17:50 Oct 21, 2008 Jkt 217001 particular resource agency, they must also serve a copy of the document on that resource agency. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application. k. Description of Request: The licensee requests that the Commission grant a two-year extension of time from the existing deadlines to commence and complete project construction of the Reynolds Creek Hydroelectric Project. This will be the last 2-year extension of three authorized by Public Law No. 109–297. The requested new deadlines would be October 24, 2010, and October 24, 2012, to commence and complete construction, respectively. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h. above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’, as applicable, and the PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 Project Number of the particular application to which the filing refers. p. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. q. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘eFiling’’ link. Kimberly D. Bose, Secretary. [FR Doc. E8–25087 Filed 10–21–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13290–000] Riverbank Energy Center, LLC; Notice of Competing Preliminary Permit Application Accepted for Filing and Soliciting Comments and Motions To Intervene October 16, 2008. On September 24, 2008, Riverbank Energy Center, LLC filed an application, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Wiscasset Pumped Storage Project to be located on the Back River in Lincoln County, Maine. The proposed project would consist of: (1) The Back River as an upper reservoir; (2) an underground lower reservoir with an elevation of 1,800 feet below MSL and a storage capacity of 3,775 acre-feet; (3) four 13 foot diameter, 2,000 foot long, concrete and steel penstocks; (4) an underground powerhouse containing four pump/ turbine units with a total installed capacity of 1,000 MW; (5) a 345 kV, 4,000 foot long transmission line and; (6) appurtenant facilities. The annual production would be 2,190 GWh which would be sold to a local utility. Applicant Contact: William S. Helmer, Esq., 194 Washington Ave. Suite 315, Albany, New York 12210 (518) 689–3570. FERC Contact: Steven Sachs (202) 502–8666. Competing Application: This application competes with Project No. E:\FR\FM\22OCN1.SGM 22OCN1

Agencies

[Federal Register Volume 73, Number 205 (Wednesday, October 22, 2008)]
[Notices]
[Page 62976]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-25087]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 11480-010]


Haida Corporation; Notice of Request for Extension of Time To 
Commence and Complete Project Construction and Soliciting Comments, 
Motions To Intervene, and Protests

October 15, 2008.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Request for Extension of Time.
    b. Project No.: 11480-010.
    c. Date Filed: July 23, 2008.
    d. Applicant: Haida Corporation.
    e. Name of Project: Upper Reynolds Creek Hydroelectric Project.
    f. Location: On Reynolds Creek, near the town of Hydaburg, Copper 
River Meridian, Prince of Wales, in the Ketchikan Borough recording 
district, Alaska.
    g. Pursuant to: Public Law 109-297, 120 STAT. 1471.
    h. Applicant Contact: Donald H. Clarke, Law Offices of GKRSE, 1500 
K Street, NW., Suite 330, Washington, DC 20005; (202) 408-5400.
    i. FERC Contact: Diane M. Murray, Telephone: (202) 502-8838 and e-
mail: diane.murray@ferc.gov.
    j. Deadline for filing comments, motions to intervene, and 
protests: November 17, 2008.
    All documents (original and eight copies) should be filed with: 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426. Please include the project number (P-11480-010) 
on any comments.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person whose name appears on the official service 
list for the project. Further, if an intervenor files comments or 
documents with the Commission relating to the merits of an issue that 
may affect the responsibilities of a particular resource agency, they 
must also serve a copy of the document on that resource agency. A copy 
of any motion to intervene must also be served upon each representative 
of the Applicant specified in the particular application.
    k. Description of Request: The licensee requests that the 
Commission grant a two-year extension of time from the existing 
deadlines to commence and complete project construction of the Reynolds 
Creek Hydroelectric Project. This will be the last 2-year extension of 
three authorized by Public Law No. 109-297. The requested new deadlines 
would be October 24, 2010, and October 24, 2012, to commence and 
complete construction, respectively.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street, NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. This filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. You may also 
register online at https://www.ferc.gov/docs-filing/esubscription.asp to 
be notified via e-mail of new filings and issuances related to this or 
other pending projects. For assistance, call toll-free 1-866-208-3676 
or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A 
copy is also available for inspection and reproduction at the address 
in item h. above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
and .214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    o. Any filings must bear in all capital letters the title 
``COMMENTS'', ``PROTEST'', or ``MOTION TO INTERVENE'', as applicable, 
and the Project Number of the particular application to which the 
filing refers.
    p. Agency Comments--Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.
    q. Comments, protests, and interventions may be filed 
electronically via the Internet in lieu of paper. See, 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
at https://www.ferc.gov under the ``e-Filing'' link.

Kimberly D. Bose,
Secretary.
[FR Doc. E8-25087 Filed 10-21-08; 8:45 am]