Pipeline Safety: Standards for Increasing the Maximum Allowable Operating Pressure for Gas Transmission Pipelines, 62148-62181 [E8-23915]
Download as PDF
62148
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials
Safety Administration
49 CFR Part 192
[Docket No. PHMSA–2005–23447]
RIN 2137–AE25
Pipeline Safety: Standards for
Increasing the Maximum Allowable
Operating Pressure for Gas
Transmission Pipelines
Pipeline and Hazardous
Materials Safety Administration
(PHMSA), Department of Transportation
(DOT).
ACTION: Final rule.
AGENCY:
jlentini on PROD1PC65 with RULES3
SUMMARY: PHMSA is amending the
pipeline safety regulations to prescribe
safety requirements for the operation of
certain gas transmission pipelines at
pressures based on higher operating
stress levels. The result is an increase of
maximum allowable operating pressure
(MAOP) over that currently allowed in
the regulations. Improvements in
pipeline technology assessment
methodology, maintenance practices,
and management processes over the past
twenty-five years have significantly
reduced the risk of failure in pipelines
and necessitate updating the standards
that govern the MAOP. This rule will
generate significant public benefits by
reducing the number and consequences
of potential incidents and boosting the
potential capacity and efficiency of
pipeline infrastructure, while promoting
rigorous life-cycle maintenance and
investment in improved pipe
technology.
DATES: Effective Date: This final rule
takes effect November 17, 2008.
Incorporation by Reference Date: The
incorporation by reference of a certain
publication listed in this rule is
approved by the Director of the Federal
Register as of November 17, 2008.
FOR FURTHER INFORMATION CONTACT:
Alan Mayberry by phone at (202) 366–
5124, or by e-mail at
alan.mayberry@dot.gov.
SUPPLEMENTARY INFORMATION:
Table of Contents
A. Purpose of the Rulemaking
B. Background
B.1. Current Regulations
B.2. Evolution in Views on Pressure
B.3. History of PHMSA Consideration
B.4. Safety Conditions in Special Permits
B.5. Codifying the Special Permit
Standards
B.6. How to Handle Special Permits and
Requests for Special Permits
B.7. Statutory Considerations
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
C. Comments on the NPRM
C.1. General Comments
C.2. Comments on Specific Provisions in
the Proposed Rule
C.2.1. Section 192.7, Incorporation by
Reference
C.2.2. Design Requirements
C.2.3. Construction Requirements
C.2.4. Eligibility for and Implementing
Alternative MAOP
C.2.5. Operation and Maintenance
Requirements
C.3. Comments on Regulatory Analysis
D. Consideration by the Technical Pipeline
Safety Standards Committee
E. The Final Rule
E.1. In General
E.2. Amendment to § 192.7—Incorporation
by Reference
E.3. New § 192.112—Additional Design
Requirements
E.4. New § 192.328—Additional
Construction Requirements
E.5. Amendment to § 192.611—Change in
Class Location: Confirmation or Revision
of Maximum Operating Pressure
E.6. Amendment to § 192.619—Maximum
Allowable Operating Pressure
E.7. New § 192.620—Operation at an
Alternative MAOP
E.7.1. § 192.620(a)—Calculating the
Alternative MAOP
E.7.2. § 192.620(b)—Which Pipelines
Qualify
E.7.3. §§ 192.620(c)(1), (2), and (3)—How
an Operator Selects Operation Under
This Section
E.7.4. § 192.620(c)(4)—Initial Strength
Testing
E.7.5. § 192.620(c)(5)—Operation and
Maintenance
E.7.6. § 192.620(c)(6)—New Construction
and Maintenance Tasks
E.7.7. § 192.620(c)(7)—Recordkeeping
E.7.8. § 192.620(c)(8)—Class Upgrades
E.8. § 192.620(d)—Additional Operation
and Maintenance Requirements
E.8.1. § 192.620(d)(1)—Threat Assessments
E.8.2. § 192.620(d)(1)—Public Awareness
E.8.3. § 192.620(d)(2)—Emergency
Response
E.8.4. § 192.620(d)(3)—Damage Prevention
E.8.5. § 192.620(d)(4)—Internal Corrosion
Control
E.8.6. §§ 192.620(d)(5), (6), and (7)—
External Corrosion Control
E.8.7. §§ 192.620(d)(8) and (9)—Integrity
Assessments
E.8.8. § 192.620(d)(10)—Repair Criteria
E.9. § 192.620(e)—Overpressure
Protection—Proposed § 192.620(e)
F. Regulatory Analyses and Notices
F.1. Privacy Act Statement
F.2. Executive Order 12866 and DOT
Policies and Procedures
F.3. Regulatory Flexibility Act
F.4. Executive Order 13175
F.5. Paperwork Reduction Act
F.6. Unfunded Mandates Reform Act of
1995
F.7. National Environmental Policy Act
F.8. Executive Order 13132
F.9. Executive Order 13211
12, 2008 (73 FR 13167), to establish
standards under which certain natural
or other gas (gas) transmission pipelines
would be allowed to operate at higher
maximum allowable operating pressure
(MAOP). The proposed changes were
made possible by dramatic
improvements in pipeline technology
and risk controls over the past 25 years.
The current standards for calculating
MAOP on gas transmission pipelines
were adopted in 1970, in the original
pipeline safety regulations promulgated
under Federal law. Almost all risk
controls on gas transmission pipelines
have been strengthened in the
intervening years, beginning with the
introduction of improved
manufacturing, metallurgy, testing, and
assessment tools and standards. Pipe
manufactured and tested to modern
standards is far less likely to contain
defects that can grow to failure over
time than pipe manufactured and
installed a generation ago. Likewise,
modern maintenance practices, if
consistently followed, significantly
reduce the risk that corrosion, or other
defects affecting pipeline integrity, will
develop in installed pipelines. Most
recently, operators’ development and
implementation of integrity
management programs have increased
understanding about the condition of
pipelines and how to reduce pipeline
risks. In view of these developments,
PHMSA concludes that certain gas
transmission pipelines can be safely and
reliably operated at pressures above
current Federal pipeline safety design
limits. With appropriate conditions and
controls, permitting operation at higher
pressures will increase energy capacity
and efficiency without diminishing
system safety.
Currently, PHMSA has granted
special permits on a case-by-case basis
to allow operation of particular pipeline
segments at a higher MAOP than
currently allowed under the existing
design requirements. These special
permits, that have been granted, have
been limited to operation in Class 1, 2,
and 3 locations and conditioned on
demonstrated rigor in the pipeline’s
design and construction and the
operator’s performance of additional
safety measures. Building on the record
of success developed in the special
permit proceedings, PHMSA is
codifying the conditions and limitations
of the special permits into standards of
general applicability.
A. Purpose of the Rulemaking
PHMSA published a Notice of
Proposed Rulemaking (NPRM) on March
B.1. Current Regulations
The design factor specified in
§ 192.105 restricts the MAOP of a steel
PO 00000
Frm 00002
Fmt 4701
Sfmt 4700
B. Background
E:\FR\FM\17OCR3.SGM
17OCR3
jlentini on PROD1PC65 with RULES3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
gas transmission pipeline based on
stress levels and class location. For most
steel pipelines, the MAOP is defined in
§ 192.619 based on design pressure
calculated using a formula, found at
§ 192.111, which includes the design
factor. The regulations establish four
classifications based on population
density, ranging from Class 1
(undeveloped, rural land) through Class
4 (densely populated urban areas). In
sparsely populated Class 1 locations, the
design factor specified in § 192.105
restricts the stress level at which a
pipeline can be operated to 72 percent
of the specified minimum yield strength
(SMYS) of the steel. The operating
pressures in more populated Class 2 and
Class 3 locations are limited to 60 and
50 percent of SMYS, respectively.
Paragraph (c) of § 192.619 provides an
exception to this calculation of MAOP
for pipelines built before the issuance of
the Federal pipeline safety standards. A
pipeline that is ‘‘grandfathered’’ under
this section may be operated at a stress
level exceeding 72 percent of SMYS if
it was operated at that pressure for five
years prior to July 1, 1970.
Part 192 also prescribes safety
standards for designing, constructing,
operating, and maintaining steel
pipelines used to transport gas.
Although these standards have always
included several requirements for initial
and periodic testing and inspection,
prior to 2003, part 192 contained no
Federal requirements for internal
inspection of existing pipelines. Internal
inspection is performed using a tool
known as an ‘‘instrumented pig’’ (or
‘‘smart pig’’). Many pipelines
constructed before the advent of this
technology cannot accommodate an
instrumented pig and, accordingly,
cannot be inspected internally.
Beginning in 1994, PHMSA required
operators to design new pipelines so
that they could accommodate
instrumented pigs, paving the way for
internal inspection (59 FR 17281; Apr.
12, 1994).
In December 2003, PHMSA adopted
its gas transmission integrity
management rule, requiring operators to
develop and implement plans to extend
additional protections, including
internal inspection, to pipelines located
in ‘‘high consequence areas’’ (HCAs) (68
FR 69816). Integrity management
programs, as required by subpart O of
part 192, include threat assessments,
both baseline and periodic internal
inspection, pressure testing, or direct
assessment (DA), and additional
measures designed to prevent and
mitigate pipeline failures and their
consequences. AN HCA, as defined in
§ 192.903, is a geographic territory in
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
which, by virtue of its population
density and proximity to a pipeline, a
pipeline failure would pose a higher
risk to people. In addition to class
location, one of the criteria for
identifying an HCA is a potential impact
circle surrounding a pipeline. The
calculation of the circle includes a
factor for the MAOP, with the result that
a higher MAOP results in a larger
impact circle.
B.2. Evolution in Views on Pressure
Absent any defects, and with proper
maintenance and management practices,
steel pipe can last for many decades in
gas service. However, the manufacture
of the steel or rolling of the pipe can
introduce flaws. In addition, during
construction, improper backfilling can
damage the pipe and pipe coating. Over
time, damaged coating unchecked can
allow corrosion to continue and cause
leaks. Excavation-related damage can
produce an immediate pipeline failure
or leave a dent or coating damage that
could grow to failure over time.
The regulations on MAOP in part 192
have their origin in engineering
standards developed in the 1950s, when
industry had relatively limited
information about the material
properties of pipe and limited ability to
evaluate a pipeline’s integrity during its
operating lifetime. Early pipeline codes
allowed maximum operating pressures
to be set at a fixed amount under the
pressure of the initial strength test
without regard to SMYS. Pipeline
engineers developing consensus
standards looked for ways to lengthen
the time before defects initiated during
manufacture, construction, or operation
could grow to failure. Their solutions
focused on tests done at the mill to
evaluate the ability of the pipe to
contain pressure during operation. They
added an additional factor to the
hydrostatic test pressure of the mill test.
At the time during the 1950’s, the
consensus standard, known as the B31.8
Code, used this conservative margin of
safety for gas pipe design. A 25 percent
margin of safety translated into a design
factor limiting stress level to 72 percent
of SMYS in rural areas. Specifically, the
MAOP of 72 percent of SMYS comes
from dividing the typical maximum mill
test pressure of 90 percent of SMYS by
1.25. When issuing the first Federal
pipeline safety regulations in 1970,
regulators incorporated this design
factor, as found in the 1968 edition of
the B31.8 Code, into the requirements
for determining the MAOP.
Even as the Federal regulations were
being developed, some technical
support existed for operation at a higher
stress level, provided initial strength
PO 00000
Frm 00003
Fmt 4701
Sfmt 4700
62149
testing resulted in operators removing
defects. In 1968, the American Gas
Association published Report No.
L30050 entitled Study of Feasibility of
Basing Natural Gas Pipeline Operating
Pressure on Hydrostatic Test Pressure
prepared by the Battelle Memorial
Institute. The research study concluded
that:
• It is inherently safer to base the
MAOP on the test pressure, which
demonstrates the actual in-place yield
strength of the pipeline, than to base it
on SMYS alone.
• High pressure hydrostatic testing is
able to remove defects that may fail in
service.
• Hydrostatic testing to actual yield,
as determined with a pressure-volume
plot, does not damage a pipeline.
The report specifically recommended
setting the MAOP as a percentage of the
field test pressure. In particular, it
recommended setting the MAOP at 80
percent of the test pressure when the
minimum test pressure was 90 percent
of SMYS or higher. Although the
committee responsible for the B31.8
Code received the report, the committee
deferred consideration of its findings at
that time because the Federal regulators
had already begun the process to
incorporate the 1968 edition of the
B31.8 Code into the Federal pipeline
safety standards.
More than a decade later, the
committee responsible for development
of the B31.8 Code, now under the
auspices of the American Society of
Mechanical Engineers (ASME), revisited
the question of the design factor it had
deferred in the late 1960s. The
committee determined pipelines could
operate safely at stress levels up to 80
percent of SMYS. ASME updated the
design factors in a 1990 addendum to
the 1989 edition of the B31.8 Code, and
they remain in the current edition.
Although part 192 incorporates parts of
the B31.8 Code by reference, it does not
incorporate the updated design factors.
With the benefit of operating experience
with pipelines, it seems clear that
operating pressure plays a less critical
role in pipeline integrity and failure
consequence than other factors within
the operator’s control.
By any measure, new technologies
and risk controls have had a far greater
impact on pipeline safety and integrity.
A great deal of progress has occurred in
the manufacture of steel pipe and in its
initial inspection and testing.
Technological advances in metallurgy
and pipe manufacture decrease the risk
of incipient flaws occurring and going
undetected during manufacture. The
detailed standards now followed in steel
and pipe manufacturing provide
E:\FR\FM\17OCR3.SGM
17OCR3
jlentini on PROD1PC65 with RULES3
62150
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
engineers considerable information
about their material properties.
Toughness standards make new steel
pipe more likely to resist fracture and to
survive mechanical damage. Knowledge
about the material properties allows
engineers to predict how quickly flaws,
whether inherent or introduced during
construction or operation, will grow to
failure under known operating
conditions.
Initial inspection and hydrostatic
testing of pipelines allow operators to
discover flaws that have occurred prior
to operation, such as during
transportation or construction. They
also serve to validate the integrity of the
pipeline before operation. Initial
pressure testing causes longitudinal and
some other flaws introduced during
manufacture, transportation, or
construction to grow to the point of
failure. Initial pressure testing detects
all but one type of manufacturing or
construction defect that could cause
failure in the near-term. The sole type
of defect that pressure testing may not
identify, a flaw in a girth weld, is
detectable through pre-operational nondestructive testing, which is required in
this rule.
The most common defects initiated
during operation are caused by
mechanical damage or corrosion.
Improvements in technology have
resulted in internal inspection
techniques that provide operators a
significant amount of information about
defects. Although there is significant
variance in the capability of the tools
used for internal inspections, each
provides the operator information about
flaws in the pipeline that an operator
would not otherwise have. An operator
can then examine these flaws to
determine whether they are defects
requiring repair. In addition, internal
inspections with in-line inspection (ILI)
devices, unlike pressure testing, are not
destructive and can be done while the
pipeline is in operation. Initial internal
inspection establishes a baseline.
Operators can use subsequent internal
inspections at appropriate intervals to
monitor for changes in flaws already
discovered or to find new flaws
requiring repair or monitoring. Internal
inspections, and other improved lifecycle management practices, increase
the likelihood operators will detect any
flaws that remain in the pipe after initial
inspection and testing, or that develop
after construction, well before the flaws
grow to failure.
B.3. History of PHMSA Consideration
Although the agency had never
formally revisited its part 192 MAOP
standards, prior to this rulemaking,
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
developments in related arenas have
increasingly set the stage for changes to
those standards. Grandfathered
pipelines have operated successfully at
higher stress levels in the United States
during more than 35 years of Federal
safety regulation. Many of these
grandfathered pipelines have operated
at higher stress levels for more than 50
years without a higher rate of failure.
We have also been aware of pipelines
outside the United States operating
successfully at the higher stress levels
permitted under the ASME standard. A
technical study published in December
2000 by R.J. Eiber, M. McLamb, and
W.B. McGehee, Quantifying Pipeline
Design at 72% SMYS as a Precursor to
Increasing the Design Stress Level, GRI–
00/0233, further raised interest in the
issue.
In connection with our issuance of the
2003 gas transmission integrity
management regulations, PHMSA
announced a policy to grant ‘‘class
location’’ waivers (now called special
permits) to operators demonstrating an
alternative integrity management
program for the affected pipeline. A
‘‘class location’’ waiver allows an
operator to maintain current operating
pressure on a pipeline following an
increase in population that changes the
class location. Absent a waiver, the
operator would have to reduce pressure
or replace the pipe with thicker walled
pipe. PHMSA held a meeting on April
14–15, 2004, to discuss the criteria for
the waivers. In a notice seeking public
involvement in the process (69 FR
22116; Apr. 23, 2004), PHMSA
announced:
Waivers will only be granted when pipe
condition and active integrity management
provides a level of safety greater than or
equal to a pipe replacement or pressure
reduction.
A second notice (69 FR 38948; June
29, 2004) announced the criteria. The
criteria included the use of high quality
manufacturing and construction
processes, effective coating, and a lack
of systemic problems identified in
internal inspections Although the class
location special permits/waivers do not
address increases in stress levels per se,
the risk management approach
developed in those cases takes account
of operating pressure and addresses
many of the same concerns. The same
risk management approach, and many of
the specific criteria applied in the class
location waivers, guided PHMSA’s
handling of the special permits
discussed below and, ultimately, this
rule.
Beginning in 2005, operators began
addressing the issue of stress level
PO 00000
Frm 00004
Fmt 4701
Sfmt 4700
directly with requests that PHMSA
allow operation at the MAOP levels that
the ASME B31.8 Code would allow.
With the increasing interest, PHMSA
held a public meeting on March 21,
2006, to discuss whether to allow
increased MAOP consistent with the
updated ASME standards. PHMSA also
solicited technical papers on the issue.
Papers filed in response, as well as the
transcript of the public meeting, are in
the docket for this rulemaking. Later in
2006, PHMSA again sought public
comment at a meeting of its advisory
committee, the Technical Pipeline
Safety Standards Committee (TPSSC).
The transcript and briefing materials for
the June 28, 2006, meeting are in the
docket for the advisory committee,
Docket ID PHMSA–RSPA–1998–4470–
204, 220. This docket can be found at
https://www.regulations.gov. Comments
and papers written during the period
these efforts were undertaken
overwhelmingly supported examining
increased MAOP as a way to increase
energy efficiency and capacity while
maintaining safety.
B.4. Safety Conditions in Special
Permits
In 2005, operators began requesting
waivers, now called special permits, to
allow operation at the MAOP levels that
the ASME B31.8 Code would allow. In
some cases, operators filed these
requests at the same time they were
seeking approval from the Federal
Energy Regulatory Commission (FERC)
to build new gas transmission pipelines.
In other cases, operators sought relief
from current MAOP limits for existing
pipelines that had been built to more
rigorous design and construction
standards.
In developing an approach to the
requests, PHMSA examined the
operating history of lines already
operated at higher stress levels.
Canadian and British standards have
allowed operation at the higher stress
levels for some time. The Canadian
pipeline authority, which has allowed
higher stress levels since 1973, reports
the following regarding pipelines
operating at stress levels higher than 72
percent of SMYS:
• About 6,000 miles of pipelines on
the Alberta system, ranging from six to
42 inches in diameter, were installed or
upgraded between the early 1970s and
2005;
• About 4,500 miles of pipelines on
the Mainline system east of the AlbertaSaskatchewan border, ranging from 20
to 42 inches in diameter, were installed
or upgraded between the early 1970s
and 2005; and,
E:\FR\FM\17OCR3.SGM
17OCR3
jlentini on PROD1PC65 with RULES3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
• More than 600 miles in the
Foothills Pipe Line system, ranging from
36 to 40 inches in diameter, were
installed between 1979 and 1998.
In the United Kingdom, about 1,140
miles of the Northern pipeline system
have been uprated to operate at higher
stress level in the past ten years.
Accident rates for pipelines in these
countries have not indicated a
measurable increased risk from
operation at these higher operating
stress levels.
In the United States, some 5,000 miles
of gas transmission lines have MAOPs
that were grandfathered under
§ 192.619(c), when the Federal pipeline
safety regulations were adopted in the
early 1970s, continue to operate at stress
levels higher than 72 percent of SMYS.
After some accidents caused by
corrosion on grandfathered pipelines,
PHMSA considered whether to remove
the exception in § 192.619(c). In 1992,
PHMSA decided to continue to allow
operation at the grandfathered pressures
(57 FR 41119; Sept. 9, 1992). PHMSA
based its decision on the operating
history of two of the operators whose
pipelines contained most of the mileage
operated at the grandfathered pressures.
PHMSA noted the incident rate on these
pipelines, operated at stress levels above
72 percent of SMYS, was between 10
percent and 50 percent of the incident
rate of pipelines operated at the lower
pressure. Texas Eastern Gas Pipeline
Company (now Spectra Energy), the
operator of many of the grandfathered
pipelines, attributed the lower incident
rate to aggressive inspection and
maintenance. This included initial
hydrostatic testing to 100 percent of
SMYS, internal inspection, visual
examination of anomalies found during
internal inspection, repair of defects,
and selective pressure testing to validate
the results of the internal inspection.
Internal inspection was not in common
use in the industry prior to the 1980s.
PHMSA’s statistics show these pipelines
continue to have an equivalent safety
record when compared with pipelines
operating according to the design factors
in the pipeline safety regulations.
PHMSA also considered technical
studies and required companies seeking
special permits to provide information
about the pipelines’ design and
construction and to specify the
additional inspection and testing to be
used. PHMSA also considered how to
handle findings that could compromise
the long-term serviceability of the pipe.
PHMSA concluded that pipelines can
operate safely and reliably at stress
levels up to 80 percent of SMYS if the
pipeline has well-established
metallurgical properties and can be
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
managed to protect it against known
threats, such as corrosion and
mechanical damage.
Early and vigilant corrosion
protection reduces the possibility of
corrosion occurring. At the earliest
stage, this includes care in applying a
protective coating before transporting
the pipe to the right-of-way. With the
newer coating materials and careful
application, coating provides
considerable protection against external
corrosion and facilitates the application
of induced current, commonly called
cathodic protection, to prevent
corrosion from developing at any breaks
that may occur in the coating. Regularly
monitoring the level of protection and
addressing any low readings will detect
and correct conditions that can cause
corrosion at an early stage. Vigilant
corrosion protection includes close
attention to operating conditions that
lead to internal corrosion, such as poor
gas quality. In addition, for new
pipelines, operators’ compliance with a
rule issued last year requiring greater
attention to internal corrosion
protection during design and
construction (72 FR 20059; Apr. 23,
2007) will prevent internal corrosion.
Finally, corrosion protection includes
internal inspection and other
assessment techniques for early
detection of both internal and external
corrosion.
One of the major causes of serious
pipeline failure is mechanical damage
caused by outside forces, such as an
equipment strike during excavation
activities. Burying the pipeline deeper,
increased patrolling, and additional line
marking help prevent the risk that
excavation will cause mechanical
damage. Further, enhanced pipe
properties increase the pipe’s resistance
to immediate puncture from a single
equipment strike. Improved toughness
increases the ability of the pipe to
withstand mechanical damage from an
outside force and may also limit any
failure consequences to leaks rather
than ruptures. This toughness usually
allows time for the operator to detect the
damage during internal inspection well
before the pipe fails.
To evaluate each request for a special
permit, PHMSA established a docket
and sought public comment on the
request. We received several public
comments, most in response to the first
special permits considered. Many of the
comments supported granting the
special permits. Those who were not
supportive may have underestimated
the significance of the safety upgrades
required for the special permits. A few
commenters raised technical concerns.
Among these were questions about the
PO 00000
Frm 00005
Fmt 4701
Sfmt 4700
62151
impact of rail crossings and blasting
activities in the vicinity of the pipeline.
The special permits did not change the
current requirements where road
crossings exist and added a requirement
to monitor activities, such as blasting,
that could impact earth movement.
Some commenters expressed concern
about the impact radius of the pipeline
operating at a higher stress level.
PHMSA included supplemental safety
criteria to address the increased radius.
The remainder of the comments
addressed concerns, such as
compensation or aesthetics, which were
outside the scope of the special permits.
PHMSA special permits do not address
issues on siting, which are governed by
the FERC.
PHMSA expects to issue seven special
permits, and possibly more, in response
to these requests. In each case, PHMSA
has provided oversight to confirm the
line pipe is, or will be (for pipe yet to
be constructed), as free of inherent flaws
as possible, that construction and
operation do not introduce flaws, and
that any flaws are detected before they
can fail. PHMSA accomplishes this by
imposing a series of conditions on the
grant of special permits. The conditions
imposed as part of the special permits
are designed to address the potential
additional risk involved in operating the
pipeline at a higher stress level. A
proposed pipeline must be built to
rigorous design and construction
standards, and the operator requesting a
special permit for an existing pipeline
must demonstrate that the pipeline was
built to rigorous design and
construction standards. These
additional design and construction
standards focused on producing a high
quality pipeline that is free from
inherent defects that could grow more
rapidly under operation at a higher
stress level and is more resistant to
expected operational risks. In addition,
PHMSA requires the operator of a
pipeline receiving a special permit to
comply with operation and maintenance
(O&M) requirements that exceed current
pipeline safety regulations. These
additional O&M and integrity
management requirements focused on
the potential for corrosion and
mechanical damage and on detecting
defects before the defects can grow to
failure.
B.5. Codifying the Special Permit
Standards
This rule puts in place a process for
managing the life-cycle of a pipeline
operating at a higher stress level based
on our experience with the special
permits. Integrity management focuses
on managing and extending the service
E:\FR\FM\17OCR3.SGM
17OCR3
jlentini on PROD1PC65 with RULES3
62152
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
life of the pipeline. Life-cycle
management goes beyond the operations
and maintenance practices, including
integrity management, to address steel
production, pipeline manufacture,
pipeline design, and installation.
Industry experience with integrity
management demonstrates the value of
life-cycle management. Through
baseline assessments in integrity
management programs, gas transmission
operators identified and repaired 2,883
defects in the first three years of the
program (2004, 2005, and 2006). More
than 2,000 of these were discovered in
the first two years as operators assessed
their highest risk, generally older,
pipelines. In a September 2006 report,
GAO–09–946, the Government
Accountability Office noted this data as
an early indication of improvement in
pipeline safety. In order to qualify for
operation at higher stress levels under
this rule, pipelines will be designed and
constructed under more rigorous
standards. Baseline assessment of these
lines will likely uncover few defects,
but removing those few defects will
result in safer pipelines. In addition, the
results of the baseline assessment will
aid in evaluating anomalies discovered
during future assessments.
This rule, based on the terms and
conditions of the special permits
allowing operation at higher stress
levels, imposes similar terms and
conditions and limitations on operators
seeking to apply the new rule. The
terms and conditions, which include
meeting design standards that go
beyond current regulation, address the
safety concerns related to operating the
pipeline at a higher stress level. PHMSA
will step up inspection and oversight of
pipeline design and construction, in
addition to review and inspection of
enhanced life-cycle management
requirements for these pipelines.
With special permits, PHMSA
individually examined the design,
construction, and O&M plans for a
particular pipeline before allowing
operation at a higher pressure than
currently authorized. In each case,
PHMSA conditioned approval on
compliance with a series of rigorous
design, construction, O&M, and
management standards, including
enhanced damage prevention practices.
PHMSA’s experience with these
requests for special permits led to the
conclusion that a rule of general
applicability is appropriate. With a rule
of general applicability, the conditions
for approval are established for all
without need to craft the conditions
based on individual evaluation. Thus,
this rule sets rigorous safety standards.
In place of individual examination, the
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
rule requires senior executive
certification of an operator’s adherence
to the more rigorous safety standards.
An operator seeking to operate at a
higher pressure than allowed by current
regulation must certify that a pipeline is
built according to rigorous design and
construction standards and must agree
to operate under stringent O&M
standards. After PHMSA or state
pipeline safety authority (when the
pipeline is located in a state where
PHMSA has an interstate agent
agreement, or an intrastate pipeline is
regulated by that state) receives an
operator’s certification indicating its
intention to operate at a higher
operating stress level, PHMSA or the
state would then follow up with the
operator to verify compliance. As with
the special permits, this rule would
allow an operator to qualify both new
and existing segments of pipeline for
operation at the higher MAOP, provided
the operator meets the conditions for the
pipeline segment.
Several types of pipeline segments
will not qualify under this rule. These
include the following:
• Pipeline segments in densely
populated Class 4 locations. In addition
to the increased consequences of failure
in a Class 4 location, the level of activity
in such a location increases the risk of
excavation damage.
• Pipeline segments of grandfathered
pipeline already operating at a higher
stress level but not constructed in
accordance with modern standards.
Although grandfathered pipeline has
been operated successfully at the higher
stress level, PHMSA or the state would
examine any further increases
individually through the special permit
process.
• Bare or ineffectively coated pipe.
This pipe lacks the coating needed to
prevent corrosion and to make cathodic
protection effective.
• Pipelines with wrinkle bends.
Section 192.315(a) currently prohibits
wrinkle bends in pipeline operating at
hoop stress exceeding 30 percent of
SMYS.
• Pipelines experiencing failures
indicative of a systemic problem, such
as seam flaws, during initial hydrostatic
testing. Such pipe is more likely to have
inherent defects that can grow to failure
more rapidly at higher stress levels.
• Pipe manufactured by certain
processes, such as low frequency
electric welding process.
• Pipeline segments which cannot
accommodate internal inspection
devices.
We are establishing slightly different
requirements for segments that have
already been operating and those which
PO 00000
Frm 00006
Fmt 4701
Sfmt 4700
are to be newly built. Some variation is
necessary or appropriate for an existing
pipeline. For example, the requirement
for cathodically protecting pipeline
within 12 months of construction is an
existing requirement for all pipelines. A
requirement for the operator of an
existing pipeline segment to prove that
the segment was in fact cathodically
protected within 12 months of
construction provides greater
confidence in the condition of the
existing segment. Allowing proof of five
percent fewer nondestructive tests done
on an existing segment at the time of
construction recognizes the possibility
that some welds may not be tested when
100 percent nondestructive testing is
not required. The overriding principle
in the variation is to allow qualification
of a quality pipeline with minimal
distinction. Based on our review of
requests for special permits on existing
pipelines, PHMSA does not believe the
more rigorous standards we are
requiring are too high for existing
segments of modern design and
construction. Setting the qualification
standards lower for existing pipeline
segments could encourage operators to
construct a pipeline at the lower
standards and seek to raise the operating
pressure at some future date.
PHMSA acknowledges this rule may
not cover all conditions encountered by
a pipeline operator. Further, operators
may have innovative alternative
methods to the guidelines contained in
this rule. To that end, operators may
apply to PHMSA or state pipeline safety
authority (when the pipeline is located
in a state where PHMSA has an
interstate agent agreement, or an
intrastate pipeline is regulated by that
state) for a special permit requesting to
implement the alternative methods.
B.6. How To Handle Special Permits
and Requests for Special Permits
A number of pipeline operators have
submitted requests for special permits
seeking relief from the current design
requirements to allow operation at
higher stress levels. For the most part,
this rule addresses the relief requested.
PHMSA has already granted many of
these under terms and conditions that
may vary slightly from those in this
final rule. In some cases, the relief
granted is specific to the relief requested
by the operator and extends beyond the
scope of this rulemaking. PHMSA has
continued review of pending special
permit applications while working on
this rulemaking, in recognition that a
final rule may not be issued by the time
an operator intended to operate its
pipeline at a higher operating stress
level. With the publication of this final
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
rule, this case-by-case approach to
approving operation under a special
permit at higher operating stress levels
is no longer needed.
PHMSA will terminate its review of
any pending applications for special
permits associated with operation at
higher operating stress levels once this
final rule is issued. Operators of those
pipelines must comply with this final
rule in order to operate their pipelines
at a higher alternative MAOP. PHMSA
will examine special permits that have
already been granted, as appropriate, to
determine if any modifications are
needed in light of safety decisions made
in preparing this rule.
jlentini on PROD1PC65 with RULES3
B.7. Statutory Considerations
Under 49 U.S.C. 60102(a), PHMSA
has broad authority to issue safety
standards for the design, construction,
O&M of gas transmission pipelines.
Under 49 U.S.C. 60104(b), PHMSA may
not require an operator to modify or
replace existing pipelines to meet a new
design or construction standard.
Although this rule includes design and
construction standards, these standards
simply add more rigorous, nonmandatory requirements. This rule does
not require an operator to modify or
replace existing pipelines or to design
and construct new pipeline in
accordance with these non-mandatory
standards. If, however, a new or existing
pipeline meets these more rigorous
standards, the rule allows an operator to
elect to calculate the MAOP for the
pipeline based on a higher stress level.
This would allow operation at an
increased pressure over that otherwise
allowed for pipeline built since the
Federal regulations were issued in the
1970s. To operate at the higher pressure,
the operator would have to comply with
more rigorous O&M, and management
requirements.
Under 49 U.S.C. 60102(b), a gas
pipeline safety standard must be
practicable and designed to meet the
need for gas pipeline safety and for
protection of the environment. PHMSA
must consider several factors in issuing
a safety standard. These factors include
the relevant available pipeline safety
and environmental information, the
appropriateness of the standard for the
type of pipeline, the reasonableness of
the standard, and reasonably
identifiable or estimated costs and
benefits. PHMSA has considered these
factors in developing this rule and
provides its analysis in the preamble.
PHMSA must also consider any
comments received from the public and
any comments and recommendations of
the TPSSC. These are discussed below.
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
62153
C. Comments on the NPRM
Response
PHMSA received comments from 19
organizations in response to the NPRM.
These included eleven pipeline
operators, four trade associations and
related organizations, three steel/pipe
manufacturers, and one state pipeline
safety regulatory agency.
As noted above, PHMSA continued
reviewing special permit applications
throughout this rulemaking proceeding,
generally applying the same criteria
adopted in this rule. Having now
published the final rule, we consider it
unnecessary to complete review of
pending special permit applications on
the subject. Accordingly, PHMSA
intends to terminate these proceedings,
with appropriate notice to the
individual applicants.
In contrast, this regulatory action has
no effect on the status of special permits
or waivers currently in effect. As we
explained recently in Docket No.
PHMSA–2007–0033, Pipeline Safety:
Administrative Procedures, Address
Updates, and Technical Amendments,
(FR Volume 73, No. 61, 16562,
published March 28, 2008), PHMSA
reserves the right to revoke or modify a
special permit or waiver based on an
operator’s failure to comply with the
conditions of the special permit/waiver
or on a showing of material error,
misrepresentation, or changed
circumstances. Although an operator
may elect to surrender its special permit
at any time, nothing in this rule requires
the operator to do so or otherwise
triggers reopening of a special permit/
waiver currently in effect. The existing
MAOP special permits were issued
based upon a PHMSA review of the
operator’s engineering, construction,
O&M procedures and operating history.
While some of the pipeline segments
may not meet all of the requirements
specified in this final rule, the
operational history and O&M practices
provide an equivalent level of safety as
provided in this final rule. Furthermore,
whether a pipeline is operating at higher
MAOP under this rule or a special
permit/waiver, PHMSA will monitor
and enforce compliance with the
applicable conditions and safety
controls.
C.1. General Comments
API 5L, 44th Edition
Many commenters noted that pipe
material/design requirements in
American Pipeline Institute (API)
Standard 5L (API 5L) have been
significantly revised in the 44th edition,
which they stated would be in effect by
the time a final rule is issued. These
commenters generally suggested that
PHMSA should defer to, or incorporate,
requirements from the 44th edition
where applicable rather than
establishing different technical
requirements in regulation.
Response
API 5L, 43rd edition, is currently
incorporated by reference into the Code
of Federal Regulations (CFR). PHMSA
has begun a technical review of the 44th
edition to determine whether and to
what extent it is appropriate to update
this reference or if exceptions need be
taken when so incorporating the
standard. PHMSA cannot reference
requirements in the 44th edition until
this review is completed and the
regulations have been revised to
incorporate the new edition. Where
differences in the 44th edition would
affect requirements in this rule,
appropriate changes will be made when
that edition is incorporated.
Effect on Special Permits
All commenters who addressed the
question suggested that requirements in
a final rule should not apply
retroactively to pipelines operating at
alternative MAOP based on special
permits issued after detailed review by
PHMSA. One pipeline operator
provided a legal analysis maintaining
that such retroactive application would
be contrary to PHMSA’s statutory
authority. These organizations also
commented that PHMSA should
continue review of special permit
applications until the final rule is
issued, noting that in many cases
operation at the proposed higher MAOP
is necessary to meet contractual
commitments operators have made in
anticipation of a special permit being
granted and to meet national energy
needs.
PO 00000
Frm 00007
Fmt 4701
Sfmt 4700
Structure
One state pipeline safety regulatory
agency expressed concern about the
complexity and inconsistency being
added to the regulations as a result of
the structure of the proposed rule. The
state agency noted that the proposal
would add many pages to part 192 that
would apply to only a limited number
of gas transmission operators. The
agency suggested that it would be more
effective, and cause less confusion, if
requirements for pipelines operating at
an alternative MAOP were presented in
a separate subpart, applicable only to
those pipelines.
E:\FR\FM\17OCR3.SGM
17OCR3
62154
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
Response
PHMSA has not previously used a
separate subpart to include varied
requirements applicable to specific
types of pipelines. Instead, subparts
have been used for individual topics,
such as Corrosion Control or Integrity
Management. PHMSA considers it more
appropriate to incorporate requirements
applicable to each subpart as the
requirements in this rule implicate
several subparts. PHMSA also notes that
no other commenters indicated that the
structure of the proposed rule was
confusing. PHMSA has retained the
structure of the proposal in this final
rule. PHMSA intends to post this notice
of final rulemaking on its web site,
which will provide a reference for
pipeline operators that includes all of
the requirements associated with
alternative MAOP in one document.
C.2. Comments on Specific Provisions in
the Proposed Rule
jlentini on PROD1PC65 with RULES3
C.2.1. Section 192.7, Incorporation by
Reference
Interstate Natural Gas Association of
America (INGAA) and three pipeline
operators supported incorporation of
American Society of Testing and
Materials (ASTM) standard ASTM A–
578/A578M–96 into the regulations.
These commenters generally noted that
this action is consistent with reliance on
consensus standards, which they
support. American Gas Association
(AGA) and the Gas Piping Technology
Committee (GPTC) took the contrary
position and opposed incorporation of
the ASTM standard. GPTC commented
that the standard is used by one mill
and that other mills use other standards
(including International Standards
Organization (ISO) standards). GPTC
also noted that there are a number of
equivalent standards and that PHMSA
should not select one for incorporation.
AGA added that incorporating the
standard could have unintended
consequences of making the rule too
prescriptive and precluding the use of
equivalent standards.
Response
The final rule incorporates ASTM
A578/A578M–96 into the regulations.
Incorporation by reference makes the
provisions of the standard apply, when
it is referenced in a regulation, in the
same manner as if they were written in
the CFR. Referencing consensus
standards wherever possible is the
policy of the Federal government.
This standard is referenced in the
regulation for assuring plate/coil quality
control (QC). That reference requires
that ultrasonic (UT) testing be
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
conducted in accordance with the
standard, API 5L paragraph 7.8.10, or
equivalent. The pipe must also be
manufactured in accordance with API
5L which is already referenced in
§ 192.7. PHMSA considers that the
allowance for use of an equivalent
standard renders moot the concerns
expressed by AGA and GPTC.
C.2.2. Design Requirements
Section 192.112(a), General Standards
for the Steel Pipe
Carbon equivalent: INGAA, five
pipeline operators and two pipe
manufacturers all noted that the
proposed limit in paragraph (a)(1) on
carbon equivalent (CE) (0.23 percent
Pcm) is inconsistent with the 44th
edition of API 5L. INGAA and one
operator suggested deleting the limit
from the proposed rule. Two operators
noted that the NPRM described no
analysis or data showing the need for a
different limit. Several commenters
indicated that high-strength pipe (grades
X–80 and above) is difficult to achieve
with the stated limit. One operator
suggested that weldability is the key
issue and that allowance for a higher CE
is particularly important for highstrength and strain-based pipe. A steel
manufacturer objected to sole reliance
on the Pcm formula for determining the
CE value.
Response
PHMSA agrees that the limit in API
5L is acceptable. PHMSA has changed
the limit for CE to 0.25 Pcm (Ito-Bessyo
formula for CE), which is consistent
with API 5L. PHMSA does not agree
that no limit should be included in the
CFR. PHMSA considers that a limit is
necessary to assure the quality of steel
used for pipelines to operate at an
alternative MAOP. Weldability tests are
not timely for determining the
acceptability of steel, as they cannot be
performed until pipe is manufactured.
Recent experience with several new
pipelines using X–80 steel has indicated
that such high strength steel can meet
the CE limit. PHMSA does not currently
have experience with steels of grades
higher than X–80 and will need to
understand what is important for such
pipe grades as they are used.
PHMSA acknowledges that there are
other methods for calculating the CE
value of steel. The Pcm formula
included in the proposed rule is a
method used by several mills. PHMSA
has revised the final rule to include use
of an alternate International Institute of
Welding (IIW) CE formula, used by
other mills for determining CE.
PO 00000
Frm 00008
Fmt 4701
Sfmt 4700
Diameter to thickness ratio: INGAA
and three pipeline operators suggested
deleting the limit in proposed paragraph
(a)(3) on the ratio of pipe diameter to
thickness (D/t). They maintained that
this limit may be inappropriate for highgrade pipe and that the concerns that
might underlie such a limit are
adequately addressed by the proposed
rule and common construction practices
and quality assurance (QA). One
operator noted that ovality and denting
issues are addressed by the proposed
construction requirements of § 192.328,
that QA is required by proposed
§ 192.620(d)(9), and that the baseline
geometry ILI and the provisions of the
ASME Code would also address the
underlying concerns.
Response
PHMSA has retained the proposed
limit. PHMSA adopted this limit (i.e., D/
t ≤ 100) based upon presentations made
by industry experts at the public
meeting on ‘‘Reconsideration of
Maximum Allowable Operating
Pressure in Natural Gas Pipelines’’ held
on March 21, 2006 in Reston, VA.
Higher D/t ratios can lead to excessive
denting during transportation,
construction bending, pipe stringing on
the right-of-way, backfilling, and
hydrostatic testing.
Section 192.112(b), Fracture Control
Several commenters noted that some
requirements included in the proposed
rule are being eliminated or
significantly revised in the 44th edition
of API 5L. The steel/pipe manufacturers
suggested referencing the new standard
to, among other things, avoid
unnecessarily limiting approaches to
deriving arrest toughness and treating
all sizes and types of pipe (e.g.,
seamless) the same for purposes of the
drop weight test.
INGAA and three pipeline operators
suggested a change to allow a crack
arrest design other than mechanical
arrestors if crack propagation cannot be
made self-limiting. (One operator noted
that Clock Spring 1 is marketed as a
crack arrestor). They suggested that a
rule should allow an option for
engineering analysis, including an
analysis of consequences. One operator
noted that this option could be
particularly important for high-pressure,
large-diameter pipelines. Two operators
generally supported the proposed
approach for fracture control if selfarrest is attainable. They noted that it is
critical that operators have a plan and
consider the potential under1 Clock Spring is a commercially available
composite sleeve used for pipeline repairs.
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
conservativeness of Charpy toughness
equations for high grade pipe (X–70 and
above).
jlentini on PROD1PC65 with RULES3
Response
PHMSA has not yet incorporated the
44th edition of API 5L into the
regulations. PHMSA is conducting a
technical review of this edition to
determine if it is acceptable for
incorporation. If, after that review,
PHMSA determines that the standard is
acceptable, PHMSA will propose to
incorporate the 44th edition and change
other affected rules as appropriate.
The final rule requires an overall
fracture control plan to resist crack
initiation and propagation and to arrest
a fracture within eight pipe joints with
a 99 percent occurrence probability and
within five pipe joints with a 90 percent
occurrence probability. Research has
shown that an effective fracture plan
should include acceptable Charpy
impact and drop weight tear tests,
which are required in this final rule.
PHMSA considers composite sleeves
to be suitable mechanical crack
arrestors. Operators could use
composite sleeves for this purpose,
install periodic joints of thicker-walled
pipe, or use other design features to
provide crack arrest if it is not possible
to achieve the toughness properties
specified in the rule and also assure
self-limiting arrest. PHMSA has revised
the language in this final rule to allow
additional design features and to make
mechanical crack arrestors an example
of such features rather than the only
method allowed.
Section 192.112(c), Plate/Coil Quality
Control
One pipeline operator and two pipe
manufacturers suggested expanding the
mill control inspection program to a full
internal quality management program
and including caster and plate/coil/pipe
mills.
INGAA, three pipeline operators and
two pipe manufacturers commented that
the specificity of requirements
applicable to mill inspection should be
reduced. These commenters agreed that
a macro etch test is appropriate but
suggested that the details of how this
test is applied should be left to
decisions of the mill and the pipe
purchaser. They suggested that API 5L
provides a foundation for those
decisions and the specific requirements
in the proposed rule add unnecessary
cost impact. One pipe manufacturer
noted that the Mannesmann scale is
very subjective, while a second
separately commented that reference to
the Mannesmann scale should be
deleted because it is proprietary and
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
thus inappropriate for inclusion in a
regulation. One operator requested that
the mill inspection requirements,
including those for macro etch and UT
examination, be explicitly limited to
new pipelines, noting that it is unlikely
these tests were performed for any
existing pipelines and that they have
minimal relevance for existing pipelines
that would be subject to the proposed
rule.
INGAA and four pipeline operators
suggested that an alternative to the UT
testing specified should be allowed for
identifying laminations. They suggested
that a full-body UT inspection, for
example, should be acceptable.
One operator and two manufacturers
commented that it is inappropriate to
use the proposed macro etch test and
acceptance criteria as a heat/slab
rejection criteria. These commenters
noted that no consensus standard
references this test. The operator
maintained that the test does not
accomplish what PHMSA suggested in
the preamble of the NPRM, that it is a
lagging rather than a leading test and its
use as an acceptance test without a
retest allowance could result in
rejection of up to 2,000 tons of steel or
more. The operator suggested that this
should be a mill control test rather than
an acceptance test with specifics,
including retest allowance, to be
negotiated between the mill and pipe
purchaser.
One operator and one manufacturer
noted that ASTM A578 is a plate UT
inspection standard. They commented
that specifying this standard for coil/
pipe is beyond its scope. They also
commented that we gave no basis for
proposing that 50 percent of surface and
90 percent of joints be examined. They
noted that pipe seam welds and pipe
ends are inspected radiographically or
by UT and that additional UT is more
appropriately a purchaser-specified
requirement. Another operator also
suggested that the 50 percent surface
coverage requirement be deleted in
favor of reference to ASTM A578/
A578M.
Two manufacturers suggested that the
rule allow UT on plate/coil or pipe
body, noting that most United States
mills lack equipment to perform ASTM
A578 testing. Another manufacturer
suggested that a combination of
electromagnetic inspection (EMI) and
UT inspection is superior and would
produce the most dramatic impact. This
combination, according to this
manufacturer, is also applicable to
seamless and electric resistance welded
(ERW) pipe.
One manufacturer recommended that
the inspection program of proposed
PO 00000
Frm 00009
Fmt 4701
Sfmt 4700
62155
section 192.112(c)(2)(ii) be limited to
submerged arc welded (SAW) pipe, and
that the acceptance criteria for UT
testing be referenced to ASTM A578 or
equivalent. This commenter noted that
laminations are not a significant issue
for modern pipe.
Response
PHMSA agrees that an ‘‘internal
quality management program’’ is more
descriptive than a ‘‘mill control
inspection program’’ and that such a
program should be required at all mills
associated with the manufacture of steel
and pipe. The final rule has been
revised accordingly.
PHMSA considers that a macro etch
test or other equivalent method is
needed to identify inclusions that may
cause centerline segregation during the
continuous casting process. The
acceptance criteria must be agreed to
between the purchaser and the mill.
PHMSA has added an alternative to the
requirement for a macro etch test
consisting of an operator QA monitoring
plan that includes audits conducted by
the operator (or an agent operating
under its authority) of: (a) Steelmaking
and casting facilities; (b) QC plans and
manufacturing procedure specifications
(MPS); (c) equipment maintenance and
records of conformance; (d) applicable
casting superheat and speeds; and (e)
centerline segregation monitoring
records to ensure mitigation of
centerline segregation during the
continuous casting process.
PHMSA agrees that alternate methods
to test the pipe body for laminations,
cracks, and inclusions should be
acceptable and has revised the rule to
allow methods per API 5L Section
7.8.10 or ASTM A578-Level B, or other
equivalent methods. PHMSA
understands that it is unlikely that
many existing pipelines were
manufactured using processes that
included the specified examinations but
does not consider that sufficient reason
for excluding existing pipelines from
the requirements.
The requirement for 50 percent of
surface and 95 percent of lengths of pipe
to be UT tested was set to ensure
adequate QC standards. PHMSA agrees
that the specified QC requirements also
must be practical. In the final rule, we
have reduced the requirement for 50
percent of surface coverage to 35
percent because we recognize that it
may be difficult to achieve 50 percent
coverage for pipe manufactured with
helical seams.
PHMSA has not deleted reference to
the Mannesmann scale, which is widely
used by steel manufacturers. In
E:\FR\FM\17OCR3.SGM
17OCR3
62156
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
addition, the regulation allows for use of
equivalent measures.
PHMSA does not agree that the
inspection program of proposed
192.112(c)(2)(ii) should be limited to
SAW pipe. PHMSA considers this
requirement to be an overall quality
management tool and not just for
laminations. Additionally, PHMSA
notes that at least one recently
constructed pipeline has had problems
with laminations.
jlentini on PROD1PC65 with RULES3
Section 192.112(d), Seam Quality
Control
INGAA, four pipeline operators, and
two pipe manufacturers all
recommended additional reliance on the
procedures of API 5L 44th edition. The
manufacturers would have referenced
API 5L for toughness requirements and
made them applicable to weld and heat
affected zone in SAW pipe only. They
noted that the proposed requirement is
inappropriate for ERW pipe, that the
specified toughness is higher than that
called for in API 5L and is not
necessary. The manufacturers believe
that fracture arrest capabilities are not
needed in weld metal, since staggered
seams in pipeline construction result in
arrest occurring in the pipe body.
INGAA and three pipeline operators
would have eliminated reference to
specific hardness testing or a maximum
hardness level, arguing that API 5L
contains sufficient guidance. They
further noted that the specified hardness
of 280 Vickers (Hv10) is only for sour
gas. One manufacturer would have
relaxed the hardness requirement to 300
Hv10 and allowed for equivalent test
methods (per ASTM E140). Another
would have specified a maximum
hardness ‘‘appropriate for the pipeline
design’’ vs. specifying a limit. The first
manufacturer noted that API 5L does
not specify hardness limits except for
sour gas service or offshore pipelines
and that the technical justification for
these limits on other pipe is not
obvious. The manufacturers maintained
that limiting hardness may not allow
attaining the best weld properties and
that 280 Hv10 is likely not attainable for
pipe grades X–80 and above.
Two pipe manufacturers requested
that the rule be clarified to indicate that
the seam QC requirements apply only to
longitudinal or helical seams. They
noted that pipe mill jointer welds
require radiography per API 1104 and
that significant capital expense would
be required for pipe mills to UT test
jointer and skelp end welds after cold
expansion and hydrostatic testing.
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
Response
PHMSA has not yet incorporated the
44th edition of API 5L into the
regulations. PHMSA is conducting a
technical review of this edition to
determine if it is acceptable for
incorporation. If, after review, PHMSA
determines that the standard is
acceptable, PHMSA will propose to
incorporate the 44th edition and
propose changes to other affected
regulations as appropriate.
PHMSA has deleted the proposed
limit on toughness. This limit was not
included in the conditions applied to
special permits issued for alternative
MAOP operation. Pipe procured to
modern standards generally meets the
proposed limit, and other requirements
in this rule, provide for crack arrest.
Thus, PHMSA concluded that a
toughness limit was not needed.
PHMSA does not agree that it is not
necessary to specify a hardness limit.
All recent pipelines for which special
permits have been issued to operate at
alternative MAOP have met the
proposed hardness limit without
apparent difficulty. This includes X–80
pipe. The requirement helps assure that
only high-quality steel is used for
pipelines to be operated at alternative
MAOP. Hardness must be limited to
assure welds are not susceptible to
cracking. The proposed limit has been
retained in the final rule.
PHMSA intends the proposed seam
inspection requirements to apply to
pipe seam welds and not to jointer or
skelp welds. The title of this
subparagraph is ‘‘Seam quality control,’’
and its requirements all refer to ‘‘seam
welds’’ or ‘‘seams.’’ PHMSA does not
consider that additional changes are
needed to clarify the applicability of
these requirements.
Section 192.112(e), Mill Hydrostatic
Test
Most commenters objected to the
proposed requirement that mill
hydrostatic tests be held for 20 seconds.
They noted that mills typically follow
API 5L, which specifies a hydrostatic
test of 10 seconds and that changing this
standard could reduce mill
productivity. One operator also noted
that a more rigorous qualification test is
already specified elsewhere in the
proposed regulation.
One manufacturer would have limited
the required maximum test pressure to
3,000 psi if there are physical
limitations in mill test equipment that
preclude obtaining higher pressures.
The manufacturer stated that most mills
cannot achieve test pressures above
3,000 psi, which is the maximum
PO 00000
Frm 00010
Fmt 4701
Sfmt 4700
specified in API 5L and that upgrades to
equipment would cost from $0.5 to $4
million per tester.
Response
PHMSA agrees that a 20-second mill
hydrostatic test is not needed and has
revised the final rule to reduce the
required hold time to 10 seconds. While
a longer mill hydrostatic test may allow
the discovery of more pipe defects, the
benefit is marginal. The pipeline will
later be subject to a much longer
hydrostatic test prior to being placed in
service according to 192.505(c).
Moreover, in the case of Class 1 and 2
locations, the pipe will be tested at a
higher stress level than the mill
hydrostatic test according to
192.620(a)(2).
PHMSA does not consider it
appropriate to limit the maximum test
pressure to reflect the reported mill
limitations. In practice, the need for
tests above 3,000 psi should be rare.
Test pressures that high would only be
required for pipeline in a Class 3
location operating at a very high MAOP.
Section 192.112(f), Coating
INGAA, GPTC, and eight pipeline
operators all objected to the proposed
requirements that would have limited
operation at an alternative MAOP to
pipe coated with fusion bonded epoxy
(FBE). The commenters noted that
specifying any single coating type
would stifle innovation. They suggested
that a performance-based requirement
would be more appropriate. The
important performance characteristics
they identified include non-disbonding
and non-cracking. Two operators would
add non-shielding, and GPTC suggested
specifying that coating must meet or
exceed the protection of FBE.
GPTC and one operator requested
clarification that girth welds can be
coated with other than FBE. GPTC also
requested clarification that the proposed
requirement in subparagraph 2 that
coatings used for trenchless installation
must resist abrasion and other damage
applies to the coatings described under
subparagraph 1.
Response
PHMSA agrees that specifying a
particular coating could stifle
innovation and we have revised the
final rule to require non-shielding
coatings. Eliminating reference to FBE
coating in this section obviates the need
for additional changes to note that girth
welds can be coated with other than
FBE.
PHMSA has made a minor change in
response to GPTC’s request for
clarification. Subparagraph 192.112(f)(2)
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
now requires that coatings used for
trenchless installation must resist
abrasions and other installation damage
‘‘in addition to being non-shielding.’’
Section 192.112(g), Flanges and Fittings
INGAA and three pipeline operators
generally supported the proposed
requirements for certification records
and a pre-heat procedure for welding of
components with CE greater than 0.42
percent, but maintained that existing
standards and operator supplemental
requirements are adequate to assure the
integrity of flanges and fittings. The
operators cited specific standards to
which fittings and flanges should be
purchased. Another operator noted that
the proposed requirements go beyond
API and ASTM standards, and
suggested that the new requirements
should be part of an industry standard.
This operator also suggested that
PHMSA establish a minimum size
below which certifications would not be
required.
GPTC requested clarification as to
what certification is required and what
requirements/specifications are to be
certified.
jlentini on PROD1PC65 with RULES3
Response
PHMSA has concluded that no
changes are needed to the standards
proposed for flanges and fittings. It is
likely that flanges and fittings procured
to current standards will meet the rule’s
requirements. PHMSA will review the
degree of compliance during inspections
of pipelines being constructed or
upgraded for operation at an alternative
MAOP. PHMSA does not agree that the
proposed requirements go beyond API
and ASTM standards. Fittings, flanges
and valves manufactured to API, ASTM,
and/or ASME/ANSI standards should
not be operated above the maximum
operating pressure limits of those
industry standards for the product
rating. This rule change is not intended
to increase maximum operating pressure
limits or designated pressure or
temperature rating of referenced code
standards.
In the final rule, PHMSA has clarified
that certification must address
chemistry, strength and wall thickness.
Section 192.112(h), Compressor Stations
Commenters expressed concern about
the proposed requirement to limit
compressor station discharge
temperatures to 120 degrees Fahrenheit
(49 degrees Celsius) unless testing
shows the coating can withstand higher
temperatures in long-term operations.
INGAA and four pipeline operators
would allow ‘‘research’’ in addition to
testing to permit operation above 120
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
degrees Fahrenheit. INGAA submitted a
white paper titled ‘‘A Review of the
Performance of Fusion-Bonded Epoxy
Coatings on Pipelines at Operating
Temperatures Above 120 °F’’, dated
May 16, 2008, describing research it
believes is relevant. The commenters
stated that more testing is not needed,
because FBE coating has been shown
effective by research and experience in
service. They maintained that
disbonding may occur but is irrelevant
because FBE coating is conductive and
cathodic protection is still effective.
One pipeline operator would have
allowed operation at a higher
compressor station discharge
temperature if justified by test or data
held by the manufacturer, coating
applicator, or operator. The operator
maintained that modern coating can
withstand higher temperatures, and that
maintaining 120 degrees Fahrenheit
may be impractical on hot days (during
which peak loads often occur) in
southern locations. Another operator
suggested allowing operators to rely on
FBE manufacturers’ specifications as the
‘‘testing’’ adequate to allow operation
above 120 degrees Fahrenheit, limiting
operation to 90 percent of the
manufacturer’s continuous operating
temperature. Another operator
suggested allowing a long-term coating
integrity monitoring program as an
alternative to designing compressor
stations to limit discharge temperature
to 120 degrees Fahrenheit.
A state pipeline safety regulatory
agency suggested that alternative
approaches be allowed. The agency
suggested that operators could install
heavier walled pipe and operate at
conventional MAOP for the distance
required to assure that pipe wall
temperatures would be below 120
degrees Fahrenheit. This commenter
stated its belief that this would be a
simpler and cheaper solution to the
concern over compressor station outlet
temperature and that its use should not
be precluded.
Response
PHMSA is not persuaded by the
arguments put forth by commenters, and
in the INGAA white paper titled ‘‘A
Review of the Performance of FusionBonded Epoxy Coatings on Pipelines at
Operating Temperatures Above 120 °F’’,
dated May 16, 2008, that operation
above 120 degrees Fahrenheit is simply
acceptable. In fact, the INGAA white
paper confirms that disbonding and
possibly cracking of FBE coating is more
likely to occur at operating temperatures
above 120 degrees Fahrenheit. PHMSA
disagrees that disbonding is irrelevant
because disbonded FBE remains
PO 00000
Frm 00011
Fmt 4701
Sfmt 4700
62157
conductive and an operating cathodic
protection system will protect the
pipeline from corrosion.
External corrosion is one of the most
significant threats affecting steel
pipelines. PHMSA regulations require
two levels of protection against this
threat: Coating and cathodic protection.
These requirements are intended to
provide redundant protection. If coating
fails, cathodic protection continues to
protect the pipe. If cathodic protection
fails, the coating is still present. PHMSA
agrees that it is important that
disbonded coating remain conductive to
assure continued protection by cathodic
protection. This is why the rule has
been revised to require ‘‘non-shielding’’
coating. At the same time, PHMSA does
not consider it acceptable to ignore
known circumstances in which one of
the protections against corrosion is
likely to fail simply because the other
exists. If PHMSA believed only one
level of protection were needed, the
regulations would require either coating
or cathodic protection. INGAA’s white
paper confirms that there is a significant
likelihood that one of the levels of
protection against corrosion (i.e.,
coating) will fail if operated above 120
degrees Fahrenheit. For pipelines to be
operated at an alternative MAOP, where
the margin for corrosion is smaller than
for pipelines conforming to the existing
regulations, PHMSA will not accept this
higher likelihood of failure of the
coating system.
Nevertheless, PHMSA recognizes that
improvements in coating systems may
allow operation above 120 degrees
Fahrenheit without significantly higher
likelihood of disbonding. Thus, the rule
allows operation above this temperature
if research, testing, and field monitoring
tests demonstrate that the coating type
being used will withstand long-term
operation at the higher temperature. The
operator must assemble and maintain
the data supporting higher-temperature
operation. Research, testing and field
monitoring must be for coating by the
same manufacturer and must be specific
to the brand of coating (if the
manufacturer makes more than one
brand), application temperature, or
operating temperature rated coating.
PHMSA agrees that a long-term
coating integrity monitoring program
can also assure that coating remains
effective at higher operating
temperatures, but the effectiveness of
such a program depends on how it is
structured and implemented. PHMSA
would expect, for example, that a
monitoring program being used as a
basis for operating at temperatures
above 120 degrees Fahrenheit would
include periodic examinations to assure
E:\FR\FM\17OCR3.SGM
17OCR3
62158
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
coating integrity (e.g., direct current
voltage gradient). PHMSA has modified
the final rule to allow a long-term
coating integrity monitoring program to
be used as a basis for allowing pipe
temperatures in excess of 120 degrees
Fahrenheit, but operators must submit
their programs to the PHMSA pipeline
safety regional office in which the
pipeline is located for review before
pipeline segments may be operated at
alternative MAOP at these higher
temperatures. PHMSA’s review will
help assure that the monitoring
programs are comprehensive enough to
assure long-term coating integrity, to
identify instances in which coating
integrity becomes degraded, and to
address those problems. An operator
must also notify a state pipeline safety
authority when the pipeline is located
in a state where PHMSA has an
interstate agent agreement, or an
intrastate pipeline is regulated by that
state.
Where compressor station
compression ratios raise the temperature
of the flowing gas to above 120 degrees
Fahrenheit, operators should consider
installing gas coolers at compressor
stations. This practice has been
successfully used in the industry to cool
the gas stream to not damage the pipe
external coating.
PHMSA agrees that the alternative of
heavier walled pipe operated at
conventional MAOP for the distance
required to assure that pipe wall
temperatures do not exceed 120 degrees
Fahrenheit suggested by the state
regulator is also an acceptable method
of addressing the concern of hightemperature operation. PHMSA has
made minor changes to the rule to make
it clear that this option is not precluded.
C.2.3. Construction Requirements
Section 192.328(a), Quality Assurance
(QA)
Four pipeline operators supported the
QA requirements of proposed
§ 192.328(a). A state pipeline safety
regulator noted that subparagraph 2(ii)
duplicated requirements in proposed
§ 192.620(c)(5) and questioned why both
sub-rules were needed.
jlentini on PROD1PC65 with RULES3
Response
PHMSA’s experience in regulating
pipelines operating at higher MAOPs
under special permits has indicated that
control of quality is subject to frequent
problems. As a result, PHMSA considers
that an explicit requirement for a QA
plan during construction is needed. The
requirements of proposed
§ 192.620(c)(5) also addressed quality
concerns, but they relate principally to
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
personnel qualification. As described
below, this proposed paragraph has
been revised in the final rule to more
explicitly address the qualification of
personnel performing construction
tasks.
Section 192.328(b), Girth Welds
INGAA and four pipeline operators
suggested moving the requirement for
testing of girth welds on existing
pipelines from § 192.328 to § 192.620.
They believe that the requirement is
inappropriately located in a
construction section that is not
otherwise applicable to existing pipe.
Response
PHMSA agrees and has moved this
requirement in the final rule to
§ 192.620(b) as one of the criteria for
determining when an existing pipeline
can be operated at alternative MAOP.
Section 192.328(c), Depth of Cover
Three pipeline operators supported
the proposed depth of cover
requirements, although one would
clarify that they apply to new
construction. Another operator
suggested that allowance be made for
less depth of cover if alternative means
of protection are used (e.g., concrete
slabs) that offer equivalent protection.
Response
PHMSA agrees that alternative
protection is acceptable and has revised
its proposed rule accordingly in this
final rule. To satisfy the rule, alternative
protection must provide equivalent
protection and the operator must
demonstrate this equivalence. Simply
providing barriers without
demonstrating that they provide
equivalent protection is not sufficient.
PHMSA did not intend this
requirement to apply to new
construction only and thus, has not
changed the requirement in the final
rule. PHMSA considers that a pipeline
to be operated at alternative MAOP,
including existing pipelines, must have
superior protection from outside force
damage. PHMSA recognizes that
existing pipelines constructed in
compliance with § 192.327 may have
less cover than required in this rule.
Operators of those pipelines desiring to
implement alternative MAOP must
provide equivalent protection for those
segments not meeting the depth of cover
requirements.
Section 192.328(d), Initial Strength
Testing
A number of commenters objected to
the proposed requirement that any
failure indicative of a fault in material
PO 00000
Frm 00012
Fmt 4701
Sfmt 4700
disqualifies a pipeline segment from
operation at an alternative MAOP. The
commenters suggested that a root cause
analysis be permitted, consistent with
previously-issued special permits, to
determine if the fault indicates a
systemic issue. Disqualification is only
appropriate, according to the
commenters, if a systemic issue exists,
and failures can result from isolated
causes. One operator would also clarify
that these requirements apply to base
pipe material rather than flanges,
gaskets, etc. Another suggested that
multiple test failures can actually be
beneficial, because they prompt
additional failure analyses that better
assure the integrity of the non-failed
pipe.
Response
PHMSA agrees that a single failure
can reflect an isolated cause and should
not disqualify an entire segment from
operation at an alternative MAOP if it
can be demonstrated that the failure is
not indicative of a problem that could
affect the rest of the pipeline segment.
PHMSA has revised the final rule to
allow a root cause analysis of any
failures as a way of justifying
qualification of a pipeline segment. Root
cause analysis must demonstrate that
failures in alternative MAOP pipeline
segments are not systemic. Operators are
required to notify PHMSA of the results
of their evaluations, which will allow us
to validate their conclusions.
Section 192.328(e), Cathodic Protection
INGAA and seven pipeline operators
suggested that this paragraph be deleted,
since it duplicates requirements in
§ 192.455. One of the operators further
commented that whether cathodic
protection was operational within 12
months becomes irrelevant once the line
is assessed and its condition is known.
Response
PHMSA recognizes that § 192.455
requires that cathodic protection be
operational within 12 months of placing
a pipeline in service but does not
consider the requirement in this rule
duplicative. Operators who complied
with § 192.455 will, of course, meet this
criterion for operation at alternative
MAOP. Those who did not install
cathodic protection within 12 months of
initial operation will not, whether or not
§ 192.455 was effective at the time.
PHMSA considers it critical that
cathodic protection be provided as
quickly as possible after construction,
because there are some forms of
corrosion that can result in high
corrosion rates (e.g., microbiological
corrosion and corrosion from current
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
faults) producing significant loss of pipe
wall in a short period of time. Operation
at alternative MAOP is thus not allowed
for those pipelines for which cathodic
protection was not provided within 12
months of initial operation.
PHMSA has moved this requirement
from § 192.328, a section addressing
construction requirements, to
§ 192.620(d)(8), a section addressing
operations and maintenance
requirements. PHMSA believes that this
change will help emphasize that this is
not simply a re-statement of the
requirement in § 192.455.
Section 192.328(f), Interference Currents
Three pipeline operators supported
the proposed requirements in this
subparagraph (one with the
understanding that § 192.473 will
govern for an existing Class 1 pipeline).
Taking a contrary position, another
operator urges PHMSA to delete this
paragraph because the requirement is
already addressed in the regulations and
it is difficult to address all interference
issues during construction without
active cathodic protection (cathodic
protection is not required to be in
service until 12 months after
construction).
jlentini on PROD1PC65 with RULES3
Response
It is important to address the potential
for interference currents as early as
possible. Some pipelines have
experienced significant wall loss in the
first months of operation due to the
effect of interference currents. While it
may be true that all interference
currents cannot be identified before
cathodic protection is in operation,
many can be anticipated and remediated
during construction. These include the
effects of electric transmission lines or
electrified trains sharing or paralleling a
right of way, or other ground beds in
proximity to the pipeline’s route.
Operators need to address, during
construction, interference currents that
can be anticipated. Review of cathodic
protection effectiveness once it is in
operation may identify additional
issues, and operators need to deal
effectively with these. It is not
necessary, however, and potentially
deleterious to pipeline integrity to delay
all actions addressing interference
currents until this time. The provisions
proposed in the NPRM remain
unchanged in the final rule.
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
C.2.4. Eligibility for and Implementing
Alternative MAOP
Section 192.620(a), Calculating an
Alternative MAOP
Most commenters from the pipeline
industry objected that the proposed
requirements for calculating an
alternative MAOP did not recognize that
class locations may change once a
pipeline is in service. They noted that
§ 192.611 recognizes this for
conventional MAOP pipelines, and
allows operation following a class
change at a higher MAOP than would be
required for new pipe in that class
provided that testing was performed at
a sufficiently high pressure. The
commenters sought similar treatment for
alternative MAOPs in this paragraph
and conforming changes to the language
in § 192.611 concerning class location
changes. These commenters also noted
that the proposed rule does not
explicitly address compressor stations,
meter stations, etc.
Two pipeline operators would reduce
the test factor for Class 2 locations from
1.5 to 1.25. They contended that this
would allow testing of Class 1 and 2
pipelines to be done together, thereby
minimizing environmental disruption
that would be associated with separately
testing Class 2 to a higher factor. They
noted that testing of both classes
together would not be possible with a
specified test factor of 1.5 for Class 2,
since this would overstress the Class 1
pipe (i.e., exceed 100 percent SMYS).
One operator suggested allowing a test
factor of 1.25 for existing pipelines and
requiring 1.5 only for lines installed
after the effective date of this rule. They
contended that specifying 1.5 as a
design factor for Class 2 results in the
alternative MAOP for Class 2 pipe
segments being less than currently
allowed for existing pipelines.
Two operators suggested that PHMSA
amend the proposed rule to explicitly
state that the design factors will increase
for facilities (stations, crossings,
fabricated assemblies, etc.) upgraded in
accordance with the rule. One suggested
stating that an increase of approximately
11 percent is allowed. The other
suggested specific design factors of 0.56
for station pipe, 0.67 for fabricated
assemblies and uncased road/railroad
crossings in Class 1 areas, and 0.56 for
such assemblies/crossings in Class 2
locations.
The state pipeline safety regulatory
agency commented that the rule should
contain only one provision regarding
the test pressure used in determining
the MAOP. This commenter noted
proposed § 192.620(a)(2)(ii) limits
MAOP to 1.5 times the test pressure in
PO 00000
Frm 00013
Fmt 4701
Sfmt 4700
62159
Class 2 and 3 locations and that
proposed § 192.620(c)(3) allows 1.25
times test pressure in all classes. The
commenter contends that a reference in
the latter requirement to the former
creates a confusing circularity.
Response
PHMSA agrees that the proposed
regulation could be more restrictive
than existing requirements in § 192.611
in the event of a class change. As noted
in the comments, the existing regulation
allows operation at a higher MAOP
following a class change (i.e., higher
than would be required for a new
pipeline installed in that class location)
provided that testing has been
conducted at a sufficiently high
pressure to demonstrate adequate safety.
PHMSA has revised the final rule to be
more consistent with § 192.611 in
allowing operation at a higher pressure
following a class change.
PHMSA has reduced the required test
pressure for existing pipelines (i.e.,
pipelines installed prior to the effective
date of the rule) in Class 2 locations to
1.25 times MAOP. This is consistent
with § 192.611(a)(1). However, if Class 2
pipeline is tested at 1.25 times MAOP,
then operation at an increased
alternative MAOP following a class
change is not allowed. Such testing does
not provide sufficient assurance of
safety margin for the higher population
Class 3 areas. Operators who desire to
operate at higher pressures following a
change from Class 2 to Class 3 must test
their pipe at 1.5 times alternative
MAOP.
PHMSA has included alternate design
factors for existing facilities and
fabricated assemblies to be operated at
alternative MAOP. PHMSA does not
agree that design factors for facilities
and fabricated assemblies are needed for
new installations (i.e., those constructed
after the effective date of this final rule).
PHMSA expects design factors for new
facilities (stations, crossings, fabricated
assemblies, etc.) to be in accordance
with § 192.111(b), (c), and (d).
Section 192.620(b), When may an
alternative MAOP be used?
Proposed paragraph b(6) limited
eligibility for an alternative MAOP for
pipeline segments that have previously
been operated to those that have not
experienced any failure during normal
operations indicative of a fault in
material. A number of commenters
objected to this limitation, which is
similar to the limitation in proposed
§ 192.328(d) described above. Here,
again, the commenters indicated that
root cause analysis should be allowed
and operation at an alternative MAOP
E:\FR\FM\17OCR3.SGM
17OCR3
62160
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
should be proscribed only if the
evaluation reveals a systemic issue.
GPTC requested that paragraph b(3)
be clarified. That paragraph requires
that segments to be operated at
alternative MAOP must have remote
monitoring and control provided by a
supervisory control and data acquisition
system. GPTC requested that PHMSA
clarify the degree of ‘‘control’’ that is
required and questioned whether
remote control of flow and pressure are
required or if remote control of valves
is all that was intended.
One pipeline operator requested that
either this paragraph or existing
§ 192.611 be revised to clarify the
applicability of the current 72/60/50
percent SMYS limitation on hoop stress.
The operator believes it is unclear when
and if the § 192.611 limitations on hoop
stress apply if an alternative MAOP is
used.
jlentini on PROD1PC65 with RULES3
Response
PHMSA agrees that exclusion from
operation at an alternative MAOP is
appropriate only if a failure during mill
hydrostatic testing, construction
hydrostatic testing, or operation is
indicative of a systematic issue. PHMSA
has revised the final rule here (in this
paragraph and in § 192.328(d) above) to
allow root cause analysis with operators
required to notify PHMSA of the results.
Control requires that operators
monitor pressures and flows as well as
compressor start-up and shut-down.
Valves must also be able to be remotely
closed. The final rule has been modified
to make these requirements clear.
PHMSA has revised § 192.611 to
include hoop stress limits applicable to
pipeline operating at alternative MAOP.
Section 192.620(c), What must an
operator do to use an alternative MAOP?
INGAA and four pipeline operators
suggested that an engineering analysis
should be allowed for existing pipe that
was not tested to 125 percent of the
alternative MAOP. They noted that
some existing pipe may have been
tested to higher pressures but not quite
to 125 percent, and that this pipe should
not be automatically excluded. They
noted that experience shows that the
vast majority of existing pipe is tested
successfully without systemic problems,
and that the allowance for 95 percent vs.
100 percent of girth weld examinations
in proposed § 192.328(b)(2) establishes a
precedent for allowing existing pipe that
can not fully meet new pipe criteria to
operate at an alternative MAOP.
One pipeline operator suggested that
the rule either state that pressure test
must be at 125 percent of alternative
MAOP for Classes 1, 2, and 3 or be
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
revised to refer to the factors in
§ 192.620(a)(2)(ii). They contended the
proposed language was unclear as to
whether 125 percent is sufficient in all
class locations.
A state pipeline safety regulatory
agency again suggested that the rule
should contain only one provision
regarding test pressure (see discussion
under § 192.620(a) above).
Several commenters addressed
training and qualification requirements
in proposed § 192.620(c)(5). The state
agency noted that they duplicated
proposed § 192.328(a)(2)(ii) and
essentially applied operator
qualification (OQ) requirements
(subpart N) to construction personnel.
The state agency suggested it would be
simpler and less confusing if it were
done in subpart N. One pipeline
operator also suggested deleting
paragraph c(5) and referring to subpart
N. This operator noted that the
proposed rule used undefined and
vague language—terms such as QC and
integrity verification (which could be
confused with assessments under
subpart O). The operator further noted
that subpart N requires OQ and that the
meaning of its requirements is well
known.
GPTC requested clarification that the
requirements are only applicable to
segments that operate at an alternative
MAOP and as to the meaning of the
term ‘‘integrity verification method.’’
Response
PHMSA does not agree that an
engineering analysis provides an
adequate basis to justify operation at
alternative MAOP. Operators who desire
to use an alternative MAOP for existing
pipelines that were not tested to
sufficient pressures should re-test their
pipelines.
PHMSA has revised the final rule to
refer to paragraph (a) for test pressures
rather than duplicating them. PHMSA
agrees that this change could help avoid
confusion.
PHMSA agrees that applying the
known requirements of subpart N,
related to the qualification of personnel
performing work on the pipeline, would
likely cause less confusion than
specifying the alternative, but similar,
requirements included in the proposed
rule. Pipeline operators are familiar
with subpart N, and their training
programs under that subpart have been
subjected to audits by PHMSA or states,
as appropriate. By its terms, though,
subpart N does not apply to
construction tasks, since they are not
‘‘an operations or maintenance task’’—
one part of the four-part test in
§ 192.801(b). PHMSA has revised this
PO 00000
Frm 00014
Fmt 4701
Sfmt 4700
final rule to provide that ‘‘construction’’
tasks associated with implementing
alternative MAOP be treated as covered
tasks notwithstanding the definition in
§ 192.801(b). For those tasks, then, the
requirements of subpart N will apply.
This change obviates the concerns
expressed by GPTC and the state
agency. (PHMSA disagrees with the
state comment, however, that the
requirement as proposed duplicated
§ 192.328(a)(2)(ii), as the latter
requirement applied only to girth weld
coating and not to all constructionrelated tasks.)
C.2.5. Operation and Maintenance
Requirements
Section 192.620(d), Additional O & M
Requirements
Two pipeline operators and one state
pipeline regulatory agency suggested
that covered pipelines should be held to
the same requirements as pipelines in
HCA under subpart O. They believe that
this would make most of § 192.620(d)
unnecessary and would increase
flexibility for operators.
The state regulator noted that it would
avoid confusion that might be created
for covered pipelines that would be
subject to both sets of requirements. One
operator commented that no technical
basis is provided for the proposed
requirements, while subpart O is based
on science and research.
Response
PHMSA disagrees with these
comments and has not changed the final
rule because some provisions are more
restrictive than subpart O.
Section 192.620(d)(1), Identifying
Threats
INGAA and three pipeline operators
suggested eliminating the requirement
for a threat matrix and the implied need
for additional preventive and mitigative
measures. They noted that operation at
incrementally higher pressures does not
inherently increase risk or introduce
new threats and that the proposed rule
already includes requirements sufficient
to address the incremental change.
Response
PHMSA does not agree that the rule
necessarily addresses all threats to a
pipeline. The rule addresses many
known threats; however, other threats
may exist or develop that may affect the
pipeline’s integrity. It is up to the
operator to identify and evaluate
possible pipeline threats and therefore
PHMSA retained the requirement to
identify and evaluate threats consistent
with § 192.917. The term ‘‘assess’’ was
changed to ‘‘evaluate’’ to avoid
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
confusion with a similar term used in
integrity management.
Section 192.620(d)(2), Notifying the
Public
INGAA and five pipeline operators
would eliminate the requirements in
this proposed section. They contended
they are unnecessary as they duplicate
requirements in existing § 192.616 for
public education. They further
contended that a dedicated notification,
specific to operation at a higher
pressure, is not needed. One operator
would delete subparagraph (d)(2)(ii) and
replace it with a one-time notification
before operation under an alternative
MAOP begins. This operator believes
that the proposed requirement for a
continuing information program is
excessive, but that a one-time
notification could be appropriate.
jlentini on PROD1PC65 with RULES3
Response
Because of the higher consequences of
operating a pipeline at a higher
alternative MAOP (and thus a greater
impact radius), PHMSA believes that
additional public information is
necessary to inform any stakeholders
living along the right-of-way of this
increase. Where the alternative MAOP
pipeline is in an HCA already identified
per Subpart O, then no additional
notification is necessary beyond what is
already required.
Section 192.620(d)(3), Responding to an
Emergency in High Consequence Areas
Most industry commenters suggested
deleting the requirement that operators
be able to remotely open mainline
valves. They maintained this
requirement is unnecessary as an
emergency response measure and is
contrary to the operating practice of
many gas transmission pipeline
operators. Some also opposed a
requirement for remote pressure
monitoring, indicating that it would be
costly to provide and would add no
value. AGA commented that the
language relating to remote control of
valves was too prescriptive and could
have the unintended consequence of
requiring operators to make their safety
procedures less stringent (presumably
by allowing remote opening of valves).
GPTC and two pipeline operators
questioned the requirement for remote
valve operation if personnel response
time to the valves exceeds one hour.
They argued that the one-hour criterion
is arbitrary and not justified by research.
One operator suggested that it is also
counter to experience. These
commenters also noted that it is unclear
how the response time is to be applied,
from the time of notification of an event,
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
from the time a responder is requested
to go to the valve location, or from some
other triggering event. GPTC suggested
that PHMSA consider a requirement
based on mileage, similar to § 192.179.
One operator indicated that the need for
remote control should be based on risk
analysis rather than an arbitrary
specified response time.
Response
PHMSA agrees that the proposed
requirement that operators be able to
remotely open mainline valves is not
needed for emergency response.
PHMSA agrees that it is more
conservative to require local action to
open valves that may have been closed
in response to an emergency. PHMSA
has modified the final rule to eliminate
the requirement that operators be able to
remotely open valves. PHMSA
considers it important to be able to
monitor pressure in order to know that
valve closure has been effective.
PHMSA has retained this requirement.
PHMSA considers a one-hour
response time appropriate and
reasonable. It provides time to respond
to events while limiting the
consequences of an extended
conflagration. In the final rule, PHMSA
has clarified that the one-hour period
begins from the time an event requiring
valve closure is identified in the control
room and is to be determined using
normal driving conditions and speed
limits.
Section 192.620(d)(4), Protecting the
Right-of-way
All commenters except the state
pipeline safety regulatory agency and
the steel/pipe manufacturers addressed
this section. All contended that the
requirement to patrol the right-of-way
26 times per year was excessive and that
experience indicates that more frequent
patrolling does not prevent pipeline
events. They maintained that the
proposed frequency has no apparent
basis other than that it is the patrolling
frequency required for hazardous liquid
pipelines and that application of a
hazardous liquid pipeline frequency to
gas transmission lines is inappropriate.
One operator noted that its experience
with monthly patrols has demonstrated
that there is very little excavation
activity during winter and the summer
growing season, making patrols then of
little value. The commenters’ proposals
for alternate patrolling intervals varied,
with some suggesting intervals that
would vary based on the class location.
INGAA suggested patrolling every 41⁄2
months and after known events.
INGAA and one pipeline operator
suggested deleting the requirement for a
PO 00000
Frm 00015
Fmt 4701
Sfmt 4700
62161
soil monitoring plan, because it would
be costly and only duplicates other
existing requirements.
INGAA and six pipeline operators
suggested deleting the requirement to
maintain depth of cover. In its place,
they would require restoring depth of
cover or providing appropriate
preventive and mitigation measures
only where damage may occur due to
loss of cover. They noted that
maintaining the original depth of cover
is impractical and unnecessary. Normal
erosion and other events can reduce
depth of cover, but that reduction does
not necessarily lead to an increased risk
of damage. Action may be needed in
limited circumstances and providing
other protection in those circumstances
may be more effective and less costly
than restoring the original depth of
cover. One operator suggested that a
monitoring/maintaining depth of cover
requirement should be driven by events
or risk analysis and that discussion in
the preamble of the NPRM implied such
an approach. This operator suggested
allowing engineered solutions in
addition to restoring depth of cover.
INGAA and four pipeline operators
would delete or relax the requirement
for line-of-sight pipeline markers.
INGAA noted that discussion at the
March 2007 public meeting indicated
that such markers add no value. One
operator suggested that it would be
more effective to emphasize one-call
damage prevention in the preamble of
the final rule. Another operator noted
that installation of such markers is
‘‘non-trivial,’’ and that there is no data
or analysis supporting the need for
them. Yet another operator commented
that the intent of the requirement is
unclear and suggested that
circumstances other than agricultural
areas and large bodies of water
(exclusions included in the proposed
rule) would also make it difficult to
install line-of-sight markers (e.g., steep
terrain, swamps).
INGAA and five pipeline operators
objected to what they characterized as
an ‘‘open ended’’ requirement to
implement national consensus
standards for damage prevention. These
commenters suggested that the
requirements focus on the damage
prevention best practices identified by
the Common Ground Alliance (CGA)
and require that operators implement
the CGA best practices that apply to
their situation. One operator suggested
that operators be allowed to evaluate
and choose among CGA practices.
Another operator also supported a right
to choose, indicating that the CGA guide
includes no expectation that operators
will adopt all best practices.
E:\FR\FM\17OCR3.SGM
17OCR3
62162
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
jlentini on PROD1PC65 with RULES3
INGAA and five pipeline operators
objected to the proposed requirement
for a right-of-way management plan,
because it duplicates existing
requirements for damage prevention.
Response
PHMSA has revised the required
patrol frequency to once per month, at
intervals not to exceed 45 days. The
decision to reduce the patrolling
frequency from 26 patrols per year was
based on further analysis of the value
added by the cost of additional
patrolling, PHMSA’s greater experience
with administering special permits, and
comments from industry and public
advocates supporting risk-based
requirements rather than a one-size-fitsall approach. PHMSA believes that the
right of way management plan required
by § 192.620(d)(4)(vi), coupled with the
patrolling requirement, will provide
appropriate safety coverage through
requiring an operator to develop and
implement an array of actions based on
the risk of third-party damage to the
pipeline. These preventative actions
may well include additional patrolling
above what is required by this rule in
areas that are more heavily-populated or
that possess greater chances for thirdparty activities in the vicinity of a
pipeline.
PHMSA has retained the requirement
for a soil monitoring program. Gas
transmission pipelines are often located
in areas that can exhibit unstable soils,
such as clay, hills, and mountainous
areas. It is important to assure that
stresses caused by soil movement do not
damage pipelines in these areas with
reduced design safety factors. PHMSA
recognizes that operators may already
address these issues in their damage
prevention plans or other operating and
maintenance procedures. If so, an
additional plan is not required.
Operators must be able to demonstrate,
during regulatory audits, that soil
monitoring is addressed within their
procedures.
PHMSA has retained the requirement
for line-of-sight pipeline markers.
Outside damage is the most significant
threat to gas transmission pipelines,
resulting in the greatest number of
accidents. These accidents occur despite
current requirements for pipeline
markers. Those requirements in
§ 192.707 already require that markers
be maintained ‘‘as close as practical’’ in
the areas required to be covered.
PHMSA continues to believe that it is
important to provide line-of-sight
markers for pipelines operating at
alternative MAOP in order to reduce the
frequency of outside damage. PHMSA
supports one-call programs, and
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
regularly takes actions to encourage and
foster their use. Still, damage incidents
occur. It is important to reinforce the
need for using a one-call program by
providing visual evidence that a
pipeline is located in an area subject to
potential excavation.
At the same time, PHMSA recognizes
that installation of line-of-sight markers
is not feasible in all locations. The rule
does not require installation of line-ofsight markings in agricultural areas or
large water crossings such as lakes and
swamps where line-of-sight markers are
not practicable. The marking of
pipelines is also subject to FERC orders
or environmental permits and local
laws/regulations. The rule does not
require installation where these other
authorities prohibit markers.
PHMSA also retained the requirement
for a right-of-way management plan
since PHMSA data indicates recurring
similarities in pipeline accidents on
construction sites where better
management of the right-of-way could
have prevented the accidents. This
provision is not redundant with existing
damage prevention program
requirements, but requires operators to
take further steps to integrate activities
under those programs to provide for
better protection of the right-of-way.
Section 192.620(d)(5), Controlling
Internal Corrosion
INGAA, GPTC, four pipeline
operators and the state pipeline safety
regulatory agency would require a
program to monitor gas quality and to
remediate internal corrosion as needed
but would delete all the specific
requirements in this section. One
operator suggested that a program
complying with Subpart I is all that is
needed. The state regulatory agency
noted that the NPRM provided no
rationale for more stringent or
prescriptive requirements than those
recently published as § 192.476.
Two pipeline operators objected to
the requirement for filter separators,
contending that these devices are not
effective for dealing with upsets
involving free water and can provide a
false sense of security. One suggested
that other actions could be required to
assure gas quality. Two other operators
suggested that properly designed gas
separators would be as effective as filter
separators.
One operator objected to requirements
for cleaning pigs, inhibitors, and
sampling of accumulated liquids.
Another opposed the requirement for
inhibitors. These operators noted that
these actions are not needed if gas
monitoring confirms no deleterious
constituents. They maintained that the
PO 00000
Frm 00016
Fmt 4701
Sfmt 4700
requirements are unnecessary and can
potentially result in unintended
consequences and risks.
AGA contended that operators should
be allowed to determine appropriate
methods for monitoring gas quality and
that these methods need not always
require testing by individual operators.
AGA believes this is especially true if
tariffs and operating experience
demonstrate the absence of
contaminants. One pipeline operator
asked that PHMSA clarify that the
required chromatographs are for
analysis of corrosive constituents and
need not provide complete analysis for
heating value or other purposes.
Two pipeline operators suggested that
PHMSA define deleterious gas stream
constituents of concern. Two pipeline
operators suggested that the limits on
gas constituents should be deleted or
revised based on research and testing.
They believe that the proposed limits
are not technically justified. One further
noted that deleterious effects may result
from contaminants acting ‘‘in concert.’’
One pipeline operator would revise
the requirement for review of an
operator’s internal corrosion monitoring
and mitigation program to annual
review because there is no technical
justification for quarterly reviews.
Another operator suggested that the gas
quality requirements be deleted, as they
may conflict with tariffs and result in
duplicate enforcement. This operator
also suggested that sampling intervals
be established by reference to section
§ 192.477 and agreed that a requirement
for quarterly review of internal
corrosion monitoring programs is
excessive.
Response
PHMSA concludes that the proposed
requirements do not duplicate or
conflict with those in the recently
published § 192.476. The latter
requirements deal principally with
design considerations related to internal
corrosion, while those included here
address monitoring to determine
whether conditions conducive to such
corrosion occur. Similarly, § 192.477
only requires monitoring if corrosive gas
is present. The requirements included
here specify contaminants to be
monitored and limits to be achieved.
Since § § 192.476 and 192.477 represent
the requirements in subpart I related to
internal corrosion, PHMSA does not
agree that a program complying with
subpart I alone is sufficient.
PHMSA has revised the requirement
for use of cleaning pigs, inhibitors, and
collection of accumulated liquids to
apply only in those situations in which
corrosive gas is determined to be
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
present. For the particular case of
hydrogen sulfide, PHMSA has specified
a limit (0.5 grain per hundred cubic feet,
8 parts per million (ppm)) above which
this requirement applies.
PHMSA has retained the requirements
for gas monitoring. It is important to
monitor the gas stream to assure that
internal corrosion will not occur or will
be identified if corrosion does occur.
Continuous monitoring is the most
effective way of doing this. PHMSA
agrees that monitoring equipment
required by this rule is for the purpose
of analyzing corrosive gas constituents
and need not provide estimates of
heating value or other characteristics.
Operators can rely on others (e.g., those
supplying gas to them) to perform
monitoring, but they must assure that
such monitoring covers all gas streams
and meets the requirements of this rule,
including the need for continuous
monitoring. PHMSA has also retained
the requirement to review the internal
corrosion monitoring program quarterly.
Such reviews are needed to help assure
that upset conditions that could
potentially cause internal corrosion are
identified and addressed promptly.
Annual reviews are insufficient to do
this.
PHMSA has revised the limit for
hydrogen sulfide to 1.0 grain per
hundred cubic feet, or 16 ppm. (PHMSA
has also presented this limit in both
forms of measurement, as suggested by
one commenter). This limit is more
consistent with typical tariff limits. At
the same time, the final rule requires
that additional mitigative actions,
including use of cleaning pigs and
inhibitors be required when the
hydrogen sulfide content exceeds 0.5
grain per hundred cubic feet, as this
concentration increases the likelihood
of internal corrosion.
The final rule clarifies that deleterious
gas stream constituents also include
entrained or suspended solids
(regardless of size) that are detrimental
to the pipeline or pipeline facilities.
jlentini on PROD1PC65 with RULES3
Section 192.620(d)(6), Controlling
Interferences That Can Impact External
Corrosion
Two pipeline operators requested that
we clarify that interference surveys are
only required where interference is
likely, are to be developed using
operator judgment, and can be
performed using voltage measurements
versus ‘‘current.’’
Response
PHMSA has clarified the final rule to
require that surveys be performed in
areas where interference is suspected.
Operators should consider the
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
proximity of potential sources of
interference, including electrical
transmission lines, other cathodic
protection systems, foreign pipelines,
and electrified railways in deciding
where surveys are needed. Operators
must conduct surveys capable of
detecting the effect of interfering
currents, but these surveys need not
measure ‘‘current’’ directly.
Section 192.620(d)(7), Confirming
External Corrosion Control Through
Indirect Assessment
INGAA and four pipeline operators
requested that this section be revised to
require close interval survey (CIS) alone
versus one of CIS, direct current voltage
gradient (DCVG), or alternating current
voltage gradient (ACVG). One of these
operators requested clarification that
indirect examination is not necessary if
additional measures are taken to assure
the integrity of the pipeline. Yet another
operator suggested that this section be
revised to allow other methods of
indirect assessment, noting that C–
SCAN (which is a current measurement
technique) is one possibility that
appears to be precluded by the proposed
language. All of these commenters plus
three additional pipeline operators
requested that the timeframe for
conducting these examinations be
relaxed from six months to one year.
They noted that six months may often
be impractical because of limitations
associated with seasonal weather.
One pipeline operator would delete
the proposed requirement for a coating
survey of existing pipelines,
maintaining that this examination is not
needed, since the results of ILI and CIS
show that the combination of coating
and cathodic protection is working to
protect against corrosion. This operator
would move the requirement for
indirect survey and coating damage
remediation to § 192.328 to make it clear
that this is a construction requirement
applicable to new pipelines only.
Another operator also commented that
requirements to remediate construction
damaged coating should be limited to
new pipe only. This operator further
requested deleting the proposed
requirement to repair all voltage drops
classified as moderate or severe by
National Association of Corrosion
Engineers (NACE), since it is
unnecessary and impractical to repair
every voltage drop. Another operator
commented that operators should be
allowed to develop specific repair
criteria based on their experience.
INGAA and four pipeline operators
would relax the proposed requirement
to remediate construction coating
damage to require either remediation or
PO 00000
Frm 00017
Fmt 4701
Sfmt 4700
62163
appropriate cathodic protection. They
suggested that the proposed requirement
conflicts with the NACE standard
referenced in this section (NACE RP–
0502–2002) and that coating
remediation is not needed as cathodic
protection provides adequate protection
for areas affected by coating holidays.
Another operator noted that the NACE
defect classification guidelines are
qualitative and that interpretation
differences could result in differing
repair expectations.
INGAA and two pipeline operators
recommended relaxing the requirement
to integrate indirect assessment results
with ILI from six months to one year.
They believe that more rapid integration
is not needed and that the value of
quicker integration is not explained in
the NPRM. Another operator suggested
there is an inconsistency in that
paragraph (ii) requires action based on
the results of one assessment while
paragraph (iii) requires that the results
of two assessments be integrated.
INGAA and three pipeline operators
would delete the periodic assessment
requirements of proposed paragraph
(iv). They would move the requirements
for location of CIS test points in
proposed subparagraph (B) to § 192.328,
as they contended these are more
appropriate as construction
requirements. These commenters would
further revise the CIS location
requirements to state that a CIS test
station must be within one mile of each
HCA, versus within each HCA. They
contended that it is not practical to
require a test station within each HCA,
noting that the length of the pipeline in
some HCAs may be very short. Another
operator would combine subparagraphs
(A) and (B).
Response
CIS is a technique to locate areas of
poor cathodic protection and is
considered a macro tool. Micro tools,
such as DCVG or ACVG, must be used
to locate small but critical coating
holidays. C–SCAN, which is a current
measurement technique, is considered a
macro tool and will only find large
coating holidays. Small coating holidays
can be just as critical as large ones,
especially in areas where cathodic
protection potentials can be depressed.
PHMSA considers it important to
monitor coating condition. The
comments suggesting that macro tools
be allowed appear to be based on the
premise that small coating holidays are
not important as long as cathodic
protection continues to protect the
pipeline. As discussed above, PHMSA
does not agree with this presumption,
and here, again, does not agree that
E:\FR\FM\17OCR3.SGM
17OCR3
jlentini on PROD1PC65 with RULES3
62164
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
either coating or cathodic protection is
required; both are needed. PHMSA
recognizes that if one accepts the
presumption that assuring coating
integrity is not important on pipelines
subject to cathodic protection, then
prompt resolution of coating issues is
not important either. Since PHMSA
does not accept the premise, PHMSA
has not relaxed the proposed timeframes
for conducting surveys or integrating
results.
In particular, PHMSA does not agree
that a one year interval should be
allowed to assess coating adequacy.
Experience has demonstrated that
significant corrosion can occur during
very short intervals. PHMSA notes that
the proposed requirement potentially
extends the period between the
beginning of pipeline operation and
coating assessment to 18 months—12
months after operation in which
cathodic protection must be made
operational (§ 192.455(a)(2)) plus the six
months allowed here. PHMSA considers
this to be the maximum period that
should be allowed before determining
coating adequacy. Proper planning and
scheduling should allow operators to
accommodate weather and other
scheduling concerns. Operators can
delay the start of operation at an
alternative MAOP if they cannot
schedule coating surveys within six
months.
PHMSA’s conclusion that coating
integrity is important, regardless of the
presence of cathodic protection, means
that determining coating adequacy is
important for existing pipelines as well
as new construction. As such, it is not
appropriate to move this requirement to
a section applicable to new construction
only. Further, it is not acceptable to rely
on ILI or other assessment methods to
identify corrosion after it has occurred.
The purpose here is to prevent
corrosion. ILI or other assessments are a
second level of defense, detecting
corrosion after it occurs, but PHMSA
does not consider them to obviate the
need for actions to prevent the problem
from occurring in the first place. CIS is
a verified method of determining if all
of a segment is protected by appropriate
cathodic protection potentials. The use
of CIS will allow an operator to find any
‘‘hot spots’’ along the pipeline that
could cause active corrosion. The CIS
will find any depressed locations
whereas a test station survey may miss
such locations unless they are in close
proximity to the test station.
With respect to proximity to a test
station, PHMSA agrees that there could
be situations in which it may not be
practical to locate a test station within
an HCA. This could occur, for example,
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
when the HCA is determined by an
identified site near the outer radius of
the potential impact circle, in which
case the length of pipeline in the HCA
could be very short (on the order of
several feet). Still, PHMSA does not
agree that this limitation should be
addressed by requiring that a test station
be within one mile of an HCA. PHMSA
has revised the final rule to require that
a test station be located within an HCA
if practicable and has retained the
proposed requirement that test stations
be located at half-mile intervals on
pipelines to be operated at alternative
MAOP.
Section 192.620(d)(8), Controlling
External Corrosion Through Cathodic
Protection
INGAA, GPTC and eight pipeline
operators considered the requirement to
address inadequate cathodic protection
readings in six months to be excessive.
They also noted that seasonal and land
use issues make responding within one
year much more reasonable, and
suggested the proposed rule be changed
accordingly. GPTC and one operator
noted that the proposed change is
inconsistent with an existing PHMSA
interpretation, which states that
remediation of inadequate cathodic
protection readings is required before
the next scheduled monitoring. The
operator noted that this is typically one
year (not to exceed 15 months),
supporting the proposed change to a
one-year response in this rule.
INGAA and three pipeline operators
objected to the proposed requirement to
conduct CISs after remediating cathodic
protection problems to evaluate
effectiveness. They noted that a CIS is
not needed to confirm resolution of
many problems (e.g., loss of power, cut
cable, short). They agreed that operators
should confirm that remedial action was
appropriate and effective, but contended
that a requirement to perform a CIS after
any remedial action is unjustified and
excessive.
Response
As discussed above, experience has
shown that significant corrosion damage
can occur over brief periods. Pipelines
operating at an alternative MAOP have
less margin for corrosion than do
pipelines operating at MAOP
determined in accordance with
§ 192.111. Cathodic protection is an
important protection against corrosion
damage, as recognized by those
commenting on this rule. PHMSA does
not agree that it is acceptable to wait
one year to resolve known cathodic
protection problems. At the same time,
PHMSA recognizes that there may be
PO 00000
Frm 00018
Fmt 4701
Sfmt 4700
situations in which remediation in six
months is not practical. PHMSA has
revised the final rule to require
operators to notify the PHMSA Regional
Office where a pipeline is located (and
states where appropriate) if inadequate
cathodic protection readings are not
addressed within six months, providing
the reason for the delay and a
justification that the delay is not
detrimental to pipeline safety. This will
allow regulators to review the
circumstances of each situation in
which resolution takes longer than six
months and to make a judgment of
adequacy based on the particular
circumstances.
PHMSA agrees that it is not necessary
to perform a complete CIS again to
verify that any remedial action has
addressed an identified problem.
Commenters are correct in noting that
problems such as a cut cable or short
can result in inadequate cathodic
protection readings and that correction
of these problems can be verified
without a new CIS. PHMSA has revised
the final rule to require that operators
verify that corrective action is adequate,
leaving the means to do so up to the
operator’s discretion and judgment.
Section 192.620(d)(9), Conducting a
Baseline Assessment of Integrity
Proposed § 192.620(d)(9)(iii) would
require that headers, mainline valve bypasses, compressor station piping, meter
station piping, or other short portions
that cannot accommodate ILI tools be
assessed using DA. INGAA and four
pipeline operators objected to this
requirement as unjustified and
inconsistent with previous special
permits. They suggested a change that
would also allow pressure testing or
development and implementation of a
corrosion control plan. They further
noted that these segments may be
designed to § 192.111, may not operate
at an alternative MAOP, and thus may
not be subject to this section.
One operator also noted that there
may be portions of a pipeline facility
that will not be operated at an
alternative MAOP. The operator
requested clarification that the proposed
requirements apply only to segments
that are intended to operate at an
alternative MAOP. This commenter also
suggested an exclusion for small pipe
and equipment to be consistent with a
frequently asked question (FAQ) #84 on
the gas transmission integrity
management Web site (https://
primis.phmsa.dot.gov/gasimp/). (The
FAQ addresses whether small-diameter
piping, e.g., within a compressor
station, must be considered to be part of
an HCA. It states that potential impact
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
jlentini on PROD1PC65 with RULES3
radii should be calculated, and a
determination made as to whether an
HCA exists, based on the diameter of
individual pipeline segments.)
The same operator would also allow
the baseline assessment for an existing
pipeline segment to be conducted before
operation at an alternative MAOP begins
but within the assessment interval
specified in subpart O rather than the
proposed two years. The operator
contended that there is no scientific
basis to require assessments every two
years, particularly if a pipeline segment
is being managed under subpart O.
Response
PHMSA agrees that assessment of
small-diameter station piping can be
performed using pressure testing and
has revised the final rule accordingly.
PHMSA does not agree that it is
acceptable for such a non-piggable
pipeline to be under an unspecified
corrosion control plan rather than to be
subject to assessment.
PHMSA agrees that FAQ #84
addresses the same pipe, but does not
agree that it is a precedent for
determining whether a small-diameter
pipeline requires assessment. An FAQ is
advisory in nature and this FAQ
provides guidance in the context of
integrity management, on whether this
pipeline should itself be determined to
be an HCA. For this rule, additional
assessment requirements are being
applied to a pipeline operating at an
alternative MAOP, regardless of whether
it is in an HCA. PHMSA has revised this
paragraph to clarify that it applies only
to a pipeline operating at an alternative
MAOP. Small-diameter pipe within a
station that does not operate at
alternative MAOP would not be affected
by these requirements. PHMSA agrees
that small-diameter pipe, headers, meter
stations, compressor stations, river
crossings, road crossings and any other
pipeline facility can be designed and
constructed in accordance with
§ 192.111 criteria and then would not be
subject to alternative MAOP integrity
assessment criteria such as ILI and DA.
PHMSA does not agree that it is
acceptable to rely on assessments that
may have been performed within the
time intervals allowed by subpart O.
Under subpart O, it may have been
nearly ten years (in some limited cases
15 years) since a complete assessment
was performed. PHMSA considers that
more current information is needed
before deciding that it is acceptable to
operate a pipeline at an alternative
MAOP. PHMSA considers the two-year
period reasonable for operators to
schedule and perform assessments that
will result in more current information
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
when the operating stresses on the
pipeline are increased.
Section 192.620(d)(11), Making Repairs
INGAA and three pipeline operators
noted that the repair requirements in the
proposed rule are inconsistent with
subpart O and, they believe, overly
conservative and burdensome. INGAA
contended that the proposed
requirements will be unachievable in
many cases. Another operator
commented that the repair criteria
proposed for Class 2 and 3 areas are
extremely conservative and
unnecessary.
Two pipeline operators suggested that
this section be replaced with a reference
to subpart O, since they believe the
repair requirements of that subpart and
ASME/ANSI B31.8S (referenced in
subpart O) are appropriate for pipelines
operating at 80 percent SMYS.
Two pipeline operators noted that the
dent repair criteria in subparagraph
(i)(A) are those for new pipelines
following construction and before
commissioning and suggested that these
are inappropriate for existing pipelines.
One of these operators contended that
the repair criteria for existing pipelines
should be as in subpart O, § 192.933(d).
The other noted that there is experience
demonstrating that plain dents of much
greater than two percent of pipe
diameter in depth are not a threat to
pipeline integrity.
Three pipeline operators proposed
alternative repair criteria. They would
require immediate repair of defects for
which the failure pressure is 1.1 times
the revised alternative MAOP. They
would require repairs within one year
for defects for which the failure pressure
is 1.25 times the MAOP. They
contended that these criteria are
consistent with those in subpart O and
ASME/ANSI B31.8S and are
appropriate. They believe that the
criteria in the proposed rule represent
an inappropriate shortening of the time
allowed to address identified defects.
Proposed subparagraph (i)(A) would
require that an operator ‘‘use the most
conservative calculation for determining
remaining strength’’ of a pipeline
segment containing an identified
anomaly. INGAA and four pipeline
operators contended that this
requirement could be interpreted to
require that multiple calculations be
performed, using all available tools/
models, to determine which is most
conservative. They believe this is
inappropriate and that operators should
use the most appropriate calculational
tool.
PO 00000
Frm 00019
Fmt 4701
Sfmt 4700
62165
Response
PHMSA recognizes that the repair
criteria in this rule are more stringent
than those in subpart O. PHMSA
considers this appropriate. A pipeline
that will operate under alternative
MAOP is subject to more stress and has
less wall thickness margin to failure
than most pipelines operating under
subpart O (with the exception of some
grandfathered lines). Most pipelines that
will be subject to this rule will be new
pipelines. PHMSA’s repair criteria use
safety factors similar to those for the
design of a new pipeline based upon
class location design factors, and are
intended to maintain overall safety
margins at corrosion anomalies based
upon all operating and environmental
factors. The net effect of the QA and
O&M requirements in this rule for
construction and operation of those
pipelines covered by the rule will likely
result in the need for few repairs, even
with these stricter criteria. PHMSA
considers these factors of safety a key
element in assuring public safety on
higher MAOP pipelines.
Similarly, PHMSA disagrees that
failure pressures of 1.1 and 1.25 times
MAOP are appropriate for immediate
and one-year (respectively) repairs for
all class locations. Class 2 and Class 3
locations require more stringent safety
factors for anomaly evaluation and
remediation due to the higher
consequences to public safety that may
be caused by a leak or rupture of the
pipeline. As discussed extensively
throughout this response to comments,
pipelines to be operated at alternative
MAOP will operate at higher pressures
with less margin to failure than most
pipelines. Use of repair criteria different
from and requiring repairs quicker than
in subpart O is appropriate.
With respect to dents, the repair
criteria of § 192.309(b) apply only for
dents found during construction
baseline assessments (i.e., for new
pipelines). PHMSA notes that this
section already requires repair of two
percent dents for pipelines over 123⁄4
inches in diameter. The criteria for
repairing dents on existing pipelines
and subsequent assessments on new
pipelines and existing pipelines are in
§ 192.933(d).
PHMSA acknowledges that an
operator cannot know which method for
calculating remaining strength is most
conservative without applying each
method. Questions have been raised
concerning the applicability of some
current methods for calculating the
remaining strength of high-strength
pipelines and greater depth corrosion
anomalies in all field operating
E:\FR\FM\17OCR3.SGM
17OCR3
62166
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
conditions. PHMSA is planning to
sponsor a public meeting to review
these questions and help determine the
adequacy of existing calculational
methods for the kind of high-strength
pipe that will operate at alternative
MAOP. PHMSA will propose changes to
this rule at a later date, if appropriate.
jlentini on PROD1PC65 with RULES3
C.3. Comments on Regulatory Analysis
One pipeline operator submitted two
comments relating directly to the
regulatory analysis supporting the
proposed rule.
First, the operator contends that the
expected reduction in expenditure for
compressors for new pipelines should
not be claimed as a benefit. The operator
contended that reductions may be
realized for existing pipelines that
operate at an alternative MAOP but not
for new pipelines.
Second, the operator contended that
PHMSA should not state that new
design factors will result in increased
capacity for new pipelines and noted
that new pipelines will be designed for
the required capacity. The effect of the
proposed rule will be to reduce costs by
allowing the use of thinner-walled pipe.
Response
PHMSA understands that the
operator’s statement that new pipelines
will be designed for the required
capacity is at the heart of both of these
comments. The operator essentially
contended that new pipelines that will
be so designed will see no increased
capacity or change in costs as a result
of this rule. PHMSA does not agree.
New pipelines designed with alternative
MAOPs should mean less cost to the
customer/public, and thus a benefit to
society, due to less capital costs for the
same natural gas through-put/flow
volumes. Existing pipelines will be able
to carry up to an additional 11 percent
natural gas flow volumes based upon
the overall design of the pipeline and
compressor stations with this alternative
MAOP.
In the absence of this rule (or of
obtaining a special permit to operate at
alternative MAOP) new pipelines would
need to be designed for less capacity or
at increased cost (due to the need to use
thicker-walled pipe). Thus, there is a
societal benefit to this rule in that it will
allow more gas to be transported at a
higher standard of safety for a given
dollar investment. The companies
designing and constructing new
pipelines under this rule will also
realize a benefit, since in the absence of
this rule (or a special permit addressing
the same issues) they would either have
to carry less gas or incur additional
costs. PHMSA has revised the
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
discussion in the regulatory analysis to
help make this point more clearly.
D. Consideration by the Technical
Pipeline Safety Standards Committee
(TPSSC)
The TPSSC met on June 10, 2008, and
considered the proposed rule. During
this discussion, PHMSA provided its
preliminary views of changes that might
be made in response to comments
submitted in response to the proposed
rule.
PHMSA informed the TPSSC that
some changes would be made in rule
structure, moving some requirements to
other sections for better applicability
(e.g., requirements applicable to existing
pipelines would be moved from the
section of the rule in which
construction requirements are located).
PHMSA informed the TPSSC it has
not adopted the suggestion by the state
pipeline safety regulatory agency that
submitted comments supported by its
director (a member of the committee) to
place the rule in a separate subpart, as
that is counter to the general structure
of part 192.
TPSSC members expressed concern,
as did many commenters, about reliance
on individual standards or tests. In the
final rule, PHMSA has allowed use of
equivalent methods (e.g., for the macro
etch test, hardness limits, type of crack
arrestors).
PHMSA informed the TPSSC that the
vast majority of commenters objected to
the proposed requirement for mill
hydrostatic inspection tests of longer
duration and that, as a result, that
change would not be included in the
final rule. PHMSA also noted that most
industry commenters noted that the
proposed rule did not make allowances
for changes in class location after a
pipeline is in service, as do the existing
regulations.
The anomaly repair requirements
were of concern to industry, who
asserted the requirements were overly
conservative. PHMSA informed the
TPSSC that this issue is complicated by
questions recently raised concerning the
applicability of remaining strength
calculational methods to high-stress
pipelines and that resolving those
questions before completing this rule
would delay issuance of the rule.
PHMSA stated that it would conduct a
public meeting later this year to address
the global issue of appropriate
calculational methods and repair
criteria. Changes to this or other
regulations requiring pipeline repair
may be appropriate following that
workshop.
Treatment of existing and pending
applications for special permits was a
PO 00000
Frm 00020
Fmt 4701
Sfmt 4700
significant concern for several members
of the TPSSC. PHMSA noted that the
standards in the final rule are very
similar to those applied in recent
special permits. PHMSA reported its
intention to continue to review pending
special permit applications while this
rulemaking proceeded. Upon issuance
of the final rule, PHMSA expects
operators desiring to use alternative
MAOP to comply with the rule. PHMSA
will examine special permits that have
already been granted, as appropriate, to
determine if any modifications are
needed in light of the outcome of this
rulemaking.
Subsequent to discussion, the TPSSC
voted unanimously to find the proposed
rule and supporting regulatory
evaluations technically feasible,
reasonable, practicable, and cost
effective, subject to incorporation of the
changes discussed by PHMSA during
this meeting. A transcript of the meeting
is available in the docket.
E. The Final Rule
Revisions described in this section are
changes to the corresponding section in
the proposed rule.
E.1. In General
The rule adds a new section
(§ 192.620) to Subpart L—Operations.
This new section explains what an
operator would have to do to operate at
a higher MAOP than currently allowed
by the design requirements. Among the
conditions set forth in new § 192.620 is
the requirement that the pipeline be
designed and constructed to more
rigorous standards. These additional
design and construction standards are
set forth in two additional new sections
(§§ 192.112 and 192.328) located in
Subpart C—Pipe Design and Subpart
G—General Construction Requirements
for Transmission Lines and Mains,
respectively. In addition, the rule makes
necessary conforming changes to
existing sections on incorporation by
reference (§ 192.7), change in class
location (§ 192.611), and maximum
allowable operating pressure
(§ 192.619).
E.2. Amendment to § 192.7—
Incorporation by Reference
The rule adds ASTM Designation: A
578/A578M—96 (Re-approved 2001)
‘‘Standard Specification for StraightBeam Ultrasonic Examination of Plain
and Clad Steel Plates for Special
Applications’’ to the documents
incorporated by reference under § 192.7.
This specification prescribes standards
for ultrasonic testing of steel plates. It is
referenced in new § 192.112.
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
The rule also revises the description
of item (B)(1) in the table of
§ 192.7(c)(2), API 5L ‘‘Specification for
Line Pipe,’’ (43rd edition and errata),
2004, to indicate that it is referenced in
new § 192.112 in addition to the
locations at which it was referenced
previously.
jlentini on PROD1PC65 with RULES3
E.3. New § 192.112—Additional Design
Requirements
The rule adds a new section to
Subpart C—Pipe Design in 49 CFR Part
192. The new section, § 192.112,
prescribes additional design standards
required for the steel pipeline to be
qualified for operation at an alternative
MAOP based on higher stress levels.
These include requirements for rigorous
steel chemistry and manufacturing
practices and standards. Pipelines
designed under these standards contain
pipe with toughness properties to resist
damage from outside forces and to
control fracture initiation and growth.
The considerable attention paid to the
quality of seams, coatings, and fittings
will prevent flaws leading to pipeline
failure. Unlike other design standards,
§ 192.112 applies to a new or existing
pipeline only to the extent that an
operator elects to operate at a higher
alternative MAOP than allowed in
current regulations.
Paragraph (a) sets high manufacturing
standards for the steel plate or coil used
for the pipe. The pipe would be
manufactured in accordance with Level
2 of API 5L, with the ratio between
diameter and wall thickness limited to
prevent the occurrence of denting and
ovality during construction or
operation. Improved construction and
inspection practices addressed
elsewhere in this rule also help prevent
denting and ovality.
Paragraph (a) has been revised in
response to comments to add an
alternative method (and applicable
limit) for determining equivalent carbon
content. In addition, the proposed limit
on equivalent carbon content of 0.23
(Pcm formula) has been raised to 0.25.
Several comments suggested deleting
the limit on the ratio of pipe D/t, but
this limit has been retained, as
discussed above.
Paragraph (b) addresses fracture
control of the metal. First PHMSA
expects the metal would be tough; that
is, deform plastically before fracturing.
Second, the pipe would have to pass
several tests designed to reduce the risk
that fractures would initiate. Third, to
the extent it would be physically
impossible for particular pipe to meet
toughness standards under certain
conditions, crack arrestors would have
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
to be added to stop a fracture within a
specified length.
Paragraph (b) has been revised to
allow alternate means of crack arrest.
This can include the ‘‘mechanical’’
means included in the proposed rule
but can also include other design
features such as use of composite
sleeves, spacing, increases in wall
thickness at appropriate distances, etc.
This paragraph has also been revised to
clarify the factors that must be
considered by an operator in evaluating
resistance to fracture initiation and to
make clear that this evaluation is
intended to address the full range of
relevant parameters to which the pipe
will be exposed over its operating
lifetime. If unexpected situations or a
change in operating conditions result in
a change in these parameters during
operation, such that they are outside the
bounds of those analyzed, operators will
be required to review and update their
evaluation and implement remedial
measures to assure continued resistance
to fracture initiation.
Paragraph (c) provides tests to verify
that there are no deleterious
imperfections in the plate or coil. The
macro etch test will identify flaws such
as segregation that impact the plate or
coil quality. Surface and interior flaws
such as laminations and cracking will
show up in UT testing.
This paragraph has been revised, in
response to comments, to change ‘‘mill
inspection program’’ to an internal
quality management program designed
to eliminate or detect defects or
inclusions that can affect pipe quality
and to require that such a program be
implemented at all mills involved in the
process of casting the steel, rolling it
into plate, coil or skelp, and the process
of manufacturing the steel into line
pipe. The revised paragraph also
includes an alternative to the macro
etch test and reference to an additional
standard for UT testing the plate, coil,
skelp or manufactured line pipe.
(Equivalent standards are also still
allowed.)
In addition to the quality of the steel,
the integrity of a pipe depends on the
integrity of the seams. Paragraph (d)
provides for a QA program to assure
tensile strength and toughness of the
seams so that they resist breaking under
regular operations. Hardness and UT
tests after mill hydrostatic tests would
ensure that the seams did not have
defects or imperfections that were
exposed by the stresses of the
hydrostatic test pressure.
Paragraph (e) requires a mill pressure
test for new pipe at a higher hoop stress
than required by current regulations.
The mill test is used to discover flaws
PO 00000
Frm 00021
Fmt 4701
Sfmt 4700
62167
introduced in manufacturing. Because
the pipeline will be operated at a higher
stress level, the more rigorous mill test
is needed to match (or exceed) the level
of safety provided for pipelines operated
at less than 72 percent of SMYS.
Paragraph (e) has been revised to
eliminate the proposed extension of the
duration of mill pressure tests.
Paragraph (f) sets rigorous standards
for factory coating designed to protect
the pipeline from external corrosion. A
QA program must address all aspects of
the application of coating that will
protect the pipeline. This would include
applying a coating resistant to damage
during transportation and installation of
the pipe and examining the coated
pipeline to determine whether the
applied coating is uniform and without
defects. Thin spots or voids/holidays in
the coating make it more likely for
corrosion to occur and more difficult to
protect the pipeline cathodically.
Paragraph (g) requires that factorymade fittings, induction bends, and
flanges be certified as to their
serviceability and quality. In addition
the CE of these fittings and flanges
would need to be documented, so that
welding procedures could require preheat temperature to eliminate welding
defects.
Paragraph (g) has been revised to
clarify that the serviceability
certification must address properties
such as chemistry, minimum yield
strength, and minimum wall thickness
to meet design conditions. PHMSA
expects that valves, flanges and fittings
should be rated based upon the required
specification rating class for the
alternative MAOP and the operator to
have documented mill reports with
chemistry, minimum yield strength, and
minimum wall thickness. Where
specialty bends such as hot bends are
used for pipeline segments operating
per the alternative MAOP, PHMSA
expects the operator to address
properties such as chemistry, minimum
yield strength, minimum wall thickness
and other properties that the hot
bending process could alter.
Paragraph (h) requires compressor
design to limit the temperature of
downstream pipe operating at an
alternative MAOP to a specified
maximum. Higher temperature can
damage pipe coating. An exception to
the specified maximum is allowed if
testing of the coating shows it can
withstand a higher temperature. The
testing duration, qualification
procedures and results must be of
sufficient length and rigor to detect
coating integrity issues for the type
coating, operating and environmental
conditions on the pipeline. Operators
E:\FR\FM\17OCR3.SGM
17OCR3
62168
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
jlentini on PROD1PC65 with RULES3
may also rely on a long-term coating
integrity monitoring program to justify
operation at higher temperatures,
provided the program is submitted to
and reviewed by PHMSA.
Paragraph (h) has been revised to
clarify the allowed exception. Testing
must address coating adhesion and
condition as well as cathodic
disbondment. Operators are required to
submit their test results, including the
acceptance criteria they applied to
assure themselves that these
characteristics are adequate, to the
appropriate PHMSA regional office(s)
and applicable state regulatory
authorities at least 60 days prior to
operating at elevated temperature. (State
notification applies when the pipeline is
located in a state where PHMSA has an
interstate agent agreement, or an
intrastate pipeline is regulated by that
state.)
A subtle, but important, change has
also been made in the language in this
paragraph. As proposed, the discharge
temperature of compressor stations
would have been limited to the
specified temperature. As revised, the
temperature of the nearest downstream
pipeline segment to operate at
alternative MAOP must be limited. For
situations in which the pipeline
segment at the discharge of a
compressor station operates at
alternative MAOP, there is no practical
difference. The revised language,
however, allows pipeline operators to
implement an alternative approach in
which they would use pipe operating at
conventional MAOP from the discharge
of a compressor station downstream to
the point at which pipe temperature
will drop to the specified limit. This
may provide an alternative for situations
in which it may be difficult to limit the
compressor station discharge to the
specified limit (e.g., southern locations
on hot summer days). Gas coolers may
be installed at compressor stations on
pipelines operating per the alternative
MAOP that need to operate above 120
degrees Fahrenheit. Gas cooling at
compressor stations is a long standing
method for most operators to reduce gas
pipeline temperatures.
E.4. New § 192.328—Additional
Construction Requirements
The rule also adds a new section to
Subpart G—General Construction
Requirements for Transmission Lines
and Mains. The new section, § 192.328,
prescribes additional construction
requirements, including rigorous QC
and inspections, as conditions for
operation of the steel pipeline at higher
stress levels. Unlike other construction
standards, § 192.328 would apply to a
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
new or existing pipeline only to the
extent that an operator elects to operate
at a higher alternative MAOP than
allowed in current regulations.
Paragraph (a) requires a QA plan for
construction. QA, also called QC, is
common in modern pipeline
construction. Activities such as
lowering the pipe into the ditch and
backfilling, if done poorly, can damage
the pipe and coating. Other construction
activities such as nondestructive
examination of girth welds, if done
poorly, will result in flaws remaining in
the pipeline or failures during
hydrostatic testing or while in gas
service. Using a QA plan helps to verify
that the basic tasks done during
construction of a pipeline are done
correctly.
Field application of coating is one of
these basic tasks to be covered in a QA
plan. During the course of analyzing
requests for special permits, PHMSA
discovered field coatings at one
construction site which were applied at
lower temperature than needed for good
adhesion to the pipe. Because coating is
so critical to corrosion protection,
paragraph (a) requires quality assurance
plans to contain specific performance
measures for field coating. Field coating
must meet substantially the same
standards as coating applied at the mill
and the individuals applying the coating
must be appropriately trained and
qualified.
Installation of the pipe into the ditch
and backfilling of the pipe are critical
operations. PHMSA has found that
construction and inspection lapses
during the backfilling of the pipe have
resulted in pipe denting and coating
damage. Sometimes during backfilling
of the pipe there are design
requirements for the installation of other
engineered items such as concrete
weights at creek and water saturated soil
areas. The proper installation of these
types of engineered items is critical to
ensure that the pipe and coating are not
damaged and the item is installed as
required in the specifications. PHMSA
has found operator lapses in this critical
QC aspect of pipeline construction.
Paragraph (b) requires non-destructive
testing of all girth welds. Although past
industry practice sometimes has been to
non-destructively test only a sample of
girth welds, no alternative exists for
verifying the integrity of the remaining
welds. The initial pressure testing once
construction is complete does not
normally detect flaws in girth welds
unless the girth weld is cracked, has
severe lack of penetration or is under
undue tension stresses, which would be
indicative of systemic problems on the
pipeline. PHMSA believes that most
PO 00000
Frm 00022
Fmt 4701
Sfmt 4700
modern pipeline construction projects
include non-destructive testing of all
girth welds. However, because the
regulations do not require testing of all
girth welds, an operator’s records for
pipelines already in operation may not
be complete on 100 percent of girth
welds. To account for this, proposed
paragraph (b) would have required
testing records for only 95 percent of
girth welds on existing segments. This
requirement has been retained, but
proposed paragraph (b) has been moved
to new § 192.620, as it applies to
existing pipelines. This section
addresses pipeline construction.
Paragraph (c) requires deeper burial of
segments operated at higher stress level.
A greater depth of cover decreases the
risk of damage to the pipeline from
excavation, including farming
operations.
Paragraph (d) addresses the results of
the initial strength test and the
assurance these results provide that the
material in the pipeline is free of preoperational flaws which can grow to
failure over time. Since the initial
strength test is a destructive test, it only
detects flaws that would fail at the test
pressure. This could leave in place
smaller flaws. To prevent this from
occurring, the proposed paragraph
would have disqualified any segment
which experienced a failure during the
initial strength test indicative of flaws in
the material. Most commenters objected
to this provision as too restrictive. They
noted that failures can be isolated and
that it was unreasonable to preclude an
entire pipeline segment from operation
at alternative MAOP because of a single
failure. This paragraph has been revised
to allow conduct of a root cause
examination of a failure, including
metallurgic examination of the failed
pipe, as a way of justifying qualification
of the pipeline segment. If that
examination determines that the cause
of the failure is not systemic, then the
pipeline segment would not be
disqualified from alternative MAOP
operation. Operators must report the
results of their root cause evaluation to
regulators (PHMSA Regional Office or
applicable state regulatory authorities).
Review of these analyses by pipeline
safety regulators will provide oversight
for operator conclusions regarding the
non-systemic nature of a failure.
Proposed paragraph (e) addressed
cathodic protection on an existing
segment. This paragraph has been
moved to new § 192.620.
Paragraph (e) (proposed as paragraph
(f)) addresses electrical interference for
new segments. During construction,
sources of electrical interference which
can impair future cathodic protection or
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
damage the pipe prior to placing
cathodic protection in service need to be
identified. Addressing interference at
this time supports better corrosion
control. Operators will need to
coordinate with electric transmission
line operators prior to pipeline
construction to identify locations of
grounding structures and power line
currents and voltages and their effect on
the pipe. The additional O&M
requirements of new § 192.620(d)(6)
require operators electing to operate
existing pipelines at higher stress levels
to address electrical interference prior to
raising the MAOP.
E.5. Amendment to § 192.611—Change
in Class Location: Confirmation or
Revision of Maximum Allowable
Operating Pressure
The proposed rule did not include a
provision to amend this section.
Commenters pointed out that this
section addresses changes in class
location (e.g., increase in population
density near the pipeline) during
operation. The existing requirements
allow continued operation at pressures
higher than would be required for new
pipe installed in the new class location,
provided pressure testing has been
performed at appropriate pressures. The
commenters noted that without
addressing operation at alternative
MAOP in this section, the regulations
would effectively rescind the
authorization provided by this rule to
operate at higher pressure whenever
there was a change in class location.
PHMSA agrees that this result was not
intended. This section has been revised
to include provisions for pipelines
operating at alternative MAOP
substantially the same as those already
provided for existing pipelines.
Operation at higher alternative
pressures can continue after a class
location change, again provided that the
pipeline has been tested at appropriate
pressures and is not an alternative
MAOP operating in a Class 3 location
that is upgraded to a Class 4 location.
The limits on hoop stress included in
this section have been revised to reflect
the higher hoop stress that will be
experienced by a pipeline at alternative
MAOP.
jlentini on PROD1PC65 with RULES3
E.6. Amendment to § 192.619—
Maximum Allowable Operating Pressure
The final rule amends existing
§ 192.619 by adding a new paragraph (d)
providing an additional means to
determine the alternative MAOP for
certain steel pipelines. In addition, the
rule makes conforming changes to
existing paragraph (a) of the section.
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
E.7. New § 192.620—Operation at an
Alternative MAOP
The final rule adds a new section,
§ 192.620, to subpart L of part 192, to
specify what actions an operator must
take in order to elect an alternative
MAOP based on higher operating stress
levels. The rule applies to both new and
existing pipelines.
E.7.1. § 192.620(a)—Calculating the
Alternative MAOP
Paragraph (a) describes how to
calculate the alternative MAOP based
on the higher operating stress levels.
Qualifying segments of pipeline would
use higher design factors to calculate the
alternative MAOP. For a segment
currently in operation this would result
in an increase in MAOP. No changes
were proposed in the design factors
used for segments within compressor or
meter stations or segments underlying
certain crossings. PHMSA expects new
pipelines operating per the alternative
MAOP to have road/railroad crossings,
fabrications, headers, mainline valve
assemblies, separators, meter stations
and compressor stations designed and
operated per existing design factors in
§ 192.111.
Paragraph (a) has been revised to
include new design factors for
compressor/meter stations or segments
underlying certain crossings. These
factors apply to facilities in existence
prior to the effective date of this rule.
Commenters pointed out that
compressor stations for existing
pipelines have been designed and that
failure to allow alternative design
factors for them could effectively
preclude operation at alternative MAOP
for the existing pipelines of which they
are a part. PHMSA agrees this was not
our intent. The additional risk
associated with use of slightly higher
design factors for these facilities is
marginal. At the same time, there is
little additional cost associated with
designing stations/crossings/
fabrications/headers for future pipelines
to serve at the desired MAOP using
existing design factors in § 192.111(b),
(c), and (d). The rule includes no
alternative design factors for these
facilities in future pipelines, and
operators must use the existing
requirements.
E.7.2. § 192.620(b)—Which Pipeline
Qualifies
Paragraph (b) describes which
segments of new or existing pipeline are
qualified for operation at the alternative
MAOP. The alternative MAOP is
allowed only in Class 1, 2, and 3
locations. Only steel pipelines meeting
PO 00000
Frm 00023
Fmt 4701
Sfmt 4700
62169
the rigorous design and construction
requirements of §§ 192.112 and 192.328
and monitored by supervisory data
control and acquisition systems qualify.
Mechanical couplings in lieu of welding
are not allowed. Although the special
permits did not expressly mention
mechanical couplings, PHMSA would
not have granted a special permit if the
pipeline involved had mechanical
couplings.
As proposed, paragraph (b) would
have excluded from consideration any
existing pipeline that had experienced a
failure indicative of materials concerns.
This provision has been revised to allow
root cause analysis to determine if the
failure is indicative of a systemic
problem and to preclude use of an
alternative MAOP only if a failure is
determined to be systematic in nature.
Results of the analysis must be reported
to regulators (PHMSA Regional Office or
applicable state regulatory authorities).
This is essentially the same change
made for new pipelines in new
§ 192.328(d), as described above.
Paragraph (b) has also been revised to
include the requirement that 95 percent
of girth welds must have been examined
for existing pipelines to operate at
alternative MAOP. This requirement
was moved from proposed § 192.328(e),
as discussed above.
E.7.3. §§ 192.620(c)(1), (2), and (3)—
How an Operator Selects Operation
Under This Section
Paragraph (c)(1) requires an operator
to notify PHMSA, and applicable state
pipeline safety regulators, when it elects
to establish an alternative MAOP under
this section. This notification must be
provided at least 180 days prior to
commencing operations at the
alternative MAOP established under
this section. This will provide PHMSA
and states sufficient time for appropriate
inspection which may include checks of
the manufacturing process, visits to the
pipeline construction sites, analysis of
operating history of existing pipelines,
and review of test records, plans, and
procedures.
Paragraph (c)(3) requires an operator
to further notify PHMSA when it has
completed the actions necessary to
support operation at an alternative
MAOP, by submitting a certification by
a senior executive that the pipeline
meets the requirements for operation at
alternative MAOP. The certification is
required by paragraph (c)(2). A senior
executive must certify that the pipeline
meets the additional design and
construction regulations of this rule. A
senior executive must also certify that
the operator has changed its O&M
procedures to include the more rigorous
E:\FR\FM\17OCR3.SGM
17OCR3
62170
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
additional O&M requirements. In
addition, a senior executive must certify
that the operator has reviewed its
damage prevention program in light of
best practices, such as CGA best
practices or some equivalent best
practices, and made any needed changes
to it to ensure that the program meets or
exceeds those standards or practices.
The certification must be submitted at
least 30 days prior to operation at an
alternative MAOP.
E.7.4. § 192.620(c)(4)—Initial Strength
Testing
Paragraph (c)(4) addresses initial
strength testing requirements. In order
to establish the MAOP under this
section, an operator must perform the
initial strength testing of a new segment
at a pressure at least as great as 125
percent of the MAOP in Class 1
locations and 150 percent in Class 2 and
3 locations. Since an existing pipeline
was previously operated at a lower
MAOP, it may have been initially tested
at a pressure less than these levels. If so,
paragraph (c) allows the operator to
elect to conduct a new strength test in
order to raise the MAOP.
jlentini on PROD1PC65 with RULES3
E.7.5. § 192.620(c)(5)—Operation and
Maintenance
Paragraph (c)(5) requires an operator
to comply with the additional operating
and maintenance requirements of
§ 192.620(d). An operator must comply
with these additional requirements if
the operator elects to calculate the
alternative MAOP for a segment under
§ 192.620(a) and notifies PHMSA of that
election.
E.7.6. § 192.620(c)(6)—New
Construction and Maintenance Tasks
Paragraph (c)(6) addresses the need
for competent performance of both new
construction, and future maintenance
activities, to ensure the integrity of the
segment. PHMSA now requires
operators to ensure that individuals who
perform pipeline O&M activities are
qualified. Paragraph (c)(6) requires
operators seeking to operate at the
allowable higher operating stress levels
to treat construction tasks as if they
were covered by subpart N,
‘‘Qualification of Pipeline Personnel.’’
Subpart N (commonly known as OQ)
specifies training and qualification
requirements applicable to tasks that
meet a four-part test in § 192.801(b).
Operations and maintenance tasks on
the pipeline meet this test, and it is the
requirements in subpart N that will
govern training and qualification of
personnel performing these tasks on a
pipeline to be operated at an alternative
MAOP. Construction tasks typically do
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
not meet the four-part test and are not
covered under subpart N. As proposed,
paragraph (c)(6) (then designated (c)(5))
would have required operators to take
other actions to assure qualification of
personnel performing construction tasks
on a pipeline intended to operate at
alternative MAOP. Commenters noted
that the proposed requirements were
vague and subject to interpretation and
suggested that PHMSA, instead, rely on
the known requirements of subpart N.
This paragraph has been modified, in
response to these comments, to require
that the requirements of subpart N be
applied to construction tasks for a
pipeline intended to operate at
alternative MAOP regardless of the fourpart test in § 192.801(b).
E.7.7. § 192.620(c)(7)—Recordkeeping
Paragraph (c)(7) specifies
recordkeeping requirements for
operators electing to establish the
MAOP under this section. Existing
regulations, such as §§ 192.13,
192.517(a), and 192.709, already require
operators to maintain records applicable
to this section. New § 192.620 is in
subpart L. Because the additional
requirements in this section address
requirements found in other subparts of
part 192, the recordkeeping
requirements could cause confusion.
For example, § 192.620(d)(9) requires a
baseline assessment for integrity for a
segment operated at the higher stress
level regardless of its potential impact
on an HCA. Section 192.947, in subpart
O, requires operators to maintain
records of baseline assessments for the
useful life of the pipeline. Section
192.709 requires an operator to retain
records for an inspection done under
subpart L for a more limited time.
Accordingly, this paragraph clarifies the
need to maintain all records
demonstrating compliance with all
alternative MAOP requirements for the
useful life of the pipeline.
E.7.8 § 192.620(c)(8)—Class Upgrades
Paragraph (c)(8) allows pipelines in
Class 1 and 2 to be upgraded one class
when class changes occur per § 192.611.
This paragraph precludes operation of
pipeline in Class 4 at alternative MAOP.
E.8. § 192.620(d)—Additional Operation
and Maintenance Requirements
Paragraph (d) sets forth ten operating
and maintenance requirements that
supplement the existing requirements in
part 192. Currently § 192.605 requires
an operator to develop O&M procedures
to implement the requirements of
subparts L and M. Since § 192.620(d) is
in subpart L, an operator must develop
and follow the O&M procedures
PO 00000
Frm 00024
Fmt 4701
Sfmt 4700
developed under this section. These
include requirements for an operator to
evaluate and address the issues
associated with operating at higher
pressures. Through its public education
program, an operator would inform the
public of any risks attributable to higher
pressure operations. The additional
operating and maintenance
requirements address the two main risks
the pipelines face, excavation damage
and corrosion, through a combination of
traditional practices and integrity
management. Traditional practices
include cathodic protection, control of
gas quality, and maintenance of burial
depth. Integrity management includes
internal inspection on a periodic basis
to identify and repair flaws before they
can fail. The additional O&M and
management requirements are discussed
in more detail below.
E.8.1. § 192.620(d)(1)—Threat
Assessments
Paragraph (d)(1) requires an operator
to identify and evaluate threats to the
pipeline consistent with the similar
procedures done under integrity
management to address the risks of
operating at an increased stress level.
E.8.2. § 192.620(d)(2)—Public
Awareness
Paragraph (d)(2) requires an operator
to include any people potentially
impacted by operation at a higher stress
level within the outreach effort in its
public education program required
under existing § 192.616. In order to
identify this population, an operator
would use a broad area measured from
the centerline of the pipe plus, in HCAs,
the potential impact circle recalculated
to reflect operation at a higher operating
stress level. This is intended to get
necessary information for safety to the
people potentially impacted by a failure.
E.8.3. § 192.620(d)(3)—Emergency
Response
Paragraph (d)(3) addresses the
additional needs for responding to
emergencies for operation at higher
operating stress levels. Consistent with
the conditions imposed in the special
permits, and past experience with
response issues, the paragraph requires
methods such as remote control valves
to provide more rapid shut-down in the
event of an emergency.
E.8.4. § 192.620(d)(4)—Damage
Prevention
Paragraph (d)(4) addresses one of the
major risks of failure faced by a
pipeline, damage from outside force
such as damage occurring during
excavation in the right-of-way. Although
E:\FR\FM\17OCR3.SGM
17OCR3
jlentini on PROD1PC65 with RULES3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
the improved toughness of pipe reduces
the risk of damage, it does not prevent
it and additional measures are
appropriate for pipelines operating at
higher operating stress levels. This
paragraph adds several new or more
specific measures to existing
requirements designed to prevent
damage to pipelines from outside force.
The first more specific measure, in
paragraph (d)(4)(i), addresses patrolling,
required for all transmission pipelines
by § 192.705. More frequent patrols of
the right-of-way prevent damage by
giving the operator more accurate and
timely information about potential
sources of ground disturbance and other
outside force damage. These include
both naturally occurring conditions,
such as wash outs, and human activity,
such as construction in the vicinity of
the pipeline. The requirement is for
patrols to be made monthly, at intervals
not to exceed 45 days. The patrolling
requirement along with other right-ofway requirements including line-ofsight markers, use of national consensus
standards, and the right-of-way
management plan comprise a multifaceted approach to protecting the
pipeline.
Other more specific or new measures
to address damage prevention include
developing and implementing a plan to
monitor and address ground movement,
a requirement of paragraph (d)(4)(ii).
Ground movement such as earthquakes,
landslides, soil erosion, and nearby
demolition or tunneling can damage
pipelines. Since pipelines near the
surface are more likely to be damaged
by surface activities, paragraph
(d)(4)(iii) requires an operator to
maintain the depth of cover over a
pipeline or provide alternative
protection. Line-of-sight markers alert
excavators, emergency responders, and
the general public of the presence and
general location of pipelines. Paragraph
(d)(4)(iv) requires these markers both to
improve damage prevention and to
enhance public awareness.
Damage prevention programs are
improving because of the work being
done by the CGA, a national, non-profit
educational organization dedicated to
preventing damage to pipelines and
other underground utilities. The CGA
has compiled best practices applicable
to all parties relevant to preventing
damage to underground utilities and
actively promotes their use. Paragraph
(d)(5)(v) requires operators electing to
operate at higher stress levels to
evaluate their damage prevention
programs in light of industry best
practices, such as those developed by
CGA. An operator must identify the
practices applicable to its circumstances
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
and make appropriate changes to its
damage prevention program. This
approach is consistent with annual
reviews of O&M programs under
§ 192.605. An operator must include in
the certification required under
§ 192.620(c)(1) that the review and
upgrade have occurred.
Paragraph (d)(4) also requires the
preparation of a right-of-way
management plan. In the past several
years, PHMSA has seen recurring
similarities in pipeline accidents on
construction sites. In each case, better
management of the pipeline right-ofway could have prevented the
accidents. Better management includes
closer attention to the qualifications of
individuals critical to damage
prevention, better marking practices,
and closer oversight of the excavation.
In 2006, PHMSA issued two advisory
bulletins to alert operators of the need
to pay closer attention to these
important damage prevention issues.
The first advisory bulletin described
three accidents in which either operator
personnel or contractors damaged gas
transmission pipelines during
excavation in the rights-of-way (ADB–
06–01; 71 FR 2613; Jan.17, 2006). This
bulletin advised operators to pay closer
attention to integrating OQ regulations
into excavation activities and providing
that excavation is included as a covered
task under OQ programs required by
subpart N. The second advisory bulletin
pointed to an additional excavation
accident where the excavator struck an
inadequately marked gas transmission
pipeline (ADB–06–003; 71 FR 67703;
Nov. 22, 2006). This advisory bulletin
advised pipeline operators to pay closer
attention to locating and marking
pipelines before excavation activities
begin and pointed to several good
practices as well as the best practices
described by the CGA. This paragraph
requires an operator electing to operate
at a higher stress level to develop a plan
to manage the protection of their rightof-way from excavation activities. Each
operator already has a damage
prevention program, under § 192.614,
and a program to ensure qualification of
pipeline personnel, under subpart N.
This management program requires the
operator to integrate activities under
those programs to provide better
protection for the right-of-way of the
pipeline operated at the higher stress
level.
E.8.5. § 192.620(d)(5)—Internal
Corrosion Control
Paragraph (d)(5) adds specificity to
the requirements for internal corrosion
control now in pipeline safety standards
for pipelines operated at higher stress
PO 00000
Frm 00025
Fmt 4701
Sfmt 4700
62171
levels. These internal corrosion control
programs must include use of gas
separators or filter separators and gas
quality monitoring equipment.
Operators are required to use cleaning
pigs and inhibitors when corrosive gas
is present. (Use of cleaning pigs and
inhibitors is required when the level of
one corrosive contaminant, hydrogen
sulfide (H2S), is between 0.5 and 1.0
grain per hundred cubic feet). Most
operators who have applied for special
permits to operate their pipeline at
alternative MAOP limit H2S to 0.5 grain.
The higher levels allowed in this rule
are within typical FERC tariffs, but may
present an increased likelihood of
internal corrosion. Maximum levels of
contaminants that could promote
corrosion must be reviewed quarterly,
and operators must adjust their
programs as needed to monitor and
mitigate any deleterious gas stream
constituents. PHMSA believes the levels
are fully consistent with the
requirements in FERC tariffs designed to
prevent internal corrosion.
E.8.6. §§ 192.620(d)(6), (7), and (8)—
External Corrosion Control
Since external corrosion is one of the
greatest risks to the integrity of
pipelines operating at higher stress
levels, the special permits and this rule
contain several measures to prevent it
from occurring. These include use of
effective external coating, addressing
interference, early installation of
cathodic protection, confirming the
adequacy of coating and cathodic
protection and diligent monitoring of
cathodic protection levels. The
requirements concerning quality of the
coating and installation of cathodic
protection for new pipelines are
addressed in sections on design and
construction, as discussed above. The
remaining external corrosion provisions
are addressed here.
Interference from overhead power
lines, railroad signaling, stray currents,
or other sources can interfere with the
cathodic protection system and, if not
properly mitigated, even accelerate the
rate of external corrosion. Paragraph
(d)(6) requires an operator to identify
and address interference early before
damage to the pipeline can occur.
Paragraph (d)(7) requires an operator
to confirm both the effectiveness of the
coating and the adequacy of the
cathodic protection system soon after
deciding on operation at higher
operating stress levels/alternative
MAOP. This is accomplished through
indirect assessments, such as a CIS for
cathodic protection and DCVG or ACVG
for coating condition. After completion
of the baseline internal inspection
E:\FR\FM\17OCR3.SGM
17OCR3
62172
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
required by § 192.620(d)(9), an operator
is required to integrate the results of that
inspection with the indirect
assessments. An operator must take
remedial action to correct any
inadequacies. In HCAs, an operator
must periodically repeat indirect
assessment to confirm that the cathodic
protection system remains as functional
as when first installed.
Paragraph (d)(8) requires more
rigorous attention to ensure adequate
levels of cathodic protection.
Regulations now require an operator
discovering a low reading, meaning a
reduced level of protection, to act
promptly to correct the deficiency. This
section puts an outer limit of six months
on the time for completion of the
remedial action and restoration of an
adequate level of cathodic protection. In
addition, the operator must confirm that
its actions have been effective in
restoring cathodic protection.
jlentini on PROD1PC65 with RULES3
E.8.7. §§ 192.620(d)(9) and (10)—
Integrity Assessments
Among the most important ways of
ensuring integrity during pipeline
operations are the assessments done
under the integrity management
program requirements in subpart O.
Paragraphs (d)(9) and (d)(10) require
operators electing to operate at higher
stress levels to perform both baseline
and periodic assessments of the entire
pipeline segment operating at the higher
stress level, regardless of whether the
pipeline segment is located in an HCA.
The operator must use both a geometry
tool and a high resolution magnetic flux
tool for the entire pipeline segment. In
very limited circumstances in which
internal inspection is not possible
because internal inspection tools cannot
be accommodated, such as a short
crossover segment connecting two
pipelines in a right-of-way, an operator
would substitute pressure testing or DA.
The operator must then integrate the
information provided by these
assessments with testing done under
previously described paragraphs. This
analysis would form the basis for
mitigating measures, and for prompt
repairs under paragraph (d)(11).
E.8.8. § 192.620(d)(11)—Repair Criteria
The repair criteria under paragraph
(d)(11) for anomalies in a pipeline
segment operating at a higher stress
level are slightly more conservative than
for other pipelines, including pipelines
covered by an integrity management
program. With the tougher pipe, better
coating, construction quality inspection
program, coating surveys after
installation and backfill, and careful
attention to damage prevention and
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
corrosion protection, a pipeline
operated at higher operating stress
levels should experience few anomalies
needing evaluation.
E.9. § 192.620(e)—Overpressure
Protection
The alternative MAOP is higher than
the upper limit of the required
overpressure protection under existing
regulations. Paragraph (e) increases the
overpressure protection limit to 104
percent of the MAOP, which is 83.2
percent of SMYS for a pipeline segment
operating at the alternative MAOP in a
Class 1 location.
F. Regulatory Analyses and Notices
F.1. Privacy Act Statement
Anyone may search the electronic
form of all comments received for any
of our dockets. You may review DOT’s
complete Privacy Act Statement in the
Federal Register published on April 11,
2000 (65 FR 19477).
F.2. Executive Order 12866 and DOT
Policies and Procedures
Due to magnitude of expected
benefits, the DOT considers this
rulemaking to be a significant regulatory
action under section 3(f)(1) of Executive
Order 12866 (58 FR 51735; Oct. 4,
1993). Therefore, DOT submitted it to
the Office of Management and Budget
for review. This rulemaking is also
significant under DOT regulatory
policies and procedures (44 FR 11034;
Feb. 26, 1979).
PHMSA prepared a Regulatory
Evaluation of the final rule. A copy is
in Docket ID PHMSA–2005–23447.
PHMSA estimates that the rule will
result in gas transmission pipeline
operators uprating 3,500 miles of
existing pipelines to an alternative
MAOP. Additionally PHMSA estimates
that, in the future, the rule will result in
an annual additional 700 miles of new
pipelines each year whose operators
elect to use an alternative MAOP.
PHMSA expects the benefits of the
rule to be substantial and in excess of
$100 million per year. This expectation
is based on quantified benefits in excess
of $100 million per year (see below),
coupled with un-quantified benefits
associated with the rule that industry
and PHMSA technical staff have
identified. The expected benefits of the
rule that cannot be readily quantified
include:
• Reductions in incident
consequences.
• Increases in pipeline capacity.
• Increases in the amount of natural
gas filling the line, commonly called
line pack.
PO 00000
Frm 00026
Fmt 4701
Sfmt 4700
• Reductions in adverse
environmental impacts.
The rule’s requirements, such as
monthly right-of-way patrolling,
additional internal inspections, and
anomaly repair, are expected to prevent
incidents that would have occurred in
the absence of the rule, and to help
mitigate the consequences of the
incidents that do occur. In the case of
new pipelines, the ability to use an
alternative MAOP will make it possible
to transport more product per dollar of
pipeline cost than would be possible
without this new rule. Quantifying the
value of this increased capacity is
difficult, and no estimate has been
developed for this analysis. For existing
pipelines, operation at a higher MAOP
increases the amount of gas that can be
transported. PHMSA expects the value
of increased capacity due to use of
alternative MAOP by gas pipelines to be
significant. In areas where production is
already well-established, there is an
even greater potential for increased
pipeline capacity. For example, one
recipient of a special permit estimated
a daily increase of at least 62 million
standard cubic feet of gas.
Similarly, increases in line pack will
produce increased benefits which are
difficult to quantify. Line pack is
increased due to gas compressibility at
higher operating pressures which results
in increased gas volumes in the
pipeline. The reduced amount of
exterior storage capacity needed
resulting from increased line pack may
result in capital or O&M savings for the
pipelines or their customers. Greater
line pack in a pipeline increases the
ability of the operator to continue gas
delivery during short outages such as
maintenance and during peak flow
periods. These benefits are not readily
quantifiable.
The quantified benefits consist of:
• Fuel cost savings.
• Capital expenditure savings on pipe
for new pipelines.
Of these, pipeline fuel cost savings is
the most important contributor to the
estimated benefits. Although these
quantified benefits do not capture the
full benefits of the rule, they exceed
$100 million per year.
As a consequence of the rule, PHMSA
estimates that pipeline operators will
realize annually recurring benefits due
to fuel cost savings of $49 million that
will begin in the initial year after the
rule goes into effect. Additionally,
PHMSA estimates that each year
pipeline operators will realize one-time
benefits for savings in capital
expenditures of $54.6 million (since 700
miles of new pipeline operating at an
alternative MAOP are added each year,
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
the one-time benefits resulting from this
added mileage will be the same each
year.) The benefits of the rule over 20
62173
years are expected to be as presented in
the following table:
TABLE D.2.–1—SUMMARY AND TOTAL FOR THE ESTIMATED BENEFITS OF THE RULE
[Millons of dollars per year]
Estimate of new benefits occurring
in each subsequent year
Benefit
Estimate for year 1
Reduced incident consequences ............................................................
Fuel cost savings ....................................................................................
Reduced capital expenditures .................................................................
Increased pipeline capacity .....................................................................
Increased line pack .................................................................................
Reduced adverse environmental impacts ...............................................
Other expected benefits ..........................................................................
Not quantified ................................
$49.0 ..............................................
$54.6 ..............................................
Not quantified ................................
Not quantified ................................
Not quantified ................................
Not quantified ................................
Not quantified.
$49.0
$54.6
Not quantified.
Not quantified.
Not quantified.
Not quantified.
Total .................................................................................................
$103.6 ............................................
$103.6
The present value of the benefits
evaluated over 20 years at a three
percent discount rate is $1,541 million,
while the present value of the benefits
over 20 years at a seven percent
discount rate is $1,098 million. For both
discount rates, the annualized benefits
would be $103.6 million.
PHMSA expects the costs attributable
to the rule are most likely to be incurred
by operators for:
• Performing baseline internal
inspections.
• Performing additional internal
inspections.
• Performing anomaly repairs.
• Installing remotely controlled
valves on either side of HCAs.
• Preparing threat assessments.
• Patrolling pipeline rights-of-way.
• Preparing the paperwork notifying
PHMSA of the decision to use an
alternative MAOP.
Overall, the costs of the rule over 20
years are expected to be as presented in
the following table:
TABLE D.2.–2— SUMMARY AND TOTALS FOR THE ESTIMATED COSTS OF THE RULE
Cost by year after implementation
[thousands of dollars]
Cost item
2nd—10th
11th
Baseline internal inspections.
Additional internal inspections.
Anomaly repairs ................
Remotely controlled valves
Threat Assessments ..........
Patrolling ............................
Notifying PHMSA ...............
$29,119 .............................
None ..................................
None ..................................
None
None ..................................
None ..................................
$17,471 .............................
$2,912 each year.
$1,015 ...............................
$3,528 ...............................
$180 ..................................
$4,620 ...............................
Nominal .............................
None ..................................
$588 each year .................
$30 each year ...................
$5,390 to $11,550 .............
Nominal .............................
$1,218 ...............................
$588 ..................................
$30 ....................................
$12,320 .............................
Nominal .............................
$203 each year.
$588 each year.
$30 each year.
$15,090 to $19,250.
Nominal.
Total ...........................
jlentini on PROD1PC65 with RULES3
1st
$38,462 .............................
$618 each year plus patrolling costs.
$31,627 .............................
$3,733 each year plus patrolling costs.
The present value of the costs
evaluated over 20 years at a three
percent discount rate are approximately
$239 million, while the present value of
the costs over 20 years at a seven
percent discount rate are approximately
$165 million. The annualized costs at
the three percent discount rate are
approximately $16 million, while the
annualized costs at the seven percent
discount rate are approximately $15
million.
Since the present value of the
quantified benefits ($1,541 million at
three percent and $1,098 million at
seven percent) exceeds the present
value of the costs ($328 million at three
percent and $164 million at seven
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
percent), the rule is expected to have net
benefits.
F.3. Regulatory Flexibility Act
Under the Regulatory Flexibility Act
(5 U.S.C. 601 et seq.), PHMSA must
consider whether rulemaking actions
would have a significant economic
impact on a substantial number of small
entities.
The final rule affects operators of gas
pipelines. Based on annual reports
submitted by operators, there are
approximately 1,450 gas transmission
and gathering systems and an equivalent
number of distribution systems
potentially affected by this rule. The
size distribution of these operators is
unknown and must be estimated.
PO 00000
Frm 00027
Fmt 4701
Sfmt 4700
12th—20th
The affected gas transmission systems
all belong to NAICS 486210, Pipeline
Transportation of Natural Gas. In
accordance with the size standards
published by the Small Business
Administration, a business with $6.5
million or less in annual revenue is
considered a small business in this
NAICS.
Based on August 2006 information
from Dunn & Bradstreet on firms in
NAICS 486210, PHMSA estimates that
33 percent of the gas transmission and
gathering systems have $6.5 million or
less in revenue. Thus, PHMSA estimates
that 479 of the gas transmission and
gathering systems affected by the rule
will have $6.5 million or less in annual
revenue. PHMSA does not expect that
E:\FR\FM\17OCR3.SGM
17OCR3
62174
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
any local gas distribution companies or
gathering systems will be taking
advantage of the potential to use an
alternative MAOP.
The rule mandates no action by gas
transmission pipeline operators. Rather,
it provides those operators with the
option of using an alternative MAOP in
certain circumstances, when certain
conditions can be met. Consequently, it
imposes no economic burden on the
affected gas pipeline operators, large or
small. Based on these facts, I certify that
this rule will not have a substantial
economic impact on a substantial
number of small entities.
F.4. Executive Order 13175
PHMSA has analyzed this rulemaking
according to Executive Order 13175,
‘‘Consultation and Coordination with
Indian Tribal Governments.’’ Because
the rule does not significantly or
uniquely affect the communities of the
Indian tribal governments, nor impose
substantial direct compliance costs, the
funding and consultation requirements
of Executive Order 13175 do not apply.
F.5. Paperwork Reduction Act
This rule adds notification paperwork
requirements and record retention on
pipeline operators voluntarily choosing
an alternative MAOP for their pipelines.
Based on analysis of the regulation,
there will be an estimated nine total
annual burden hours attributable to the
notification and recordkeeping
requirements in the first year. In
following years, the annual burden is
expected to decrease to one and one-half
hours. The associated cost of these
annual burden hours is $720 in year
one, and $120 thereafter. No other
burden hours and associated costs are
expected. The Paperwork Reduction Act
analysis in the docket has a more
detailed explanation.
jlentini on PROD1PC65 with RULES3
F.6. Unfunded Mandates Reform Act of
1995
This rule does not impose unfunded
mandates under the Unfunded
Mandates Reform Act of 1995. It does
not result in costs of $132 million or
more in any one year to either State,
local, or tribal governments, in the
aggregate, or to the private sector, and
is the least burdensome alternative that
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
achieves the objective of the
rulemaking.
F.7. National Environmental Policy Act
PHMSA has analyzed the rulemaking
for purposes of the National
Environmental Policy Act (42 U.S.C.
4321 et seq.). The rulemaking will
require limited physical change or other
work that would disturb pipeline rightsof-way. In addition, the rule codifies the
terms of special permits PHMSA has
granted. Although PHMSA sought
public comment on environmental
impacts with respect to most requests
for special permits to allow operation at
pressures based on higher stress levels,
no commenters addressed
environmental impacts. Further,
PHMSA did not receive any comment
on the environmental assessment it had
prepared in conjunction with the
proposed rule. PHMSA has determined
the rulemaking is unlikely to
significantly affect the quality of the
human environment. An environmental
assessment document is available for
review in the docket.
F.8. Executive Order 13132
PHMSA has analyzed the rulemaking
according to Executive Order 13132 (64
FR 43255, Aug. 10, 1999) and concluded
that no additional consultation with
States, local governments or their
representatives is mandated beyond the
rulemaking process. The rule does not
have a substantial direct effect on the
States, the relationship between the
national government and the States, or
the distribution of power and
responsibilities among the various
levels of government. The rule does not
impose substantial direct compliance
costs on State or local governments.
Further, no consultation is needed to
discuss the preemptive effect of the
proposed rule. The pipeline safety law,
specifically 49 U.S.C. 60104(c),
prohibits State safety regulation of
interstate pipelines. Under the pipeline
safety law, States have the ability to
augment pipeline safety requirements
for intrastate pipelines PHMSA
regulates, but may not approve safety
requirements less stringent than those
required by Federal law. And a State
may regulate an intrastate pipeline
facility PHMSA does not regulate. In
PO 00000
Frm 00028
Fmt 4701
Sfmt 4700
addition, 49 U.S.C. 60120(c) provides
that the Federal pipeline safety law
‘‘does not affect the tort liability of any
person.’’ It is these statutory provisions,
not the rule, that govern preemption of
State law. Therefore, the consultation
and funding requirements of Executive
Order 13132 do not apply.
F.9. Executive Order 13211
This rulemaking is likely to increase
the efficiency of gas transmission
pipelines. A gas transmission pipeline
operating at an increased MAOP will
result in increased capacity, fuel
savings, and flexibility in addressing
supply demands. This is a positive
rather than an adverse effect on the
supply, distribution, and use of energy.
Thus this rulemaking is not a
‘‘significant energy action’’ under
Executive Order 13211. Further, the
Administrator of the Office of
Information and Regulatory Affairs has
not identified this rule as a significant
energy action.
List of Subjects in 49 CFR Part 192
Design pressure, Incorporation by
reference, Maximum allowable
operating pressure, and Pipeline safety.
For the reasons provided in the
preamble, PHMSA amends 49 CFR part
192 as follows:
■
PART 192—TRANSPORTATION OF
NATURAL AND OTHER GAS BY
PIPELINE: MINIMUM FEDERAL
SAFETY STANDARDS
1. The authority citation for part 192
continues to read as follows:
■
Authority: 49 U.S.C. 5103, 60102, 60104,
60108, 60109, 60110, 60113, and 60118; and
49 CFR 1.53.
2. In § 192.7, in paragraph (c)(2)
amend the table of referenced material
by revising item (B)(1), redesignating
items (C)(6) through (C)(13) as (C)(7)
through (C)(14), and adding a new item
(C)(6) to read as follows:
■
§ 192.7 What documents are incorporated
by reference partly or wholly in this part?
*
*
*
(c) * * *
(2) * * *
E:\FR\FM\17OCR3.SGM
17OCR3
*
*
62175
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
Source and name of referenced material
49 CFR reference
B. * * * ...............................................................................................................................................................
(1) API Specification 5L ‘‘Specification for Line Pipe,’’ (43rd edition and errata), 2004 ...................................
* * *
§§ 192.55(e); 192.112; 192.113;
Item I of Appendix B.
*
*
*
*
*
*
*
C. * * * ..............................................................................................................................................................
(6) ASTM Designation: A 578/A578M–96 (Re-approved 2001) ‘‘Standard Specification for Straight-Beam
Ultrasonic Examination of Plain and Clad Steel Plates for Special Applications’’.
*
*
*
*
*
3. Add § 192.112 to subpart C to read
as follows:
■
§ 192.112 Additional design requirements
for steel pipe using alternative maximum
allowable operating pressure.
For a new or existing pipeline
segment to be eligible for operation at
the alternative maximum allowable
operating pressure (MAOP) calculated
§§ 192.112(c)(2)(iii).
*
*
under § 192.620, a segment must meet
the following additional design
requirements. Records for alternative
MAOP must be maintained, for the
useful life of the pipeline,
demonstrating compliance with these
requirements:
To address this design issue:
The pipeline segment must meet these additional requirements:
(a) General standards for the steel
pipe.
(1) The plate, skelp, or coil used for the pipe must be micro-alloyed, fine grain, fully killed, continuously
cast steel with calcium treatment.
(2) The carbon equivalents of the steel used for pipe must not exceed 0.25 percent by weight, as calculated by the Ito-Bessyo formula (Pcm formula) or 0.43 percent by weight, as calculated by the International Institute of Welding (IIW) formula.
(3) The ratio of the specified outside diameter of the pipe to the specified wall thickness must be less than
100. The wall thickness or other mitigative measures must prevent denting and ovality anomalies during
construction, strength testing and anticipated operational stresses.
(4) The pipe must be manufactured using API Specification 5L, product specification level 2 (incorporated
by reference, see § 192.7) for maximum operating pressures and minimum and maximum operating temperatures and other requirements under this section.
(1) The toughness properties for pipe must address the potential for initiation, propagation and arrest of
fractures in accordance with:
(i) API Specification 5L (incorporated by reference, see § 192.7); or
(ii) American Society of Mechanical Engineers (ASME) B31.8 (incorporated by reference, see § 192.7); and
(iii) Any correction factors needed to address pipe grades, pressures, temperatures, or gas compositions
not expressly addressed in API Specification 5L, product specification level 2 or ASME B31.8 (incorporated by reference, see § 192.7).
(2) Fracture control must:
(i) Ensure resistance to fracture initiation while addressing the full range of operating temperatures, pressures, gas compositions, pipe grade and operating stress levels, including maximum pressures and minimum temperatures for shut-in conditions, that the pipeline is expected to experience. If these parameters change during operation of the pipeline such that they are outside the bounds of what was considered in the design evaluation, the evaluation must be reviewed and updated to assure continued resistance to fracture initiation over the operating life of the pipeline;
(ii) Address adjustments to toughness of pipe for each grade used and the decompression behavior of the
gas at operating parameters;
(iii) Ensure at least 99 percent probability of fracture arrest within eight pipe lengths with a probability of
not less than 90 percent within five pipe lengths; and
(iv) Include fracture toughness testing that is equivalent to that described in supplementary requirements
SR5A, SR5B, and SR6 of API Specification 5L (incorporated by reference, see § 192.7) and ensures
ductile fracture and arrest with the following exceptions:
(A) The results of the Charpy impact test prescribed in SR5A must indicate at least 80 percent minimum
shear area for any single test on each heat of steel; and
(B) The results of the drop weight test prescribed in SR6 must indicate 80 percent average shear area with
a minimum single test result of 60 percent shear area for any steel test samples. The test results must
ensure a ductile fracture and arrest.
(3) If it is not physically possible to achieve the pipeline toughness properties of paragraphs (b)(1) and (2)
of this section, additional design features, such as mechanical or composite crack arrestors and/or heavier walled pipe of proper design and spacing, must be used to ensure fracture arrest as described in
paragraph (b)(2)(iii) of this section.
(1) There must be an internal quality management program at all mills involved in producing steel, plate,
coil, skelp, and/or rolling pipe to be operated at alternative MAOP. These programs must be structured
to eliminate or detect defects and inclusions affecting pipe quality.
(2) A mill inspection program or internal quality management program must include (i) and either (ii) or (iii):
(i) An ultrasonic test of the ends and at least 35 percent of the surface of the plate/coil or pipe to identify
imperfections that impair serviceability such as laminations, cracks, and inclusions. At least 95 percent of
the lengths of pipe manufactured must be tested. For all pipelines designed after [the effective date of
the final rule], the test must be done in accordance with ASTM A578/A578M Level B, or API 5L Paragraph 7.8.10 (incorporated by reference, see § 192.7) or equivalent method, and either
(b) Fracture control .........................
jlentini on PROD1PC65 with RULES3
(c) Plate/coil quality control .............
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
PO 00000
Frm 00029
Fmt 4701
Sfmt 4700
E:\FR\FM\17OCR3.SGM
17OCR3
62176
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
To address this design issue:
The pipeline segment must meet these additional requirements:
(d) Seam quality control ..................
(e) Mill hydrostatic test ....................
(f) Coating .......................................
(g) Fittings and flanges ...................
(h) Compressor stations .................
(ii) A macro etch test or other equivalent method to identify inclusions that may form centerline segregation
during the continuous casting process. Use of sulfur prints is not an equivalent method. The test must
be carried out on the first or second slab of each sequence graded with an acceptance criteria of one or
two on the Mannesmann scale or equivalent; or
(iii) A quality assurance monitoring program implemented by the operator that includes audits of: (a) all
steelmaking and casting facilities, (b) quality control plans and manufacturing procedure specifications,
(c) equipment maintenance and records of conformance, (d) applicable casting superheat and speeds,
and (e) centerline segregation monitoring records to ensure mitigation of centerline segregation during
the continuous casting process.
(1) There must be a quality assurance program for pipe seam welds to assure tensile strength provided in
API Specification 5L (incorporated by reference, see § 192.7) for appropriate grades.
(2) There must be a hardness test, using Vickers (Hv10) hardness test method or equivalent test method,
to assure a maximum hardness of 280 Vickers of the following:
(i) A cross section of the weld seam of one pipe from each heat plus one pipe from each welding line per
day; and
(ii) For each sample cross section, a minimum of 13 readings (three for each heat affected zone, three in
the weld metal, and two in each section of pipe base metal).
(3) All of the seams must be ultrasonically tested after cold expansion and mill hydrostatic testing.
(1) All pipe to be used in a new pipeline segment must be hydrostatically tested at the mill at a test pressure corresponding to a hoop stress of 95 percent SMYS for 10 seconds. The test pressure may include
a combination of internal test pressure and the allowance for end loading stresses imposed by the pipe
mill hydrostatic testing equipment as allowed by API Specification 5L, Appendix K (incorporated by reference, see § 192.7).
(2) Pipe in operation prior to November 17, 2008, must have been hydrostatically tested at the mill at a
test pressure corresponding to a hoop stress of 90 percent SMYS for 10 seconds.
(1) The pipe must be protected against external corrosion by a non-shielding coating.
(2) Coating on pipe used for trenchless installation must be non-shielding and resist abrasions and other
damage possible during installation.
(3) A quality assurance inspection and testing program for the coating must cover the surface quality of the
bare pipe, surface cleanliness and chlorides, blast cleaning, application temperature control, adhesion,
cathodic disbondment, moisture permeation, bending, coating thickness, holiday detection, and repair.
(1) There must be certification records of flanges, factory induction bends and factory weld ells. Certification must address material properties such as chemistry, minimum yield strength and minimum wall
thickness to meet design conditions.
(2) If the carbon equivalents of flanges, bends and ells are greater than 0.42 percent by weight, the qualified welding procedures must include a pre-heat procedure.
(3) Valves, flanges and fittings must be rated based upon the required specification rating class for the alternative MAOP.
(1) A compressor station must be designed to limit the temperature of the nearest downstream segment
operating at alternative MAOP to a maximum of 120 degrees Fahrenheit (49 degrees Celsius) or the
higher temperature allowed in paragraph (h)(2) of this section unless a long-term coating integrity monitoring program is implemented in accordance with paragraph (h)(3) of this section.
(2) If research, testing and field monitoring tests demonstrate that the coating type being used will withstand a higher temperature in long-term operations, the compressor station may be designed to limit
downstream piping to that higher temperature. Test results and acceptance criteria addressing coating
adhesion, cathodic disbondment, and coating condition must be provided to each PHMSA pipeline safety
regional office where the pipeline is in service at least 60 days prior to operating above 120 degrees
Fahrenheit (49 degrees Celsius). An operator must also notify a State pipeline safety authority when the
pipeline is located in a State where PHMSA has an interstate agent agreement, or an intrastate pipeline
is regulated by that State.
(3) Pipeline segments operating at alternative MAOP may operate at temperatures above 120 degrees
Fahrenheit (49 degrees Celsius) if the operator implements a long-term coating integrity monitoring program. The monitoring program must include examinations using direct current voltage gradient (DCVG),
alternating current voltage gradient (ACVG), or an equivalent method of monitoring coating integrity. An
operator must specify the periodicity at which these examinations occur and criteria for repairing identified indications. An operator must submit its long-term coating integrity monitoring program to each
PHMSA pipeline safety regional office in which the pipeline is located for review before the pipeline segments may be operated at temperatures in excess of 120 degrees Fahrenheit (49 degrees Celsius). An
operator must also notify a State pipeline safety authority when the pipeline is located in a State where
PHMSA has an interstate agent agreement, or an intrastate pipeline is regulated by that State.
4. Add § 192.328 to subpart G to read
as follows:
jlentini on PROD1PC65 with RULES3
■
§ 192.328 Additional construction
requirements for steel pipe using
alternative maximum allowable operating
pressure.
For a new or existing pipeline
segment to be eligible for operation at
VerDate Aug<31>2005
20:43 Oct 16, 2008
Jkt 217001
PO 00000
Frm 00030
Fmt 4701
Sfmt 4700
the alternative maximum allowable
operating pressure calculated under
§ 192.620, a segment must meet the
following additional construction
requirements. Records must be
maintained, for the useful life of the
pipeline, demonstrating compliance
with these requirements:
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
62177
To address this construction issue:
The pipeline segment must meet this additional construction requirement:
(a) Quality assurance ......................
(1) The construction of the pipeline segment must be done under a quality assurance plan addressing pipe
inspection, hauling and stringing, field bending, welding, non-destructive examination of girth welds, applying and testing field applied coating, lowering of the pipeline into the ditch, padding and backfilling,
and hydrostatic testing.
(2) The quality assurance plan for applying and testing field applied coating to girth welds must be:
(i) Equivalent to that required under § 192.112(f)(3) for pipe; and
(ii) Performed by an individual with the knowledge, skills, and ability to assure effective coating application.
(1) All girth welds on a new pipeline segment must be non-destructively examined in accordance with
§ 192.243(b) and (c).
(1) Notwithstanding any lesser depth of cover otherwise allowed in § 192.327, there must be at least 36
inches (914 millimeters) of cover or equivalent means to protect the pipeline from outside force damage.
(2) In areas where deep tilling or other activities could threaten the pipeline, the top of the pipeline must be
installed at least one foot below the deepest expected penetration of the soil.
(1) The pipeline segment must not have experienced failures indicative of systemic material defects during
strength testing, including initial hydrostatic testing. A root cause analysis, including metallurgical examination of the failed pipe, must be performed for any failure experienced to verify that it is not indicative
of a systemic concern. The results of this root cause analysis must be reported to each PHMSA pipeline
safety regional office where the pipe is in service at least 60 days prior to operating at the alternative
MAOP. An operator must also notify a State pipeline safety authority when the pipeline is located in a
State where PHMSA has an interstate agent agreement, or an intrastate pipeline is regulated by that
State.
(1) For a new pipeline segment, the construction must address the impacts of induced alternating current
from parallel electric transmission lines and other known sources of potential interference with corrosion
control.
(b) Girth welds ................................
(c) Depth of cover ...........................
(d) Initial strength testing ................
(e) Interference currents .................
5. Amend § 192.611 by revising
paragraph (a)(1) and (a)(3)(i) and (ii) and
adding new paragraph (a)(3)(iii) to read
as follows:
■
jlentini on PROD1PC65 with RULES3
§ 192.611 Change in class location:
Confirmation or revision of maximum
allowable operating pressure.
(a) * * *
(1) If the segment involved has been
previously tested in place for a period
of not less than 8 hours:
(i) The maximum allowable operating
pressure is 0.8 times the test pressure in
Class 2 locations, 0.667 times the test
pressure in Class 3 locations, or 0.555
times the test pressure in Class 4
locations. The corresponding hoop
stress may not exceed 72 percent of the
SMYS of the pipe in Class 2 locations,
60 percent of SMYS in Class 3 locations,
or 50 percent of SMYS in Class 4
locations.
(ii) The alternative maximum
allowable operating pressure is 0.8
times the test pressure in Class 2
locations and 0.667 times the test
pressure in Class 3 locations. For
pipelines operating at alternative
maximum allowable pressure per
§ 192.620, the corresponding hoop stress
may not exceed 80 percent of the SMYS
of the pipe in Class 2 locations and 67
percent of SMYS in Class 3 locations.
*
*
*
*
*
(3) * * *
(i) The maximum allowable operating
pressure after the requalification test is
0.8 times the test pressure for Class 2
locations, 0.667 times the test pressure
for Class 3 locations, and 0.555 times
the test pressure for Class 4 locations.
VerDate Aug<31>2005
20:43 Oct 16, 2008
Jkt 217001
(ii) The corresponding hoop stress
may not exceed 72 percent of the SMYS
of the pipe in Class 2 locations, 60
percent of SMYS in Class 3 locations, or
50 percent of SMYS in Class 4 locations.
(iii) For pipeline operating at an
alternative maximum allowable
operating pressure per § 192.620, the
alternative maximum allowable
operating pressure after the
requalification test is 0.8 times the test
pressure for Class 2 locations and 0.667
times the test pressure for Class 3
locations. The corresponding hoop
stress may not exceed 80 percent of the
SMYS of the pipe in Class 2 locations
and 67 percent of SMYS in Class 3
locations.
*
*
*
*
*
6. Amend § 192.619 by revising
paragraph (a) introductory text and by
adding paragraph (d) to read as follows:
§ 192.620 Alternative maximum allowable
operating pressure for certain steel
pipelines.
(a) How does an operator calculate
the alternative maximum allowable
operating pressure? An operator
calculates the alternative maximum
allowable operating pressure by using
different factors in the same formulas
used for calculating maximum
allowable operating pressure under
§ 192.619(a) as follows:
(1) In determining the alternative
design pressure under § 192.105, use a
design factor determined in accordance
with § 192.111(b), (c), or (d) or, if none
of these paragraphs apply, in
accordance with the following table:
Class location
■
§ 192.619 Maximum allowable operating
pressure: Steel or plastic pipelines.
(a) No person may operate a segment
of steel or plastic pipeline at a pressure
that exceeds a maximum allowable
operating pressure determined under
paragraph (c) or (d) of this section, or
the lowest of the following:
*
*
*
*
*
(d) The operator of a pipeline segment
of steel pipeline meeting the conditions
prescribed in § 192.620(b) may elect to
operate the segment at a maximum
allowable operating pressure
determined under § 192.620(a).
7. Add § 192.620 to subpart L to read
as follows:
■
PO 00000
Frm 00031
Fmt 4701
Sfmt 4700
1 ............................................
2 ............................................
3 ............................................
Alternative design factor (F)
0.80
0.67
0.56
(i) For facilities installed prior to
November 17, 2008, for which
§ 192.111(b), (c), or (d) apply, use the
following design factors as alternatives
for the factors specified in those
paragraphs: § 192.111(b)—0.67 or less;
192.111(c) and (d)—0.56 or less.
(ii) [Reserved]
(2) The alternative maximum
allowable operating pressure is the
lower of the following:
(i) The design pressure of the weakest
element in the pipeline segment,
determined under subparts C and D of
this part.
(ii) The pressure obtained by dividing
the pressure to which the pipeline
segment was tested after construction by
E:\FR\FM\17OCR3.SGM
17OCR3
62178
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
in a State where PHMSA has an
interstate agent agreement, or an
intrastate pipeline is regulated by that
Alternative test State; and
Class location
factor
(7) At least 95 percent of girth welds
on a segment that was constructed prior
1 ............................................
1.25
to November 17, 2008, must have been
1 1.50
2 ............................................
3 ............................................
1.50 non-destructively examined in
accordance with § 192.243(b) and (c).
1 For Class 2 alternative maximum allowable
(c) What is an operator electing to use
operating pressure segments installed prior to the alternative maximum allowable
November 17, 2008, the alternative test factor
operating pressure required to do? If an
is 1.25.
operator elects to use the alternative
(b) When may an operator use the
maximum allowable operating pressure
alternative maximum allowable
calculated under paragraph (a) of this
operating pressure calculated under
section for a pipeline segment, the
paragraph (a) of this section? An
operator must do each of the following:
operator may use an alternative
(1) Notify each PHMSA pipeline
maximum allowable operating pressure
safety regional office where the pipeline
calculated under paragraph (a) of this
is in service of its election with respect
section if the following conditions are
to a segment at least 180 days before
met:
operating at the alternative maximum
(1) The pipeline segment is in a Class
allowable operating pressure. An
1, 2, or 3 location;
operator must also notify a State
(2) The pipeline segment is
pipeline safety authority when the
constructed of steel pipe meeting the
pipeline is located in a State where
additional design requirements in
PHMSA has an interstate agent
§ 192.112;
agreement, or an intrastate pipeline is
(3) A supervisory control and data
regulated by that State.
acquisition system provides remote
(2) Certify, by signature of a senior
monitoring and control of the pipeline
executive officer of the company, as
segment. The control provided must
follows:
include monitoring of pressures and
(i) The pipeline segment meets the
flows, monitoring compressor start-ups
conditions described in paragraph (b) of
and shut-downs, and remote closure of
this section; and
valves;
(ii) The operating and maintenance
(4) The pipeline segment meets the
procedures include the additional
additional construction requirements
operating and maintenance
described in § 192.328;
requirements of paragraph (d) of this
(5) The pipeline segment does not
section; and
contain any mechanical couplings used
(iii) The review and any needed
in place of girth welds;
program upgrade of the damage
(6) If a pipeline segment has been
prevention program required by
previously operated, the segment has
paragraph (d)(4)(v) of this section has
not experienced any failure during
been completed.
normal operations indicative of a
(3) Send a copy of the certification
systemic fault in material as determined required by paragraph (c)(2) of this
by a root cause analysis, including
section to each PHMSA pipeline safety
metallurgical examination of the failed
regional office where the pipeline is in
pipe. The results of this root cause
service 30 days prior to operating at the
analysis must be reported to each
alternative MAOP. An operator must
PHMSA pipeline safety regional office
also send a copy to a State pipeline
where the pipeline is in service at least
safety authority when the pipeline is
60 days prior to operation at the
located in a State where PHMSA has an
alternative MAOP. An operator must
interstate agent agreement, or an
also notify a State pipeline safety
intrastate pipeline is regulated by that
authority when the pipeline is located
State.
a factor determined in the following
table:
jlentini on PROD1PC65 with RULES3
To address increased risk of a
maximum allowable operating pressure based on higher stress levels
in the following areas:
(1) Identifying
threats.
and
evaluating
(2) Notifying the public ....................
VerDate Aug<31>2005
20:43 Oct 16, 2008
(4) For each pipeline segment, do one
of the following:
(i) Perform a strength test as described
in § 192.505 at a test pressure calculated
under paragraph (a) of this section or
(ii) For a pipeline segment in
existence prior to November 17, 2008,
certify, under paragraph (c)(2) of this
section, that the strength test performed
under § 192.505 was conducted at a test
pressure calculated under paragraph (a)
of this section, or conduct a new
strength test in accordance with
paragraph (c)(4)(i) of this section.
(5) Comply with the additional
operation and maintenance
requirements described in paragraph (d)
of this section.
(6) If the performance of a
construction task associated with
implementing alternative MAOP can
affect the integrity of the pipeline
segment, treat that task as a ‘‘covered
task’’, notwithstanding the definition in
§ 192.801(b) and implement the
requirements of subpart N as
appropriate.
(7) Maintain, for the useful life of the
pipeline, records demonstrating
compliance with paragraphs (b), (c)(6),
and (d) of this section.
(8) A Class 1 and Class 2 pipeline
location can be upgraded one class due
to class changes per § 192.611(a)(3)(i).
All class location changes from Class 1
to Class 2 and from Class 2 to Class 3
must have all anomalies evaluated and
remediated per: The ‘‘original pipeline
class grade’’ § 192.620(d)(11) anomaly
repair requirements; and all anomalies
with a wall loss equal to or greater than
40 percent must be excavated and
remediated. Pipelines in Class 4 may
not operate at an alternative MAOP.
(d) What additional operation and
maintenance requirements apply to
operation at the alternative maximum
allowable operating pressure? In
addition to compliance with other
applicable safety standards in this part,
if an operator establishes a maximum
allowable operating pressure for a
pipeline segment under paragraph (a) of
this section, an operator must comply
with the additional operation and
maintenance requirements as follows:
Take the following additional step:
Develop a threat matrix consistent with § 192.917 to do the following:
(i) Identify and compare the increased risk of operating the pipeline at the increased stress level under this
section with conventional operation; and
(ii) Describe and implement procedures used to mitigate the risk.
(i) Recalculate the potential impact circle as defined in § 192.903 to reflect use of the alternative maximum
operating pressure calculated under paragraph (a) of this section and pipeline operating conditions; and
(ii) In implementing the public education program required under § 192.616, perform the following:
Jkt 217001
PO 00000
Frm 00032
Fmt 4701
Sfmt 4700
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
To address increased risk of a
maximum allowable operating pressure based on higher stress levels
in the following areas:
(3) Responding to an emergency in
an area defined as a high consequence area in § 192.903.
(4) Protecting the right-of-way ........
(5) Controlling internal corrosion ....
(6) Controlling interference that can
impact external corrosion.
jlentini on PROD1PC65 with RULES3
(7) Confirming external corrosion
control through indirect assessment.
VerDate Aug<31>2005
19:47 Oct 16, 2008
62179
Take the following additional step:
(A) Include persons occupying property within 220 yards of the centerline and within the potential impact
circle within the targeted audience; and
(B) Include information about the integrity management activities performed under this section within the
message provided to the audience.
(i) Ensure that the identification of high consequence areas reflects the larger potential impact circle recalculated under paragraph (d)(1)(i) of this section.
(ii) If personnel response time to mainline valves on either side of the high consequence area exceeds one
hour (under normal driving conditions and speed limits) from the time the event is identified in the control
room, provide remote valve control through a supervisory control and data acquisition (SCADA) system,
other leak detection system, or an alternative method of control.
(iii) Remote valve control must include the ability to close and monitor the valve position (open or closed),
and monitor pressure upstream and downstream.
(iv) A line break valve control system using differential pressure, rate of pressure drop or other widely-accepted method is an acceptable alternative to remote valve control.
(i) Patrol the right-of-way at intervals not exceeding 45 days, but at least 12 times each calendar year, to
inspect for excavation activities, ground movement, wash outs, leakage, or other activities or conditions
affecting the safety operation of the pipeline.
(ii) Develop and implement a plan to monitor for and mitigate occurrences of unstable soil and ground
movement.
(iii) If observed conditions indicate the possible loss of cover, perform a depth of cover study and replace
cover as necessary to restore the depth of cover or apply alternative means to provide protection equivalent to the originally-required depth of cover.
(iv) Use line-of-sight line markers satisfying the requirements of § 192.707(d) except in agricultural areas,
large water crossings or swamp, steep terrain, or where prohibited by Federal Energy Regulatory Commission orders, permits, or local law.
(v) Review the damage prevention program under § 192.614(a) in light of national consensus practices, to
ensure the program provides adequate protection of the right-of-way. Identify the standards or practices
considered in the review, and meet or exceed those standards or practices by incorporating appropriate
changes into the program.
(vi) Develop and implement a right-of-way management plan to protect the pipeline segment from damage
due to excavation activities.
(i) Develop and implement a program to monitor for and mitigate the presence of, deleterious gas stream
constituents.
(ii) At points where gas with potentially deleterious contaminants enters the pipeline, use filter separators
or separators and gas quality monitoring equipment.
(iii) Use gas quality monitoring equipment that includes a moisture analyzer, chromatograph, and periodic
hydrogen sulfide sampling.
(iv) Use cleaning pigs and inhibitors, and sample accumulated liquids when corrosive gas is present.
(v) Address deleterious gas stream constituents as follows:
(A) Limit carbon dioxide to 3 percent by volume;
(B) Allow no free water and otherwise limit water to seven pounds per million cubic feet of gas; and
(C) Limit hydrogen sulfide to 1.0 grain per hundred cubic feet (16 ppm) of gas, where the hydrogen sulfide
is greater than 0.5 grain per hundred cubic feet (8 ppm) of gas, implement a pigging and inhibitor injection program to address deleterious gas stream constituents, including follow-up sampling and quality
testing of liquids at receipt points.
(vi) Review the program at least quarterly based on the gas stream experience and implement adjustments
to monitor for, and mitigate the presence of, deleterious gas stream constituents.
(i) Prior to operating an existing pipeline segment at an alternate maximum allowable operating pressure
calculated under this section, or within six months after placing a new pipeline segment in service at an
alternate maximum allowable operating pressure calculated under this section, address any interference
currents on the pipeline segment.
(ii) To address interference currents, perform the following:
(A) Conduct an interference survey to detect the presence and level of any electrical current that could impact external corrosion where interference is suspected;
(B) Analyze the results of the survey; and
(C) Take any remedial action needed within 6 months after completing the survey to protect the pipeline
segment from deleterious current.
(i) Within six months after placing the cathodic protection of a new pipeline segment in operation, or within
six months after certifying a segment under § 192.620(c)(1) of an existing pipeline segment under this
section, assess the adequacy of the cathodic protection through an indirect method such as close-interval survey, and the integrity of the coating using direct current voltage gradient (DCVG) or alternating
current voltage gradient (ACVG).
(ii) Remediate any construction damaged coating with a voltage drop classified as moderate or severe (IR
drop greater than 35% for DCVG or 50 dBµv for ACVG) under section 4 of NACE RP–0502–2002 (incorporated by reference, see § 192.7).
(iii) Within six months after completing the baseline internal inspection required under paragraph (8) of this
section, integrate the results of the indirect assessment required under paragraph (6)(i) of this section
with the results of the baseline internal inspection and take any needed remedial actions.
(iv) For all pipeline segments in high consequence areas, perform periodic assessments as follows:
Jkt 217001
PO 00000
Frm 00033
Fmt 4701
Sfmt 4700
E:\FR\FM\17OCR3.SGM
17OCR3
62180
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
To address increased risk of a
maximum allowable operating pressure based on higher stress levels
in the following areas:
(8) Controlling external corrosion
through cathodic protection.
(9) Conducting a baseline assessment of integrity.
(10) Conducting periodic assessments of integrity.
jlentini on PROD1PC65 with RULES3
(11) Making repairs .........................
VerDate Aug<31>2005
19:47 Oct 16, 2008
Take the following additional step:
(A) Conduct periodic close interval surveys with current interrupted to confirm voltage drops in association
with periodic assessments under subpart O of this part.
(B) Locate pipe-to-soil test stations at half-mile intervals within each high consequence area ensuring at
least one station is within each high consequence area, if practicable.
(C) Integrate the results with those of the baseline and periodic assessments for integrity done under paragraphs (d)(8) and (d)(9) of this section.
(i) If an annual test station reading indicates cathodic protection below the level of protection required in
subpart I of this part, complete remedial action within six months of the failed reading or notify each
PHMSA pipeline safety regional office where the pipeline is in service demonstrating that the integrity of
the pipeline is not compromised if the repair takes longer than 6 months. An operator must also notify a
State pipeline safety authority when the pipeline is located in a State where PHMSA has an interstate
agent agreement, or an intrastate pipeline is regulated by that State; and
(ii) After remedial action to address a failed reading, confirm restoration of adequate corrosion control by a
close interval survey on either side of the affected test station to the next test station.
(iii) If the pipeline segment has been in operation, the cathodic protection system on the pipeline segment
must have been operational within 12 months of the completion of construction.
(i) Except as provided in paragraph (d)(8)(iii) of this section, for a new pipeline segment operating at the
new alternative maximum allowable operating pressure, perform a baseline internal inspection of the entire pipeline segment as follows:
(A) Assess using a geometry tool after the initial hydrostatic test and backfill and within six months after
placing the new pipeline segment in service; and
(B) Assess using a high resolution magnetic flux tool within three years after placing the new pipeline segment in service at the alternative maximum allowable operating pressure.
(ii) Except as provided in paragraph (d)(8)(iii) of this section, for an existing pipeline segment, perform a
baseline internal assessment using a geometry tool and a high resolution magnetic flux tool before, but
within two years prior to, raising pressure to the alternative maximum allowable operating pressure as allowed under this section.
(iii) If headers, mainline valve by-passes, compressor station piping, meter station piping, or other short
portion of a pipeline segment operating at alternative maximum allowable operating pressure cannot accommodate a geometry tool and a high resolution magnetic flux tool, use direct assessment (per
§ 192.925, § 192.927 and/or § 192.929) or pressure testing (per subpart J of this part) to assess that portion.
(i) Determine a frequency for subsequent periodic integrity assessments as if all the alternative maximum
allowable operating pressure pipeline segments were covered by subpart O of this part and
(ii) Conduct periodic internal inspections using a high resolution magnetic flux tool on the frequency determined under paragraph (d)(9)(i) of this section, or
(iii) Use direct assessment (per § 192.925, § 192.927 and/or § 192.929) or pressure testing (per subpart J
of this part) for periodic assessment of a portion of a segment to the extent permitted for a baseline assessment under paragraph (d)(8)(iii) of this section.
(i) Perform the following when evaluating an anomaly:
(A) Use the most conservative calculation for determining remaining strength or an alternative validated
calculation based on pipe diameter, wall thickness, grade, operating pressure, operating stress level,
and operating temperature: and
(B) Take into account the tolerances of the tools used for the inspection.
(ii) Repair a defect immediately if any of the following apply:
(A) The defect is a dent discovered during the baseline assessment for integrity under paragraph (d)(8) of
this section and the defect meets the criteria for immediate repair in § 192.309(b).
(B) The defect meets the criteria for immediate repair in § 192.933(d).
(C) The alternative maximum allowable operating pressure was based on a design factor of 0.67 under
paragraph (a) of this section and the failure pressure is less than 1.25 times the alternative maximum allowable operating pressure.
(D) The alternative maximum allowable operating pressure was based on a design factor of 0.56 under
paragraph (a) of this section and the failure pressure is less than or equal to 1.4 times the alternative
maximum allowable operating pressure.
(iii) If paragraph (d)(10)(ii) of this section does not require immediate repair, repair a defect within one year
if any of the following apply:
(A) The defect meets the criteria for repair within one year in § 192.933(d).
(B) The alternative maximum allowable operating pressure was based on a design factor of 0.80 under
paragraph (a) of this section and the failure pressure is less than 1.25 times the alternative maximum allowable operating pressure.
(C) The alternative maximum allowable operating pressure was based on a design factor of 0.67 under
paragraph (a) of this section and the failure pressure is less than 1.50 times the alternative maximum allowable operating pressure.
(D) The alternative maximum allowable operating pressure was based on a design factor of 0.56 under
paragraph (a) of this section and the failure pressure is less than or equal to 1.80 times the alternative
maximum allowable operating pressure.
(iv) Evaluate any defect not required to be repaired under paragraph (d)(10)(ii) or (iii) of this section to determine its growth rate, set the maximum interval for repair or re-inspection, and repair or re-inspect
within that interval.
Jkt 217001
PO 00000
Frm 00034
Fmt 4701
Sfmt 4700
E:\FR\FM\17OCR3.SGM
17OCR3
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 / Rules and Regulations
jlentini on PROD1PC65 with RULES3
(e) Is there any change in overpressure
protection associated with operating at
the alternative maximum allowable
operating pressure? Notwithstanding
the required capacity of pressure
relieving and limiting stations otherwise
required by § 192.201, if an operator
establishes a maximum allowable
operating pressure for a pipeline
VerDate Aug<31>2005
19:47 Oct 16, 2008
Jkt 217001
segment in accordance with paragraph
(a) of this section, an operator must:
(1) Provide overpressure protection
that limits mainline pressure to a
maximum of 104 percent of the
maximum allowable operating pressure;
and
(2) Develop and follow a procedure
for establishing and maintaining
PO 00000
Frm 00035
Fmt 4701
Sfmt 4700
62181
accurate set points for the supervisory
control and data acquisition system.
Issued in Washington, DC, on October 2,
2008.
Carl T. Johnson,
Administrator.
[FR Doc. E8–23915 Filed 10–16–08; 8:45 am]
BILLING CODE 4910–60–P
E:\FR\FM\17OCR3.SGM
17OCR3
Agencies
[Federal Register Volume 73, Number 202 (Friday, October 17, 2008)]
[Rules and Regulations]
[Pages 62148-62181]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-23915]
[[Page 62147]]
-----------------------------------------------------------------------
Part V
Department of Transportation
-----------------------------------------------------------------------
Pipeline and Hazardous Materials Safety Administration
-----------------------------------------------------------------------
49 CFR Part 192
Pipeline Safety: Standards for Increasing the Maximum Allowable
Operating Pressure for Gas Transmission Pipelines; Final Rule
Federal Register / Vol. 73, No. 202 / Friday, October 17, 2008 /
Rules and Regulations
[[Page 62148]]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Pipeline and Hazardous Materials Safety Administration
49 CFR Part 192
[Docket No. PHMSA-2005-23447]
RIN 2137-AE25
Pipeline Safety: Standards for Increasing the Maximum Allowable
Operating Pressure for Gas Transmission Pipelines
AGENCY: Pipeline and Hazardous Materials Safety Administration (PHMSA),
Department of Transportation (DOT).
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: PHMSA is amending the pipeline safety regulations to prescribe
safety requirements for the operation of certain gas transmission
pipelines at pressures based on higher operating stress levels. The
result is an increase of maximum allowable operating pressure (MAOP)
over that currently allowed in the regulations. Improvements in
pipeline technology assessment methodology, maintenance practices, and
management processes over the past twenty-five years have significantly
reduced the risk of failure in pipelines and necessitate updating the
standards that govern the MAOP. This rule will generate significant
public benefits by reducing the number and consequences of potential
incidents and boosting the potential capacity and efficiency of
pipeline infrastructure, while promoting rigorous life-cycle
maintenance and investment in improved pipe technology.
DATES: Effective Date: This final rule takes effect November 17, 2008.
Incorporation by Reference Date: The incorporation by reference of
a certain publication listed in this rule is approved by the Director
of the Federal Register as of November 17, 2008.
FOR FURTHER INFORMATION CONTACT: Alan Mayberry by phone at (202) 366-
5124, or by e-mail at alan.mayberry@dot.gov.
SUPPLEMENTARY INFORMATION:
Table of Contents
A. Purpose of the Rulemaking
B. Background
B.1. Current Regulations
B.2. Evolution in Views on Pressure
B.3. History of PHMSA Consideration
B.4. Safety Conditions in Special Permits
B.5. Codifying the Special Permit Standards
B.6. How to Handle Special Permits and Requests for Special
Permits
B.7. Statutory Considerations
C. Comments on the NPRM
C.1. General Comments
C.2. Comments on Specific Provisions in the Proposed Rule
C.2.1. Section 192.7, Incorporation by Reference
C.2.2. Design Requirements
C.2.3. Construction Requirements
C.2.4. Eligibility for and Implementing Alternative MAOP
C.2.5. Operation and Maintenance Requirements
C.3. Comments on Regulatory Analysis
D. Consideration by the Technical Pipeline Safety Standards
Committee
E. The Final Rule
E.1. In General
E.2. Amendment to Sec. 192.7--Incorporation by Reference
E.3. New Sec. 192.112--Additional Design Requirements
E.4. New Sec. 192.328--Additional Construction Requirements
E.5. Amendment to Sec. 192.611--Change in Class Location:
Confirmation or Revision of Maximum Operating Pressure
E.6. Amendment to Sec. 192.619--Maximum Allowable Operating
Pressure
E.7. New Sec. 192.620--Operation at an Alternative MAOP
E.7.1. Sec. 192.620(a)--Calculating the Alternative MAOP
E.7.2. Sec. 192.620(b)--Which Pipelines Qualify
E.7.3. Sec. Sec. 192.620(c)(1), (2), and (3)--How an Operator
Selects Operation Under This Section
E.7.4. Sec. 192.620(c)(4)--Initial Strength Testing
E.7.5. Sec. 192.620(c)(5)--Operation and Maintenance
E.7.6. Sec. 192.620(c)(6)--New Construction and Maintenance
Tasks
E.7.7. Sec. 192.620(c)(7)--Recordkeeping
E.7.8. Sec. 192.620(c)(8)--Class Upgrades
E.8. Sec. 192.620(d)--Additional Operation and Maintenance
Requirements
E.8.1. Sec. 192.620(d)(1)--Threat Assessments
E.8.2. Sec. 192.620(d)(1)--Public Awareness
E.8.3. Sec. 192.620(d)(2)--Emergency Response
E.8.4. Sec. 192.620(d)(3)--Damage Prevention
E.8.5. Sec. 192.620(d)(4)--Internal Corrosion Control
E.8.6. Sec. Sec. 192.620(d)(5), (6), and (7)--External
Corrosion Control
E.8.7. Sec. Sec. 192.620(d)(8) and (9)--Integrity Assessments
E.8.8. Sec. 192.620(d)(10)--Repair Criteria
E.9. Sec. 192.620(e)--Overpressure Protection--Proposed Sec.
192.620(e)
F. Regulatory Analyses and Notices
F.1. Privacy Act Statement
F.2. Executive Order 12866 and DOT Policies and Procedures
F.3. Regulatory Flexibility Act
F.4. Executive Order 13175
F.5. Paperwork Reduction Act
F.6. Unfunded Mandates Reform Act of 1995
F.7. National Environmental Policy Act
F.8. Executive Order 13132
F.9. Executive Order 13211
A. Purpose of the Rulemaking
PHMSA published a Notice of Proposed Rulemaking (NPRM) on March 12,
2008 (73 FR 13167), to establish standards under which certain natural
or other gas (gas) transmission pipelines would be allowed to operate
at higher maximum allowable operating pressure (MAOP). The proposed
changes were made possible by dramatic improvements in pipeline
technology and risk controls over the past 25 years. The current
standards for calculating MAOP on gas transmission pipelines were
adopted in 1970, in the original pipeline safety regulations
promulgated under Federal law. Almost all risk controls on gas
transmission pipelines have been strengthened in the intervening years,
beginning with the introduction of improved manufacturing, metallurgy,
testing, and assessment tools and standards. Pipe manufactured and
tested to modern standards is far less likely to contain defects that
can grow to failure over time than pipe manufactured and installed a
generation ago. Likewise, modern maintenance practices, if consistently
followed, significantly reduce the risk that corrosion, or other
defects affecting pipeline integrity, will develop in installed
pipelines. Most recently, operators' development and implementation of
integrity management programs have increased understanding about the
condition of pipelines and how to reduce pipeline risks. In view of
these developments, PHMSA concludes that certain gas transmission
pipelines can be safely and reliably operated at pressures above
current Federal pipeline safety design limits. With appropriate
conditions and controls, permitting operation at higher pressures will
increase energy capacity and efficiency without diminishing system
safety.
Currently, PHMSA has granted special permits on a case-by-case
basis to allow operation of particular pipeline segments at a higher
MAOP than currently allowed under the existing design requirements.
These special permits, that have been granted, have been limited to
operation in Class 1, 2, and 3 locations and conditioned on
demonstrated rigor in the pipeline's design and construction and the
operator's performance of additional safety measures. Building on the
record of success developed in the special permit proceedings, PHMSA is
codifying the conditions and limitations of the special permits into
standards of general applicability.
B. Background
B.1. Current Regulations
The design factor specified in Sec. 192.105 restricts the MAOP of
a steel
[[Page 62149]]
gas transmission pipeline based on stress levels and class location.
For most steel pipelines, the MAOP is defined in Sec. 192.619 based on
design pressure calculated using a formula, found at Sec. 192.111,
which includes the design factor. The regulations establish four
classifications based on population density, ranging from Class 1
(undeveloped, rural land) through Class 4 (densely populated urban
areas). In sparsely populated Class 1 locations, the design factor
specified in Sec. 192.105 restricts the stress level at which a
pipeline can be operated to 72 percent of the specified minimum yield
strength (SMYS) of the steel. The operating pressures in more populated
Class 2 and Class 3 locations are limited to 60 and 50 percent of SMYS,
respectively. Paragraph (c) of Sec. 192.619 provides an exception to
this calculation of MAOP for pipelines built before the issuance of the
Federal pipeline safety standards. A pipeline that is ``grandfathered''
under this section may be operated at a stress level exceeding 72
percent of SMYS if it was operated at that pressure for five years
prior to July 1, 1970.
Part 192 also prescribes safety standards for designing,
constructing, operating, and maintaining steel pipelines used to
transport gas. Although these standards have always included several
requirements for initial and periodic testing and inspection, prior to
2003, part 192 contained no Federal requirements for internal
inspection of existing pipelines. Internal inspection is performed
using a tool known as an ``instrumented pig'' (or ``smart pig''). Many
pipelines constructed before the advent of this technology cannot
accommodate an instrumented pig and, accordingly, cannot be inspected
internally. Beginning in 1994, PHMSA required operators to design new
pipelines so that they could accommodate instrumented pigs, paving the
way for internal inspection (59 FR 17281; Apr. 12, 1994).
In December 2003, PHMSA adopted its gas transmission integrity
management rule, requiring operators to develop and implement plans to
extend additional protections, including internal inspection, to
pipelines located in ``high consequence areas'' (HCAs) (68 FR 69816).
Integrity management programs, as required by subpart O of part 192,
include threat assessments, both baseline and periodic internal
inspection, pressure testing, or direct assessment (DA), and additional
measures designed to prevent and mitigate pipeline failures and their
consequences. AN HCA, as defined in Sec. 192.903, is a geographic
territory in which, by virtue of its population density and proximity
to a pipeline, a pipeline failure would pose a higher risk to people.
In addition to class location, one of the criteria for identifying an
HCA is a potential impact circle surrounding a pipeline. The
calculation of the circle includes a factor for the MAOP, with the
result that a higher MAOP results in a larger impact circle.
B.2. Evolution in Views on Pressure
Absent any defects, and with proper maintenance and management
practices, steel pipe can last for many decades in gas service.
However, the manufacture of the steel or rolling of the pipe can
introduce flaws. In addition, during construction, improper backfilling
can damage the pipe and pipe coating. Over time, damaged coating
unchecked can allow corrosion to continue and cause leaks. Excavation-
related damage can produce an immediate pipeline failure or leave a
dent or coating damage that could grow to failure over time.
The regulations on MAOP in part 192 have their origin in
engineering standards developed in the 1950s, when industry had
relatively limited information about the material properties of pipe
and limited ability to evaluate a pipeline's integrity during its
operating lifetime. Early pipeline codes allowed maximum operating
pressures to be set at a fixed amount under the pressure of the initial
strength test without regard to SMYS. Pipeline engineers developing
consensus standards looked for ways to lengthen the time before defects
initiated during manufacture, construction, or operation could grow to
failure. Their solutions focused on tests done at the mill to evaluate
the ability of the pipe to contain pressure during operation. They
added an additional factor to the hydrostatic test pressure of the mill
test. At the time during the 1950's, the consensus standard, known as
the B31.8 Code, used this conservative margin of safety for gas pipe
design. A 25 percent margin of safety translated into a design factor
limiting stress level to 72 percent of SMYS in rural areas.
Specifically, the MAOP of 72 percent of SMYS comes from dividing the
typical maximum mill test pressure of 90 percent of SMYS by 1.25. When
issuing the first Federal pipeline safety regulations in 1970,
regulators incorporated this design factor, as found in the 1968
edition of the B31.8 Code, into the requirements for determining the
MAOP.
Even as the Federal regulations were being developed, some
technical support existed for operation at a higher stress level,
provided initial strength testing resulted in operators removing
defects. In 1968, the American Gas Association published Report No.
L30050 entitled Study of Feasibility of Basing Natural Gas Pipeline
Operating Pressure on Hydrostatic Test Pressure prepared by the
Battelle Memorial Institute. The research study concluded that:
It is inherently safer to base the MAOP on the test
pressure, which demonstrates the actual in-place yield strength of the
pipeline, than to base it on SMYS alone.
High pressure hydrostatic testing is able to remove
defects that may fail in service.
Hydrostatic testing to actual yield, as determined with a
pressure-volume plot, does not damage a pipeline.
The report specifically recommended setting the MAOP as a
percentage of the field test pressure. In particular, it recommended
setting the MAOP at 80 percent of the test pressure when the minimum
test pressure was 90 percent of SMYS or higher. Although the committee
responsible for the B31.8 Code received the report, the committee
deferred consideration of its findings at that time because the Federal
regulators had already begun the process to incorporate the 1968
edition of the B31.8 Code into the Federal pipeline safety standards.
More than a decade later, the committee responsible for development
of the B31.8 Code, now under the auspices of the American Society of
Mechanical Engineers (ASME), revisited the question of the design
factor it had deferred in the late 1960s. The committee determined
pipelines could operate safely at stress levels up to 80 percent of
SMYS. ASME updated the design factors in a 1990 addendum to the 1989
edition of the B31.8 Code, and they remain in the current edition.
Although part 192 incorporates parts of the B31.8 Code by reference, it
does not incorporate the updated design factors. With the benefit of
operating experience with pipelines, it seems clear that operating
pressure plays a less critical role in pipeline integrity and failure
consequence than other factors within the operator's control.
By any measure, new technologies and risk controls have had a far
greater impact on pipeline safety and integrity. A great deal of
progress has occurred in the manufacture of steel pipe and in its
initial inspection and testing. Technological advances in metallurgy
and pipe manufacture decrease the risk of incipient flaws occurring and
going undetected during manufacture. The detailed standards now
followed in steel and pipe manufacturing provide
[[Page 62150]]
engineers considerable information about their material properties.
Toughness standards make new steel pipe more likely to resist fracture
and to survive mechanical damage. Knowledge about the material
properties allows engineers to predict how quickly flaws, whether
inherent or introduced during construction or operation, will grow to
failure under known operating conditions.
Initial inspection and hydrostatic testing of pipelines allow
operators to discover flaws that have occurred prior to operation, such
as during transportation or construction. They also serve to validate
the integrity of the pipeline before operation. Initial pressure
testing causes longitudinal and some other flaws introduced during
manufacture, transportation, or construction to grow to the point of
failure. Initial pressure testing detects all but one type of
manufacturing or construction defect that could cause failure in the
near-term. The sole type of defect that pressure testing may not
identify, a flaw in a girth weld, is detectable through pre-operational
non-destructive testing, which is required in this rule.
The most common defects initiated during operation are caused by
mechanical damage or corrosion. Improvements in technology have
resulted in internal inspection techniques that provide operators a
significant amount of information about defects. Although there is
significant variance in the capability of the tools used for internal
inspections, each provides the operator information about flaws in the
pipeline that an operator would not otherwise have. An operator can
then examine these flaws to determine whether they are defects
requiring repair. In addition, internal inspections with in-line
inspection (ILI) devices, unlike pressure testing, are not destructive
and can be done while the pipeline is in operation. Initial internal
inspection establishes a baseline. Operators can use subsequent
internal inspections at appropriate intervals to monitor for changes in
flaws already discovered or to find new flaws requiring repair or
monitoring. Internal inspections, and other improved life-cycle
management practices, increase the likelihood operators will detect any
flaws that remain in the pipe after initial inspection and testing, or
that develop after construction, well before the flaws grow to failure.
B.3. History of PHMSA Consideration
Although the agency had never formally revisited its part 192 MAOP
standards, prior to this rulemaking, developments in related arenas
have increasingly set the stage for changes to those standards.
Grandfathered pipelines have operated successfully at higher stress
levels in the United States during more than 35 years of Federal safety
regulation. Many of these grandfathered pipelines have operated at
higher stress levels for more than 50 years without a higher rate of
failure. We have also been aware of pipelines outside the United States
operating successfully at the higher stress levels permitted under the
ASME standard. A technical study published in December 2000 by R.J.
Eiber, M. McLamb, and W.B. McGehee, Quantifying Pipeline Design at 72%
SMYS as a Precursor to Increasing the Design Stress Level, GRI-00/0233,
further raised interest in the issue.
In connection with our issuance of the 2003 gas transmission
integrity management regulations, PHMSA announced a policy to grant
``class location'' waivers (now called special permits) to operators
demonstrating an alternative integrity management program for the
affected pipeline. A ``class location'' waiver allows an operator to
maintain current operating pressure on a pipeline following an increase
in population that changes the class location. Absent a waiver, the
operator would have to reduce pressure or replace the pipe with thicker
walled pipe. PHMSA held a meeting on April 14-15, 2004, to discuss the
criteria for the waivers. In a notice seeking public involvement in the
process (69 FR 22116; Apr. 23, 2004), PHMSA announced:
Waivers will only be granted when pipe condition and active
integrity management provides a level of safety greater than or
equal to a pipe replacement or pressure reduction.
A second notice (69 FR 38948; June 29, 2004) announced the
criteria. The criteria included the use of high quality manufacturing
and construction processes, effective coating, and a lack of systemic
problems identified in internal inspections Although the class location
special permits/waivers do not address increases in stress levels per
se, the risk management approach developed in those cases takes account
of operating pressure and addresses many of the same concerns. The same
risk management approach, and many of the specific criteria applied in
the class location waivers, guided PHMSA's handling of the special
permits discussed below and, ultimately, this rule.
Beginning in 2005, operators began addressing the issue of stress
level directly with requests that PHMSA allow operation at the MAOP
levels that the ASME B31.8 Code would allow. With the increasing
interest, PHMSA held a public meeting on March 21, 2006, to discuss
whether to allow increased MAOP consistent with the updated ASME
standards. PHMSA also solicited technical papers on the issue. Papers
filed in response, as well as the transcript of the public meeting, are
in the docket for this rulemaking. Later in 2006, PHMSA again sought
public comment at a meeting of its advisory committee, the Technical
Pipeline Safety Standards Committee (TPSSC). The transcript and
briefing materials for the June 28, 2006, meeting are in the docket for
the advisory committee, Docket ID PHMSA-RSPA-1998-4470-204, 220. This
docket can be found at https://www.regulations.gov. Comments and papers
written during the period these efforts were undertaken overwhelmingly
supported examining increased MAOP as a way to increase energy
efficiency and capacity while maintaining safety.
B.4. Safety Conditions in Special Permits
In 2005, operators began requesting waivers, now called special
permits, to allow operation at the MAOP levels that the ASME B31.8 Code
would allow. In some cases, operators filed these requests at the same
time they were seeking approval from the Federal Energy Regulatory
Commission (FERC) to build new gas transmission pipelines. In other
cases, operators sought relief from current MAOP limits for existing
pipelines that had been built to more rigorous design and construction
standards.
In developing an approach to the requests, PHMSA examined the
operating history of lines already operated at higher stress levels.
Canadian and British standards have allowed operation at the higher
stress levels for some time. The Canadian pipeline authority, which has
allowed higher stress levels since 1973, reports the following
regarding pipelines operating at stress levels higher than 72 percent
of SMYS:
About 6,000 miles of pipelines on the Alberta system,
ranging from six to 42 inches in diameter, were installed or upgraded
between the early 1970s and 2005;
About 4,500 miles of pipelines on the Mainline system east
of the Alberta-Saskatchewan border, ranging from 20 to 42 inches in
diameter, were installed or upgraded between the early 1970s and 2005;
and,
[[Page 62151]]
More than 600 miles in the Foothills Pipe Line system,
ranging from 36 to 40 inches in diameter, were installed between 1979
and 1998.
In the United Kingdom, about 1,140 miles of the Northern pipeline
system have been uprated to operate at higher stress level in the past
ten years. Accident rates for pipelines in these countries have not
indicated a measurable increased risk from operation at these higher
operating stress levels.
In the United States, some 5,000 miles of gas transmission lines
have MAOPs that were grandfathered under Sec. 192.619(c), when the
Federal pipeline safety regulations were adopted in the early 1970s,
continue to operate at stress levels higher than 72 percent of SMYS.
After some accidents caused by corrosion on grandfathered pipelines,
PHMSA considered whether to remove the exception in Sec. 192.619(c).
In 1992, PHMSA decided to continue to allow operation at the
grandfathered pressures (57 FR 41119; Sept. 9, 1992). PHMSA based its
decision on the operating history of two of the operators whose
pipelines contained most of the mileage operated at the grandfathered
pressures. PHMSA noted the incident rate on these pipelines, operated
at stress levels above 72 percent of SMYS, was between 10 percent and
50 percent of the incident rate of pipelines operated at the lower
pressure. Texas Eastern Gas Pipeline Company (now Spectra Energy), the
operator of many of the grandfathered pipelines, attributed the lower
incident rate to aggressive inspection and maintenance. This included
initial hydrostatic testing to 100 percent of SMYS, internal
inspection, visual examination of anomalies found during internal
inspection, repair of defects, and selective pressure testing to
validate the results of the internal inspection. Internal inspection
was not in common use in the industry prior to the 1980s. PHMSA's
statistics show these pipelines continue to have an equivalent safety
record when compared with pipelines operating according to the design
factors in the pipeline safety regulations.
PHMSA also considered technical studies and required companies
seeking special permits to provide information about the pipelines'
design and construction and to specify the additional inspection and
testing to be used. PHMSA also considered how to handle findings that
could compromise the long-term serviceability of the pipe. PHMSA
concluded that pipelines can operate safely and reliably at stress
levels up to 80 percent of SMYS if the pipeline has well-established
metallurgical properties and can be managed to protect it against known
threats, such as corrosion and mechanical damage.
Early and vigilant corrosion protection reduces the possibility of
corrosion occurring. At the earliest stage, this includes care in
applying a protective coating before transporting the pipe to the
right-of-way. With the newer coating materials and careful application,
coating provides considerable protection against external corrosion and
facilitates the application of induced current, commonly called
cathodic protection, to prevent corrosion from developing at any breaks
that may occur in the coating. Regularly monitoring the level of
protection and addressing any low readings will detect and correct
conditions that can cause corrosion at an early stage. Vigilant
corrosion protection includes close attention to operating conditions
that lead to internal corrosion, such as poor gas quality. In addition,
for new pipelines, operators' compliance with a rule issued last year
requiring greater attention to internal corrosion protection during
design and construction (72 FR 20059; Apr. 23, 2007) will prevent
internal corrosion. Finally, corrosion protection includes internal
inspection and other assessment techniques for early detection of both
internal and external corrosion.
One of the major causes of serious pipeline failure is mechanical
damage caused by outside forces, such as an equipment strike during
excavation activities. Burying the pipeline deeper, increased
patrolling, and additional line marking help prevent the risk that
excavation will cause mechanical damage. Further, enhanced pipe
properties increase the pipe's resistance to immediate puncture from a
single equipment strike. Improved toughness increases the ability of
the pipe to withstand mechanical damage from an outside force and may
also limit any failure consequences to leaks rather than ruptures. This
toughness usually allows time for the operator to detect the damage
during internal inspection well before the pipe fails.
To evaluate each request for a special permit, PHMSA established a
docket and sought public comment on the request. We received several
public comments, most in response to the first special permits
considered. Many of the comments supported granting the special
permits. Those who were not supportive may have underestimated the
significance of the safety upgrades required for the special permits. A
few commenters raised technical concerns. Among these were questions
about the impact of rail crossings and blasting activities in the
vicinity of the pipeline. The special permits did not change the
current requirements where road crossings exist and added a requirement
to monitor activities, such as blasting, that could impact earth
movement. Some commenters expressed concern about the impact radius of
the pipeline operating at a higher stress level. PHMSA included
supplemental safety criteria to address the increased radius. The
remainder of the comments addressed concerns, such as compensation or
aesthetics, which were outside the scope of the special permits. PHMSA
special permits do not address issues on siting, which are governed by
the FERC.
PHMSA expects to issue seven special permits, and possibly more, in
response to these requests. In each case, PHMSA has provided oversight
to confirm the line pipe is, or will be (for pipe yet to be
constructed), as free of inherent flaws as possible, that construction
and operation do not introduce flaws, and that any flaws are detected
before they can fail. PHMSA accomplishes this by imposing a series of
conditions on the grant of special permits. The conditions imposed as
part of the special permits are designed to address the potential
additional risk involved in operating the pipeline at a higher stress
level. A proposed pipeline must be built to rigorous design and
construction standards, and the operator requesting a special permit
for an existing pipeline must demonstrate that the pipeline was built
to rigorous design and construction standards. These additional design
and construction standards focused on producing a high quality pipeline
that is free from inherent defects that could grow more rapidly under
operation at a higher stress level and is more resistant to expected
operational risks. In addition, PHMSA requires the operator of a
pipeline receiving a special permit to comply with operation and
maintenance (O&M) requirements that exceed current pipeline safety
regulations. These additional O&M and integrity management requirements
focused on the potential for corrosion and mechanical damage and on
detecting defects before the defects can grow to failure.
B.5. Codifying the Special Permit Standards
This rule puts in place a process for managing the life-cycle of a
pipeline operating at a higher stress level based on our experience
with the special permits. Integrity management focuses on managing and
extending the service
[[Page 62152]]
life of the pipeline. Life-cycle management goes beyond the operations
and maintenance practices, including integrity management, to address
steel production, pipeline manufacture, pipeline design, and
installation.
Industry experience with integrity management demonstrates the
value of life-cycle management. Through baseline assessments in
integrity management programs, gas transmission operators identified
and repaired 2,883 defects in the first three years of the program
(2004, 2005, and 2006). More than 2,000 of these were discovered in the
first two years as operators assessed their highest risk, generally
older, pipelines. In a September 2006 report, GAO-09-946, the
Government Accountability Office noted this data as an early indication
of improvement in pipeline safety. In order to qualify for operation at
higher stress levels under this rule, pipelines will be designed and
constructed under more rigorous standards. Baseline assessment of these
lines will likely uncover few defects, but removing those few defects
will result in safer pipelines. In addition, the results of the
baseline assessment will aid in evaluating anomalies discovered during
future assessments.
This rule, based on the terms and conditions of the special permits
allowing operation at higher stress levels, imposes similar terms and
conditions and limitations on operators seeking to apply the new rule.
The terms and conditions, which include meeting design standards that
go beyond current regulation, address the safety concerns related to
operating the pipeline at a higher stress level. PHMSA will step up
inspection and oversight of pipeline design and construction, in
addition to review and inspection of enhanced life-cycle management
requirements for these pipelines.
With special permits, PHMSA individually examined the design,
construction, and O&M plans for a particular pipeline before allowing
operation at a higher pressure than currently authorized. In each case,
PHMSA conditioned approval on compliance with a series of rigorous
design, construction, O&M, and management standards, including enhanced
damage prevention practices. PHMSA's experience with these requests for
special permits led to the conclusion that a rule of general
applicability is appropriate. With a rule of general applicability, the
conditions for approval are established for all without need to craft
the conditions based on individual evaluation. Thus, this rule sets
rigorous safety standards. In place of individual examination, the rule
requires senior executive certification of an operator's adherence to
the more rigorous safety standards. An operator seeking to operate at a
higher pressure than allowed by current regulation must certify that a
pipeline is built according to rigorous design and construction
standards and must agree to operate under stringent O&M standards.
After PHMSA or state pipeline safety authority (when the pipeline is
located in a state where PHMSA has an interstate agent agreement, or an
intrastate pipeline is regulated by that state) receives an operator's
certification indicating its intention to operate at a higher operating
stress level, PHMSA or the state would then follow up with the operator
to verify compliance. As with the special permits, this rule would
allow an operator to qualify both new and existing segments of pipeline
for operation at the higher MAOP, provided the operator meets the
conditions for the pipeline segment.
Several types of pipeline segments will not qualify under this
rule. These include the following:
Pipeline segments in densely populated Class 4 locations.
In addition to the increased consequences of failure in a Class 4
location, the level of activity in such a location increases the risk
of excavation damage.
Pipeline segments of grandfathered pipeline already
operating at a higher stress level but not constructed in accordance
with modern standards. Although grandfathered pipeline has been
operated successfully at the higher stress level, PHMSA or the state
would examine any further increases individually through the special
permit process.
Bare or ineffectively coated pipe. This pipe lacks the
coating needed to prevent corrosion and to make cathodic protection
effective.
Pipelines with wrinkle bends. Section 192.315(a) currently
prohibits wrinkle bends in pipeline operating at hoop stress exceeding
30 percent of SMYS.
Pipelines experiencing failures indicative of a systemic
problem, such as seam flaws, during initial hydrostatic testing. Such
pipe is more likely to have inherent defects that can grow to failure
more rapidly at higher stress levels.
Pipe manufactured by certain processes, such as low
frequency electric welding process.
Pipeline segments which cannot accommodate internal
inspection devices.
We are establishing slightly different requirements for segments
that have already been operating and those which are to be newly built.
Some variation is necessary or appropriate for an existing pipeline.
For example, the requirement for cathodically protecting pipeline
within 12 months of construction is an existing requirement for all
pipelines. A requirement for the operator of an existing pipeline
segment to prove that the segment was in fact cathodically protected
within 12 months of construction provides greater confidence in the
condition of the existing segment. Allowing proof of five percent fewer
nondestructive tests done on an existing segment at the time of
construction recognizes the possibility that some welds may not be
tested when 100 percent nondestructive testing is not required. The
overriding principle in the variation is to allow qualification of a
quality pipeline with minimal distinction. Based on our review of
requests for special permits on existing pipelines, PHMSA does not
believe the more rigorous standards we are requiring are too high for
existing segments of modern design and construction. Setting the
qualification standards lower for existing pipeline segments could
encourage operators to construct a pipeline at the lower standards and
seek to raise the operating pressure at some future date.
PHMSA acknowledges this rule may not cover all conditions
encountered by a pipeline operator. Further, operators may have
innovative alternative methods to the guidelines contained in this
rule. To that end, operators may apply to PHMSA or state pipeline
safety authority (when the pipeline is located in a state where PHMSA
has an interstate agent agreement, or an intrastate pipeline is
regulated by that state) for a special permit requesting to implement
the alternative methods.
B.6. How To Handle Special Permits and Requests for Special Permits
A number of pipeline operators have submitted requests for special
permits seeking relief from the current design requirements to allow
operation at higher stress levels. For the most part, this rule
addresses the relief requested. PHMSA has already granted many of these
under terms and conditions that may vary slightly from those in this
final rule. In some cases, the relief granted is specific to the relief
requested by the operator and extends beyond the scope of this
rulemaking. PHMSA has continued review of pending special permit
applications while working on this rulemaking, in recognition that a
final rule may not be issued by the time an operator intended to
operate its pipeline at a higher operating stress level. With the
publication of this final
[[Page 62153]]
rule, this case-by-case approach to approving operation under a special
permit at higher operating stress levels is no longer needed.
PHMSA will terminate its review of any pending applications for
special permits associated with operation at higher operating stress
levels once this final rule is issued. Operators of those pipelines
must comply with this final rule in order to operate their pipelines at
a higher alternative MAOP. PHMSA will examine special permits that have
already been granted, as appropriate, to determine if any modifications
are needed in light of safety decisions made in preparing this rule.
B.7. Statutory Considerations
Under 49 U.S.C. 60102(a), PHMSA has broad authority to issue safety
standards for the design, construction, O&M of gas transmission
pipelines. Under 49 U.S.C. 60104(b), PHMSA may not require an operator
to modify or replace existing pipelines to meet a new design or
construction standard. Although this rule includes design and
construction standards, these standards simply add more rigorous, non-
mandatory requirements. This rule does not require an operator to
modify or replace existing pipelines or to design and construct new
pipeline in accordance with these non-mandatory standards. If, however,
a new or existing pipeline meets these more rigorous standards, the
rule allows an operator to elect to calculate the MAOP for the pipeline
based on a higher stress level. This would allow operation at an
increased pressure over that otherwise allowed for pipeline built since
the Federal regulations were issued in the 1970s. To operate at the
higher pressure, the operator would have to comply with more rigorous
O&M, and management requirements.
Under 49 U.S.C. 60102(b), a gas pipeline safety standard must be
practicable and designed to meet the need for gas pipeline safety and
for protection of the environment. PHMSA must consider several factors
in issuing a safety standard. These factors include the relevant
available pipeline safety and environmental information, the
appropriateness of the standard for the type of pipeline, the
reasonableness of the standard, and reasonably identifiable or
estimated costs and benefits. PHMSA has considered these factors in
developing this rule and provides its analysis in the preamble.
PHMSA must also consider any comments received from the public and
any comments and recommendations of the TPSSC. These are discussed
below.
C. Comments on the NPRM
PHMSA received comments from 19 organizations in response to the
NPRM. These included eleven pipeline operators, four trade associations
and related organizations, three steel/pipe manufacturers, and one
state pipeline safety regulatory agency.
C.1. General Comments
API 5L, 44th Edition
Many commenters noted that pipe material/design requirements in
American Pipeline Institute (API) Standard 5L (API 5L) have been
significantly revised in the 44th edition, which they stated would be
in effect by the time a final rule is issued. These commenters
generally suggested that PHMSA should defer to, or incorporate,
requirements from the 44th edition where applicable rather than
establishing different technical requirements in regulation.
Response
API 5L, 43rd edition, is currently incorporated by reference into
the Code of Federal Regulations (CFR). PHMSA has begun a technical
review of the 44th edition to determine whether and to what extent it
is appropriate to update this reference or if exceptions need be taken
when so incorporating the standard. PHMSA cannot reference requirements
in the 44th edition until this review is completed and the regulations
have been revised to incorporate the new edition. Where differences in
the 44th edition would affect requirements in this rule, appropriate
changes will be made when that edition is incorporated.
Effect on Special Permits
All commenters who addressed the question suggested that
requirements in a final rule should not apply retroactively to
pipelines operating at alternative MAOP based on special permits issued
after detailed review by PHMSA. One pipeline operator provided a legal
analysis maintaining that such retroactive application would be
contrary to PHMSA's statutory authority. These organizations also
commented that PHMSA should continue review of special permit
applications until the final rule is issued, noting that in many cases
operation at the proposed higher MAOP is necessary to meet contractual
commitments operators have made in anticipation of a special permit
being granted and to meet national energy needs.
Response
As noted above, PHMSA continued reviewing special permit
applications throughout this rulemaking proceeding, generally applying
the same criteria adopted in this rule. Having now published the final
rule, we consider it unnecessary to complete review of pending special
permit applications on the subject. Accordingly, PHMSA intends to
terminate these proceedings, with appropriate notice to the individual
applicants.
In contrast, this regulatory action has no effect on the status of
special permits or waivers currently in effect. As we explained
recently in Docket No. PHMSA-2007-0033, Pipeline Safety: Administrative
Procedures, Address Updates, and Technical Amendments, (FR Volume 73,
No. 61, 16562, published March 28, 2008), PHMSA reserves the right to
revoke or modify a special permit or waiver based on an operator's
failure to comply with the conditions of the special permit/waiver or
on a showing of material error, misrepresentation, or changed
circumstances. Although an operator may elect to surrender its special
permit at any time, nothing in this rule requires the operator to do so
or otherwise triggers reopening of a special permit/waiver currently in
effect. The existing MAOP special permits were issued based upon a
PHMSA review of the operator's engineering, construction, O&M
procedures and operating history. While some of the pipeline segments
may not meet all of the requirements specified in this final rule, the
operational history and O&M practices provide an equivalent level of
safety as provided in this final rule. Furthermore, whether a pipeline
is operating at higher MAOP under this rule or a special permit/waiver,
PHMSA will monitor and enforce compliance with the applicable
conditions and safety controls.
Structure
One state pipeline safety regulatory agency expressed concern about
the complexity and inconsistency being added to the regulations as a
result of the structure of the proposed rule. The state agency noted
that the proposal would add many pages to part 192 that would apply to
only a limited number of gas transmission operators. The agency
suggested that it would be more effective, and cause less confusion, if
requirements for pipelines operating at an alternative MAOP were
presented in a separate subpart, applicable only to those pipelines.
[[Page 62154]]
Response
PHMSA has not previously used a separate subpart to include varied
requirements applicable to specific types of pipelines. Instead,
subparts have been used for individual topics, such as Corrosion
Control or Integrity Management. PHMSA considers it more appropriate to
incorporate requirements applicable to each subpart as the requirements
in this rule implicate several subparts. PHMSA also notes that no other
commenters indicated that the structure of the proposed rule was
confusing. PHMSA has retained the structure of the proposal in this
final rule. PHMSA intends to post this notice of final rulemaking on
its web site, which will provide a reference for pipeline operators
that includes all of the requirements associated with alternative MAOP
in one document.
C.2. Comments on Specific Provisions in the Proposed Rule
C.2.1. Section 192.7, Incorporation by Reference
Interstate Natural Gas Association of America (INGAA) and three
pipeline operators supported incorporation of American Society of
Testing and Materials (ASTM) standard ASTM A-578/A578M-96 into the
regulations. These commenters generally noted that this action is
consistent with reliance on consensus standards, which they support.
American Gas Association (AGA) and the Gas Piping Technology Committee
(GPTC) took the contrary position and opposed incorporation of the ASTM
standard. GPTC commented that the standard is used by one mill and that
other mills use other standards (including International Standards
Organization (ISO) standards). GPTC also noted that there are a number
of equivalent standards and that PHMSA should not select one for
incorporation. AGA added that incorporating the standard could have
unintended consequences of making the rule too prescriptive and
precluding the use of equivalent standards.
Response
The final rule incorporates ASTM A578/A578M-96 into the
regulations. Incorporation by reference makes the provisions of the
standard apply, when it is referenced in a regulation, in the same
manner as if they were written in the CFR. Referencing consensus
standards wherever possible is the policy of the Federal government.
This standard is referenced in the regulation for assuring plate/
coil quality control (QC). That reference requires that ultrasonic (UT)
testing be conducted in accordance with the standard, API 5L paragraph
7.8.10, or equivalent. The pipe must also be manufactured in accordance
with API 5L which is already referenced in Sec. 192.7. PHMSA considers
that the allowance for use of an equivalent standard renders moot the
concerns expressed by AGA and GPTC.
C.2.2. Design Requirements
Section 192.112(a), General Standards for the Steel Pipe
Carbon equivalent: INGAA, five pipeline operators and two pipe
manufacturers all noted that the proposed limit in paragraph (a)(1) on
carbon equivalent (CE) (0.23 percent Pcm) is inconsistent with the 44th
edition of API 5L. INGAA and one operator suggested deleting the limit
from the proposed rule. Two operators noted that the NPRM described no
analysis or data showing the need for a different limit. Several
commenters indicated that high-strength pipe (grades X-80 and above) is
difficult to achieve with the stated limit. One operator suggested that
weldability is the key issue and that allowance for a higher CE is
particularly important for high-strength and strain-based pipe. A steel
manufacturer objected to sole reliance on the Pcm formula for
determining the CE value.
Response
PHMSA agrees that the limit in API 5L is acceptable. PHMSA has
changed the limit for CE to 0.25 Pcm (Ito-Bessyo formula for CE), which
is consistent with API 5L. PHMSA does not agree that no limit should be
included in the CFR. PHMSA considers that a limit is necessary to
assure the quality of steel used for pipelines to operate at an
alternative MAOP. Weldability tests are not timely for determining the
acceptability of steel, as they cannot be performed until pipe is
manufactured. Recent experience with several new pipelines using X-80
steel has indicated that such high strength steel can meet the CE
limit. PHMSA does not currently have experience with steels of grades
higher than X-80 and will need to understand what is important for such
pipe grades as they are used.
PHMSA acknowledges that there are other methods for calculating the
CE value of steel. The Pcm formula included in the proposed rule is a
method used by several mills. PHMSA has revised the final rule to
include use of an alternate International Institute of Welding (IIW) CE
formula, used by other mills for determining CE.
Diameter to thickness ratio: INGAA and three pipeline operators
suggested deleting the limit in proposed paragraph (a)(3) on the ratio
of pipe diameter to thickness (D/t). They maintained that this limit
may be inappropriate for high-grade pipe and that the concerns that
might underlie such a limit are adequately addressed by the proposed
rule and common construction practices and quality assurance (QA). One
operator noted that ovality and denting issues are addressed by the
proposed construction requirements of Sec. 192.328, that QA is
required by proposed Sec. 192.620(d)(9), and that the baseline
geometry ILI and the provisions of the ASME Code would also address the
underlying concerns.
Response
PHMSA has retained the proposed limit. PHMSA adopted this limit
(i.e., D/t <= 100) based upon presentations made by industry experts at
the public meeting on ``Reconsideration of Maximum Allowable Operating
Pressure in Natural Gas Pipelines'' held on March 21, 2006 in Reston,
VA. Higher D/t ratios can lead to excessive denting during
transportation, construction bending, pipe stringing on the right-of-
way, backfilling, and hydrostatic testing.
Section 192.112(b), Fracture Control
Several commenters noted that some requirements included in the
proposed rule are being eliminated or significantly revised in the 44th
edition of API 5L. The steel/pipe manufacturers suggested referencing
the new standard to, among other things, avoid unnecessarily limiting
approaches to deriving arrest toughness and treating all sizes and
types of pipe (e.g., seamless) the same for purposes of the drop weight
test.
INGAA and three pipeline operators suggested a change to allow a
crack arrest design other than mechanical arrestors if crack
propagation cannot be made self-limiting. (One operator noted that
Clock Spring \1\ is marketed as a crack arrestor). They suggested that
a rule should allow an option for engineering analysis, including an
analysis of consequences. One operator noted that this option could be
particularly important for high-pressure, large-diameter pipelines. Two
operators generally supported the proposed approach for fracture
control if self-arrest is attainable. They noted that it is critical
that operators have a plan and consider the potential under-
[[Page 62155]]
conservativeness of Charpy toughness equations for high grade pipe (X-
70 and above).
---------------------------------------------------------------------------
\1\ Clock Spring is a commercially available composite sleeve
used for pipeline repairs.
---------------------------------------------------------------------------
Response
PHMSA has not yet incorporated the 44th edition of API 5L into the
regulations. PHMSA is conducting a technical review of this edition to
determine if it is acceptable for incorporation. If, after that review,
PHMSA determines that the standard is acceptable, PHMSA will propose to
incorporate the 44th edition and change other affected rules as
appropriate.
The final rule requires an overall fracture control plan to resist
crack initiation and propagation and to arrest a fracture within eight
pipe joints with a 99 percent occurrence probability and within five
pipe joints with a 90 percent occurrence probability. Research has
shown that an effective fracture plan should include acceptable Charpy
impact and drop weight tear tests, which are required in this final
rule.
PHMSA considers composite sleeves to be suitable mechanical crack
arrestors. Operators could use composite sleeves for this purpose,
install periodic joints of thicker-walled pipe, or use other design
features to provide crack arrest if it is not possible to achieve the
toughness properties specified in the rule and also assure self-
limiting arrest. PHMSA has revised the language in this final rule to
allow additional design features and to make mechanical crack arrestors
an example of such features rather than the only method allowed.
Section 192.112(c), Plate/Coil Quality Control
One pipeline operator and two pipe manufacturers suggested
expanding the mill control inspection program to a full internal
quality management program and including caster and plate/coil/pipe
mills.
INGAA, three pipeline operators and two pipe manufacturers
commented that the specificity of requirements applicable to mill
inspection should be reduced. These commenters agreed that a macro etch
test is appropriate but suggested that the details of how this test is
applied should be left to decisions of the mill and the pipe purchaser.
They suggested that API 5L provides a foundation for those decisions
and the specific requirements in the proposed rule add unnecessary cost
impact. One pipe manufacturer noted that the Mannesmann scale is very
subjective, while a second separately commented that reference to the
Mannesmann scale should be deleted because it is proprietary and thus
inappropriate for inclusion in a regulation. One operator requested
that the mill inspection requirements, including those for macro etch
and UT examination, be explicitly limited to new pipelines, noting that
it is unlikely these tests were performed for any existing pipelines
and that they have minimal relevance for existing pipelines that would
be subject to the proposed rule.
INGAA and four pipeline operators suggested that an alternative to
the UT testing specified should be allowed for identifying laminations.
They suggested that a full-body UT inspection, for example, should be
acceptable.
One operator and two manufacturers commented that it is
inappropriate to use the proposed macro etch test and acceptance
criteria as a heat/slab rejection criteria. These commenters noted that
no consensus standard references this test. The operator maintained
that the test does not accomplish what PHMSA suggested in the preamble
of the NPRM, that it is a lagging rather than a leading test and its
use as an acceptance test without a retest allowance could result in
rejection of up to 2,000 tons of steel or more. The operator suggested
that this should be a mill control test rather than an acceptance test
with specifics, including retest allowance, to be negotiated between
the mill and pipe purchaser.
One operator and one manufacturer noted that ASTM A578 is a plate
UT inspection standard. They commented that specifying this standard
for coil/pipe is beyond its scope. They also commented that we gave no
basis for proposing that 50 percent of surface and 90 percent of joints
be examined. They noted that pipe seam welds and pipe ends are
inspected radiographically or by UT and that additional UT is more
appropriately a purchaser-specified requirement. Another operator also
suggested that the 50 percent surface coverage requirement be deleted
in favor of reference to ASTM A578/A578M.
Two manufacturers suggested that the rule allow UT on plate/coil or
pipe body, noting that most United States mills lack equipment to
perform ASTM A578 testing. Another manufacturer suggested that a
combination of electromagnetic inspection (EMI) and UT inspection is
superior and would produce the most dramatic impact. This combination,
according to this manufacturer, is also applicable to seamless and
electric resistance welded (ERW) pipe.
One manufacturer recommended that the inspection program of
proposed section 192.112(c)(2)(ii) be limited to submerged arc welded
(SAW) pipe, and that the acceptance criteria for UT testing be
referenced to ASTM A578 or equivalent. This commenter noted that
laminations are not a significant issue for modern pipe.
Response
PHMSA agrees that an ``internal quality management program'' is
more descriptive than a ``mill control inspection program'' and that
such a program should be required at all mills associated with the
manufacture of steel and pipe. The final rule has been revised
accordingly.
PHMSA considers that a macro etch test or other equivalent method
is needed to identify inclusions that may cause centerline segregation
during the continuous casting process. The acceptance criteria must be
agreed to between the purchaser and the mill. PHMSA has added an
alternative to the requirement for a macro etch test consisting of an
operator QA monitoring plan that includes audits conducted by the
operator (or an agent operating under its authority) of: (a)
Steelmaking and casting facilities; (b) QC plans and manufacturing
procedure specifications (MPS); (c) equipment maintenance and records
of conformance; (d) applicable casting superheat and speeds; and (e)
centerline segregation monitoring records to ensure mitigation of
centerline segregation during the continuous casting process.
PHMSA agrees that alternate methods to test the pipe body for
laminations, cracks, and inclusions should be acceptable and has
revised the rule to allow methods per API 5L Section 7.8.10 or ASTM
A578-Level B, or other equivalent methods. PHMSA understands that it is
unlikely that many existing pipelines were manufactured using processes
that included the specified examinations but does not consider that
sufficient reason for excluding existing pipelines from the
requirements.
The requirement for 50 percent of surface and 95 percent of lengths
of pipe to be UT tested was set to ensure adequate QC standards. PHMSA
agrees that the specified QC requirements also must be practical. In
the final rule, we have reduced the requirement for 50 percent of
surface coverage to 35 percent because we recognize that it may be
difficult to achieve 50 percent coverage for pipe manufactured with
helical seams.
PHMSA has not deleted reference to the Mannesmann scale, which is
widely used by steel manufacturers. In
[[Page 62156]]
addition, the regulation allows for use of equivalent measures.
PHMSA does not agree that the inspection program of proposed
192.112(c)(2)(ii) should be limited to SAW pipe. PHMSA considers this
requirement to be an overall quality management tool and not just for
laminations. Additionally, PHMSA notes that at least one recently
constructed pipeline has had problems with laminations.
Section 192.112(d), Seam Quality Control
INGAA, four pipeline operators, and two pipe manufacturers all
recommended additional reliance on the procedures of API 5L 44th
edition. The manufacturers would have referenced API 5L for toughness
requirements and made them applicable to weld and heat affected zone in
SAW pipe only. They noted that the proposed requirement is
inappropriate for ERW pipe, that the specified toughness is higher than
that called for in API 5L and is not necessary. The manufacturers
believe that fracture arrest capabilities are not needed in weld metal,
since staggered seams in pipeline construction result in arrest
occurring in the pipe body.
INGAA and three pipeline operators would have eliminated reference
to specific hardness testing or a maximum hardness level, arguing that
API 5L contains sufficient guidance. They further noted that the
specified hardness of 280 Vickers (Hv10) is only for sour gas. One
manufacturer would have relaxed the hardness requirement to 300 Hv10
and allowed for equivalent test methods (per ASTM E140). Another would
have specified a maximum hardness ``appropriate for the pipeline
design'' vs. specifying a limit. The first manufacturer noted that API
5L does not specify hardness limits except for sour gas service or
offshore pipelines and that the technical justification for these
limits on other pipe is not obvious. The manufacturers maintained that
limiting hardness may not allow attaining the best weld properties and
that 280 Hv10 is likely not attainable for pipe grades X-80 and above.
Two pipe manufacturers requested that the rule be clarified to
indicate that the seam QC requirements apply only to longitudinal or
helical seams. They noted that pipe mill jointer welds require
radiography per API 1104 and that significant capital expense would be
required for pipe mills to UT test jointer and skelp end welds after
cold expansion and hydrostatic testing.
Response
PHMSA has not yet incorporated the 44th edition of API 5L into the
regulations. PHMSA is conducting a technical review of this edition to
determine if it is acceptable for incorporation. If, after review,
PHMSA determines that the standard is acceptable, PHMSA will propose to
incorporate the 44th edition and propose changes to other affected
regulations as appropriate.
PHMSA has deleted the proposed limit on toughness. This limit was
not included in the conditions applied to special permits issued for
alternative MAOP operation. Pipe procured to modern standards generally
meets the proposed limit, and other requirements in this rule, provide
for crack arrest. Thus, PHMSA concluded that a toughness limit was not
needed.
PHMSA does not agree that it is not necessary to specify a hardness
limit. All recent pipelines for which special permits have been issued
to operate at alternative MAOP have met the proposed hardness limit
without apparent difficulty. This includes X-80 pipe. The requirement
helps assure that only high-quality steel is used for pipelines to be
operated at alternative MAOP. Hardness must be limited to assure welds
are not susceptible to cracking. The proposed limit has been retained
in the final rule.
PHMSA intends the proposed seam inspection requirements to apply to
pipe seam welds and not to jointer or skelp welds. The title of this
subparagraph is ``Seam quality control,'' and its requirements all
refer to ``seam welds'' or ``seams.'' PHMSA does not consider that
additional changes are needed to clarify the applicability of these
requirements.
Section 192.112(e), Mill Hydrostatic Test
Most commenters objected to the proposed requirement that mill
hydrostatic tests be held for 20 seconds. They noted that mills
typically follow API 5L, which specifies a hydrostatic test of 10
seconds and that changing this standard could reduce mill productivity.
One operator also noted that a more rigorous qualification test is
already specified elsewhere in the proposed regulation.
One manufacturer would have limited the required maximum test
pressure to 3,000 psi if there are physical limitations in mill test
equipment that preclude obtaining higher pressures. The manufacturer
stated that most mills cannot achieve test pressures above 3,000 psi,
which is the maximum specified in API 5L and that upgrades to equipment
would cost from $0.5 to $4 million per tester.
Response
PHMSA agrees that a 20-second mill hydrostatic test is not needed
and has revised the final rule to reduce the required hold time to 10
seconds. While a longer mill hydrostatic test may allow the discovery
of more pipe defects, the benefit is marginal. The pipeline will later
be subject to a much longer hydrostatic test prior to being pl