55898
Federal Register / Vol. 73, No. 188 / Friday, September 26, 2008 / Notices
Satellite Bus Facility Environmental
Assessment released on June 15, 2008.
3. Project name and location:
Gustavus Causeway Replacement,
Gustavus, Alaska. Project sponsor: State
of Alaska Department of Transportation
and Public Facilities (Alaska DOT&PF).
Project description: Alaska DOT&PF
intends to replace a dock facility in
Gustavus, Alaska that supports freight
movement, bulk fuel transfer, and
marine passenger vessels. The
replacement dock will include a wider
trestle to allow two-way traffic, a
securable staging area for passenger
vehicles and freight, and an upgraded
fuel-transfer pipeline. Final agency
actions: FONSI signed on August 14,
2008. Supporting documentation:
Environmental Assessment for the
Gustavus Causeway Replacement
Project issued in May 2008.
4. Project name and location:
Northwest Corridor to Irving/Dallas-Fort
Worth Light Rail Transit Line, Dallas,
Texas. Project sponsor: Dallas Area
Rapid Transit (DART). Project
description: DART is proposing to
construct a 9.3-mile light rail transit
extension from the existing Northwest
Corridor line to the Dallas/Forth Worth
Airport Property. The project will
involve the construction of six light rail
transit stations and seven traction power
substations and the purchase of ten light
rail vehicles. DART would defer
construction of two proposed light rail
stations until they are warranted by
development. Final agency actions:
ROD signed on September 5, 2008;
Section 106 Finding of No Historic
Properties Affected; Section 4(f) finding,
and Project-level Air Conformity
Determination. Supporting
documentation: Northwest Corridor to
Irving/Dallas-Fort Worth Light Rail
Transit Line Environmental Impact
Statement signed on July 17, 2008.
5. Project name and location: Foothill
Transit Park-and-Ride, West Covina,
California. Project sponsor: Foothill
Transit. Project description: The project
involves the construction of a six-level
parking structure on an existing surface
parking lot in West Covina, California.
Final agency actions: FONSI signed on
July 10, 2008; Project-level Air
Conformity Determination; Section 106
Finding of No Historic Properties
Affected. Supporting documentation:
Environmental Assessment for the
Foothill Transit Park-and-Ride signed
on May 23, 2008.
6. Project name and location:
Lackawanna Cut-Off Rail Restoration
Project, Minimal Operable Segment,
Andover, New Jersey. Project sponsor:
New Jersey Transit (NJT). Project
description: The project involves the
VerDate Aug<31>2005
18:07 Sep 25, 2008
Jkt 214001
construction of one station and parking
facility with 65 spaces in Andover, New
Jersey, construction of 7.3 miles of new
railroad infrastructure (track, signals,
communications, and grade crossing
improvements) on existing right-of-way
in New Jersey, and rehabilitation of the
Roseville Tunnel. The service will
operate out to Andover, New Jersey
from Hoboken, New Jersey, extending
from the existing NJT Morris & Essex
and Montclair-Boonton Line trains.
Final agency actions: FONSI signed on
September 12, 2008; Section 106
Finding of No Adverse Effect.
Supporting documentation:
Environmental Assessment on the
Lackawanna Cut-Off Rail Restoration
Project issued on July 1, 2008.
Issued on: September 17, 2008.
Susan Borinsky,
Associate Administrator for Planning and
Environment, Washington, DC.
[FR Doc. E8–22634 Filed 9–25–08; 8:45 am]
BILLING CODE 4910–57–P
DEPARTMENT OF TRANSPORTATION
Surface Transportation Board
[STB Docket No. AB–6 (Sub-No. 464X)]
BNSF Railway Company—
Abandonment Exemption—in King
County, WA
BNSF Railway Company (BNSF) has
filed a notice of exemption under 49
CFR 1152 Subpart F–Exempt
Abandonments to abandon a 5.60-mile
rail line 1 between milepost 5.00, at
Kennydale, and milepost 10.60 at
Wilburton, in King County, WA.2 The
line traverses United States Postal
Service Zip Codes 98004, 98005, 98006,
and 98056.
BNSF has certified that: (1) No local
traffic has moved over the line for at
least 2 years; (2) all overhead traffic on
the line has been rerouted over other
lines; (3) no formal complaint filed by
1 The rail line at issue in this proceeding is part
of a larger BNSF segment in King County that is the
subject of two pending proceedings before the
Board. For information regarding these proceedings
see: BNSF Railway Company—Abandonment
Exemption—in King County, WA, STB Docket No.
AB–6 (Sub-No. 465X) (STB served Aug. 29, 2008),
and The Port of Seattle—Acquisition Exemption—
Certain Assets of BNSF Railway Company, STB
Finance Docket No. 35128 (STB served June 20,
2008). An abandonment proposal involving a
connecting BNSF branch line is also pending in
BNSF Railway Company—Abandonment
Exemption—in King County, WA, STB Docket No.
AB–6 (Sub-No. 463X) (STB served Sept. 26, 2008).
2 By petition for exemption filed on September 8,
2008, BNSF is also seeking an exemption from the
offer of financial assistance (OFA) requirements of
49 U.S.C. 10904. The merits of the petition will be
addressed in a separate decision.
PO 00000
Frm 00088
Fmt 4703
Sfmt 4703
a user of rail service on the line (or by
a state or local government entity acting
on behalf of such user) regarding
cessation of service over the line either
is pending with the Surface
Transportation Board or with any U.S.
District Court or has been decided in
favor of complainant within the 2-year
period; and (4) the requirements at 49
CFR 1105.7 (environmental reports), 49
CFR 1105.8 (historic reports), 49 CFR
1105.11 (transmittal letter), 49 CFR
1105.12 (newspaper publication), and
49 CFR 1152.50(d)(1) (notice to
governmental agencies) have been met.
As a condition to this exemption, any
employee adversely affected by the
abandonment shall be protected under
Oregon Short Line R. Co.—
Abandonment—Goshen, 360 I.C.C. 91
(1979). To address whether this
condition adequately protects affected
employees, a petition for partial
revocation under 49 U.S.C. 10502(d)
must be filed.
Provided no formal expression of
intent to file an OFA has been received,
this exemption will be effective on
October 28, 2008, unless stayed pending
reconsideration. Petitions to stay that do
not involve environmental issues,3
formal expressions of intent to file an
OFA under 49 CFR 1152.27(c)(2),4 and
trail use/rail banking requests under 49
CFR 1152.29 must be filed by October
6, 2008. Petitions to reopen or requests
for public use conditions under 49 CFR
1152.28 must be filed by October 16,
2008, with the Surface Transportation
Board, 395 E Street, SW., Washington,
DC 20423–0001.
A copy of any petition filed with the
Board should be sent to BNSF’s
representative: Kristy D. Clark, BNSF
Railway Company, 2500 Lou Menk
Drive, AOB–3, Fort Worth, TX 76131.
If the verified notice contains false or
misleading information, the exemption
is void ab initio.
BNSF has filed both an environmental
report and a historic report that address
the effects, if any, of the abandonment
on the environment and historic
resources. SEA will issue an
environmental assessment (EA) by
3 The Board will grant a stay if an informed
decision on environmental issues (whether raised
by a party or by the Board’s Section of
Environmental Analysis (SEA) in its independent
investigation) cannot be made before the
exemption’s effective date. See Exemption of Outof-Service Rail Lines, 5 I.C.C.2d 377 (1989). Any
request for a stay should be filed as soon as possible
so that the Board may take appropriate action before
the exemption’s effective date.
4 Effective July 18, 2008, the filing fee for an OFA
increased to $1,500. See Regulations Governing
Fees for Services Performed in Connection With
Licensing and Related Services—2008 update, STB
Ex Parte No. 542 (Sub-No. 15) (STB served June 18,
2008).
E:\FR\FM\26SEN1.SGM
26SEN1
Federal Register / Vol. 73, No. 188 / Friday, September 26, 2008 / Notices
October 3, 2008. Interested persons may
obtain a copy of the EA by writing to
SEA (Room 1100, Surface
Transportation Board, Washington, DC
20423–0001) or by calling SEA, at (202)
245–0305. [Assistance for the hearing
impaired is available through the
Federal Information Relay Service
(FIRS) at 1–800–877–8339.] Comments
on environmental and historic
preservation matters must be filed
within 15 days after the EA becomes
available to the public.
Environmental, historic preservation,
public use, or trail use/rail banking
conditions will be imposed, where
appropriate, in a subsequent decision.
Pursuant to the provisions of 49 CFR
1152.29(e)(2), BNSF shall file a notice of
consummation with the Board to signify
that it has exercised the authority
granted and fully abandoned the line. If
consummation has not been effected by
BNSF’s filing of a notice of
consummation by September 26, 2009,
and there are no legal or regulatory
barriers to consummation, the authority
to abandon will automatically expire.
Board decisions and notices are
available on our Web site at https://
www.stb.dot.gov.
Decided: September 22, 2008.
By the Board, David M. Konschnik,
Director, Office of Proceedings.
Anne K. Quinlan,
Acting Secretary.
[FR Doc. E8–22657 Filed 9–25–08; 8:45 am]
BILLING CODE 4915–01–P
DEPARTMENT OF TRANSPORTATION
Surface Transportation Board
[STB Docket No. AB–6 (Sub-No. 463X)]
BNSF Railway Company—
Abandonment Exemption—in King
County, WA
jlentini on PROD1PC65 with NOTICES
BNSF Railway Company (BNSF) has
filed a notice of exemption under 49
CFR 1152 Subpart F–Exempt
Abandonments to abandon a 7.30-mile
rail line 1 located between milepost 0.00
at Woodinville and milepost 7.30 at
1 The rail line at issue is a branch line which
connects with another BNSF line at Woodinville,
WA. That BNSF line is the subject of three pending
proceedings before the Board. For information
regarding these proceedings see: BNSF Railway
Company—Abandonment Exemption—in King
County, WA, STB Docket No. AB–6 (Sub-No. 465X)
(STB served Aug. 29, 2008), The Port of Seattle—
Acquisition Exemption—Certain Assets of BNSF
Railway Company, STB Finance Docket No. 35128
(STB served June 20, 2008), and BNSF Railway
Company—Abandonment Exemption—in King
County, WA, STB Docket No. AB–6 (Sub-No. 464X)
(STB served Sept. 26, 2008).
VerDate Aug<31>2005
18:07 Sep 25, 2008
Jkt 214001
Redmond, King County, WA.2 The line
traverses United States Postal Service
Zip Codes 98011, 98034, 98052, and
98072.
BNSF has certified that: (1) No local
traffic has moved over the line for at
least 2 years; (2) any overhead traffic on
the line can be rerouted over other lines;
(3) no formal complaint filed by a user
of rail service on the line (or by a state
or local government entity acting on
behalf of such user) regarding cessation
of service over the line either is pending
with the Surface Transportation Board
or with any U.S. District Court or has
been decided in favor of complainant
within the 2-year period; and (4) the
requirements at 49 CFR 1105.7
(environmental reports), 49 CFR 1105.8
(historic reports), 49 CFR 1105.11
(transmittal letter), 49 CFR 1105.12
(newspaper publication), and 49 CFR
1152.50(d)(1) (notice to governmental
agencies) have been met.
As a condition to this exemption, any
employee adversely affected by the
abandonment shall be protected under
Oregon Short Line R. Co.—
Abandonment—Goshen, 360 I.C.C. 91
(1979). To address whether this
condition adequately protects affected
employees, a petition for partial
revocation under 49 U.S.C. 10502(d)
must be filed.
Provided no formal expression of
intent to file an OFA has been received,
this exemption will be effective on
October 28, 2008, unless stayed pending
reconsideration. Petitions to stay that do
not involve environmental issues,3
formal expressions of intent to file an
OFA under 49 CFR 1152.27(c)(2),4 and
trail use/rail banking requests under 49
CFR 1152.29 must be filed by October
6, 2008. Petitions to reopen or requests
for public use conditions under 49 CFR
1152.28 must be filed by October 16,
2008, with the Surface Transportation
Board, 395 E Street, SW., Washington,
DC 20423–0001.
2 By petition filed on September 8, 2008, BNSF
is also seeking an exemption from the offer of
financial assistance (OFA) requirements of 49
U.S.C. 10904. The merits of the petition will be
addressed in a separate decision.
3 The Board will grant a stay if an informed
decision on environmental issues (whether raised
by a party or by the Board’s Section of
Environmental Analysis (SEA) in its independent
investigation) cannot be made before the
exemption’s effective date. See Exemption of Outof-Service Rail Lines, 5 I.C.C.2d 377 (1989). Any
request for a stay should be filed as soon as possible
so that the Board may take appropriate action before
the exemption’s effective date.
4 Effective July 18, 2008, the filing fee for an OFA
increased to $1,500. See Regulations Governing
Fees for Services Performed in Connection with
Licensing and Related Services—2008 update, STB
Ex Parte No. 542 (Sub-No. 15) (STB served June 18,
2008).
PO 00000
Frm 00089
Fmt 4703
Sfmt 4703
55899
A copy of any petition filed with the
Board should be sent to BNSF’s
representative: Kristy D. Clark, BNSF
Railway Company, 2500 Lou Menk
Drive, AOB–3, Fort Worth, TX 76131.
If the verified notice contains false or
misleading information, the exemption
is void ab initio.
BNSF has filed both an environmental
report and a historic report that address
the effects, if any, of the abandonment
on the environment and historic
resources. SEA will issue an
environmental assessment (EA) by
October 3, 2008. Interested persons may
obtain a copy of the EA by writing to
SEA (Room 1100, Surface
Transportation Board, Washington, DC
20423–0001) or by calling SEA, at (202)
245–0305. [Assistance for the hearing
impaired is available through the
Federal Information Relay Service
(FIRS) at 1–800–877–8339.] Comments
on environmental and historic
preservation matters must be filed
within 15 days after the EA becomes
available to the public.
Environmental, historic preservation,
public use, or trail use/rail banking
conditions will be imposed, where
appropriate, in a subsequent decision.
Pursuant to the provisions of 49 CFR
1152.29(e)(2), BNSF shall file a notice of
consummation with the Board to signify
that it has exercised the authority
granted and fully abandoned the line. If
consummation has not been effected by
BNSF’s filing of a notice of
consummation by September 26, 2009,
and there are no legal or regulatory
barriers to consummation, the authority
to abandon will automatically expire.
Board decisions and notices are
available on our Web site at https://
www.stb.dot.gov.
Decided: September 22, 2008.
By the Board, David M. Konschnik,
Director, Office of Proceedings.
Anne K. Quinlan,
Acting Secretary.
[FR Doc. E8–22677 Filed 9–25–08; 8:45 am]
BILLING CODE 4915–01–P
DEPARTMENT OF TRANSPORTATION
Surface Transportation Board
[STB Finance Docket No. 35176]
Georgia Southwestern Railroad, Inc.—
Acquisition Exemption—CSX
Transportation, Inc.
Georgia Southwestern Railroad, Inc.
(GSWR), a Class III rail carrier, has filed
a verified notice of exemption under 49
CFR 1150.41 to acquire by purchase
from CSX Transportation, Inc. (CSXT),
E:\FR\FM\26SEN1.SGM
26SEN1
Agencies
[Federal Register Volume 73, Number 188 (Friday, September 26, 2008)]
[Notices]
[Pages 55898-55899]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-22657]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Surface Transportation Board
[STB Docket No. AB-6 (Sub-No. 464X)]
BNSF Railway Company--Abandonment Exemption--in King County, WA
BNSF Railway Company (BNSF) has filed a notice of exemption under
49 CFR 1152 Subpart F-Exempt Abandonments to abandon a 5.60-mile rail
line \1\ between milepost 5.00, at Kennydale, and milepost 10.60 at
Wilburton, in King County, WA.\2\ The line traverses United States
Postal Service Zip Codes 98004, 98005, 98006, and 98056.
---------------------------------------------------------------------------
\1\ The rail line at issue in this proceeding is part of a
larger BNSF segment in King County that is the subject of two
pending proceedings before the Board. For information regarding
these proceedings see: BNSF Railway Company--Abandonment Exemption--
in King County, WA, STB Docket No. AB-6 (Sub-No. 465X) (STB served
Aug. 29, 2008), and The Port of Seattle--Acquisition Exemption--
Certain Assets of BNSF Railway Company, STB Finance Docket No. 35128
(STB served June 20, 2008). An abandonment proposal involving a
connecting BNSF branch line is also pending in BNSF Railway
Company--Abandonment Exemption--in King County, WA, STB Docket No.
AB-6 (Sub-No. 463X) (STB served Sept. 26, 2008).
\2\ By petition for exemption filed on September 8, 2008, BNSF
is also seeking an exemption from the offer of financial assistance
(OFA) requirements of 49 U.S.C. 10904. The merits of the petition
will be addressed in a separate decision.
---------------------------------------------------------------------------
BNSF has certified that: (1) No local traffic has moved over the
line for at least 2 years; (2) all overhead traffic on the line has
been rerouted over other lines; (3) no formal complaint filed by a user
of rail service on the line (or by a state or local government entity
acting on behalf of such user) regarding cessation of service over the
line either is pending with the Surface Transportation Board or with
any U.S. District Court or has been decided in favor of complainant
within the 2-year period; and (4) the requirements at 49 CFR 1105.7
(environmental reports), 49 CFR 1105.8 (historic reports), 49 CFR
1105.11 (transmittal letter), 49 CFR 1105.12 (newspaper publication),
and 49 CFR 1152.50(d)(1) (notice to governmental agencies) have been
met.
As a condition to this exemption, any employee adversely affected
by the abandonment shall be protected under Oregon Short Line R. Co.--
Abandonment--Goshen, 360 I.C.C. 91 (1979). To address whether this
condition adequately protects affected employees, a petition for
partial revocation under 49 U.S.C. 10502(d) must be filed.
Provided no formal expression of intent to file an OFA has been
received, this exemption will be effective on October 28, 2008, unless
stayed pending reconsideration. Petitions to stay that do not involve
environmental issues,\3\ formal expressions of intent to file an OFA
under 49 CFR 1152.27(c)(2),\4\ and trail use/rail banking requests
under 49 CFR 1152.29 must be filed by October 6, 2008. Petitions to
reopen or requests for public use conditions under 49 CFR 1152.28 must
be filed by October 16, 2008, with the Surface Transportation Board,
395 E Street, SW., Washington, DC 20423-0001.
---------------------------------------------------------------------------
\3\ The Board will grant a stay if an informed decision on
environmental issues (whether raised by a party or by the Board's
Section of Environmental Analysis (SEA) in its independent
investigation) cannot be made before the exemption's effective date.
See Exemption of Out-of-Service Rail Lines, 5 I.C.C.2d 377 (1989).
Any request for a stay should be filed as soon as possible so that
the Board may take appropriate action before the exemption's
effective date.
\4\ Effective July 18, 2008, the filing fee for an OFA increased
to $1,500. See Regulations Governing Fees for Services Performed in
Connection With Licensing and Related Services--2008 update, STB Ex
Parte No. 542 (Sub-No. 15) (STB served June 18, 2008).
---------------------------------------------------------------------------
A copy of any petition filed with the Board should be sent to
BNSF's representative: Kristy D. Clark, BNSF Railway Company, 2500 Lou
Menk Drive, AOB-3, Fort Worth, TX 76131.
If the verified notice contains false or misleading information,
the exemption is void ab initio.
BNSF has filed both an environmental report and a historic report
that address the effects, if any, of the abandonment on the environment
and historic resources. SEA will issue an environmental assessment (EA)
by
[[Page 55899]]
October 3, 2008. Interested persons may obtain a copy of the EA by
writing to SEA (Room 1100, Surface Transportation Board, Washington, DC
20423-0001) or by calling SEA, at (202) 245-0305. [Assistance for the
hearing impaired is available through the Federal Information Relay
Service (FIRS) at 1-800-877-8339.] Comments on environmental and
historic preservation matters must be filed within 15 days after the EA
becomes available to the public.
Environmental, historic preservation, public use, or trail use/rail
banking conditions will be imposed, where appropriate, in a subsequent
decision.
Pursuant to the provisions of 49 CFR 1152.29(e)(2), BNSF shall file
a notice of consummation with the Board to signify that it has
exercised the authority granted and fully abandoned the line. If
consummation has not been effected by BNSF's filing of a notice of
consummation by September 26, 2009, and there are no legal or
regulatory barriers to consummation, the authority to abandon will
automatically expire.
Board decisions and notices are available on our Web site at http:/
/www.stb.dot.gov.
Decided: September 22, 2008.
By the Board, David M. Konschnik, Director, Office of
Proceedings.
Anne K. Quinlan,
Acting Secretary.
[FR Doc. E8-22657 Filed 9-25-08; 8:45 am]