Salt Lake City Area Integrated Projects and Colorado River Storage Project-Rate Order No. WAPA-137, 52980-52996 [E8-21176]
Download as PDF
52980
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
Kimberly D. Bose,
Secretary.
[FR Doc. E8–21151 Filed 9–11–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Western Area Power Administration
Salt Lake City Area Integrated Projects
and Colorado River Storage Project—
Rate Order No. WAPA–137
Western Area Power
Administration, DOE.
ACTION: Notice of Order Concerning
Power, Transmission, and Ancillary
Services Rates.
ebenthall on PROD1PC60 with NOTICES
AGENCY:
SUMMARY: The Acting Deputy Secretary
of Energy confirmed and approved Rate
Order No. WAPA–137 and Rate
Schedule SLIP–F9, placing firm power
rates for the Salt Lake City Area
Integrated Projects (SLCA/IP) of the
Western Area Power Administration
(Western) into effect on an interim basis.
The Acting Deputy Secretary also
confirmed Rate Schedules SP–PTP7,
SP–NW3, SP–NFT6, SP–SD3, SP–RS3,
SP–EI3, SP–FR3, and SP–SSR3, placing
firm and non-firm transmission rates
and ancillary services rates on the
Colorado River Storage Project (CRSP)
transmission system into effect on an
interim basis. The provisional rates will
be in effect until the Federal Energy
Regulatory Commission (FERC)
confirms, approves, and places them
into effect on a final basis or until they
are replaced by other rates. The
provisional rates will provide sufficient
revenue to pay all annual costs,
including interest expense, and
repayment of power investment and
irrigation aid, within the allowable
periods.
DATES: Rate Schedules SLIP–F9, SP–
PTP7, SP–NW3, SP–NFT6, SP–SD3, SP–
RS3, SP–EI3, SP–FR3, and SP–SSR3
will be placed into effect on an interim
basis on the first day of the first full
billing period beginning on or after
October 1, 2008, and will be in effect
until FERC confirms, approves, and
places the rate schedules in effect on a
final basis through September 30, 2013,
or until the rate schedules are
superseded.
FOR FURTHER INFORMATION CONTACT: Mr.
Bradley S. Warren, CRSP Manager,
Colorado River Storage Project
Management Center, Western Area
Power Administration, 150 East Social
Hall Avenue, Suite 300, Salt Lake City,
UT 84111–1580, (801) 524–5493, e-mail
warren@wapa.gov, or Ms. Carol A.
Loftin, Rates Manager, Colorado River
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
Storage Project Management Center,
Western Area Power Administration,
150 East Social Hall Avenue, Suite 300,
Salt Lake City, UT 84111–1580, (801)
524–6380, e-mail loftinc@wapa.gov.
SUPPLEMENTARY INFORMATION: The
Deputy Secretary of Energy approved
Rate Order No. WAPA–117 on August 1,
2005 (70 Fed. Reg. 47823). This Order
included existing Rate Schedule SLIP–
F8 for SLCA/IP firm power.1 The
existing firm power Rate Schedule
SLIP–F8 is being superseded by Rate
Schedule SLIP–F9. Under Rate
Schedule SLIP–F8, the energy rate is
10.43 mills/kilowatthour (mills/kWh),
and the capacity rate is $4.43/
kilowattmonth ($/kWmonth). The
composite rate is 25.28 mills/kWh. The
provisional firm power rate will be
implemented over a 2-year period. In
the first year, the provisional firm power
rate consists of an energy charge of
11.06 mills/kWh and a capacity charge
of $4.70/kWmonth. The second step of
the rate will be effective October 1,
2009, and will be capped at the energy
charge of 12.29 mills/kWh and a
capacity charge of $5.22/kWmonth. The
provisional rates for SLCA/IP firm
power in Rate Schedule SLIP–F9 will
result in an overall composite rate of
26.80 mills/kWh on October 1, 2008,
and a composite rate capped at 29.68
mills/kWh on October 1, 2009, through
September 30, 2013, or until
superseded. This second step rate
adjustment will result in an overall
increase of about 17.4 percent when
compared with the existing SLCA/IP
firm power composite rate under Rate
Schedule SLIP–F8.
The firm power rate will continue to
include a cost recovery mechanism
called the Cost Recovery Charge (CRC).
The CRC is necessary to adequately
maintain a sufficient cash balance in the
Upper Colorado River Basin Fund. The
CRC is a charge on Sustainable
Hydropower (SHP) energy, as
determined by financial conditions.
Every May, Western will provide
customers with information concerning
any anticipated CRC for the upcoming
fiscal year (FY). If Western determines
a CRC is necessary, firm power
customers may choose not to take as
much firm energy and, in exchange,
Western will waive the CRC charge. In
addition to the potential for a CRC being
implemented every year, Western will
consider assessing the CRC upon a 45day notice to customers, should water
1 FERC confirmed and approved Rate Order No.
WAPA–117 on June 13, 2006, in Docket EF05–5171.
See United States Department of Energy, Western
Area Power Administration, Salt Lake City
Integrated Projects, 115 FERC ¶ 62,271 (June 13,
2006).
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
releases at Glen Canyon Dam be reduced
to less than 8.23 million acre-feet (MAF)
in a FY.
By Delegation Order No. 00–037.00,
effective December 6, 2001, the
Secretary of Energy delegated: (1) The
authority to develop power and
transmission rates to Western’s
Administrator, (2) the authority to
confirm, approve, and place such rates
into effect on an interim basis to the
Deputy Secretary of Energy, and (3) the
authority to confirm, approve, and place
into effect on a final basis, to remand or
to disapprove such rates to FERC.
Existing Department of Energy
procedures for public participation in
power rate adjustments (10 CFR part
903) were published on September 18,
1985.
Under Delegation Order Nos. 00–
037.00 and 00–001.00A, 10 CFR part
903, and 18 CFR part 300, I hereby
confirm, approve, and place Rate Order
No. WAPA–137, the proposed SLCA/IP
firm power rate, CRSP firm and nonfirm transmission rates, and ancillary
services rates into effect on an interim
basis.
The new Rate Schedules SLIP–F9,
SP–PTP7, SP–NW3, SP–NFT6, SP–SD3,
SP–RS3, SP–EI3, SP–FR3, and SP–SSR3
will be promptly submitted to FERC for
confirmation and approval on a final
basis.
Dated: September 4, 2008.
Jeffrey F. Kupfer,
Acting Deputy Secretary.
Department of Energy
Deputy Secretary
[Rate Order No. WAPA–137]
In the Matter of: Western Area Power
Administration Rate Adjustment for the Salt
Lake City Area Integrated Projects and
Colorado River Storage Project; Order
Confirming, Approving, and Placing the Salt
Lake City Area Integrated Projects Firm
Power, Colorado River Storage Project
Transmission and Ancillary Services Rates
Into Effect on an Interim Basis
These rates were established in
accordance with section 302 of the
Department of Energy (DOE)
Organization Act (42 U.S.C. 7152). This
Act transferred to and vested in the
Secretary of Energy the power marketing
functions of the Secretary of the
Department of the Interior and the
Bureau of Reclamation (Reclamation)
under the Reclamation Act of 1902 (ch.
1093, 32 Stat. 388), as amended and
supplemented by subsequent laws,
particularly section 9(c) of the
Reclamation Project Act of 1939 (43
U.S.C. 485h(c)), and other acts that
specifically apply to the project
involved.
By Delegation Order No. 00–037.00,
effective December 6, 2001, the
E:\FR\FM\12SEN1.SGM
12SEN1
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
ebenthall on PROD1PC60 with NOTICES
Secretary of Energy delegated: (1) The
authority to develop power and
transmission rates to Western’s
Administrator, (2) the authority to
confirm, approve, and place such rates
into effect on an interim basis to the
Deputy Secretary of Energy, and (3) the
authority to confirm, approve, and place
into effect on a final basis, to remand or
to disapprove such rates to the Federal
Energy Regulatory Commission (FERC).
Existing DOE procedures for public
participation in power rate adjustments
(10 CFR part 903) were published on
September 18, 1985.
Acronyms and Definitions
As used in this Rate Order, the
following acronyms and definitions
apply:
Administrator: The Administrator of the
Western Area Power Administration.
A.F.: Acre-feet.
AFC: Actual firming energy costs (MWh)
as used in the PYA formula.
AHP: Available Hydropower.
ALP: Animas La Plata Project.
ATRR: Annual Transmission Revenue
Requirement.
Basin Fund: Upper Colorado River
Basin Fund.
BFBB: Basin Fund Beginning Balance as
used in the CRC formula.
BFTB: Basin Fund Target Balance as
used in the CRC formula.
Capacity: The electric capability of a
generator, transformer, transmission
circuit, or other equipment. It is
expressed in kW.
Capacity Rate: The rate which sets forth
the charges for capacity. It is
expressed in $/kWmonth and applied
to each kW of the Contract Rate of
Delivery (CROD).
CDP: Customer Displacement Power.
Composite Rate: The rate for firm power
which is the total annual revenue
requirement for capacity and energy
divided by the total annual energy
sales. It is expressed in mills/kWh
and used for comparison purposes.
CRC: Cost Recovery Charge. A
mechanism to assist in recovery of
purchased power costs during
financial hardship.
CRCE: CRC Energy (GWh) as used in the
CRC and PYA formulas.
CRCEP: CRC Energy Percentage of full
SHP as used in the CRC and PYA
formulas.
CROD: Contract Rate of Delivery. The
maximum amount of capacity made
available to a preference customer for
a period specified under a contract.
CRSP: Colorado River Storage Project.
CRSP Act: An act to authorize the
Secretary of the Interior to construct,
operate, and maintain the Colorado
River Storage Project and
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
Participating Projects, and for other
purposes. (Act of April 11, 1956, ch.
203, 70 Stat. 105)
CRSP MC: The CRSP Management
Center of Western Area Power
Administration.
Customer: An entity with a contract that
is receiving firm electric service and
transmission from Western’s CRSP
MC.
DOE: United States Department of
Energy.
DOE Order RA 6120.2: An order
outlining power marketing
administration financial reporting and
ratemaking procedures.
DSW: Desert Southwest Region of
Western Area Power Administration.
EA: SHP Energy Allocation (GWh) as
used in the CRC formula.
EAC: Sum of customers’ energy
allocations subject to the PYA
formula.
Energy: Power produced or delivered
over a period of time. It is expressed
in kilowatthours.
Energy Rate: The rate which sets forth
the charges for energy. It is expressed
in mills/kWh and applied to each
kWh delivered to each Customer.
EIS: Environmental Impact Statement.
FA: Funds Available as used in the CRC
formula.
FA1: Basin Fund Balance Factor as used
in the CRC formula.
FA2: Revenue Factor as used in the CRC
formula.
FARR: Additional revenue to be
recovered as used in the CRC formula.
FE: Forecasted purchased energy as
used in the CRC formula.
FERC: Federal Energy Regulatory
Commission.
FFC: Forecasted average energy price
per MWh as used in the CRC and PYA
formulas.
Firm: A type of product and/or service
always available at the time requested
by the customer.
FRN: Federal Register notice.
FX: Forecasted energy purchased
expense as used in the CRC formula.
FY: Fiscal year is the period from
October 1 to September 30.
GWh: Gigawatthour. The electrical unit
of energy that equals 1 billion watthours or 1 million kWh.
HE: Forecasted hydro energy as used in
the CRC formula.
Integrated Projects: The resources and
revenue requirements of the Collbran,
Dolores, Rio Grande, and Seedskadee
projects blended together with the
CRSP to create the SLCA/IP resources
and rate.
kW: Kilowatt. The electrical unit of
capacity that equals 1,000 watts.
kWh: Kilowatthour. The electrical unit
of energy that equals 1,000 watts
produced or delivered in 1 hour.
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
52981
kWmonth: Kilowattmonth. The
electrical unit of the monthly amount
of capacity.
kWyear: Killowattyear. A unit of
electrical capacity demanded for
8,760 hours.
Load: The amount of electric power or
energy delivered or required at any
specified point(s) on a system.
Load-Ratio Share: Network customer’s
hourly load (including its designated
network load not physically
interconnected with Western)
coincident with Western’s monthly
CRSP transmission system peak.
M&I: Municipal and Industrial water.
MAF: Million Acre-Feet. The amount of
water required to cover 1 million
acres, 1 foot in depth.
Mill: A monetary denomination of the
United States that equals one-tenth of
a cent or one-thousandth of a dollar.
Mills/kWh: Mills per kilowatthour. A
unit of charge for energy.
MW: Megawatt. The electrical unit of
capacity that equals 1 million watts or
1,000 kilowatts.
MWh: One million watt-hours of electric
energy. A unit of electrical energy
which equals 1 megawatt of power
used for 1 hour.
NATRR: Net Annual Transmission
Revenue Requirement.
NB: Net Balance as used in the CRC
formula.
NEPA: National Environmental Policy
Act of 1969 (42 U.S.C. 4321, et seq.).
Non-firm: A type of product and/or
service not always available at the
time requested by the customer.
NR: The net revenue remaining after
paying all annual expenses as used in
the CRC formula.
OASIS: Open Access Same-Time
Information System.
O&M: Operation and Maintenance.
OM&R: Operation, Maintenance, and
Replacements.
PAE: Projected Annual Expenses as
used in the CRC formula.
PAR: Projected Annual Revenue
without the CRC as used in the CRC
formula.
Participating Projects: The projects
participating with CRSP according to
the CRSP Act of 1956 (43 U.S.C. 620).
PFE: Prior year actual firming energy as
used in the PYA formula.
PFX: Prior year actual firming expenses
as used in the PYA formula.
Pinch Point: The nearest future year in
the PRS where cumulative expenses
and required payments equal
cumulative revenues.
Power: Capacity and energy.
Preference: The provisions of
Reclamation Law which require
Western to first make Federal power
available to certain entities. For
E:\FR\FM\12SEN1.SGM
12SEN1
ebenthall on PROD1PC60 with NOTICES
52982
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
example, section 9(c) of the
Reclamation Project Act of 1939 (43
U.S.C. 485h(c)) states that preference
in the sale of Federal power shall be
given to municipalities and other
public corporations or agencies and
also to cooperatives and other
nonprofit organizations financed in
whole or in part by loans made under
the Rural Electrification Act of 1936.
Price: Average price per MWh for
purchased power as used in the CRC
formula.
Project Use: Power used to operate the
CRSP Participating Projects facilities
under Reclamation Law.
Proposed Rate: A rate that has been
recommended by Western to the
Deputy Secretary of DOE for approval.
Provisional Rate: A rate which has been
confirmed, approved, and placed into
effect on an interim basis by the
Deputy Secretary of DOE.
PRS: Power Repayment Study.
PYA: Prior Year Adjustment as used in
the CRC formula.
RA: Revenue Adjustment as used in the
PYA formula.
Rate Brochure: A document explaining
the rationale and background for the
rate proposal contained in this Rate
Order, dated January 2008.
Ratesetting PRS: The PRS used for the
rate adjustment proposal.
Reclamation: United States Department
of the Interior, Bureau of Reclamation.
Reclamation Law: A series of Federal
laws, viewed as a whole that create
the originating framework under
which Western markets power.
Revenue Requirement: The revenue
required to recover annual expenses,
such as O&M, purchased power,
transmission service expenses,
interest, deferred expenses,
repayment of Federal investments,
and other assigned costs.
RMR: Rocky Mountain Region of
Western Area Power Administration.
SHP: Sustainable Hydropower as
defined in the firm power contracts
for SLCA/IP.
SLCA/IP: Salt Lake City Area Integrated
Projects. The resources and revenue
requirements of the Collbran, Dolores,
Rio Grande, and Seedskadee projects
blended together with the CRSP to
create the SLCA/IP rate.
Supporting Documentation: A
compilation of data and documents
that support the Rate Brochure and
the rate proposal.
TRC: Transmission Revenue Credits.
TSTL: CRSP Transmission System Total
Load.
Western: United States Department of
Energy, Western Area Power
Administration.
WL: Waiver Level as used in the CRC
formula.
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
WLP: Waiver Level Percentage of full
SHP as used in the CRC formula.
WPR: Work Program Review. The work
plan is a draft estimate of costs that
are expected to be included in the
Congressional Budget for Western and
Reclamation and the basis for budget
estimates to be used in the PRS.
WRP: Western Replacement Power as
defined in the firm power contracts
for SLCA/IP.
Effective Date
The new interim rates will take effect
on the first day of the first full billing
period beginning on or after October 1,
2008, and will remain in effect until
September 30, 2013, pending approval
by FERC on a final basis.
Public Notice and Comment
Western followed the Procedures for
Public Participation in Power and
Transmission Rate Adjustments and
Extensions, 10 CFR part 903, in
developing these rates. The steps
Western took to involve interested
parties in the rate process were:
1. The proposed rate adjustment
process began May 30, 2007, when
Western mailed a notice announcing an
informal customer meeting on June 19,
2007, to all SLCA/IP customers and
interested parties.
2. On June 19, 2007, August 21, 2007,
and October 10, 2007, beginning at
10:30 a.m., informal customer meetings
were held to discuss the components
and rationale for the rate adjustment, to
discuss possible rate designs, and to
answer questions.
3. A Federal Register notice,
published on January 4, 2008 (73 FR
858), announced the proposed rate
adjustments for the SLCA/IP, CRSP
Transmission, and Ancillary Services
Rates. This publication began a public
consultation and comment period and
announced the public information and
public comment forums.
4. On January 11, 2008, Western’s
CRSP MC mailed all SLCA/IP
preference customers, CRSP
transmission customers, and interested
parties letters along with the Rate
Brochure, which contains a copy of the
published Federal Register notice
proposal and a reminder of the February
5, 2008, public information forum.
5. On February 5, 2008, beginning at
1:30 p.m., Western held a public
information forum at the Radisson Hotel
Salt Lake City Airport, Salt Lake City,
Utah. Western provided detailed
explanations of the proposed SLCA/IP
firm power rate and the CRSP
transmission and ancillary service rates.
Western provided Rate Brochures,
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
supporting documentation, and
informational handouts at this meeting.
6. On March 4, 2008, beginning at
1:30 p.m., Western held a comment
forum at the Radisson Hotel Salt Lake
City Airport, Salt Lake City, Utah, to
give the public an opportunity to
comment for the record. Western also
notified its customers of its intent to
extend the comment and consultation
period through May 5, 2008, and to hold
additional information and comment
forums.
7. On March 12, 2008, Western’s
CRSP MC mailed a flyer to all SLCA/IP
customers, CRSP transmission
customers, and interested parties
notifying them of a second public
information forum and a second
comment forum.
8. A Federal Register notice,
published March 24, 2008 (73 FR
15519), announced the extension of the
comment and consultation period for
the SLCA/IP firm power, CRSP
transmission and ancillary services
rates.
9. On March 24, 2008, CRSP MC
mailed all SLCA/IP customers, CRSP
transmission customers, and interested
parties a letter with a copy of the
published FRN extending the comment
and consultation period for the SLCA/
IP firm power, CRSP transmission and
ancillary services rates.
10. On April 10, 2008, beginning at
1:30 p.m., Western held its second
public information forum at the Bureau
of Reclamation, Wallace F. Bennett
Federal Building, Room 8102, 125 South
State Street, Salt Lake City, Utah.
11. On April 10, 2008, beginning at
2:35 p.m., Western held its second
comment forum at the Bureau of
Reclamation, Wallace F. Bennett Federal
Building, Room 8102, 125 South State
Street, Salt Lake City, Utah.
12. Western received 17 comment
letters during the consultation and
comment period, which ended May 5,
2008. All formally submitted comments
have been considered in preparing this
Rate Order.
Comments
Written comments were received from
the following organizations:
Arizona Tribal Energy Association,
Arizona (2),
Farmington Electric Utility System, New
Mexico,
Colorado River Energy Distributors
Association, Arizona (3),
Grand Canyon Trust, Arizona,
Inter Tribal Council of Arizona, Inc.,
Arizona,
Irrigation & Electrical Districts
Association of Arizona, Arizona,
Living Rivers, Utah (2),
E:\FR\FM\12SEN1.SGM
12SEN1
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
were to increase marketable resources,
simplify contract and rate development
and project administration by creating
one rate and to ensure repayment of the
Projects’ costs. All Integrated Projects
maintain their individual identities for
financial accounting and repayment
purposes, but their revenue
requirements are integrated into the
SLCA/IP PRS for ratemaking.
Murray City Corporation, Utah (2),
Navajo Tribal Utility Authority,
Arizona,
Salt River Pima-Maricopa Indian
Community, Arizona,
Utah Associated Municipal Power
Systems, Utah,
Yavapai-Apache Nation, Arizona.
Representatives of the following
organizations made oral comments:
Arizona Tribal Energy Association,
Arizona, Colorado River Energy
Distributors Association, Arizona,
Navajo Tribal Utility Authority,
Arizona,
Utah Associated Municipal Power
Systems, Utah.
Project Description
The SLCA/IP consists of the CRSP,
Rio Grande, and Collbran projects. The
CRSP includes two participating
projects that have power facilities: the
Dolores and Seedskadee projects.
Western integrated the Rio Grande and
Collbran projects with CRSP for
marketing and ratemaking purposes on
October 1, 1987. The goals of integration
Power Repayment Study—Firm Power
Rate
Western prepares a PRS each FY to
determine if revenues will be sufficient
to repay, within the required time, all
costs assigned to the SLCA/IP.
Repayment criteria are based on policies
(including DOE Order RA 6120.2) and
authorizing law.
Provisional rates for SLCA/IP firm
power result in an overall composite
rate increase of approximately 17.4
percent, when compared to the existing
SLCA/IP firm power rates in Rate
Schedule SLIP–F8. The current
composite rate under Rate Schedule
SLIP–F8 is 25.28 mills/kWh. The
52983
provisional rates for SLCA/IP firm
power in Rate Schedule SLIP–F9 will be
implemented over a 2-year period
resulting in a composite rate of 26.80
mills/kWh on October 1, 2008, and a
composite rate capped at 29.68 mills/
kWh on October 1, 2009. In the first
year, the provisional firm power rate
consists of an energy charge of 11.06
mills/kWh and a capacity charge of
$4.70/kWmonth. The second step of the
rate will be effective October 1, 2009
through September 30, 2013, or until
superseded. The energy charge will not
exceed 12.29 mills/kWh and the
capacity charge will not exceed $5.22/
kWmonth. The actual rates for the
second step will be determined using
2008 actual data, updated estimates for
purchased power and transmission, as
well as other revised estimates that
could affect the rate. Western will
provide customers an opportunity to
comment on the second step during a
meeting scheduled for June 2009. The
following table compares the current
and proposed firm power rates.
COMPARISON OF CURRENT AND PROPOSED FIRM POWER RATES
Current rate
October 1, 2005–
September 30,
2010
Rate Schedule ............................................................
Energy (mills/kWh) ......................................................
Capacity ($/kWmonth) ................................................
Composite Rate (mills/kWh) .......................................
1 Maximum
Proposed rate
October 1, 2008
(1st step)
Percent
increase
for 1st
step
Proposed rate1
October 1, 2009–
September 30,
2013
(2nd step)
Total
percent
increase
SLIP–F8 .................
10.43 ......................
4.43 ........................
25.28 ......................
SLIP–F9 .................
11.06 ......................
4.70 ........................
26.80 ......................
................
6.0
6.0
6.0
SLIP–F9 .................
12.29 ......................
5.22 ........................
29.68 ......................
................
17.8
17.9
17.4
rate for FY 2010.
ebenthall on PROD1PC60 with NOTICES
Cost Recovery Charge
Trigger for Shortage Criteria
Narrative PYA Discussion
Western is proposing to continue the
CRC calculation and assessment in the
proposed rate schedule as it is in the
current SLIP–F8 rate schedule and to
add an additional triggering mechanism.
The CRC is based on a Basin Fund
cash analysis only and is independent
of the PRS calculations. In the event that
expenses significantly exceed estimates
and in order to adequately recover and
maintain a sufficient balance in the
Basin Fund, Western will calculate and
assess a CRC. The CRC is designed to
maintain a Basin Fund Target Balance
(BFTB) for the following FY and to limit
the FY loss to the Basin Fund. The
BFTB will be equal to 15 percent of the
upcoming FY’s total expenses but not
less than $20 million. The allowable FY
loss is limited to no more than 25
percent of the Basin Fund Beginning
Balance (BFBB). For purposes of
explaining how the CRC is calculated,
please refer to Rate Schedule SLIP–F9.
In the event that Reclamation’s 24month study projects that Glen Canyon
Dam water releases will drop below 8.23
MAF in a water year (October through
September), Western will recalculate the
CRC to include those lower estimates of
hydropower generation and the
estimated costs for any additional
purchased power. Western, as in the
yearly projection for the CRC, will give
the customers a 45-day notice, during
which they may request a waiver of the
CRC by voluntarily taking less energy
than allowed under the customer’s Firm
Electric Service contract. This
recalculation will remain in effect for
the remainder of the current FY. In the
event that hydropower generation
returns to 8.23 MAF or higher during
the CRC implementation, a new CRC
will be calculated for the next month,
and the customers will be notified.
Since the annual determination of the
CRC is based upon estimates, an annual
prior year adjustment (PYA) will be
calculated. The CRC PYA for
subsequent years will be determined by
comparing the prior year’s estimated
firming energy cost to the prior year’s
actual firming energy cost for the energy
provided above the Waiver Level. The
PYA will result in an increase or
decrease to a customer’s firm energy
costs over the course of the following
year. Please see Rate Schedule SLIP-F9
rate schedule for further explanation of
the PYA calculation.
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
CRC Schedule for Customers
Western will provide its customers
with information concerning the
anticipated CRC for the upcoming FY in
May. The established CRC will be in
effect for the entire FY. The table below
displays the time frame for determining
the amount of purchases needed,
E:\FR\FM\12SEN1.SGM
12SEN1
52984
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
CRC SCHEDULE
Task
April 24-Month Study (Forecast
to Model Projections).
CRC Notice to Customers .........
Waiver Request Submitted by
Customers.
CRC Effective ............................
Date1
April 1.
May 1.
June 15.
October 1.
1 Note:
This schedule does not apply if the
CRC is triggered by the Glen Canyon Dam
annual releases dropping below 8.23 MAF.
CRSP Transmission Rates Discussion
ebenthall on PROD1PC60 with NOTICES
The proposed firm and non-firm
transmission rates apply to all
transmission-only sales. The present
CRSP point-to-point, network, and nonfirm transmission rates, outlined in Rate
Schedules SP–PTP6, SP–NW2, and SP–
NFT5 became effective on October 1,
2002. On June 29, 2007, the Deputy
Secretary of Energy extended the
transmission rates through September
30, 2010. The transmission rates include
the cost for scheduling, system control,
and dispatch service. Western is
proposing that these three rates remain
in effect for this new ratesetting period.
The cost of transmission service for
Western’s SLCA/IP long-term electric
service will continue to be included in
the SLCA/IP firm power rate.
Transmission services are outlined in
Western’s Tariff.
Western is proposing to use the
current methodology, which is an
annual fixed charge formula, to
determine the revenue requirement to
be recovered from firm and non-firm
transmission service. The annual
transmission revenue requirement
includes O&M expenses, administrative
and general expenses, interest expense,
and depreciation expense. This
methodology is updated annually using
a test year, which is the most recent
historical data available. This revenue
requirement is offset by appropriate
CRSP transmission system revenues.
The provisional rate for network
transmission service is a formula
calculation based on the annual
transmission revenue requirement.
There are no changes to the existing
network integration transmission
service formula under Rate Schedule
SP–NW2.
Firm Point-to-Point
Western is seeking the continued
approval of a rate formula for
calculation of the firm point-to-point
transmission rate to be applied
annually. The provisional rate for firm
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
point-to-point transmission service is
$2.21/kWmonth for FY 2008.
The firm point-to-point transmission
rate is based upon the most recent
historical year, using an annual fixedcharge methodology. The annual
transmission revenue requirement is
reduced by revenue credits such as nonfirm transmission, existing contracts at
different rates, scheduling and dispatch
services, and phase-shifter revenues.
The resultant net annual transmission
revenue requirement is divided by the
capacity reservation needed to meet
firm power and transmission-only
commitments in kW, including the total
network integration loads at system
peak, to derive a cost/kWyear. The
formula is updated every year by
applying the most current historical test
year. If needed, a revised rate will
become effective every October 1. The
rate formula is proposed to be effective
October 1, 2008, through September 30,
2013.
The cost/kWyear is calculated using
the following formula:
(1) ATRR − TRC = NATRR
NATRR
(2)
TSTL
Where:
ATRR = Annual Transmission Revenue
Requirement. The costs associated with
facilities that support the transfer
capability of the CRSP transmission
system, excluding generation facilities.
These costs include investment costs,
interest expenses, depreciation expense,
administrative and general expenses, and
operation and maintenance expense,
including transmission purchases.
Transmission purchases reflect those
costs associated with CRSP contractual
rights.
TRC = Transmission Revenue Credits. The
revenues generated by the CRSP
transmission system not related to the
revenues from the sale of long-term firm
transmission.
NATRR = Net Annual Transmission Revenue
Requirement. The Annual Revenue
Requirement minus Transmission
Revenue Credits.
TSTL = CRSP Transmission System Total
Load. The sum of the total CRSP
transmission capacity under long-term
reservation including the total network
integration loads at system peak.
Non-Firm Point-to-Point Transmission
The proposed rate for non-firm pointto-point CRSP transmission service is a
mills/kWh rate, which is based upon the
current firm point-to-point rate and may
be discounted. This rate will remain in
effect concurrently with the firm pointto-point rate and will also be reviewed
annually. Transmission availability will
be posted on Western’s OASIS.
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
Network Transmission
The proposed rate for network
transmission is a calculation based upon
the annual revenue requirement then in
effect, as determined by the annual
fixed charge methodology.
Ancillary Services Discussion
Six ancillary services will continue to
be offered by CRSP MC, two of which
are required as part of CRSP
transmission service. These are (1)
Scheduling, system control, and
dispatch service and (2) reactive supply,
and voltage control service. The
remaining four ancillary services are (3)
regulation and frequency response
service, (4) energy imbalance service, (5)
spinning reserve service, and (6)
supplemental reserve service. These
will be offered either from the balancing
authority or from the CRSP MC
Merchant Function. Sales of regulation
and frequency response, energy
imbalance, spinning reserve, and
supplemental reserve services from
SLCA/IP power resources are limited
since Western has allocated the SLCA/
IP power resources to preference entities
under long-term commitments. Western
has made a clarification to its spinning
and supplemental reserve ancillary
services and has removed its reference
to the Western System Power Pool
Agreement. Western will continue to
use market-based rates to determine its
rate for spinning and supplemental
reserves under the Rate Schedule SSP–
SSR3. The availability and type of
ancillary service will be determined
based on excess resources available at
the time the services are requested,
except for the two ancillary services
required to be provided in conjunction
with the sale of CRSP transmission
services.
Since the CRSP transmission system
lies in two balancing authorities,
operated by Western’s RMR and DSW,
many of the ancillary services are
offered through their respective
balancing authorities.
The provisional rates for ancillary
services are designed to recover only the
costs associated with providing the
service(s). The costs for providing
scheduling, system control, and
dispatch service are included in the
appropriate provisional transmission
services rates. However, the charges for
reactive supply and voltage control
service will be in accordance with
Western’s RMR and DSW applicable
rate schedules.
Existing and Provisional Rates
A comparison of the existing and
provisional SLCA/IP firm power rates,
E:\FR\FM\12SEN1.SGM
12SEN1
EN12SE08.000
developing customer’s load schedules,
and making purchases.
52985
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
CRSP Transmission and Ancillary
Services, follows:
COMPARISON OF EXISTING AND PROVISIONAL SALT LAKE CITY AREA INTEGRATED PROJECTS FIRM POWER, COLORADO
RIVER STORAGE PROJECT TRANSMISSION AND ANCILLARY SERVICES
Current rate
October 1, 2005–
September 30, 2010
Provisional rate
October 1, 2008
(1st step)
Percent increase
for 1st step
Provisional rate1
October 1, 2009–
September 30, 2013
(2nd step)
Energy (mills/kWh) ...................
CRC (if applicable) ..................
Capacity ($/kWmonth) .............
Composite Rate (mills/kWh) ....
Firm Transmission Rate ..........
10.43 ......................
varies ......................
4.43 ........................
25.28 ......................
$2.21 (FY 08) .........
Network Transmission (net annual revenue requirement).
Non-firm Transmission Rate ....
$72,613,170 (FY
08).
3.03 mills/kWh, may
be discounted
(FY 08).
N/A .........................
11.06 ......................
varies ......................
4.70 ........................
26.80 ......................
To be determined
for FY 09.
To be determined
for FY 09.
To be determined
for FY 09.
6 .............................
varies ......................
6 .............................
6 .............................
To be determined
for FY 09.
To be determined
for FY 09.
To be determined
for FY 09.
12.29 ......................
varies ......................
5.22 ........................
29.68 ......................
To be determined
for FY 10.
To be determined
for FY 10.
To be determined
for FY 10.
17.8.
varies.
17.9.
17.4.
To be determined
for FY 10.
To be determined
for FY 10.
To be determined
for FY 10.
N/A .........................
N/A .........................
N/A .........................
N/A.
Ancillary Services 2 ..................
Total percent
increase
1 Maximum
rate for FY 2010–2013.
2 Since all of CRSP transmission facilities are located in two Western balancing authorities, these services are provided through these balancing authorities.
Certification of Rates
Western’s Administrator certified that
the provisional rates for SLCA/IP firm
power, CRSP transmission, and
ancillary services are the lowest
possible rates consistent with sound
business principles. The provisional
rates were developed following
administrative policies and applicable
laws.
SLCA/IP Firm Power Rate Discussion
According to Reclamation Law,
Western must establish power rates
sufficient to recover O&M expenses,
purchased power expenses, interest
expenses, and repayment of power
investment and irrigation aid.
The existing rate for SLCA/IP firm
power under Rate Schedule SLIP–F8
expires September 30, 2010. Effective
October 1, 2008, Rate Schedule SLIP–F8
will be superseded by the new rates in
Rate Schedule SLIP–F9. The provisional
rates for SLCA/IP firm power consist of
a capacity rate and an energy rate. The
provisional rates for SLCA/IP firm
power in Rate Schedule SLIP–F9 will
result in a composite rate of 26.80 mills/
kWh on October 1, 2008, and a
composite rate capped at 29.68 mills/
kWh on October 1, 2009. The
provisional firm power rate will be
implemented over a 2-year period. In
the first year, the provisional firm power
rate consists of an energy charge of
11.06 mills/kWh and a capacity charge
of $4.70/kWmonth. The second step of
the rate will be effective October 1,
2009, through September 30, 2013, or
until superseded, and will be capped at
the energy charge of 12.29 mills/kWh
and a capacity charge of $5.22/
kWmonth.
Statement of Revenue and Related
Expenses
The following table provides a
summary of projected revenue and
expense data for the SLCA/IP firm
power rate through the 5-year
provisional rate approval period.
SLCA/IP FIRM POWER—COMPARISON OF 5-YEAR RATE PERIOD (FY 2009–FY 2013) TOTAL REVENUES AND EXPENSES
[$000]
Existing rate
Proposed
rate with
cap
Difference
ebenthall on PROD1PC60 with NOTICES
Total revenues .......................................................................................................................................
Revenue Distribution
Expenses:
O&M ................................................................................................................................................
Purchased Power and Transmission .............................................................................................
Integrated Projects Requirements ..................................................................................................
Interest ............................................................................................................................................
Other ...............................................................................................................................................
828,785
919,125
90,340
314,501
76,489
38,820
33,165
17,789
348,731
133,525
37,733
67,551
14,784
34,230
57,036
(1,087)
34,386
(3,005)
Total Expenses ........................................................................................................................
Principal Payments:
Capitalized Expenses (deficits) ......................................................................................................
Original Project and Additions ........................................................................................................
Replacements .................................................................................................................................
Irrigation ..........................................................................................................................................
Irrigation to Participating Projects ..................................................................................................
480,764
602,324
121,560
0
198,009
137,183
12,829
0
0
96,812
206,803
13,186
0
0
(101,197)
69,620
357
0
Total Principal Payments ........................................................................................................
348,021
316,801
(31,220)
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
E:\FR\FM\12SEN1.SGM
12SEN1
52986
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
SLCA/IP FIRM POWER—COMPARISON OF 5-YEAR RATE PERIOD (FY 2009–FY 2013) TOTAL REVENUES AND
EXPENSES—Continued
[$000]
Existing rate
Total Revenue Distribution ...............................................................................................
Basis for Rate Development
The existing rates for SLCA/IP firm
power in Rate Schedule SLIP–F8 no
longer provide sufficient revenues to
pay all annual costs, including interest
expense, and repayment of investment
and irrigation aid within the allowable
periods. The adjusted rates reflect
increases primarily in O&M costs and
purchased power and transmission
costs. The provisional rates will provide
sufficient revenue to pay all annual
costs, including interest expense, and to
repay power investment and irrigation
aid within the allowable periods. To
coincide with the start of each FY, the
provisional rates for the first step will
take effect on October 1, 2008. The
provisional rates for the second step
will take effect on October 1, 2009, and
remain in effect through September 30,
2013.
Provisions for transformer losses
adjustment, power factor adjustment,
WRP administrative charge, and CDP
administrative charge adjustments are
part of the provisional rates for SLCA/
IP firm power. Western will not modify
the provisions and methodologies for
these adjustments, which will remain as
specified in Rate Schedule SLIP–F9.
Comments
The comments and responses
regarding the firm power rate,
paraphrased for brevity when not
affecting the meaning of the
statement(s), are discussed below. Direct
quotes from comment letters are used
for clarity where necessary. The rate
process issues discussed are (1) Firm
Power Rate Design, (2) Cost Recovery
Charge, (3) Stepped Rate, (4) Basin
Fund, (5) Revenue, (6) Western
Expenses, (7) Reclamation Expenses and
Related Issues, (8) Project Use, (9)
Environmental, (10) Hydrology, (11)
Transmission and Ancillary Services,
and (12) Miscellaneous.
ebenthall on PROD1PC60 with NOTICES
1. Firm Power Rate Design
Comment: Many customers expressed
appreciation for the CRSP MC and its
willingness to engage in meaningful
dialogue, entertain suggestions, and
develop alternatives to mitigate
significant rate increases.
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
Response: The CRSP MC is likewise
appreciative of the customers’ support.
Comment: Pages 6 and 8 of the Rate
Brochure reference the ‘‘ratesetting
period’’ of 17 years as opposed to 20
years. Please explain why a different
ratesetting period was used. Are the
current rates in effect based upon a 20year ratesetting period?
Response: The current rate is based on
a 20-year ratesetting period. The
ratesetting period begins the year the
rate took effect (FY 2006) and continues
through the pinch point year (FY 2025).
The pinch point year is the year of the
PRS that has the largest revenue
requirements.
The proposed rate will take effect in
October 2008, which is the beginning of
FY 2009. Since the proposed ratesetting
period extends through the same pinch
point year, the ratesetting period of the
proposed rate is 3 years shorter than
that of the current rate.
Comment: Some customers requested
copies of all documents and information
used to develop the cost basis for the
O&M component of the new rate
included in the PRS.
Response: Documents and
information used to develop the cost
basis for the O&M component of the rate
proposal were included in the
Supporting Documentation Booklet,
specifically Tab 10, which had been
previously provided to requestors. In
addition, the requestors were sent
copies of the CRSP MC Work Program
Review documents for FY 2006 through
FY 2010.
Comment: One commenter asked
Western to explain on what basis
Western could extend the collection of
revenues for apportionment such that
rate impacts of those obligations are
reduced.
Response: Western adheres
specifically to section 5(e) of the CRSP
Act, which requires the inclusion of the
apportionment of revenues for the
States, in the Power Repayment Studies.
In addition, DOE Order RA6120.2
provides further clarification of the
treatment of repayment periods,
specifically in section 12(b)(5), which
states ‘‘expected revenues are at least
sufficient to recover other costs such as
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
828,785
Proposed
rate with
cap
919,125
Difference
90,340
payments to basin funds, Participating
Projects or States.’’
Comment: One commenter asked
Western, ‘‘Please run the PRS and
provide the results excluding the funds
categorized as ‘Available w/Appor’
found behind Tab 19 of the CRSP MC
Supporting Documentation for Proposed
Rates: SLCA/IP Firm Power, CRSP
Transmission & Ancillary Services dates
January 2008 on the sheet titled
‘Colorado River Storage Project, Aid to
Participating Projects Irrigation
Repayment Obligations and
Apportioned Revenue Applied’ totaling
$642,582,791, which are not tied to
authorized projects.’’
Response: The proposed rate includes
the apportionment revenues required to
be collected through FY 2025 (about
$368 million). The PRS was rerun
without the excess revenue collection
for apportionment required by the CRSP
Act. Removing these apportionment
collections from the repayment period
lowered the composite rate by 2.61
mills/kWh.
Comment: Multiple comments were
received concerning the inclusion of
apportionment revenue collection in the
rate, mentioning that $368 million of
revenues for apportionment payments
would be received by FY 2025. The
customers objected to the inclusion of
these apportionment revenues in the
ratesetting period and recommended
that apportionment costs associated
with unauthorized, unconstructed
projects be programmed into the PRS
beyond the pinch point year.
Response: Section 5(e) of the CRSP
Act specifies that revenues in the Basin
Fund in excess of the amounts needed
to defray the cost of operation,
maintenance and replacement of the
CRSP Project, and to return to the
general fund of the Treasury costs
allocated to power, municipal water
supply, irrigation and salinity control
shall be apportioned to the four Upper
Colorado Basin States to assist in the
repayment of participating projects
located within these States. Section 5(e)
specifies that such excess ‘‘revenues in
the Basin Fund * * * shall be
apportioned among the states of the
Upper Division in the following
percentages: Colorado, 46 per centum;
E:\FR\FM\12SEN1.SGM
12SEN1
ebenthall on PROD1PC60 with NOTICES
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
Utah, 21.5 per centum; Wyoming, 15.5
per centum; and New Mexico, 17 per
centum * * *.’’ Funds so apportioned
must be used only for the repayment of
construction costs of participating units
located in the states to which such
revenues are apportioned.
Comment: A commenter stated that
approximately 60 percent of the
proposed rate increase appears to be due
to apportionment expenses associated
with presently non-existent,
unauthorized projects.
Response: The comment correctly
observes that removing the
apportionment obligation from the
proposed rate would reduce the
proposed rate increase by approximately
60 percent; however, as discussed
above, the apportionment obligation is
required by law, and as such, the
apportionment obligations are already
included in the current rate and
therefore play no part in the proposed
17 percent increase. The 17 percent
increase is due mainly to O&M and
purchased power and transmission
expense, not because of adding ‘‘new’’
Participating Projects costs.
Comment: A comment was received
referring to the 1983 agreement between
Reclamation and Western that provides
guidance for inclusion of Participating
Projects into the PRS and believes that
Western should follow this guidance.
Response: Western currently abides
by the 1983 agreement when including
Participating Projects into the PRS by
including only those authorized
Participating Projects costs in the rate
that meet the criteria. The
apportionment methodology is then
applied toward those projects.
Comment: On what basis, other than
historic practice or internal agency
opinion, does Western justify inclusions
of continued apportionment funds for
non-authorized projects in the PRS?
Response: Western adheres to the
CRSP Act, specifically section 5, which
requires the inclusion of the
Participating Projects and the
apportionment of revenues in the PRS.
In addition, DOE Order RA 6120.2,
specifically section 12(b)(5), states,
‘‘expected revenues are at least
sufficient to recover other costs such as
payments to basin funds, Participating
Projects or States.’’ Western’s obligation
to collect apportionment revenues is
independent of a state’s authorization to
spend their apportioned revenues.
Comment: A commenter states it is
undisputed that the current rate will
collect sufficient revenues to meet all
proposed expenditures over the 5-year
rate window.
Response: It is true that the current
rate will collect sufficient revenues for
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
a 5-year, rate cost evaluation period.
However, DOE Order RA 6120.2, section
12, requires revenues to be sufficient to
recover annual expenses and repayment
through the ratesetting period (through
FY 2025 in this ratesetting PRS).
According to Reclamation Law, Western
must establish power rates sufficient to
recover O&M expenses, purchased
power expenses, interest expenses, and
repayment of power investment and
irrigation aid. For the current 17-year
ratesetting period, from FY 2009
through FY 2025, the current rate is not
sufficient to cover expenses and
repayment through this period. The
current rate shows deficits in some of
these years, including the final year of
the study; therefore, the proposed rate
adjustment is needed.
Comment: Many comments were
received stating that the comment
period closing on May 5 was before the
end of the formal FY 2010 WPR period
of May 21 and wanted to ensure their
comments on the FY 2010 WPR were
incorporated into the final Rate Order.
Some comments suggested Western
extend the comment period for this rate
process another 30 days, closing on June
4, 2008. Others recommended that the
O&M components of this rate
proceeding continue to be scrubbed and
refined in consultation with the
customers prior to finalization of this
rate proposal. One commenter went on
to state, ‘‘because the formal work
program process has not yet concluded
prior to the comment deadline * * * we
reserve the right to comment on those
adjustments prior to finalization of the
rate.’’
Response: Western’s FY 2010 WPR
has been finalized; however, Western is
committed to continue to work with its
customers to try to reduce the budgeted
estimates. Western also believes that
since the second step is capped, the
second step firm power rate can be
reduced if the budget estimates are too
high. In addition, Western is willing to
work with its customers on the FY 2011
budget process which will be used to
determine the second step of the rate
that will be effective October 1, 2009.
Comments: When will the FY 2010
WPR materials be available, and when
will a new PRS be run with updated
data? Will this update be provided
before the comment forum, or will it be
after the comment forum and before the
close of the comment period? When will
the FY 2010 WPR be finalized?
Response: The WPR process for the
FY 2010 budget was held on February
28, 2008. Western has since reviewed
those costs to streamline them as much
as possible. Western presented these
updates to planned O&M costs based on
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
52987
the updated FY 2010 WPR in the second
public information forum, which was
held on April 10, 2008.
Comment: Another customer
encouraged Western to come to some
decisions so they can incorporate the
forecasted rates into their budget
planning process.
Response: Western recognizes that its
customers have a budget planning
process and the rate adjustment has an
effect on its customers’ internal
processes. Western will be forthcoming
with the final rates as soon as the Acting
Deputy Secretary places the rates into
effect on an interim basis.
2. Cost Recovery Charge
Comment: A comment was made that
the early portions of the Rate Brochure
indicate the CRC would remain in effect
for an entire FY. However, page 17
proposes triggering criteria with a 45day customer notice.
Response: The firm power rate
proposal includes the CRC similar to the
existing rate except that it also includes
a new, additional, triggering criteria
caused by reduced releases from Glen
Canyon Dam. This new triggering
criteria has the same 45-day customer
notice as the Basin Fund balance
criteria, but could occur whenever
Reclamation’s 24-month study indicates
Glen Canyon water releases will be
reduced to less than 8.23 million acrefeet in a water year. This can happen
any time during the year.
Comment: A comment was made
regarding the CRC and the example
shown on page 14 of the Rate Brochure.
The commenter asked if the calculation
of annual expenses includes other
revenues as an expense offset or are they
included in total revenue.
Response: The CRC includes all
revenues and expenses. No offsetting of
revenue or expenses occurs except for
the purpose of calculating the CRC, nonreimbursable environmental expenses
are capped at $27 million and indexed
for inflation.
Comment: Several customers
referenced a CRC ‘‘adjuster’’ or credit
mechanism whereby when actual
purchased power expenses do not meet
projections, a credit would be returned
to the firm power customers similar to
one in place at the Southwestern Power
Administration. ‘‘Consider if FX is less
than projected, the differential could be
spread over all MWh, OR if FA is greater
than FARR, the differential could be a
credit.’’
Response: The CRC already includes
a PYA true-up from estimates to actuals.
For Western to implement an
adjustment similar to Southwestern
Power Administration, purchased
E:\FR\FM\12SEN1.SGM
12SEN1
52988
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
ebenthall on PROD1PC60 with NOTICES
power would have to be unbundled
from the firm power rate. The current
method of socializing all purchased
power costs into the SLCA/IP firm
electric service rate would not be
conducive to using a purchased power
adjustment. The CRC includes a PYA
true-up from estimates to actuals that is
only applicable to those customers
actually assessed a CRC because they
are the ones who paid the estimated
costs of purchasing additional firming
energy. The customers who receive a
CRC waiver acquire their needed
additional energy elsewhere.
3. Stepped Rate
Comment: What internal process(es)
would be required in order to change
the CRSP MC ratemaking methodology
from the pinch point to another
methodology? Is Western open to this
type of discussion?
Response: Western would be willing
to discuss any ratemaking methodology
that is within its constraints of law and
policy.
Comment: When will the decision be
made whether or not Western will
implement the stepped rate?
Response: Western has decided to
implement the stepped rate with the
first step being effective October 1,
2008.
Comment: How would the stepped
rate work? Would the rate be one certain
percentage, and in the second year the
rates would automatically go up? Would
the rate be based on the most current
PRS in that year?
Response: The first year will be a
composite rate of 26.80 mills/kWh,
which is a 6 percent increase. The
second step will be capped at 29.68
mills/kWh for the composite rate. This
would be the maximum amount for the
second step. The second step rate will
be determined by using FY 2008 actual
data, updated estimates for purchased
power and transmission, as well as
other estimates that could affect the rate.
As of now, and for analysis purposes,
the total composite rate of 29.68 mills/
kWh will be effective October 1, 2009.
Comment: The majority of customers
requested that Western consider
delaying the proposed SLCA/IP rate
adjustment by at least 1 year, stating
that because there are a number of
uncertainties associated with the
proposed rate that may be resolved,
thereby eliminating or reducing the
need for such a high rate by October 1,
2009. These customers recommend a
deferment of the rate until October 1,
2009. In the event Western is unable to
defer the rate process, they recommend
the implementation of a stepped rate
with the first step October 1, 2008, of
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
zero percent and the second step
October 1, 2009, not to exceed 18
percent.
Response: Western believes that
implementation of a zero-percent
increase in the first year is the same as
a 1-year deferment of the rate
adjustment and is not fiscally
responsible. Western is implementing a
stepped rate with the first step being
26.80 mills/kWh, which is a 6 percent
increase. The second step will not
exceed the cap of 29.68 mills/kWh for
an overall 17.4 percent increase from
the current 25.28 mills/kWh rate.
Western believes that this will allow
sufficient time to adjust projections
based on the current uncertainties and
possibly a second step increase that is
less than current projections.
The second step will use the FY 2008
Final PRS, the FY 2011 WPR with the
same 5-year cost evaluation period
(2008–2012), the April 2009, 24-month
study from Reclamation, and the most
current data available for all other
projections.
4. Basin Fund
Comment: Please provide an
accounting of revenues and expenses
which would explain the Basin Fund
climbing from $40 million at the end of
FY 2005 to $80 million at the end of the
current operating year.
Response: There are many variables
that affect the Basin Fund balance
increase; however, the main reason for
the increase is the almost $116 million
collected from power revenues for
interest expense and principal payments
during the years FY 2006 through FY
2008. The main offset to these
collections is non-reimbursable
environmental expenses.
In addition, Western has not been able
to return funds to Treasury since FY
1999 because of the continued drought.
If the Basin Fund continues to be as
healthy as it is today, Western is
planning to return funds to Treasury
this FY to satisfy the return of interest
and principal obligations, as required
under the CRSP Act.
Comment: Several comments on the
projected ‘‘healthy’’ ending balance of
the Basin Fund suggest the rate process
is not necessary. A commenter cited that
Western has announced if the ending
FY 2008 Basin Fund balance is at the
current projected level, Western will
probably make a transfer of funds to
Treasury. They further stated that
‘‘under these circumstances, holding the
rate steady while adjusting for
significantly increased hydrology and a
change in law is perfectly appropriate
and the sound course of action’’.
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
Response: Western reiterates the fact
that the balance in the Basin Fund does
not determine the need for a rate
process. In accordance with DOE Order
RA 6120.2, if revenues are not sufficient
to cover expenses and repayment
obligations as determined by the PRS,
the current rate is inadequate and must
be adjusted.
Comment: One commenter stated
concern that ‘‘the fund itself may
evaporate, for which Western has
identified no contingencies. Such
revenue losses would have tremendous
repercussions on funding for those
environmental programs to reduce
salinity and remove jeopardy for
endangered fish.’’
Response: Environmental program
expenses are non-reimbursable by the
power customers and are not included
in the PRS for ratemaking purposes.
However, the programs are funded out
of the Basin Fund, and the costs are
credited as funds returned to Treasury
for repayment of CRSP obligations.
5. Revenue
Comment: A commenter asked
Western to explain the assumed
reduction in transmission revenue given
the strategic planning process to
improve transmission marketing
services and if the transmission
revenues used in this PRS factor in the
new increased transmission rate.
Response: Firm transmission revenue
estimates in the PRS are based on firm
contracts and rates currently in place.
Non-firm transmission revenue
estimates are based on a 5-year average
of historical data. Western has no way
to estimate increased revenues that may
occur due to efforts to improve
transmission marketing services.
Comment: One commenter requested
the first part of 2008 be included in the
historical averages.
Response: Western only used actuals
from FY 2003 through FY 2007. Western
will include FY 2004 through FY 2008,
when determining the second step of
the firm power rate that will be effective
October 1, 2009.
6. Western Expenses
Comment: One commenter
questioned, ‘‘Given Western’s work on
operational consolidation, what are the
implications for this rate process, and
specifically, what impacts will there be
on RMR’s work on the new billing
system?’’
Responses: The increase in power
billing is related to RMR information
technology (IT) staff that will be
supporting the new power billing
system. Over the last 3 to 4 years, the
Sierra Nevada Region maintained the
E:\FR\FM\12SEN1.SGM
12SEN1
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
old system with minimal enhancements
for RMR. As a result, the IT support
costs have been very negligible. While
the billing system is being developed,
the costs will be capitalized. After that
time, additional support will be
expected the first year or so to get the
system running smoothly and to
document processes. As for cost
allocation of the new power billing
system, additional information will be
provided next year. RMR and the CRSP
MC will work with their customers on
the allocation methodology based on the
design of the new system and various
other factors.
Comment: One customer wanted to
know if the ‘‘50–5–5’’ expenses drop
back to a lower level after FY 2010.
Response: The 50–5–5 initiative (50
‘‘over-hires,’’ over 5 years, at an
approximate cost of $5 million) is a
recent Western-wide program designed
to hire new staff into trainee positions
as part of Western’s succession
planning. The funding for these
additional over-hire positions has been
placed in Western’s FY 2010 budget
submissions. The intent of this program
is that for each trainee hired, there is a
target retirement position. Once these
retirements occur, the trainees will fill
these positions and staffing levels will
become flat again in FY 2013 and
beyond.
ebenthall on PROD1PC60 with NOTICES
7. Reclamation Expenses and Related
Issues
Comment: A commenter wanted to
know if the amounts included in the
ratesetting PRS take into account the
new legislation with a cap on security
costs. In addition, they wanted to know
how the future years’ projected amounts
were derived, and what basis was used
for the 94.7 percent share to power.
They suggest the rate process should be
deferred until the impacts of the
security cost cap are known.
Response: At this time, these amounts
do not factor in the Consolidated
Natural Resources Act of 2008, which
includes the limitation of costs to
customers of security activities at
Reclamation dams. Currently, the future
year projected amount is based on
amounts through the FY 2010 WPR.
Western has not received updated
security expenses from Reclamation that
reflect impacts of the Consolidated
Natural Resources Act of 2008. Western
plans to continue to work with
Reclamation, and these expenses are
expected to be updated and applied in
the second step of this rate adjustment.
The 94.7 percent share to power is
based on an average of allocation factors
used for the CRSP units.
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
Comment: What is the status of the
Glen Canyon cost allocation study?
Response: Reclamation has tasked
Argonne National Laboratory to study
the cost allocation revisions on the Glen
Canyon reallocation. Reclamation will
be reviewing this work in the near
future.
Comment: What is the status of
Reclamation’s analysis of project
purpose cost allocations?
Response: There have been several
projects in the region that have had final
cost allocation changes to previous
interim allocations. For example, the
San Juan-Chama Project March 2001
Final Cost Allocation incorporated
numerous project purpose changes that
occurred since earlier Definite Plan
Reports (DPR), such as the increase in
the M&I purpose and inclusion of the
purpose of the Jicarilla Apache
Settlement. Additionally, both the
Dolores Project December 2000 and the
Dallas Creek Project February 2004
Final Cost Allocations also incorporated
some cost allocation changes as a result
of slight purpose shifts since their last
DPR interim allocations. Also, the
Bonneville Unit of the Central Utah
Project, still in construction phase, has
had recent cost allocation changes to
conform to its reconfiguration pursuant
to the Reclamation Projects
Authorization and Adjustment Act of
1992 (Pub. L. No. 102–575). It is
possible that the current October 2004
Interim Cost Allocation of the
Bonneville Unit may change again until
there is a final cost allocation. Once a
final cost allocation has been approved,
any cost allocation change succeeding
that document may need Congressional
approval under Section 302 of the
Department of Energy Organization Act
(42 U.S.C. 7152).
Comment: A commenter stated and
asked the following: ‘‘The April 18,
2008 response to our February 11, 2008,
letter includes discussion regarding a
footnote contained in Tab 19 of the
Supporting Documentation material. It
refers to irrigation investment costs.
What does footnote 1 (Legal waiver of
assistance of irrigation investigation
costs still not available) mean? Are these
costs related to the ALP study costs?
The Congress directed on December 15,
2000, that ‘Federal law does not provide
a basis for allocating costs related to
ALP irrigation components to the M&I
water uses or to CRSP power customers.
Allocating such costs would require an
explicit change to Federal law. As the
July 2000 EIS recognizes, in the absence
of such a change in the law, those ‘sunk
costs’ that are attributed to project
features that are not part of the
Department’s Preferred Alternative are
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
52989
non-reimbursable.’ (S. Report, 106th
Congress, 106–513) [sic].’’
Response: Public Law 106–554, dated
December 21, 2000, states, ‘‘Such
repayment shall be consistent with
Federal Reclamation Law, including the
Colorado River Storage Project Act of
1956 (43 U.S.C. 620 et seq.). Such
agreement shall take into account the
fact that the construction of certain
project facilities, including those
facilities required to provide irrigation
water supplies from the Animas La Plata
Project, is not authorized under
paragraph (1)(A)(i) and no cost
associated with the design or
development of such facilities,
including costs associated with
environmental compliance, shall be
allocable to the municipal and
industrial users of the facilities
authorized under such paragraph.’’
Reclamation believes it is clear from
Public Law 106–554 that, although
Reclamation is no longer authorized to
construct irrigation facilities for the
ALP, the costs of the design and
development of these facilities are not
specifically declared non-reimbursable.
Public Law 106–554 provides only that
those irrigation investigation costs
cannot be allocated to the M&I users;
otherwise, repayment shall be
consistent with Federal Reclamation
law, including the CRSP Act.
Comment: An interested party asked,
‘‘What is the basis for the cost of living
adjustment included for Reclamation? Is
this authorized across all Federal
positions, across all Department of
Interior positions, throughout
Reclamation?’’
Response: The program analysts for
the Office of Personnel Management
determine the cost of living adjustments
for most Federal employees. You may
wish to visit its Web site at https://
www.opm.gov. Typically for budget
purposes, Western and Reclamation
assume a 3 percent increase based on
historical averages.
8. Project Use
Comment: One commenter asked
what causes the large increase in Project
Use in FY 2021.
Response: Increased requirements of
the Navajo Indian Irrigation Project.
Comment: One commenter asked
where Project Use revenues appear on
Table 3 of the Supporting
Documentation Booklet.
Response: The Project Use sales are
included along with the Energy and
Capacity sales on Table 3 of the
Supporting Documentation Booklet and,
therefore, are included in determining
the energy and capacity rates.
E:\FR\FM\12SEN1.SGM
12SEN1
52990
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
ebenthall on PROD1PC60 with NOTICES
9. Environmental
Comment: A commenter asked if
Reclamation and Western are seeking
appropriations for the Upper Colorado
Endangered Fish Recovery Program as
obligated in Pub. L. 102–395.
Response: The Recovery
Implementation Program Act, Public
Law 106–392, Section 3(d)(3)(2),
provides that: ‘‘If [Western] and
[Reclamation] determine that the funds
in the [Basin Fund] will not be
sufficient to meet the obligations of
section 5(c)(1) of the [CRSP] Act for a 3year period, [Western] and
[Reclamation] shall request
appropriations to meet base funding
obligations.’’ Since the Basin Fund
currently has an adequate balance for
anticipated non-reimbursable funding
requirements, no appropriations are
currently being sought for the Upper
Colorado Endangered Fish Recovery
Program.
Comment: A customer stated that the
Recovery Implementation Program (RIP)
Base Funding should be at zero after FY
2013 until specific legislation extending
the obligation has been passed.
Response: Similar to the way
Reclamation has treated security costs
in previous WPRs, it shows potential
RIP costs in an effort to show any costs
that may affect the Basin Fund. Since
RIP Base Funding is a non-reimbursable
expense, it does not impact the firm
power rate.
Comment: A commenter asked if the
Aspinall EIS is expected to be done this
FY 2008, and if so, shouldn’t FY 2009
and FY 2010 expenses be zero?
Response: The current schedule for
the Aspinall EIS shows an optimistic
anticipated completion date of
December 2008 (FY 2009). However,
due to various factors and uncertainties
in the process, Reclamation
recommends leaving the funding in the
budget until the EIS has been finalized.
Comment: Two comments were
received questioning the determination
not to require an Environmental
Assessment (EA) or EIS for this rate
adjustment.
Response: Western believes it is
categorically excluded from an EA or
EIS because this process is for a rate
adjustment. There are no proposed
changes in operations.
Comment: One commenter suggests
that the contracts for hydropower
anticipate changes in flows from Glen
Canyon Dam needed to meet the Grand
Canyon Protection Act and the
Endangered Species Act so that
acquisition of replacement power
during these flows is minimized or
eliminated.
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
Response: This rate adjustment does
not alter Western’s contractual
obligations. Western relies upon the
hydropower generation estimates
projected by the generating agency
when planning for replacement power
requirements. Western’s firm power
contracts with its customers provide for
the delivery of SHP which is the
minimum quantity of firm energy that
must be supplied under the contracts.
Western’s firm power contracts do not
expire until September 30, 2024.
10. Hydrology
Comment: A commenter asked what
the actual operational expenses have
been over the past 5 years for purchased
power expenses for operational
purposes, and what hydrology was used
post-2014.
Response: Western does not
specifically track operational purchased
power expenses; however, Western has
increased this projection for several
reasons: (a) Increased energy prices
especially during real time on-peak
conditions, (b) increased requests for
special power plant operations, (c)
increased special operations for fish
studies, (d) increased unscheduled flow
reduction activities, and (e) spinning
units for voltage support.
The hydrology study titled, ‘‘Colorado
River Interim Guidelines for Lower
Basin Shortages and Coordinated
Operation for Lake Powell and Lake
Mead’’ was used for determining the
purchased power estimates for the years
FY 2010 through FY 2013. Western used
the median level of releases from the
dams in these estimates after FY 2014.
Comment: A commenter asked what
month’s 24-month study is utilized in
Table 3 of the Rate Brochure and when
an updated study will be available with
revised hydrology.
Response: The April 2008, 24-month
study will be used for the ratesetting
Power Repayment Study (PRS) to
project purchased power estimates for
FY 2008 and FY 2009. In previous rate
analyses, Western has used
Reclamation’s long-term hydrological
study through FY 2060. In this process,
for long-term projections, we used the
same method as in the last rate process
where Western looked at the first 5
future years then dropped purchased
power projections down to the
operation cost. This effectively makes
the difference between Reclamation’s
long-term study and the most current
24-month study negligible.
Comment: Several commenters asked
if the turbine efficiency improvements
at Glen Canyon had been factored into
the energy calculations in this PRS.
They suggested deferring the rate
PO 00000
Frm 00047
Fmt 4703
Sfmt 4703
process until the impacts of the
enhanced unit efficiencies are evaluated
and included in the PRS.
Response: Improvements in turbine
efficiency have not been factored into
the energy calculation for use in the
ratesetting PRS. Western is currently
working with Reclamation to determine
the energy output of the turbine
efficiency improvements at Glen
Canyon, Flaming Gorge, and Upper and
Lower Molina dams. If the turbine
efficiency improvement studies are
completed in time for input into the
second step of the firm power rate,
Western will factor them into the rate.
Comment: A commenter cited
independent studies that concluded
climate changes could cause Lake
Powell to go empty or at least below
hydropower generation by 2021. The
commenter suggests Western
incorporate these studies into its
hydrogeneration forecasting.
Response: Western uses forecasts
based on hydrological projections that
are received from Reclamation. These
hydrological studies look at the possible
consequences of long term changes to
climate. Appendix W, Climate
Technical Work Group Report, of the
Colorado River Interim Guidelines for
Lower Basin Shortages and Coordinated
Operations for Lake Powell and Lake
Mead’s final EIS is a recent example.
Moreover, Western’s PRSs are
performed on a yearly basis with
updated hydrological projections.
Any long-term shifts in hydrology that
would reduce hydropower generation
will be incorporated into future data
provided by Reclamation and will be
reflected in Western’s PRSs at that time.
Additionally, depletions to the runoff
caused by future development of Upper
Basin water allocations are included in
Reclamation’s hydrological projections
and are thus incorporated into
Western’s rate determination process.
Comment: A commenter suggested the
rate process should be deferred until the
uncertainties of the improved
hydrological conditions, including
equalization flows are evaluated and
included in the PRS. The commenter
questioned if there is a mechanism in
place that will compensate for
drastically improved hydrology.
Response: If hydrology improves
drastically there will be less purchased
power costs built into the second step
rate, FY 2009 and beyond. In addition,
Western will use the updated generation
forecasts when it determines the second
step.
11. Transmission and Ancillary Services
Comment: A commenter wanted to
know if a customer has to be physically
E:\FR\FM\12SEN1.SGM
12SEN1
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
ebenthall on PROD1PC60 with NOTICES
connected to Western’s system in order
to receive ancillary services such as
reactive supply, etc.
Response: There is no predetermined
requirement for a customer to receive
ancillary services on Western’s
transmission system. The criteria
needed to determine whether or not a
customer can receive ancillary services
on Western’s transmission system
include: (a) Physical interconnection,
(b) balancing authority location, (c) type
of customer, and (d) type of ancillary
service required. Each request for
ancillary services needs to be evaluated
based on its own circumstances.
Depending upon the responses to the
items listed above, the providing of
ancillary services may be mandatory or
optional.
Comment: A commenter asked if there
were on/off-peak and seasonal non-firm
rates on transmission.
Response: CRSP MC does offer firm
transmission on a short-term basis,
which is usually at a non-firm rate but
can be discounted through the OASIS
posting process.
Comment: A customer wanted to
know if Contract No. 98-SLC–0390
between Western and Utah Associated
Municipal Power Systems (UAMPS) had
been extended, since it terminates
December 2008.
Response: As of this publication date,
this contract with UAMPS has not been
extended.
12. Miscellaneous
Comment: A commenter wanted to
know what the anticipated impacts on
merchant function revenues were given
the proposed merchant function
consolidation.
Response: Western performed a highlevel evaluation of the merchant
functions and decided it will not be
pursuing merchant consolidation as part
of this strategic planning process.
Comments: A commenter wanted to
know what will be Western’s treatment
regarding post-2010 SHP allocations.
Response: Western is assuming that
SHP allocations will remain constant
through FY 2013 and includes firming
purchases accordingly to meet its
commitments. After FY 2013, Western
continues to assume the same SHP
allocations through the remainder of the
PRS, but reduces the purchased power
estimates to include only those needed
for operations ($4 million per year).
Comment: A commenter states it is
unfortunate that Glen Canyon Dam was
authorized.
Response: This comment is outside
the scope of this rate process.
Comment: A comment was received
stating that since the outcome of the
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
integration of the CRSP cost allocations
between RMR and DSW for the
operational consolidation is unknown,
any rate process should be deferred
until October 1, 2009.
Response: Western has chosen to
proceed with Operations Consolidation
(‘‘Option C’’ of the April 24
presentation). Western will work with
all customers to ensure that each project
will be allocated its appropriate share of
costs. Western expects to provide its
proposed cost allocation methodologies
to interested customers by September 1,
2008, for their review and input.
Availability of Information
Information about this rate
adjustment, including PRSs, comments,
letters, memorandums, and other
supporting material made or kept by
Western and used to develop the
provisional rates, is available for public
review at the Colorado River Storage
Project Management Center, Western
Area Power Administration, 150 East
Social Hall Avenue, Suite 300, Salt Lake
City, Utah or at https://www.wapa.gov/
crsp/ratescrsp.
Ratemaking Procedure Requirements
Environmental Compliance
In compliance with the National
Environmental Policy Act (NEPA) of
1969 (42 U.S.C. 4321, et seq.); Council
on Environmental Quality Regulations
(40 CFR parts 1500–1508); and DOE
NEPA Regulations (10 CFR part 1021),
Western has determined that this action
is categorically excluded from preparing
an environmental assessment or an
environmental impact statement.
Determination Under Executive Order
12866
Western has an exemption from
centralized regulatory review under
Executive Order 12866; accordingly, no
clearance of this notice by the Office of
Management and Budget is required.
Submission to the Federal Energy
Regulatory Commission
The interim rates herein confirmed,
approved, and placed into effect,
together with supporting documents,
will be submitted to the Commission for
confirmation and final approval.
Order
In view of the foregoing and under the
authority delegated to me, I confirm and
approve on an interim basis, effective
October 1, 2008, Rate Schedule SLIP–
F9, SP–PTP7, SP–NW3, SP–NFT6, SP–
SD3, SP–RS3, SP–EI3, SP–FR3, and SP–
SSR3 for the Salt Lake City Area
Integrated Projects of the Western Area
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
52991
Power Administration. These rate
schedules shall remain in effect on an
interim basis, pending FERC’s
confirmation and approval of them or
substitute rates on a final basis through
September 30, 2013.
Dated: September 4, 2008.
Jeffrey F. Kupfer,
Acting Deputy Secretary.
Rate Schedule SLIP–F9
(Supersedes Schedule SLIP–F8)
United States Department of Energy
Western Area Power Administration
Salt Lake City Area Integrated Projects;
Arizona, Colorado, Nevada, New Mexico,
Utah, Wyoming
Schedule of Rates for Firm Power
Service
Effective: The first step of the stepped
rate will be effective on the first day of
the first full billing period beginning on
or after October 1, 2008; the second step
will be effective on the first day of the
first full billing period on or after
October 1, 2009, extending through
September 30, 2013, or until superseded
by another rate schedule, whichever
occurs earlier.
Available: In the area served by the
Salt Lake City Area Integrated Projects.
Applicable: To the wholesale power
customer for firm power service
supplied through one meter at one point
of delivery, or as otherwise established
by contract.
Character: Alternating current, 60
hertz, three-phase, delivered and
metered at the voltages and points
established by contract.
Monthly Rate: First step, effective
October 1, 2008:
DEMAND CHARGE: $4.70/kilowatt of
billing demand.
ENERGY CHARGE: 11.06 mills/
kilowatthour of use.
Second step, effective October 1,
2009, and not to exceed the following:
DEMAND CHARGE: $5.22/kilowatt of
billing demand.
ENERGY CHARGE: 12.29 mills/
kilowatthour of use.
COST RECOVERY CHARGE: This
charge will be recalculated annually
before May 1, and Western will provide
notification to the customers. The
charge, if needed, will be placed into
effect from October 1 through
September 30. If triggered by the
Shortage Criteria, the CRC will be recalculated at that time and may be
implemented at any time of the year
upon 45-day notice to customers. (See
Shortage Criteria Trigger explanation
below.) The CRC will be calculated as
follows:
E:\FR\FM\12SEN1.SGM
12SEN1
52992
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
CRC CALCULATION
Description
Formula
STEP ONE: Determine the Net Balance available in the Basin Fund
BFBB: Basin Fund Beginning Balance ($) .............................................................................
BFTB: Basin Fund Target Balance ($) ..................................................................................
PAR: Projected Annual Revenue ($) w/o CRC .....................................................................
PAE: Projected Annual Expense ($) ......................................................................................
NR: Net Revenue ($) .............................................................................................................
NB: Net Balance ($) ...............................................................................................................
Financial forecast.
.15 * PAE (not less than $20 million).
Financial forecast.
Financial forecast.
PAR¥PAE.
BFBB + NR.
STEP TWO: Determine the Forecasted Energy Purchased Expenses
EA: SHP Energy Allocation (GWh) ........................................................................................
HE: Forecasted Hydro Energy (GWh) ...................................................................................
FE: Forecasted Energy Purchased (GWh) ............................................................................
FFC: Forecasted Avg Energy Price per MWh ($) .................................................................
FX: Forecasted Energy Purchased Expense ($) ...................................................................
Customer contracts.
Hydrologic & generation forecast.
EA¥HE.
From commercially available price indices.
FE * FFC.
STEP THREE: Determine the amount of Funds Available for firming energy purchases, and then determine additional revenue to be
recovered. The following two formulas will be used to determine FA, the lesser of the two will be used
FA1: Basin Fund Balance Factor ($) .....................................................................................
FA2: Revenue Factor ($) .......................................................................................................
FA: Funds Available ($) .........................................................................................................
FARR: Additional Revenue to be Recovered ($) ...................................................................
If (NB > BFBB, FX, FX¥(BFTB¥NB)).
If (NR >¥.25 * BFBB, FX, FX + NR + .25 * BFBB).
Lesser of FA1 or FA2 (not less than $0).
FX¥FA.
STEP FOUR: Once the FA for purchases has been determined, the CRC can be calculated, and the WL can be determined
WL: Waiver Level (GWh) .......................................................................................................
WLP: Waiver Level Percentage of Full SHP .........................................................................
CRCE: CRC Energy (GWh) ...................................................................................................
CRCEP: CRC Energy Percentage of Full SHP .....................................................................
CRC: Cost Recovery Charge (mills/kWh) ..............................................................................
ebenthall on PROD1PC60 with NOTICES
Narrative CRC Example
Step One: Determine the net balance
available in the Basin Fund.
BFBB—Western will forecast the
Basin Fund Beginning Balance for the
next FY.
BFTB—Determine the Basin Fund
Target Balance for the next FY. The
BFTB will not be less than $20 million.
The target is 15 percent of projected
annual expenses for the coming FY.
BFTB = 0.15*PAE.
PAR—Projected Annual Revenue is
Western’s estimate of revenue for the
next FY.
PAE—Projected Annual Expenses is
Western’s estimate of expenses for the
next FY. The PAE includes all expenses
plus non-reimbursable expenses, which
are capped at $27 million per year plus
an inflation factor. This limitation is for
CRC formula calculation purposes only,
and is not a cap on actual nonreimbursable expenses.
NR—Net Revenue equals revenues
minus expenses. NR = PAR¥PAW.
NB—Net Balance is the Basin Fund
Beginning Balance plus net revenue. NB
= BFBB+NR.
Step Two: Determine the forecasted
energy purchased expenses.
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
If (EA < HE, EA, HE + (FE * (FA/FX))), but not less
than HE.
WL/EA * 100.
EA¥WL.
CRCE/EA * 100.
FARR/(EA * 1,000).
EA—The Sustainable Hydropower
Energy Allocation. This does not
include Project Use customers.
HE—Western’s forecast of Hydro
Energy available during the next FY
developed from Reclamation’s April, 24month, study.
FE—Forecasted Energy purchases are
the difference between the sustainable
hydropower allocation and the
forecasted hydro energy available for the
next FY, or the anticipated firming
purchases for the next year. FE =
EA¥HE.
FFC—The forecasted energy price for
the next FY per MWh.
FX—Forecasted energy purchased
power expenses based on the current
year April 24-month study, representing
an estimate of the total costs of firming
purchases for the coming FY. FX =
FE*FFC.
Step Three: Determine the amount of
Funds Available (FA) to expend on
firming energy purchases, and then
determine additional revenue to be
recovered (FARR). The following two
formulas will be used to determine FA;
the lesser of the two will be used. Funds
available shall not be less than zero.
A. Basin Fund Balance Factor (FA1)
The first factor ensures that the Net
Balance will not go below 15 percent of
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
the total expenses for that FY. If the Net
Balance is greater than the Basin Fund
Target Balance, then use the value for
forecasted energy purchased power
expenses. If the net balance is less than
the Basin Fund Target Balance, then
reduce the value of the Forecasted
Energy Purchased Power Expenses by
the difference between the Basin Fund
Target Balance and the Net Balance.
FA1 = if (NB>BFTB, FX,
FX¥(BFTB¥NB))
If the Net Balance is greater than the
Basin Fund Target Balance, then FA1 =
FX.
If the Net Balance is less than the
Basin Fund Target Balance, then FA1 =
FX¥(BFTB¥NB).
B. Basin Fund Revenue Factor (FA2)
The second factor ensures that the net
revenue does not result in a loss that
exceeds 25 percent of the Basin Fund
Beginning Balance. If the Net Revenue
is greater than a minus 25 percent of the
Basin Fund Beginning Balance, then use
the value for forecasted energy
purchased power expenses. If the Net
Revenue is less than a minus 25 percent
of the Basin Fund Beginning Balance,
then add the Net Revenue; and 25
percent of the Basin Fund Beginning
E:\FR\FM\12SEN1.SGM
12SEN1
52993
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
Balance to the forecasted energy
purchased power expenses.
FA2 = If (NR>¥0.25*BFBB, FX, FX +
NR + 0.25*BFBB)
If the Net Revenue does not result in
a loss that exceeds 25 percent of the
Basin Fund Beginning Balance, then
FA2 = FX.
If the Net Revenue results in a loss
that exceeds 25 percent of the Basin
Fund Beginning Balance, then FA2 + FX
+ NR + 0.25*BFBB.
FA—Determine the funds available
for purchasing firming energy by using
the lesser of FA1 and FA2.
FARR—Calculate the additional
revenue to be recovered by subtracting
the Funds Available from the forecasted
energy purchased power expenses.
FARR = FX¥FA.
Step Four: Once the funds available
for purchases have been determined, the
CRC can be calculated and the Waiver
Level (WL) can be determined.
A. Cost Recovery Charge: The CRC
will be a charge to recover the
additional revenue required as
calculated in Step 3. The CRC will
apply to all customers who choose not
to request a waiver of the CRC, as
discussed below. The CRC equals the
additional revenue to be recovered
divided by the total energy allocation to
all customers for the FY.
CRC = FARR/(EA*1,000)
B. Waiver Level:
Western established an energy WL
that provides customers the ability to
reduce their purchased power expenses
by scheduling less energy than their
contractual amounts. Therefore,
Western will establish an energy WL.
For those customers who voluntarily
schedule no more energy than their
proportionate share of the WL, Western
will waive the CRC for that year.
After the Funds Available have been
determined, the WL will be set at the
sum of the energy that can be provided
through hydro generation and
purchased with Funds Available. The
WL will not be less than the forecasted
Hydro Energy.
WL = If (EA2005
15:18 Sep 11, 2008
Jkt 214001
RA—The Revenue Adjustment is AFC
less FFC times CRCE.
RA = (AFC¥FFC)*CRCE)*1,000
PYA—The PYA is the RA divided by
the EAC for the CRC customers only.
PYA = (RA/EAC)/1,000
The customer’s PYA will be based on
their prior year’s energy multiplied by
the resulting mills/kWh to determine
the dollar amount that will be assessed.
The customers will be charged or
credited for this dollar amount equally
in the remaining months of the next
year’s billing cycle. Western will
attempt to complete this calculation by
December of every year. Therefore, if the
PYA is calculated in December, the
charge/credit will be spread over the
remaining 9 months of the FY (January
through September).
PO 00000
Frm 00050
Fmt 4703
Sfmt 4703
(AFC¥FFC)*CRCE*1,000.
(RA/EAC)/1,000.
Shortage Criteria Trigger: In the event
that Reclamation’s 24-month study
projects that Glen Canyon Dam water
releases will drop below 8.23 MAF in a
water year (October through September),
Western will recalculate the CRC to
include those lower estimates of
hydropower generation and the
estimated costs for the additional
purchased power necessary to meet
contractual requirements. Western, as in
the yearly projection for the CRC, will
give the customers a 45-day notice to
request a waiver of the CRC, if they do
not want to have the CRC charge added
to their energy bill. This recalculated
CRC will remain in effect for the
remainder of the current FY.
In the event that Glen Canyon Dam
water releases return to 8.23 MAF or
higher level during the trigger
E:\FR\FM\12SEN1.SGM
12SEN1
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
implementation, the CRC will be
recalculated and the customer will be
notified.
Billing Demand: The billing demand
will be the greater of:
1. The highest 30-minute integrated
demand measured during the month up
to, but not more than, the delivery
obligation under the power sales
contract, or
2. The Contract Rate of Delivery.
Billing Energy: The billing energy will
be the energy measured during the
month up to, but not more than, the
delivery obligation under the power
sales contract.
Adjustment for Waiver: Customers
may choose to take a reduced SHP
energy allocation as determined in the
attached formulas for the CRC, and they
will be billed the Energy and Capacity
rates listed above, but not the CRC.
Adjustment for Transformer Losses: If
delivery is made at transmission voltage
but metered on the low-voltage side of
the substation, the meter readings will
be increased to compensate for
transformer losses as provided in the
contract.
Adjustment for Power Factor: The
customer will be required to maintain a
power factor at all points of
measurement between 95 percent
lagging and 95 percent leading.
Adjustment for Western Replacement
Power: Pursuant to the Contractor’s
Firm Electric Service Contract, as
amended, Western will bill the
Contractor for its proportionate share of
the costs of Western Replacement Power
(WRP) within a given time period.
Western will include in the Contractor’s
monthly power bill the cost of the WRP
and the incremental administrative
costs associated with WRP.
Adjustment for Customer
Displacement Power Administrative
Charges: Western will include in the
Contractor’s regular monthly power bill
the incremental administrative costs
associated with Customer Displacement
Power.
Rate Schedule SP–PTP7
(Supersedes Schedule SP–PTP6)
United States Department of Energy
Western Area Power Administration
Colorado River Storage Project; Arizona,
Colorado, New Mexico, Utah
ebenthall on PROD1PC60 with NOTICES
Schedule of Rate for Firm Point-toPoint Transmission Service
Effective: The first day of the first full
billing period beginning on or after
October 1, 2008, and extending through
September 30, 2013, or until superseded
by another rate schedule, whichever
occurs earlier.
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
Available: In the area served by the
Colorado River Storage Project (CRSP)
transmission system.
Applicable: To firm point-to-point
transmission service customers for
which power and energy are supplied to
the CRSP transmission system at points
of interconnection with other systems
and transmitted and delivered, less
losses, to points of delivery on the CRSP
transmission system established by
contract.
Character and Conditions of Service:
Transmission service for alternating
current, 60 hertz, three-phase, delivered
and metered at the voltages and points
of delivery established by contract.
Point-to-Point Rate Formula: The firm
point-to-point rate is based on a test
year using an annual fixed charge
methodology. The test year is the most
recent historical data available. The
annual revenue requirement is reduced
by revenue credits. The resultant net
annual cost to be recovered is divided
by the capacity reservation needed to
meet firm power and transmission
commitments in kW, including the total
network integration loads at system
peak, to derive a cost/kWyear. The cost/
kWyear is calculated using the
following formula:
1. ATRR − TRC = NATRR
NATRR
2.
TSTL
Where:
ATRR = Annual Transmission Revenue
Requirement. The costs associated with
facilities that support the transfer
capability of the CRSP transmission
system, excluding generation facilities.
These costs include investment costs,
interest expense, depreciation expense,
administrative and general expenses, and
operation and maintenance expenses,
including transmission purchases.
Transmission purchases reflect those
costs associated with CRSP contractual
rights.
TRC = Transmission Revenue Credits. The
revenues generated by the CRSP
transmission system, such as scheduling
and dispatch ancillary service revenues
and phase shifter revenues, and
excluding long-term firm transmission
revenues.
NATRR = Net Annual Transmission Revenue
Requirement. The Annual Revenue
Requirement less Transmission Revenue
Credits.
TSTL = CRSP Transmission System Total
Load. The sum of the total CRSP
transmission capacity under the longterm reservation plus the total network
integration loads at system peak.
This formula will be recalculated
annually by applying the data from the
most current historical test year. If
needed, a revised rate will be placed
PO 00000
Frm 00051
Fmt 4703
Sfmt 4703
into effect every October 1. Western will
provide notification 30 days prior to a
revised rate becoming effective. The rate
for transmission service includes
scheduling, system control, and
dispatch. Rate Schedule SP–RS3, or any
superseding rate schedule, for reactive
supply and voltage control is attached
as part of this Rate Schedule and applies
to firm point-to-point transmission
customers.
Billing: The point-to-point
transmission customer will be billed
monthly by applying the resulting rate
to the maximum amount of capacity
reserved, payable whether used or not,
except as otherwise provided in existing
contracts.
Requirements for Reactive Power:
Requirements for reactive power shall
be as established by contract; otherwise,
there shall be no entitlement to transfer
of reactive kilovolt amperes at delivery
points except when such transfers may
be mutually agreed upon by the
Contractor and the contracting officer or
their authorized representatives.
Adjustment for Losses: Power and
energy losses incurred in connection
with the transmission and delivery of
power and energy under this rate
schedule shall be supplied by the
customer as established by contract. If
losses are not fully provided by a
transmission customer, charges for
financial compensation may apply.
Adjustment for Industry
Restructuring: Any transmission-related
costs incurred by Western due to
electric industry restructuring or other
industry changes associated with
providing CRSP transmission service
will be passed through to each
transmission customer, as appropriate.
Rate Schedule SP–NW3
(Supersedes Schedule SP–NW2)
United States Department of Energy
Western Area Power Administration
Colorado River Storage Project; Arizona,
Colorado, New Mexico, Utah
Monthly Charge Calculation for
Network Integration Transmission
Service
Effective: The first day of the first full
billing period beginning on or after
October 1, 2008, and extending through
September 30, 2013, or until superseded
by another rate schedule, whichever
occurs earlier.
Available: In the area served by the
Colorado River Storage Project (CRSP)
transmission system.
Applicable: To network transmission
service customers for which power and
energy are supplied to the CRSP
transmission system at points of
interconnection with other systems and
transmitted and delivered, less losses, to
E:\FR\FM\12SEN1.SGM
12SEN1
EN12SE08.001
52994
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
points of delivery on the CRSP
transmission system established by
contract.
Character and Conditions of Service:
Transmission service for alternating
current, 60 hertz, three-phase, delivered
and metered at the voltages and points
of delivery established by contract.
Monthly Network Formula: The
Network integration transmission
service charge will be the product of the
network customer’s load ratio share
times one twelfth (1⁄12) of the total net
annual transmission revenue
requirement. The same Net Annual
Transmission Revenue Requirement is
used in determining the rate for network
52995
transmission service as for point-topoint transmission service. It is based
on a test year using an annual fixed
charge methodology. The test year is the
most recent year for which historical
data is available. The annual revenue
requirement is reduced by revenue
credits. The formula is as follows:
1. ATRR − TRC = NATRR
NATRR
2.
× Transmission customer’s Load-Ratio Share
12
This formula will be recalculated
annually by applying the data from the
most current historical test year. If
needed, a revised rate will be placed
into effect every October 1. Western will
provide notification 30 days prior to a
revised rate becoming effective.
The monthly charge for network
transmission service includes
scheduling, system control, and
dispatch. Rate Schedule SP–RS3, or any
superseding rate schedule, will be
attached as part of this Rate Schedule
and applies to network transmission
customers.
Billing: Billing determinants for the
formula rate above will be as specified
in the service agreement.
Requirements for Reactive Power:
Requirements for reactive power shall
be as established by contract; otherwise,
there shall be no entitlement to transfer
of reactive kilovolt amperes at delivery
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
points except when such transfers may
be mutually agreed upon by the
Contractor and the contracting officer or
their authorized representatives.
Adjustment for Losses: Power and
energy losses incurred in connection
with the transmission and delivery of
power and energy under this rate
schedule shall be supplied by the
customer as established by contract. If
losses are not fully provided by a
transmission customer, charges for
financial compensation may apply.
Adjustment for Industry
Restructuring: Any transmission-related
costs incurred by Western due to
electric industry restructuring or other
industry changes associated with
providing CRSP transmission service
will be passed through to each
transmission customer, as appropriate.
Rate Schedule SP–NFT6
(Supersedes Schedule SP–NFT5)
United States Department of Energy
Western Area Power Administration
Colorado River Storage Project; Arizona,
Colorado, New Mexico, Utah
Schedule of Rate for Non-Firm Point-toPoint Transmission Service
Effective: The first day of the first full
billing period beginning on or after
October 1, 2008, and extending through
September 30, 2013, or until superseded
by another rate schedule, whichever
occurs earlier.
Available: In the area served by the
Colorado River Storage Project (CRSP)
transmission system.
Applicable: To non-firm point-topoint transmission service customers for
which power and energy are supplied to
the CRSP transmission system at points
of interconnection with other systems
and transmitted and delivered, less
losses, to points of delivery on the CRSP
transmission system as established by
contract.
Character and Conditions of Service:
Transmission service on an interruptible
basis for three-phase alternating current
60 hertz, delivered and metered at the
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
voltages and points of delivery specified
in the service contract or in advance by
the Western Area Power Administration
(Western). Conditions for curtailment
shall be determined by Western and in
accordance with Western’s Tariff.
Rate: The proposed rate for non-firm,
point-to-point, CRSP transmission
service is based upon the firm point-topoint rate expressed in mills/kWh. This
rate may be discounted.
Billing: The rate will be applied to
each kWh delivered at the point of
delivery, as specified in the service
contract.
Adjustments for Reactive Power:
None. There shall be no entitlement to
transfer of reactive kilovolt-amperes at
delivery points, except when such
transfers may be mutually agreed upon
by the Contractor and the contracting
officer or their authorized
representatives.
Adjustments for Losses: Power and
energy losses incurred in connection
with the transmission and delivery of
power and energy under this rate
schedule shall be supplied by the
customer in accordance with the service
contract. If losses are not fully provided
by a transmission customer, charges for
financial compensation may apply.
Adjustment for Industry
Restructuring: Any transmission-related
costs incurred by Western due to
electric industry restructuring or other
industry changes associated with
providing CRSP transmission service
will be passed through to each
transmission customer, as appropriate.
Rate Schedule SP–SD3
(Supersedes Schedule SP–SD2)
United States Department of Energy
Western Area Power Administration
Colorado River Storage Project; Arizona,
Colorado, New Mexico, Utah
E:\FR\FM\12SEN1.SGM
12SEN1
EN12SE08.002
ebenthall on PROD1PC60 with NOTICES
Where:
ATRR = Annual Transmission Revenue
Requirement. The costs associated with
facilities that support the transfer
capability of the CRSP transmission
system, excluding generation facilities.
These costs include investment costs,
interest expense, depreciation expense,
administrative and general expenses, and
operation and maintenance expenses,
including transmission purchases.
Transmission purchases reflect those
costs associated with CRSP contractual
rights.
TRC = Transmission Revenue Credits. The
revenues generated by the CRSP
transmission system, such as scheduling
and dispatch ancillary services revenues
and phase shifter revenues, and
excluding long-term firm transmission
revenues.
NATRR = Net Annual Transmission Revenue
Requirement. The Annual Revenue
Requirement less Transmission Revenue
Credits.
Load-Ratio Share = Network customer’s
hourly load (including its designated
network load not physically
interconnected with Western) coincident
with Western’s monthly CRSP
transmission system peak.
52996
Federal Register / Vol. 73, No. 178 / Friday, September 12, 2008 / Notices
Schedule of Rate for Scheduling,
System Control, and Dispatch Ancillary
Services
Effective: Beginning on October 1,
2008, and extending through September
30, 2013.
Available: In the area served by the
Colorado River Storage Project (CRSP)
transmission system.
Applicable: To all CRSP transmission
customers receiving this service.
Character of Service: Scheduling,
System Control, and Dispatch service is
required to schedule the movement of
power through, out of, within, or into a
balancing authority.
Rate: Included in appropriate
transmission rates.
Rate Schedule SP–RS3
(Supersedes Schedule SP–RS2)
United States Department of Energy
Western Area Power Administration
Colorado River Storage Project; Arizona,
Colorado, New Mexico, Utah
Schedule of Rate for Reactive Supply
and Voltage Control Ancillary Service
Effective: Beginning on October 1,
2008, and extending through September
30, 2013.
Available: In the area served by the
Colorado River Storage Project (CRSP)
Transmission system.
Applicable: To all CRSP transmission
customers receiving this service.
Character of Service: Reactive power
is support provided from generation
facilities that is necessary to maintain
transmission voltages within acceptable
limits of the system.
Rate: Provided through WALC
balancing authority under Rate
Schedule DSW–RS2 or WACM
balancing authority under Rate
Schedule L–AS2, or as superseded.
ebenthall on PROD1PC60 with NOTICES
Rate Schedule SP–EI3
(Supersedes Schedule SP–EI2)
United States Department of Energy
Western Area Power Administration
Colorado River Storage Project; Arizona,
Colorado, New Mexico, Utah
Schedule of Rate for Energy Imbalance
Ancillary Service
Effective: Beginning on October 1,
2008, and extending through September
30, 2013.
Available: In the area served by the
Colorado River Storage Project (CRSP)
transmission system.
Applicable: To all CRSP transmission
customers receiving this service.
Character of Service: Provided when
a difference occurs between the
schedules and the actual delivery of
energy to a load located within a
balancing authority over a single hour.
Rates: Provided through WALC
balancing authority under Rate
VerDate Aug<31>2005
15:18 Sep 11, 2008
Jkt 214001
Schedule DSW–EI2 or WACM balancing
authority under Rate Schedule L–AS4,
or as superseded, or the customer can
make alternative comparable
arrangements to satisfy its Energy
Imbalance service obligations.
Rate Schedule SP–FR3
(Supersedes Schedule SP–FR2)
United States Department of Energy
Western Area Power Administration
Colorado River Storage Project; Arizona,
Colorado, New Mexico, Utah
Schedule of Rate for Regulation and
Frequency Response Ancillary Service
Effective: Beginning on October 1,
2008, and extending through September
30, 2013.
Available: In the area served by the
Colorado River Storage Project (CRSP)
transmission system.
Applicable: To all CRSP transmission
customers receiving this service.
Character of Service: Necessary to
provide the continuous balancing of
resources, generation and interchange,
with load and for maintaining schedules
interconnection frequency at 60 cycles
per second (60 Hz).
Rate: If the CRSP MC has regulation
available for sale, the SLCA/IP firm
power capacity rate, currently in effect,
will be charged. If regulation is
unavailable from SLCA/IP resources, the
WALC or WACM balancing authorities
can provide the service, in accordance
with their respective rate schedules.
Rate Schedule SP–SSR3
(Supersedes Schedule SP–SSR2)
United States Department of Energy
Western Area Power Administration
Colorado River Storage Project; Arizona,
Colorado, New Mexico, Utah
Schedule of Rates for Spinning and
Supplemental Reserve Ancillary
Service
Effective: Beginning on October 1,
2008, and extending through September
30, 2013.
Available: In the area served by the
Colorado River Storage Project (CRSP)
transmission system.
Applicable: To all CRSP transmission
customers receiving this service.
Character of Service: Spinning
Reserve is defined in Schedule 5 of
Western Area Power Administration’s
Open Access Transmission Tariff.
Supplemental Reserve is defined in
Schedule 6 of Western Area Power
Administration’s Open Access
Transmission Tariff.
Rate: If CRSP resources are available,
the charge will be determined based on
market rates plus administrative costs. If
CRSP resources are not available, CRSP
will purchase spinning reserves and
pass through the costs associated with
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
these purchases, including
administrative costs.
[FR Doc. E8–21176 Filed 9–11–08; 8:45 am]
BILLING CODE 6450–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–8714–3]
Agency Information Collection
Activities OMB Responses
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
SUMMARY: This document announces the
Office of Management and Budget’s
(OMB) responses to Agency Clearance
requests, in compliance with the
Paperwork Reduction Act (44 U.S.C.
3501 et seq.). An agency may not
conduct or sponsor, and a person is not
required to respond to, a collection of
information unless it displays a
currently valid OMB control number.
The OMB control numbers for EPA’s
regulations are listed in 40 CFR part 9
and 48 CFR chapter 15.
FOR FURTHER INFORMATION CONTACT: Rick
Westlund (202) 566–1682, or e-mail at
westlund.rick@epa.gov and please refer
to the appropriate EPA Information
Collection Request (ICR) Number.
SUPPLEMENTARY INFORMATION:
OMB Responses to Agency Clearance
Requests
OMB Approvals
EPA ICR Number 1669.05; Lead-Based
Paint Pre-Renovation Information
Dissemination—TSCA Section 406(b);
in 40 CFR part 735, subpart E; was
approved 08/14/2008; OMB Number
2070–0158; expires 08/31/2011.
Dated: September 8, 2008.
Sara Hisel-McCoy,
Director, Collection Strategies Division.
[FR Doc. E8–21314 Filed 9–11–08; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OPPT–2008–0661; FRL–8381–5]
Certain New Chemicals; Receipt and
Status Information
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
SUMMARY: Section 5 of the Toxic
Substances Control Act (TSCA) requires
any person who intends to manufacture
E:\FR\FM\12SEN1.SGM
12SEN1
Agencies
[Federal Register Volume 73, Number 178 (Friday, September 12, 2008)]
[Notices]
[Pages 52980-52996]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-21176]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Western Area Power Administration
Salt Lake City Area Integrated Projects and Colorado River
Storage Project--Rate Order No. WAPA-137
AGENCY: Western Area Power Administration, DOE.
ACTION: Notice of Order Concerning Power, Transmission, and Ancillary
Services Rates.
-----------------------------------------------------------------------
SUMMARY: The Acting Deputy Secretary of Energy confirmed and approved
Rate Order No. WAPA-137 and Rate Schedule SLIP-F9, placing firm power
rates for the Salt Lake City Area Integrated Projects (SLCA/IP) of the
Western Area Power Administration (Western) into effect on an interim
basis. The Acting Deputy Secretary also confirmed Rate Schedules SP-
PTP7, SP-NW3, SP-NFT6, SP-SD3, SP-RS3, SP-EI3, SP-FR3, and SP-SSR3,
placing firm and non-firm transmission rates and ancillary services
rates on the Colorado River Storage Project (CRSP) transmission system
into effect on an interim basis. The provisional rates will be in
effect until the Federal Energy Regulatory Commission (FERC) confirms,
approves, and places them into effect on a final basis or until they
are replaced by other rates. The provisional rates will provide
sufficient revenue to pay all annual costs, including interest expense,
and repayment of power investment and irrigation aid, within the
allowable periods.
DATES: Rate Schedules SLIP-F9, SP-PTP7, SP-NW3, SP-NFT6, SP-SD3, SP-
RS3, SP-EI3, SP-FR3, and SP-SSR3 will be placed into effect on an
interim basis on the first day of the first full billing period
beginning on or after October 1, 2008, and will be in effect until FERC
confirms, approves, and places the rate schedules in effect on a final
basis through September 30, 2013, or until the rate schedules are
superseded.
FOR FURTHER INFORMATION CONTACT: Mr. Bradley S. Warren, CRSP Manager,
Colorado River Storage Project Management Center, Western Area Power
Administration, 150 East Social Hall Avenue, Suite 300, Salt Lake City,
UT 84111-1580, (801) 524-5493, e-mail warren@wapa.gov, or Ms. Carol A.
Loftin, Rates Manager, Colorado River Storage Project Management
Center, Western Area Power Administration, 150 East Social Hall Avenue,
Suite 300, Salt Lake City, UT 84111-1580, (801) 524-6380, e-mail
loftinc@wapa.gov.
SUPPLEMENTARY INFORMATION: The Deputy Secretary of Energy approved Rate
Order No. WAPA-117 on August 1, 2005 (70 Fed. Reg. 47823). This Order
included existing Rate Schedule SLIP-F8 for SLCA/IP firm power.\1\ The
existing firm power Rate Schedule SLIP-F8 is being superseded by Rate
Schedule SLIP-F9. Under Rate Schedule SLIP-F8, the energy rate is 10.43
mills/kilowatthour (mills/kWh), and the capacity rate is $4.43/
kilowattmonth ($/kWmonth). The composite rate is 25.28 mills/kWh. The
provisional firm power rate will be implemented over a 2-year period.
In the first year, the provisional firm power rate consists of an
energy charge of 11.06 mills/kWh and a capacity charge of $4.70/
kWmonth. The second step of the rate will be effective October 1, 2009,
and will be capped at the energy charge of 12.29 mills/kWh and a
capacity charge of $5.22/kWmonth. The provisional rates for SLCA/IP
firm power in Rate Schedule SLIP-F9 will result in an overall composite
rate of 26.80 mills/kWh on October 1, 2008, and a composite rate capped
at 29.68 mills/kWh on October 1, 2009, through September 30, 2013, or
until superseded. This second step rate adjustment will result in an
overall increase of about 17.4 percent when compared with the existing
SLCA/IP firm power composite rate under Rate Schedule SLIP-F8.
---------------------------------------------------------------------------
\1\ FERC confirmed and approved Rate Order No. WAPA-117 on June
13, 2006, in Docket EF05-5171. See United States Department of
Energy, Western Area Power Administration, Salt Lake City Integrated
Projects, 115 FERC ] 62,271 (June 13, 2006).
---------------------------------------------------------------------------
The firm power rate will continue to include a cost recovery
mechanism called the Cost Recovery Charge (CRC). The CRC is necessary
to adequately maintain a sufficient cash balance in the Upper Colorado
River Basin Fund. The CRC is a charge on Sustainable Hydropower (SHP)
energy, as determined by financial conditions. Every May, Western will
provide customers with information concerning any anticipated CRC for
the upcoming fiscal year (FY). If Western determines a CRC is
necessary, firm power customers may choose not to take as much firm
energy and, in exchange, Western will waive the CRC charge. In addition
to the potential for a CRC being implemented every year, Western will
consider assessing the CRC upon a 45-day notice to customers, should
water releases at Glen Canyon Dam be reduced to less than 8.23 million
acre-feet (MAF) in a FY.
By Delegation Order No. 00-037.00, effective December 6, 2001, the
Secretary of Energy delegated: (1) The authority to develop power and
transmission rates to Western's Administrator, (2) the authority to
confirm, approve, and place such rates into effect on an interim basis
to the Deputy Secretary of Energy, and (3) the authority to confirm,
approve, and place into effect on a final basis, to remand or to
disapprove such rates to FERC. Existing Department of Energy procedures
for public participation in power rate adjustments (10 CFR part 903)
were published on September 18, 1985.
Under Delegation Order Nos. 00-037.00 and 00-001.00A, 10 CFR part
903, and 18 CFR part 300, I hereby confirm, approve, and place Rate
Order No. WAPA-137, the proposed SLCA/IP firm power rate, CRSP firm and
non-firm transmission rates, and ancillary services rates into effect
on an interim basis.
The new Rate Schedules SLIP-F9, SP-PTP7, SP-NW3, SP-NFT6, SP-SD3,
SP-RS3, SP-EI3, SP-FR3, and SP-SSR3 will be promptly submitted to FERC
for confirmation and approval on a final basis.
Dated: September 4, 2008.
Jeffrey F. Kupfer,
Acting Deputy Secretary.
Department of Energy
Deputy Secretary
[Rate Order No. WAPA-137]
In the Matter of: Western Area Power Administration Rate
Adjustment for the Salt Lake City Area Integrated Projects and
Colorado River Storage Project; Order Confirming, Approving, and
Placing the Salt Lake City Area Integrated Projects Firm Power,
Colorado River Storage Project Transmission and Ancillary Services
Rates Into Effect on an Interim Basis
These rates were established in accordance with section 302 of the
Department of Energy (DOE) Organization Act (42 U.S.C. 7152). This Act
transferred to and vested in the Secretary of Energy the power
marketing functions of the Secretary of the Department of the Interior
and the Bureau of Reclamation (Reclamation) under the Reclamation Act
of 1902 (ch. 1093, 32 Stat. 388), as amended and supplemented by
subsequent laws, particularly section 9(c) of the Reclamation Project
Act of 1939 (43 U.S.C. 485h(c)), and other acts that specifically apply
to the project involved.
By Delegation Order No. 00-037.00, effective December 6, 2001, the
[[Page 52981]]
Secretary of Energy delegated: (1) The authority to develop power and
transmission rates to Western's Administrator, (2) the authority to
confirm, approve, and place such rates into effect on an interim basis
to the Deputy Secretary of Energy, and (3) the authority to confirm,
approve, and place into effect on a final basis, to remand or to
disapprove such rates to the Federal Energy Regulatory Commission
(FERC). Existing DOE procedures for public participation in power rate
adjustments (10 CFR part 903) were published on September 18, 1985.
Acronyms and Definitions
As used in this Rate Order, the following acronyms and definitions
apply:
Administrator: The Administrator of the Western Area Power
Administration.
A.F.: Acre-feet.
AFC: Actual firming energy costs (MWh) as used in the PYA formula.
AHP: Available Hydropower.
ALP: Animas La Plata Project.
ATRR: Annual Transmission Revenue Requirement.
Basin Fund: Upper Colorado River Basin Fund.
BFBB: Basin Fund Beginning Balance as used in the CRC formula.
BFTB: Basin Fund Target Balance as used in the CRC formula.
Capacity: The electric capability of a generator, transformer,
transmission circuit, or other equipment. It is expressed in kW.
Capacity Rate: The rate which sets forth the charges for capacity. It
is expressed in $/kWmonth and applied to each kW of the Contract Rate
of Delivery (CROD).
CDP: Customer Displacement Power.
Composite Rate: The rate for firm power which is the total annual
revenue requirement for capacity and energy divided by the total annual
energy sales. It is expressed in mills/kWh and used for comparison
purposes.
CRC: Cost Recovery Charge. A mechanism to assist in recovery of
purchased power costs during financial hardship.
CRCE: CRC Energy (GWh) as used in the CRC and PYA formulas.
CRCEP: CRC Energy Percentage of full SHP as used in the CRC and PYA
formulas.
CROD: Contract Rate of Delivery. The maximum amount of capacity made
available to a preference customer for a period specified under a
contract.
CRSP: Colorado River Storage Project.
CRSP Act: An act to authorize the Secretary of the Interior to
construct, operate, and maintain the Colorado River Storage Project and
Participating Projects, and for other purposes. (Act of April 11, 1956,
ch. 203, 70 Stat. 105)
CRSP MC: The CRSP Management Center of Western Area Power
Administration.
Customer: An entity with a contract that is receiving firm electric
service and transmission from Western's CRSP MC.
DOE: United States Department of Energy.
DOE Order RA 6120.2: An order outlining power marketing administration
financial reporting and ratemaking procedures.
DSW: Desert Southwest Region of Western Area Power Administration.
EA: SHP Energy Allocation (GWh) as used in the CRC formula.
EAC: Sum of customers' energy allocations subject to the PYA formula.
Energy: Power produced or delivered over a period of time. It is
expressed in kilowatthours.
Energy Rate: The rate which sets forth the charges for energy. It is
expressed in mills/kWh and applied to each kWh delivered to each
Customer.
EIS: Environmental Impact Statement.
FA: Funds Available as used in the CRC formula.
FA1: Basin Fund Balance Factor as used in the CRC formula.
FA2: Revenue Factor as used in the CRC formula.
FARR: Additional revenue to be recovered as used in the CRC formula.
FE: Forecasted purchased energy as used in the CRC formula.
FERC: Federal Energy Regulatory Commission.
FFC: Forecasted average energy price per MWh as used in the CRC and PYA
formulas.
Firm: A type of product and/or service always available at the time
requested by the customer.
FRN: Federal Register notice.
FX: Forecasted energy purchased expense as used in the CRC formula.
FY: Fiscal year is the period from October 1 to September 30.
GWh: Gigawatthour. The electrical unit of energy that equals 1 billion
watt-hours or 1 million kWh.
HE: Forecasted hydro energy as used in the CRC formula.
Integrated Projects: The resources and revenue requirements of the
Collbran, Dolores, Rio Grande, and Seedskadee projects blended together
with the CRSP to create the SLCA/IP resources and rate.
kW: Kilowatt. The electrical unit of capacity that equals 1,000 watts.
kWh: Kilowatthour. The electrical unit of energy that equals 1,000
watts produced or delivered in 1 hour.
kWmonth: Kilowattmonth. The electrical unit of the monthly amount of
capacity.
kWyear: Killowattyear. A unit of electrical capacity demanded for 8,760
hours.
Load: The amount of electric power or energy delivered or required at
any specified point(s) on a system.
Load-Ratio Share: Network customer's hourly load (including its
designated network load not physically interconnected with Western)
coincident with Western's monthly CRSP transmission system peak.
M&I: Municipal and Industrial water.
MAF: Million Acre-Feet. The amount of water required to cover 1 million
acres, 1 foot in depth.
Mill: A monetary denomination of the United States that equals one-
tenth of a cent or one-thousandth of a dollar.
Mills/kWh: Mills per kilowatthour. A unit of charge for energy.
MW: Megawatt. The electrical unit of capacity that equals 1 million
watts or 1,000 kilowatts.
MWh: One million watt-hours of electric energy. A unit of electrical
energy which equals 1 megawatt of power used for 1 hour.
NATRR: Net Annual Transmission Revenue Requirement.
NB: Net Balance as used in the CRC formula.
NEPA: National Environmental Policy Act of 1969 (42 U.S.C. 4321, et
seq.).
Non-firm: A type of product and/or service not always available at the
time requested by the customer.
NR: The net revenue remaining after paying all annual expenses as used
in the CRC formula.
OASIS: Open Access Same-Time Information System.
O&M: Operation and Maintenance.
OM&R: Operation, Maintenance, and Replacements.
PAE: Projected Annual Expenses as used in the CRC formula.
PAR: Projected Annual Revenue without the CRC as used in the CRC
formula.
Participating Projects: The projects participating with CRSP according
to the CRSP Act of 1956 (43 U.S.C. 620).
PFE: Prior year actual firming energy as used in the PYA formula.
PFX: Prior year actual firming expenses as used in the PYA formula.
Pinch Point: The nearest future year in the PRS where cumulative
expenses and required payments equal cumulative revenues.
Power: Capacity and energy.
Preference: The provisions of Reclamation Law which require Western to
first make Federal power available to certain entities. For
[[Page 52982]]
example, section 9(c) of the Reclamation Project Act of 1939 (43 U.S.C.
485h(c)) states that preference in the sale of Federal power shall be
given to municipalities and other public corporations or agencies and
also to cooperatives and other nonprofit organizations financed in
whole or in part by loans made under the Rural Electrification Act of
1936.
Price: Average price per MWh for purchased power as used in the CRC
formula.
Project Use: Power used to operate the CRSP Participating Projects
facilities under Reclamation Law.
Proposed Rate: A rate that has been recommended by Western to the
Deputy Secretary of DOE for approval.
Provisional Rate: A rate which has been confirmed, approved, and placed
into effect on an interim basis by the Deputy Secretary of DOE.
PRS: Power Repayment Study.
PYA: Prior Year Adjustment as used in the CRC formula.
RA: Revenue Adjustment as used in the PYA formula.
Rate Brochure: A document explaining the rationale and background for
the rate proposal contained in this Rate Order, dated January 2008.
Ratesetting PRS: The PRS used for the rate adjustment proposal.
Reclamation: United States Department of the Interior, Bureau of
Reclamation.
Reclamation Law: A series of Federal laws, viewed as a whole that
create the originating framework under which Western markets power.
Revenue Requirement: The revenue required to recover annual expenses,
such as O&M, purchased power, transmission service expenses, interest,
deferred expenses, repayment of Federal investments, and other assigned
costs.
RMR: Rocky Mountain Region of Western Area Power Administration.
SHP: Sustainable Hydropower as defined in the firm power contracts for
SLCA/IP.
SLCA/IP: Salt Lake City Area Integrated Projects. The resources and
revenue requirements of the Collbran, Dolores, Rio Grande, and
Seedskadee projects blended together with the CRSP to create the SLCA/
IP rate.
Supporting Documentation: A compilation of data and documents that
support the Rate Brochure and the rate proposal.
TRC: Transmission Revenue Credits.
TSTL: CRSP Transmission System Total Load.
Western: United States Department of Energy, Western Area Power
Administration.
WL: Waiver Level as used in the CRC formula.
WLP: Waiver Level Percentage of full SHP as used in the CRC formula.
WPR: Work Program Review. The work plan is a draft estimate of costs
that are expected to be included in the Congressional Budget for
Western and Reclamation and the basis for budget estimates to be used
in the PRS.
WRP: Western Replacement Power as defined in the firm power contracts
for SLCA/IP.
Effective Date
The new interim rates will take effect on the first day of the
first full billing period beginning on or after October 1, 2008, and
will remain in effect until September 30, 2013, pending approval by
FERC on a final basis.
Public Notice and Comment
Western followed the Procedures for Public Participation in Power
and Transmission Rate Adjustments and Extensions, 10 CFR part 903, in
developing these rates. The steps Western took to involve interested
parties in the rate process were:
1. The proposed rate adjustment process began May 30, 2007, when
Western mailed a notice announcing an informal customer meeting on June
19, 2007, to all SLCA/IP customers and interested parties.
2. On June 19, 2007, August 21, 2007, and October 10, 2007,
beginning at 10:30 a.m., informal customer meetings were held to
discuss the components and rationale for the rate adjustment, to
discuss possible rate designs, and to answer questions.
3. A Federal Register notice, published on January 4, 2008 (73 FR
858), announced the proposed rate adjustments for the SLCA/IP, CRSP
Transmission, and Ancillary Services Rates. This publication began a
public consultation and comment period and announced the public
information and public comment forums.
4. On January 11, 2008, Western's CRSP MC mailed all SLCA/IP
preference customers, CRSP transmission customers, and interested
parties letters along with the Rate Brochure, which contains a copy of
the published Federal Register notice proposal and a reminder of the
February 5, 2008, public information forum.
5. On February 5, 2008, beginning at 1:30 p.m., Western held a
public information forum at the Radisson Hotel Salt Lake City Airport,
Salt Lake City, Utah. Western provided detailed explanations of the
proposed SLCA/IP firm power rate and the CRSP transmission and
ancillary service rates. Western provided Rate Brochures, supporting
documentation, and informational handouts at this meeting.
6. On March 4, 2008, beginning at 1:30 p.m., Western held a comment
forum at the Radisson Hotel Salt Lake City Airport, Salt Lake City,
Utah, to give the public an opportunity to comment for the record.
Western also notified its customers of its intent to extend the comment
and consultation period through May 5, 2008, and to hold additional
information and comment forums.
7. On March 12, 2008, Western's CRSP MC mailed a flyer to all SLCA/
IP customers, CRSP transmission customers, and interested parties
notifying them of a second public information forum and a second
comment forum.
8. A Federal Register notice, published March 24, 2008 (73 FR
15519), announced the extension of the comment and consultation period
for the SLCA/IP firm power, CRSP transmission and ancillary services
rates.
9. On March 24, 2008, CRSP MC mailed all SLCA/IP customers, CRSP
transmission customers, and interested parties a letter with a copy of
the published FRN extending the comment and consultation period for the
SLCA/IP firm power, CRSP transmission and ancillary services rates.
10. On April 10, 2008, beginning at 1:30 p.m., Western held its
second public information forum at the Bureau of Reclamation, Wallace
F. Bennett Federal Building, Room 8102, 125 South State Street, Salt
Lake City, Utah.
11. On April 10, 2008, beginning at 2:35 p.m., Western held its
second comment forum at the Bureau of Reclamation, Wallace F. Bennett
Federal Building, Room 8102, 125 South State Street, Salt Lake City,
Utah.
12. Western received 17 comment letters during the consultation and
comment period, which ended May 5, 2008. All formally submitted
comments have been considered in preparing this Rate Order.
Comments
Written comments were received from the following organizations:
Arizona Tribal Energy Association, Arizona (2),
Farmington Electric Utility System, New Mexico,
Colorado River Energy Distributors Association, Arizona (3),
Grand Canyon Trust, Arizona,
Inter Tribal Council of Arizona, Inc., Arizona,
Irrigation & Electrical Districts Association of Arizona, Arizona,
Living Rivers, Utah (2),
[[Page 52983]]
Murray City Corporation, Utah (2),
Navajo Tribal Utility Authority, Arizona,
Salt River Pima-Maricopa Indian Community, Arizona,
Utah Associated Municipal Power Systems, Utah,
Yavapai-Apache Nation, Arizona.
Representatives of the following organizations made oral comments:
Arizona Tribal Energy Association, Arizona, Colorado River Energy
Distributors Association, Arizona,
Navajo Tribal Utility Authority, Arizona,
Utah Associated Municipal Power Systems, Utah.
Project Description
The SLCA/IP consists of the CRSP, Rio Grande, and Collbran
projects. The CRSP includes two participating projects that have power
facilities: the Dolores and Seedskadee projects. Western integrated the
Rio Grande and Collbran projects with CRSP for marketing and ratemaking
purposes on October 1, 1987. The goals of integration were to increase
marketable resources, simplify contract and rate development and
project administration by creating one rate and to ensure repayment of
the Projects' costs. All Integrated Projects maintain their individual
identities for financial accounting and repayment purposes, but their
revenue requirements are integrated into the SLCA/IP PRS for
ratemaking.
Power Repayment Study--Firm Power Rate
Western prepares a PRS each FY to determine if revenues will be
sufficient to repay, within the required time, all costs assigned to
the SLCA/IP. Repayment criteria are based on policies (including DOE
Order RA 6120.2) and authorizing law.
Provisional rates for SLCA/IP firm power result in an overall
composite rate increase of approximately 17.4 percent, when compared to
the existing SLCA/IP firm power rates in Rate Schedule SLIP-F8. The
current composite rate under Rate Schedule SLIP-F8 is 25.28 mills/kWh.
The provisional rates for SLCA/IP firm power in Rate Schedule SLIP-F9
will be implemented over a 2-year period resulting in a composite rate
of 26.80 mills/kWh on October 1, 2008, and a composite rate capped at
29.68 mills/kWh on October 1, 2009. In the first year, the provisional
firm power rate consists of an energy charge of 11.06 mills/kWh and a
capacity charge of $4.70/kWmonth. The second step of the rate will be
effective October 1, 2009 through September 30, 2013, or until
superseded. The energy charge will not exceed 12.29 mills/kWh and the
capacity charge will not exceed $5.22/kWmonth. The actual rates for the
second step will be determined using 2008 actual data, updated
estimates for purchased power and transmission, as well as other
revised estimates that could affect the rate. Western will provide
customers an opportunity to comment on the second step during a meeting
scheduled for June 2009. The following table compares the current and
proposed firm power rates.
Comparison of Current and Proposed Firm Power Rates
--------------------------------------------------------------------------------------------------------------------------------------------------------
Percent
Current rate October 1, 2005- Proposed rate October 1, 2008 increase Proposed rate\1\ October 1, Total
September 30, 2010 (1st step) for 1st 2009-September 30, 2013 (2nd percent
step step) increase
--------------------------------------------------------------------------------------------------------------------------------------------------------
Rate Schedule..................... SLIP-F8....................... SLIP-F9....................... ......... SLIP-F9....................... .........
Energy (mills/kWh)................ 10.43......................... 11.06......................... 6.0 12.29......................... 17.8
Capacity ($/kWmonth).............. 4.43.......................... 4.70.......................... 6.0 5.22.......................... 17.9
Composite Rate (mills/kWh)........ 25.28......................... 26.80......................... 6.0 29.68......................... 17.4
--------------------------------------------------------------------------------------------------------------------------------------------------------
\1\ Maximum rate for FY 2010.
Cost Recovery Charge
Western is proposing to continue the CRC calculation and assessment
in the proposed rate schedule as it is in the current SLIP-F8 rate
schedule and to add an additional triggering mechanism.
The CRC is based on a Basin Fund cash analysis only and is
independent of the PRS calculations. In the event that expenses
significantly exceed estimates and in order to adequately recover and
maintain a sufficient balance in the Basin Fund, Western will calculate
and assess a CRC. The CRC is designed to maintain a Basin Fund Target
Balance (BFTB) for the following FY and to limit the FY loss to the
Basin Fund. The BFTB will be equal to 15 percent of the upcoming FY's
total expenses but not less than $20 million. The allowable FY loss is
limited to no more than 25 percent of the Basin Fund Beginning Balance
(BFBB). For purposes of explaining how the CRC is calculated, please
refer to Rate Schedule SLIP-F9.
Trigger for Shortage Criteria
In the event that Reclamation's 24-month study projects that Glen
Canyon Dam water releases will drop below 8.23 MAF in a water year
(October through September), Western will recalculate the CRC to
include those lower estimates of hydropower generation and the
estimated costs for any additional purchased power. Western, as in the
yearly projection for the CRC, will give the customers a 45-day notice,
during which they may request a waiver of the CRC by voluntarily taking
less energy than allowed under the customer's Firm Electric Service
contract. This recalculation will remain in effect for the remainder of
the current FY. In the event that hydropower generation returns to 8.23
MAF or higher during the CRC implementation, a new CRC will be
calculated for the next month, and the customers will be notified.
Narrative PYA Discussion
Since the annual determination of the CRC is based upon estimates,
an annual prior year adjustment (PYA) will be calculated. The CRC PYA
for subsequent years will be determined by comparing the prior year's
estimated firming energy cost to the prior year's actual firming energy
cost for the energy provided above the Waiver Level. The PYA will
result in an increase or decrease to a customer's firm energy costs
over the course of the following year. Please see Rate Schedule SLIP-F9
rate schedule for further explanation of the PYA calculation.
CRC Schedule for Customers
Western will provide its customers with information concerning the
anticipated CRC for the upcoming FY in May. The established CRC will be
in effect for the entire FY. The table below displays the time frame
for determining the amount of purchases needed,
[[Page 52984]]
developing customer's load schedules, and making purchases.
CRC Schedule
------------------------------------------------------------------------
Task Date\1\
------------------------------------------------------------------------
April 24-Month Study (Forecast to Model April 1.
Projections).
CRC Notice to Customers................... May 1.
Waiver Request Submitted by Customers..... June 15.
CRC Effective............................. October 1.
------------------------------------------------------------------------
\1\ Note: This schedule does not apply if the CRC is triggered by the
Glen Canyon Dam annual releases dropping below 8.23 MAF.
CRSP Transmission Rates Discussion
The proposed firm and non-firm transmission rates apply to all
transmission-only sales. The present CRSP point-to-point, network, and
non-firm transmission rates, outlined in Rate Schedules SP-PTP6, SP-
NW2, and SP-NFT5 became effective on October 1, 2002. On June 29, 2007,
the Deputy Secretary of Energy extended the transmission rates through
September 30, 2010. The transmission rates include the cost for
scheduling, system control, and dispatch service. Western is proposing
that these three rates remain in effect for this new ratesetting
period. The cost of transmission service for Western's SLCA/IP long-
term electric service will continue to be included in the SLCA/IP firm
power rate. Transmission services are outlined in Western's Tariff.
Western is proposing to use the current methodology, which is an
annual fixed charge formula, to determine the revenue requirement to be
recovered from firm and non-firm transmission service. The annual
transmission revenue requirement includes O&M expenses, administrative
and general expenses, interest expense, and depreciation expense. This
methodology is updated annually using a test year, which is the most
recent historical data available. This revenue requirement is offset by
appropriate CRSP transmission system revenues.
The provisional rate for network transmission service is a formula
calculation based on the annual transmission revenue requirement. There
are no changes to the existing network integration transmission service
formula under Rate Schedule SP-NW2.
Firm Point-to-Point
Western is seeking the continued approval of a rate formula for
calculation of the firm point-to-point transmission rate to be applied
annually. The provisional rate for firm point-to-point transmission
service is $2.21/kWmonth for FY 2008.
The firm point-to-point transmission rate is based upon the most
recent historical year, using an annual fixed-charge methodology. The
annual transmission revenue requirement is reduced by revenue credits
such as non-firm transmission, existing contracts at different rates,
scheduling and dispatch services, and phase-shifter revenues. The
resultant net annual transmission revenue requirement is divided by the
capacity reservation needed to meet firm power and transmission-only
commitments in kW, including the total network integration loads at
system peak, to derive a cost/kWyear. The formula is updated every year
by applying the most current historical test year. If needed, a revised
rate will become effective every October 1. The rate formula is
proposed to be effective October 1, 2008, through September 30, 2013.
The cost/kWyear is calculated using the following formula:
[GRAPHIC] [TIFF OMITTED] TN12SE08.000
Where:
ATRR = Annual Transmission Revenue Requirement. The costs associated
with facilities that support the transfer capability of the CRSP
transmission system, excluding generation facilities. These costs
include investment costs, interest expenses, depreciation expense,
administrative and general expenses, and operation and maintenance
expense, including transmission purchases. Transmission purchases
reflect those costs associated with CRSP contractual rights.
TRC = Transmission Revenue Credits. The revenues generated by the
CRSP transmission system not related to the revenues from the sale
of long-term firm transmission.
NATRR = Net Annual Transmission Revenue Requirement. The Annual
Revenue Requirement minus Transmission Revenue Credits.
TSTL = CRSP Transmission System Total Load. The sum of the total
CRSP transmission capacity under long-term reservation including the
total network integration loads at system peak.
Non-Firm Point-to-Point Transmission
The proposed rate for non-firm point-to-point CRSP transmission
service is a mills/kWh rate, which is based upon the current firm
point-to-point rate and may be discounted. This rate will remain in
effect concurrently with the firm point-to-point rate and will also be
reviewed annually. Transmission availability will be posted on
Western's OASIS.
Network Transmission
The proposed rate for network transmission is a calculation based
upon the annual revenue requirement then in effect, as determined by
the annual fixed charge methodology.
Ancillary Services Discussion
Six ancillary services will continue to be offered by CRSP MC, two
of which are required as part of CRSP transmission service. These are
(1) Scheduling, system control, and dispatch service and (2) reactive
supply, and voltage control service. The remaining four ancillary
services are (3) regulation and frequency response service, (4) energy
imbalance service, (5) spinning reserve service, and (6) supplemental
reserve service. These will be offered either from the balancing
authority or from the CRSP MC Merchant Function. Sales of regulation
and frequency response, energy imbalance, spinning reserve, and
supplemental reserve services from SLCA/IP power resources are limited
since Western has allocated the SLCA/IP power resources to preference
entities under long-term commitments. Western has made a clarification
to its spinning and supplemental reserve ancillary services and has
removed its reference to the Western System Power Pool Agreement.
Western will continue to use market-based rates to determine its rate
for spinning and supplemental reserves under the Rate Schedule SSP-
SSR3. The availability and type of ancillary service will be determined
based on excess resources available at the time the services are
requested, except for the two ancillary services required to be
provided in conjunction with the sale of CRSP transmission services.
Since the CRSP transmission system lies in two balancing
authorities, operated by Western's RMR and DSW, many of the ancillary
services are offered through their respective balancing authorities.
The provisional rates for ancillary services are designed to
recover only the costs associated with providing the service(s). The
costs for providing scheduling, system control, and dispatch service
are included in the appropriate provisional transmission services
rates. However, the charges for reactive supply and voltage control
service will be in accordance with Western's RMR and DSW applicable
rate schedules.
Existing and Provisional Rates
A comparison of the existing and provisional SLCA/IP firm power
rates,
[[Page 52985]]
CRSP Transmission and Ancillary Services, follows:
Comparison of Existing and Provisional Salt Lake City Area Integrated Projects Firm Power, Colorado River Storage Project Transmission and Ancillary
Services
--------------------------------------------------------------------------------------------------------------------------------------------------------
Provisional rate\1\
Current rate October Provisional rate Percent increase for October 1, 2009- Total percent
1, 2005- September October 1, 2008 (1st 1st step September 30, 2013 increase
30, 2010 step) (2nd step)
--------------------------------------------------------------------------------------------------------------------------------------------------------
Energy (mills/kWh)................. 10.43................. 11.06................. 6.................... 12.29................ 17.8.
CRC (if applicable)................ varies................ varies................ varies............... varies............... varies.
Capacity ($/kWmonth)............... 4.43.................. 4.70.................. 6.................... 5.22................. 17.9.
Composite Rate (mills/kWh)......... 25.28................. 26.80................. 6.................... 29.68................ 17.4.
Firm Transmission Rate............. $2.21 (FY 08)......... To be determined for To be determined for To be determined for To be determined for
FY 09. FY 09. FY 10. FY 10.
Network Transmission (net annual $72,613,170 (FY 08)... To be determined for To be determined for To be determined for To be determined for
revenue requirement). FY 09. FY 09. FY 10. FY 10.
Non-firm Transmission Rate......... 3.03 mills/kWh, may be To be determined for To be determined for To be determined for To be determined for
discounted (FY 08). FY 09. FY 09. FY 10. FY 10.
Ancillary Services \2\............. N/A................... N/A................... N/A.................. N/A.................. N/A.
--------------------------------------------------------------------------------------------------------------------------------------------------------
\1\ Maximum rate for FY 2010-2013.
\2\ Since all of CRSP transmission facilities are located in two Western balancing authorities, these services are provided through these balancing
authorities.
Certification of Rates
Western's Administrator certified that the provisional rates for
SLCA/IP firm power, CRSP transmission, and ancillary services are the
lowest possible rates consistent with sound business principles. The
provisional rates were developed following administrative policies and
applicable laws.
SLCA/IP Firm Power Rate Discussion
According to Reclamation Law, Western must establish power rates
sufficient to recover O&M expenses, purchased power expenses, interest
expenses, and repayment of power investment and irrigation aid.
The existing rate for SLCA/IP firm power under Rate Schedule SLIP-
F8 expires September 30, 2010. Effective October 1, 2008, Rate Schedule
SLIP-F8 will be superseded by the new rates in Rate Schedule SLIP-F9.
The provisional rates for SLCA/IP firm power consist of a capacity rate
and an energy rate. The provisional rates for SLCA/IP firm power in
Rate Schedule SLIP-F9 will result in a composite rate of 26.80 mills/
kWh on October 1, 2008, and a composite rate capped at 29.68 mills/kWh
on October 1, 2009. The provisional firm power rate will be implemented
over a 2-year period. In the first year, the provisional firm power
rate consists of an energy charge of 11.06 mills/kWh and a capacity
charge of $4.70/kWmonth. The second step of the rate will be effective
October 1, 2009, through September 30, 2013, or until superseded, and
will be capped at the energy charge of 12.29 mills/kWh and a capacity
charge of $5.22/kWmonth.
Statement of Revenue and Related Expenses
The following table provides a summary of projected revenue and
expense data for the SLCA/IP firm power rate through the 5-year
provisional rate approval period.
SLCA/IP Firm Power--Comparison of 5-Year Rate Period (FY 2009-FY 2013)
Total Revenues and Expenses
[$000]
------------------------------------------------------------------------
Proposed
Existing rate with Difference
rate cap
------------------------------------------------------------------------
Total revenues.................. 828,785 919,125 90,340
Revenue Distribution
Expenses:
O&M......................... 314,501 348,731 34,230
Purchased Power and 76,489 133,525 57,036
Transmission...............
Integrated Projects 38,820 37,733 (1,087)
Requirements...............
Interest.................... 33,165 67,551 34,386
Other....................... 17,789 14,784 (3,005)
---------------------------------------
Total Expenses.......... 480,764 602,324 121,560
Principal Payments:
Capitalized Expenses 0 0 0
(deficits).................
Original Project and 198,009 96,812 (101,197)
Additions..................
Replacements................ 137,183 206,803 69,620
Irrigation.................. 12,829 13,186 357
Irrigation to Participating 0 0 0
Projects...................
---------------------------------------
Total Principal Payments 348,021 316,801 (31,220)
---------------------------------------
[[Page 52986]]
Total Revenue 828,785 919,125 90,340
Distribution.......
------------------------------------------------------------------------
Basis for Rate Development
The existing rates for SLCA/IP firm power in Rate Schedule SLIP-F8
no longer provide sufficient revenues to pay all annual costs,
including interest expense, and repayment of investment and irrigation
aid within the allowable periods. The adjusted rates reflect increases
primarily in O&M costs and purchased power and transmission costs. The
provisional rates will provide sufficient revenue to pay all annual
costs, including interest expense, and to repay power investment and
irrigation aid within the allowable periods. To coincide with the start
of each FY, the provisional rates for the first step will take effect
on October 1, 2008. The provisional rates for the second step will take
effect on October 1, 2009, and remain in effect through September 30,
2013.
Provisions for transformer losses adjustment, power factor
adjustment, WRP administrative charge, and CDP administrative charge
adjustments are part of the provisional rates for SLCA/IP firm power.
Western will not modify the provisions and methodologies for these
adjustments, which will remain as specified in Rate Schedule SLIP-F9.
Comments
The comments and responses regarding the firm power rate,
paraphrased for brevity when not affecting the meaning of the
statement(s), are discussed below. Direct quotes from comment letters
are used for clarity where necessary. The rate process issues discussed
are (1) Firm Power Rate Design, (2) Cost Recovery Charge, (3) Stepped
Rate, (4) Basin Fund, (5) Revenue, (6) Western Expenses, (7)
Reclamation Expenses and Related Issues, (8) Project Use, (9)
Environmental, (10) Hydrology, (11) Transmission and Ancillary
Services, and (12) Miscellaneous.
1. Firm Power Rate Design
Comment: Many customers expressed appreciation for the CRSP MC and
its willingness to engage in meaningful dialogue, entertain
suggestions, and develop alternatives to mitigate significant rate
increases.
Response: The CRSP MC is likewise appreciative of the customers'
support.
Comment: Pages 6 and 8 of the Rate Brochure reference the
``ratesetting period'' of 17 years as opposed to 20 years. Please
explain why a different ratesetting period was used. Are the current
rates in effect based upon a 20-year ratesetting period?
Response: The current rate is based on a 20-year ratesetting
period. The ratesetting period begins the year the rate took effect (FY
2006) and continues through the pinch point year (FY 2025). The pinch
point year is the year of the PRS that has the largest revenue
requirements.
The proposed rate will take effect in October 2008, which is the
beginning of FY 2009. Since the proposed ratesetting period extends
through the same pinch point year, the ratesetting period of the
proposed rate is 3 years shorter than that of the current rate.
Comment: Some customers requested copies of all documents and
information used to develop the cost basis for the O&M component of the
new rate included in the PRS.
Response: Documents and information used to develop the cost basis
for the O&M component of the rate proposal were included in the
Supporting Documentation Booklet, specifically Tab 10, which had been
previously provided to requestors. In addition, the requestors were
sent copies of the CRSP MC Work Program Review documents for FY 2006
through FY 2010.
Comment: One commenter asked Western to explain on what basis
Western could extend the collection of revenues for apportionment such
that rate impacts of those obligations are reduced.
Response: Western adheres specifically to section 5(e) of the CRSP
Act, which requires the inclusion of the apportionment of revenues for
the States, in the Power Repayment Studies. In addition, DOE Order
RA6120.2 provides further clarification of the treatment of repayment
periods, specifically in section 12(b)(5), which states ``expected
revenues are at least sufficient to recover other costs such as
payments to basin funds, Participating Projects or States.''
Comment: One commenter asked Western, ``Please run the PRS and
provide the results excluding the funds categorized as `Available w/
Appor' found behind Tab 19 of the CRSP MC Supporting Documentation for
Proposed Rates: SLCA/IP Firm Power, CRSP Transmission & Ancillary
Services dates January 2008 on the sheet titled `Colorado River Storage
Project, Aid to Participating Projects Irrigation Repayment Obligations
and Apportioned Revenue Applied' totaling $642,582,791, which are not
tied to authorized projects.''
Response: The proposed rate includes the apportionment revenues
required to be collected through FY 2025 (about $368 million). The PRS
was rerun without the excess revenue collection for apportionment
required by the CRSP Act. Removing these apportionment collections from
the repayment period lowered the composite rate by 2.61 mills/kWh.
Comment: Multiple comments were received concerning the inclusion
of apportionment revenue collection in the rate, mentioning that $368
million of revenues for apportionment payments would be received by FY
2025. The customers objected to the inclusion of these apportionment
revenues in the ratesetting period and recommended that apportionment
costs associated with unauthorized, unconstructed projects be
programmed into the PRS beyond the pinch point year.
Response: Section 5(e) of the CRSP Act specifies that revenues in
the Basin Fund in excess of the amounts needed to defray the cost of
operation, maintenance and replacement of the CRSP Project, and to
return to the general fund of the Treasury costs allocated to power,
municipal water supply, irrigation and salinity control shall be
apportioned to the four Upper Colorado Basin States to assist in the
repayment of participating projects located within these States.
Section 5(e) specifies that such excess ``revenues in the Basin Fund *
* * shall be apportioned among the states of the Upper Division in the
following percentages: Colorado, 46 per centum;
[[Page 52987]]
Utah, 21.5 per centum; Wyoming, 15.5 per centum; and New Mexico, 17 per
centum * * *.'' Funds so apportioned must be used only for the
repayment of construction costs of participating units located in the
states to which such revenues are apportioned.
Comment: A commenter stated that approximately 60 percent of the
proposed rate increase appears to be due to apportionment expenses
associated with presently non-existent, unauthorized projects.
Response: The comment correctly observes that removing the
apportionment obligation from the proposed rate would reduce the
proposed rate increase by approximately 60 percent; however, as
discussed above, the apportionment obligation is required by law, and
as such, the apportionment obligations are already included in the
current rate and therefore play no part in the proposed 17 percent
increase. The 17 percent increase is due mainly to O&M and purchased
power and transmission expense, not because of adding ``new''
Participating Projects costs.
Comment: A comment was received referring to the 1983 agreement
between Reclamation and Western that provides guidance for inclusion of
Participating Projects into the PRS and believes that Western should
follow this guidance.
Response: Western currently abides by the 1983 agreement when
including Participating Projects into the PRS by including only those
authorized Participating Projects costs in the rate that meet the
criteria. The apportionment methodology is then applied toward those
projects.
Comment: On what basis, other than historic practice or internal
agency opinion, does Western justify inclusions of continued
apportionment funds for non-authorized projects in the PRS?
Response: Western adheres to the CRSP Act, specifically section 5,
which requires the inclusion of the Participating Projects and the
apportionment of revenues in the PRS. In addition, DOE Order RA 6120.2,
specifically section 12(b)(5), states, ``expected revenues are at least
sufficient to recover other costs such as payments to basin funds,
Participating Projects or States.'' Western's obligation to collect
apportionment revenues is independent of a state's authorization to
spend their apportioned revenues.
Comment: A commenter states it is undisputed that the current rate
will collect sufficient revenues to meet all proposed expenditures over
the 5-year rate window.
Response: It is true that the current rate will collect sufficient
revenues for a 5-year, rate cost evaluation period. However, DOE Order
RA 6120.2, section 12, requires revenues to be sufficient to recover
annual expenses and repayment through the ratesetting period (through
FY 2025 in this ratesetting PRS). According to Reclamation Law, Western
must establish power rates sufficient to recover O&M expenses,
purchased power expenses, interest expenses, and repayment of power
investment and irrigation aid. For the current 17-year ratesetting
period, from FY 2009 through FY 2025, the current rate is not
sufficient to cover expenses and repayment through this period. The
current rate shows deficits in some of these years, including the final
year of the study; therefore, the proposed rate adjustment is needed.
Comment: Many comments were received stating that the comment
period closing on May 5 was before the end of the formal FY 2010 WPR
period of May 21 and wanted to ensure their comments on the FY 2010 WPR
were incorporated into the final Rate Order. Some comments suggested
Western extend the comment period for this rate process another 30
days, closing on June 4, 2008. Others recommended that the O&M
components of this rate proceeding continue to be scrubbed and refined
in consultation with the customers prior to finalization of this rate
proposal. One commenter went on to state, ``because the formal work
program process has not yet concluded prior to the comment deadline * *
* we reserve the right to comment on those adjustments prior to
finalization of the rate.''
Response: Western's FY 2010 WPR has been finalized; however,
Western is committed to continue to work with its customers to try to
reduce the budgeted estimates. Western also believes that since the
second step is capped, the second step firm power rate can be reduced
if the budget estimates are too high. In addition, Western is willing
to work with its customers on the FY 2011 budget process which will be
used to determine the second step of the rate that will be effective
October 1, 2009.
Comments: When will the FY 2010 WPR materials be available, and
when will a new PRS be run with updated data? Will this update be
provided before the comment forum, or will it be after the comment
forum and before the close of the comment period? When will the FY 2010
WPR be finalized?
Response: The WPR process for the FY 2010 budget was held on
February 28, 2008. Western has since reviewed those costs to streamline
them as much as possible. Western presented these updates to planned
O&M costs based on the updated FY 2010 WPR in the second public
information forum, which was held on April 10, 2008.
Comment: Another customer encouraged Western to come to some
decisions so they can incorporate the forecasted rates into their
budget planning process.
Response: Western recognizes that its customers have a budget
planning process and the rate adjustment has an effect on its
customers' internal processes. Western will be forthcoming with the
final rates as soon as the Acting Deputy Secretary places the rates
into effect on an interim basis.
2. Cost Recovery Charge
Comment: A comment was made that the early portions of the Rate
Brochure indicate the CRC would remain in effect for an entire FY.
However, page 17 proposes triggering criteria with a 45-day customer
notice.
Response: The firm power rate proposal includes the CRC similar to
the existing rate except that it also includes a new, additional,
triggering criteria caused by reduced releases from Glen Canyon Dam.
This new triggering criteria has the same 45-day customer notice as the
Basin Fund balance criteria, but could occur whenever Reclamation's 24-
month study indicates Glen Canyon water releases will be reduced to
less than 8.23 million acre-feet in a water year. This can happen any
time during the year.
Comment: A comment was made regarding the CRC and the example shown
on page 14 of the Rate Brochure. The commenter asked if the calculation
of annual expenses includes other revenues as an expense offset or are
they included in total revenue.
Response: The CRC includes all revenues and expenses. No offsetting
of revenue or expenses occurs except for the purpose of calculating the
CRC, non-reimbursable environmental expenses are capped at $27 million
and indexed for inflation.
Comment: Several customers referenced a CRC ``adjuster'' or credit
mechanism whereby when actual purchased power expenses do not meet
projections, a credit would be returned to the firm power customers
similar to one in place at the Southwestern Power Administration.
``Consider if FX is less than projected, the differential could be
spread over all MWh, OR if FA is greater than FARR, the differential
could be a credit.''
Response: The CRC already includes a PYA true-up from estimates to
actuals. For Western to implement an adjustment similar to Southwestern
Power Administration, purchased
[[Page 52988]]
power would have to be unbundled from the firm power rate. The current
method of socializing all purchased power costs into the SLCA/IP firm
electric service rate would not be conducive to using a purchased power
adjustment. The CRC includes a PYA true-up from estimates to actuals
that is only applicable to those customers actually assessed a CRC
because they are the ones who paid the estimated costs of purchasing
additional firming energy. The customers who receive a CRC waiver
acquire their needed additional energy elsewhere.
3. Stepped Rate
Comment: What internal process(es) would be required in order to
change the CRSP MC ratemaking methodology from the pinch point to
another methodology? Is Western open to this type of discussion?
Response: Western would be willing to discuss any ratemaking
methodology that is within its constraints of law and policy.
Comment: When will the decision be made whether or not Western will
implement the stepped rate?
Response: Western has decided to implement the stepped rate with
the first step being effective October 1, 2008.
Comment: How would the stepped rate work? Would the rate be one
certain percentage, and in the second year the rates would
automatically go up? Would the rate be based on the most current PRS in
that year?
Response: The first year will be a composite rate of 26.80 mills/
kWh, which is a 6 percent increase. The second step will be capped at
29.68 mills/kWh for the composite rate. This would be the maximum
amount for the second step. The second step rate will be determined by
using FY 2008 actual data, updated estimates for purchased power and
transmission, as well as other estimates that could affect the rate. As
of now, and for analysis purposes, the total composite rate of 29.68
mills/kWh will be effective October 1, 2009.
Comment: The majority of customers requested that Western consider
delaying the proposed SLCA/IP rate adjustment by at least 1 year,
stating that because there are a number of uncertainties associated
with the proposed rate that may be resolved, thereby eliminating or
reducing the need for such a high rate by October 1, 2009. These
customers recommend a deferment of the rate until October 1, 2009. In
the event Western is unable to defer the rate process, they recommend
the implementation of a stepped rate with the first step October 1,
2008, of zero percent and the second step October 1, 2009, not to
exceed 18 percent.
Response: Western believes that implementation of a zero-percent
increase in the first year is the same as a 1-year deferment of the
rate adjustment and is not fiscally responsible. Western is
implementing a stepped rate with the first step being 26.80 mills/kWh,
which is a 6 percent increase. The second step will not exceed the cap
of 29.68 mills/kWh for an overall 17.4 percent increase from the
current 25.28 mills/kWh rate. Western believes that this will allow
sufficient time to adjust projections based on the current
uncertainties and possibly a second step increase that is less than
current projections.
The second step will use the FY 2008 Final PRS, the FY 2011 WPR
with the same 5-year cost evaluation period (2008-2012), the April
2009, 24-month study from Reclamation, and the most current data
available for all other projections.
4. Basin Fund
Comment: Please provide an accounting of revenues and expenses
which would explain the Basin Fund climbing from $40 million at the end
of FY 2005 to $80 million at the end of the current operating year.
Response: There are many variables that affect the Basin Fund
balance increase; however, the main reason for the increase is the
almost $116 million collected from power revenues for interest expense
and principal payments during the years FY 2006 through FY 2008. The
main offset to these collections is non-reimbursable environmental
expenses.
In addition, Western has not been able to return funds to Treasury
since FY 1999 because of the continued drought. If the Basin Fund
continues to be as healthy as it is today, Western is planning to
return funds to Treasury this FY to satisfy the return of interest and
principal obligations, as required under the CRSP Act.
Comment: Several comments on the projected ``healthy'' ending
balance of the Basin Fund suggest the rate process is not necessary. A
commenter cited that Western has announced if the ending FY 2008 Basin
Fund balance is at the current projected level, Western will probably
make a transfer of funds to Treasury. They further stated that ``under
these circumstances, holding the rate steady while adjusting for
significantly increased hydrology and a change in law is perfectly
appropriate and the sound course of action''.
Response: Western reiterates the fact that the balance in the Basin
Fund does not determine the need for a rate process. In accordance with
DOE Order RA 6120.2, if revenues are not sufficient to cover expenses
and repayment obligations as determined by the PRS, the current rate is
inadequate and must be adjusted.
Comment: One commenter stated concern that ``the fund itself may
evaporate, for which Western has identified no contingencies. Such
revenue losses would have tremendous repercussions on funding for those
environmental programs to reduce salinity and remove jeopardy for
endangered fish.''
Response: Environmental program expenses are non-reimbursable by
the power customers and are not included in the PRS for ratemaking
purposes. However, the programs are funded out of the Basin Fund, and
the costs are credited as funds returned to Treasury for repayment of
CRSP obligations.
5. Revenue
Comment: A commenter asked Western to explain the assumed reduction
in transmission revenue given the strategic planning process to improve
transmission marketing services and if the transmission revenues used
in this PRS factor in the new increased transmission rate.
Response: Firm transmission revenue estimates in the PRS are based
on firm contracts and rates currently in place. Non-firm transmission
revenue estimates are based on a 5-year average of historical data.
Western has no way to estimate increased revenues that may occur due to
efforts to improve transmission marketing services.
Comment: One commenter requested the first part of 2008 be included
in the historical averages.
Response: Western only used actuals from FY 2003 through FY 2007.
Western will include FY 2004 through FY 2008, when determining the
second step of the firm power rate that will be effective October 1,
2009.
6. Western Expenses
Comment: One commenter questioned, ``Given Western's work on
operational consolidation, what are the implications for this rate
process, and specifically, what impacts will there be on RMR's work on
the new billing system?''
Responses: The increase in power billing is related to RMR
information technology (IT) staff that will be supporting the new power
billing system. Over the last 3 to 4 years, the Sierra Nevada Region
maintained the
[[Page 52989]]
old system with minimal enhancements for RMR. As a result, the IT
support costs have been very negligible. While the billing system is
being developed, the costs will be capitalized. After that time,
additional support will be expected the first year or so to get the
system running smoothly and to document processes. As for cost
allocation of the new power billing system, additional information will
be provided next year. RMR and the CRSP MC will work with their
customers on the allocation methodology based on the design of the new
system and various other factors.
Comment: One customer wanted to know if the ``50-5-5'' expenses
drop back to a lower level after FY 2010.
Response: The 50-5-5 initiative (50 ``over-hires,'' over 5 years,
at an approximate cost of $5 million) is a recent Western-wide program
designed to hire new staff into trainee positions as part of Western's
succession planning. The funding for these additional over-hire
positions has been placed in Western's FY 2010 budget submissions. The
intent of this program is that for each trainee hired, there is a
target retirement position. Once these retirements occur, the trainees
will fill these positions and staffing levels will become flat again in
FY 2013 and beyond.
7. Reclamation Expenses and Related Issues
Comment: A commenter wanted to know if the amounts included in the
ratesetting PRS take into account the new legislation with a cap on
security costs. In addition, they wanted to know how the future years'
projected amounts were derived, and what basis was used for the 94.7
percent share to power. They suggest the rate process should be
deferred until the impacts of the security cost cap are known.
Response: At this time, these amounts do not factor in the
Consolidated Natural Resources Act of 2008, which includes the
limitation of costs to customers of security activities at Reclamation
dams. Currently, the future year projected amount is based on amounts
through the FY 2010 WPR. Western has not received updated security
expenses from Reclamation that reflect impacts of the Consolidated
Natural Resources Act of 2008. Western plans to continue to work with
Reclamation, and these expenses are expected to be updated and applied
in the second step of this rate adjustment. The 94.7 percent share to
power is based on an average of allo