Tennessee Valley Authority; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing, 51014-51016 [E8-20118]

Download as PDF 51014 Federal Register / Vol. 73, No. 169 / Friday, August 29, 2008 / Notices Tennessee Valley Authority; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing process (CLIIP) for amending licensees’ TSs, which included a model safety evaluation (SE) and model no significant hazards consideration (NSHC) determination. The NRC staff subsequently issued a notice of availability of the models for referencing in license amendment applications in the Federal Register on January 17, 2007 (72 FR 2022), which included the resolution of public comments on the model SE and model NSHC determination. The licensee affirmed the applicability of the following NSHC determination in its application dated October 26, 2007. As required by 10 CFR 50.91(a), an analysis of the issue of no significant hazards consideration is presented below: The U.S. Nuclear Regulatory Commission (NRC, or the Commission) is considering issuance of an amendment to Facility Operating License No. NPF–90 issued to Tennessee Valley Authority (the licensee) for operation of the Watts Bar Nuclear Plant Unit 1 located in Rhea County, Tennessee. The proposed amendment would revise the Technical Specification (TS) requirements related to control room envelope (CRE) habitability in accordance with the NRC-approved Revision 3 of Technical Specification Task Force (TSTF) Standard Technical Specifications (STS) Change Traveler TSTF–448, ‘‘Control Room Habitability.’’ Before issuance of the proposed license amendment, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission’s regulations. The Commission has made a proposed determination that the amendment request involves no significant hazards consideration. Under the Commission’s regulations in Title 10 of the Code of Federal Regulations (10 CFR), Section 50.92, this means that operation of the facility in accordance with the proposed amendment would not (1) involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety. The NRC staff published a notice of opportunity for comment in the Federal Register on October 17, 2006 (71 FR 61075), on possible license amendments adopting TSTF–448 using the NRC’s consolidated line-item improvement Criterion 1—The Proposed Change Does Not Involve a Significant Increase in the Probability or Consequences of an Accident Previously Evaluated The proposed change does not adversely affect accident initiators or precursors nor alter the design assumptions, conditions, or configuration of the facility. The proposed change does not alter or prevent the ability of structures, systems, and components (SSCs) to perform their intended function to mitigate the consequences of an initiating event within the assumed acceptance limits. The proposed change revises the TS for the CRE emergency ventilation system, which is a mitigation system designed to minimize unfiltered air leakage into the CRE and to filter the CRE atmosphere to protect the CRE occupants in the event of accidents previously analyzed. An important part of the CRE emergency ventilation system is the CRE boundary. The CRE emergency ventilation system is not an initiator or precursor to any accident previously evaluated. Therefore, the probability of any accident previously evaluated is not increased. Performing tests to verify the operability of the CRE boundary and implementing a program to assess and maintain CRE habitability ensure that the CRE emergency ventilation system is capable of adequately mitigating radiological consequences to CRE occupants during accident conditions, and that the CRE emergency ventilation system will perform as assumed in the consequence analyses of design basis accidents. Thus, the consequences of any accident previously evaluated are not increased. Therefore, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated. Criterion 2—The Proposed Change Does Not Create the Possibility of a New or Different Kind of Accident From Any Accident Previously Evaluated The proposed change does not impact the accident analysis. The proposed change does not alter the required mitigation capability of the CRE emergency ventilation system, or its functioning during accident conditions as Ron Naveen, Permit No. 2009–015 Nadene G. Kennedy, Permit Officer. [FR Doc. E8–20096 Filed 8–28–08; 8:45 am] BILLING CODE 7555–01–P NUCLEAR REGULATORY COMMISSION mstockstill on PROD1PC66 with NOTICES [Docket No. 50–390] VerDate Aug<31>2005 17:32 Aug 28, 2008 Jkt 214001 PO 00000 Frm 00090 Fmt 4703 Sfmt 4703 assumed in the licensing basis analyses of design basis accident radiological consequences to CRE occupants. No new or different accidents result from performing the new surveillance or following the new program. The proposed change does not involve a physical alteration of the plant (i.e., no new or different type of equipment will be installed) or a significant change in the methods governing normal plant operation. The proposed change does not alter any safety analysis assumptions and is consistent with current plant operating practice. Therefore, this change does not create the possibility of a new or different kind of accident from any accident previously evaluated. Criterion 3—The Proposed Change Does Not Involve a Significant Reduction in the Margin of Safety The proposed change does not alter the manner in which safety limits, limiting safety system settings or limiting conditions for operation as determined. The proposed change does not affect safety analysis acceptance criteria. The proposed change will not result in plant operation in a configuration outside the design basis for an unacceptable period of time without compensatory measures. The proposed change does not adversely affect systems that respond to safely shut down the plant and to maintain the plant in a safe shutdown condition. Therefore, the proposed change does not involve a significant reduction in a margin of safety. The NRC staff has reviewed the licensee’s analysis and, based on this review, it appears that the three standards of 10 CFR 50.92(c) are satisfied. Therefore, the NRC staff proposes to determine that the amendment request involves no significant hazards consideration. The Commission is seeking public comments on this proposed determination. Any comments received within 30 days after the date of publication of this notice will be considered in making any final determination. Normally, the Commission will not issue the amendment until the expiration of 60 days after the date of publication of this notice. The Commission may issue the license amendment before expiration of the 60day period provided that its final determination is that the amendment involves no significant hazards consideration. In addition, the Commission may issue the amendment prior to the expiration of the 30-day comment period should circumstances change during the 30-day comment period such that failure to act in a timely way would result, for example, in derating or shutdown of the facility. Should the Commission take action prior to the expiration of either the comment period or the notice period, it E:\FR\FM\29AUN1.SGM 29AUN1 mstockstill on PROD1PC66 with NOTICES Federal Register / Vol. 73, No. 169 / Friday, August 29, 2008 / Notices will publish in the Federal Register a notice of issuance. Should the Commission make a final No Significant Hazards Consideration Determination, any hearing will take place after issuance. The Commission expects that the need to take this action will occur very infrequently. Written comments may be submitted by mail to the Chief, Rulemaking, Directives and Editing Branch, Division of Administrative Services, Office of Administration, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, and should cite the publication date and page number of this Federal Register notice. Written comments may also be delivered to Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Documents may be examined, and/or copied for a fee, at the NRC’s Public Document Room (PDR), located at One White Flint North, Public File Area O1F21, 11555 Rockville Pike (first floor), Rockville, Maryland. The filing of requests for hearing and petitions for leave to intervene is discussed below. Within 60 days after the date of publication of this notice, the person(s) may file a request for a hearing with respect to issuance of the amendment to the subject facility operating license and any person(s) whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request via electronic submission through the NRC E-filing system for a hearing and a petition for leave to intervene. Requests for a hearing and a petition for leave to intervene shall be filed in accordance with the Commission’s ‘‘Rules of Practice for Domestic Licensing Proceedings’’ in 10 CFR Part 2. Interested person(s) should consult a current copy of 10 CFR 2.309, which is available at the Commission’s PDR, located at One White Flint North, Public File Area O1F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/ reading-rm/doc-collections/cfr/. If a request for a hearing or petition for leave to intervene is filed by the above date, the Commission or a presiding officer designated by the Commission or by the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition; and the Secretary or the Chief Administrative Judge of the Atomic VerDate Aug<31>2005 17:32 Aug 28, 2008 Jkt 214001 Safety and Licensing Board will issue a notice of a hearing or an appropriate order. As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding. The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following general requirements: (1) The name, address and telephone number of the requestor or petitioner; (2) the nature of the requestor’s/petitioner’s right under the Act to be made a party to the proceeding; (3) the nature and extent of the requestor’s/petitioner’s property, financial, or other interest in the proceeding; and (4) the possible effect of any decision or order which may be entered in the proceeding on the requestor’s/petitioner’s interest. The petition must also identify the specific contentions which the petitioner/ requestor seeks to have litigated at the proceeding. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the petitioner/requestor shall provide a brief explanation of the bases for the contention and a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner/requestor must also provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely to establish those facts or expert opinion. The petition must include sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the amendment under consideration. The contention must be one which, if proven, would entitle the petitioner to relief. A petitioner/requestor who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as a party. Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing. If a hearing is requested, the Commission will make a final determination on the issue of no significant hazards consideration. The final determination will serve to decide when the hearing is held. If the final PO 00000 Frm 00091 Fmt 4703 Sfmt 4703 51015 determination is that the amendment request involves no significant hazards consideration, the Commission may issue the amendment and make it immediately effective, notwithstanding the request for a hearing. Any hearing held would take place after issuance of the amendment. If the final determination is that the amendment request involves a significant hazards consideration, any hearing held would take place before the issuance of any amendment. A request for hearing or a petition for leave to intervene must be filed in accordance with the NRC E-Filing rule, which the NRC promulgated on August 28, 2007 (72 FR 49139). The E-Filing process requires participants to submit and serve documents over the internet or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings unless they seek a waiver in accordance with the procedures described below. To comply with the procedural requirements of E-Filing, at least ten (10) days prior to the filing deadline, the petitioner/requestor must contact the Office of the Secretary by e-mail at hearing.docket@nrc.gov, or by calling (301) 415–1677, to request (1) a digital ID certificate, which allows the participant (or its counsel or representative) to digitally sign documents and access the E-Submittal server for any proceeding in which it is participating; and/or (2) creation of an electronic docket for the proceeding (even in instances in which the petitioner/requestor (or its counsel or representative) already holds an NRCissued digital ID certificate). Each petitioner/requestor will need to download the Workplace Forms Viewer TM to access the Electronic Information Exchange (EIE), a component of the E-Filing system. The Workplace Forms Viewer TM is free and is available at https://www.nrc.gov/sitehelp/e-submittals/install-viewer.html. Information about applying for a digital ID certificate is available on NRC’s public Web site at https://www.nrc.gov/ site-help/e-submittals/applycertificates.html. Once a petitioner/requestor has obtained a digital ID certificate, had a docket created, and downloaded the EIE viewer, it can then submit a request for hearing or petition for leave to intervene. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public Web site at https://www.nrc.gov/site-help/esubmittals.html. A filing is considered complete at the time the filer submits its E:\FR\FM\29AUN1.SGM 29AUN1 mstockstill on PROD1PC66 with NOTICES 51016 Federal Register / Vol. 73, No. 169 / Friday, August 29, 2008 / Notices documents through EIE. To be timely, an electronic filing must be submitted to the EIE system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an e-mail notice confirming receipt of the document. The EIE system also distributes an e-mail notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before a hearing request/ petition to intervene is filed so that they can obtain access to the document via the E-Filing system. A person filing electronically may seek assistance through the ‘‘Contact Us’’ link located on the NRC Web site at https://www.nrc.gov/site-help/esubmittals.html or by calling the NRC technical help line, which is available between 8:30 a.m. and 4:15 p.m., Eastern Time, Monday through Friday. The help line number is (800) 397–4209 or locally, (301) 415–4737. Participants who believe that they have a good cause for not submitting documents electronically must file a motion, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) First class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville, Pike, Rockville, Maryland, 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by firstclass mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service. Non-timely requests and/or petitions and contentions will not be entertained absent a determination by the Commission, the presiding officer, or the Atomic Safety and Licensing Board that the petition and/or request should be granted and/or the contentions VerDate Aug<31>2005 17:32 Aug 28, 2008 Jkt 214001 should be admitted, based on a balancing of the factors specified in 10 CFR 2.309(c)(1)(i)–(viii). To be timely, filings must be submitted no later than 11:59 p.m. Eastern Time on the due date. Documents submitted in adjudicatory proceedings will appear in NRC’s electronic hearing docket which is available to the public at https:// ehd.nrc.gov/ehd_proceeding/home.asp, unless excluded pursuant to an order of the Commission, an Atomic Safety and Licensing Board, or a Presiding Officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their filings. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, Participants are requested not to include copyrighted materials in their submissions. For further details with respect to this license amendment application, see the application for amendment dated October 26, 2007, which is available for public inspection at the Commission’s PDR, located at One White Flint North, File Public Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https:// www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1–800– 397–4209, 301–415–4737, or by e-mail to pdr.resource@nrc.gov. Dated at Rockville, Maryland, this 25th day of August 2008. For the Nuclear Regulatory Commission. Patrick D. Milano, Senior Project Manager, Watts Bar Special Projects Branch, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation. [FR Doc. E8–20118 Filed 8–28–08; 8:45 am] BILLING CODE 7590–01–P PO 00000 NUCLEAR REGULATORY COMMISSION [EA–08–225] In the Matter of Certain Licensees Authorized To Possess and Transfer Items Containing Radioactive Material Quantities of Concern; Order Imposing Additional Security Measures (Effective Immediately) I The Licensees identified in Attachment A 1 to this Order, hold licenses issued by the U.S. Nuclear Regulatory Commission (NRC or Commission) or an Agreement State, in accordance with the Atomic Energy Act of 1954, as amended, and 10 CFR Parts 30, 32, 70 and 71, or equivalent Agreement State regulations. The licenses authorize them to possess and transfer items containing radioactive material quantities of concern. This Order is being issued to all such Licensees who may transport radioactive material quantities of concern under the NRC’s authority to protect the common defense and security, which has not been relinquished to the Agreement States. The Orders require compliance with specific additional security measures to enhance the security for transport of certain radioactive material quantities of concern. II On September 11, 2001, terrorists simultaneously attacked targets in New York, NY, and Washington, DC, utilizing large commercial aircraft as weapons. In response to the attacks and intelligence information subsequently obtained, the Commission issued a number of Safeguards and Threat Advisories to Licensees in order to strengthen Licensees’ capabilities and readiness to respond to a potential attack on this regulated activity. The Commission has also communicated with other Federal, State and local government agencies and industry representatives to discuss and evaluate the current threat environment in order to assess the adequacy of the current security measures. In addition, the Commission commenced a comprehensive review of its safeguards and security programs and requirements. As a result of its initial consideration of current safeguards and security requirements, as well as a review of information provided by the intelligence community, the Commission has 1 Attachment A contains sensitive information and will not be released to the public. Frm 00092 Fmt 4703 Sfmt 4703 E:\FR\FM\29AUN1.SGM 29AUN1

Agencies

[Federal Register Volume 73, Number 169 (Friday, August 29, 2008)]
[Notices]
[Pages 51014-51016]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-20118]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-390]


Tennessee Valley Authority; Notice of Consideration of Issuance 
of Amendment to Facility Operating License, Proposed No Significant 
Hazards Consideration Determination, and Opportunity for a Hearing

    The U.S. Nuclear Regulatory Commission (NRC, or the Commission) is 
considering issuance of an amendment to Facility Operating License No. 
NPF-90 issued to Tennessee Valley Authority (the licensee) for 
operation of the Watts Bar Nuclear Plant Unit 1 located in Rhea County, 
Tennessee.
    The proposed amendment would revise the Technical Specification 
(TS) requirements related to control room envelope (CRE) habitability 
in accordance with the NRC-approved Revision 3 of Technical 
Specification Task Force (TSTF) Standard Technical Specifications (STS) 
Change Traveler TSTF-448, ``Control Room Habitability.''
    Before issuance of the proposed license amendment, the Commission 
will have made findings required by the Atomic Energy Act of 1954, as 
amended (the Act), and the Commission's regulations.
    The Commission has made a proposed determination that the amendment 
request involves no significant hazards consideration. Under the 
Commission's regulations in Title 10 of the Code of Federal Regulations 
(10 CFR), Section 50.92, this means that operation of the facility in 
accordance with the proposed amendment would not (1) involve a 
significant increase in the probability or consequences of an accident 
previously evaluated; or (2) create the possibility of a new or 
different kind of accident from any accident previously evaluated; or 
(3) involve a significant reduction in a margin of safety.
    The NRC staff published a notice of opportunity for comment in the 
Federal Register on October 17, 2006 (71 FR 61075), on possible license 
amendments adopting TSTF-448 using the NRC's consolidated line-item 
improvement process (CLIIP) for amending licensees' TSs, which included 
a model safety evaluation (SE) and model no significant hazards 
consideration (NSHC) determination. The NRC staff subsequently issued a 
notice of availability of the models for referencing in license 
amendment applications in the Federal Register on January 17, 2007 (72 
FR 2022), which included the resolution of public comments on the model 
SE and model NSHC determination. The licensee affirmed the 
applicability of the following NSHC determination in its application 
dated October 26, 2007.
    As required by 10 CFR 50.91(a), an analysis of the issue of no 
significant hazards consideration is presented below:

Criterion 1--The Proposed Change Does Not Involve a Significant 
Increase in the Probability or Consequences of an Accident Previously 
Evaluated

    The proposed change does not adversely affect accident 
initiators or precursors nor alter the design assumptions, 
conditions, or configuration of the facility. The proposed change 
does not alter or prevent the ability of structures, systems, and 
components (SSCs) to perform their intended function to mitigate the 
consequences of an initiating event within the assumed acceptance 
limits. The proposed change revises the TS for the CRE emergency 
ventilation system, which is a mitigation system designed to 
minimize unfiltered air leakage into the CRE and to filter the CRE 
atmosphere to protect the CRE occupants in the event of accidents 
previously analyzed. An important part of the CRE emergency 
ventilation system is the CRE boundary. The CRE emergency 
ventilation system is not an initiator or precursor to any accident 
previously evaluated. Therefore, the probability of any accident 
previously evaluated is not increased. Performing tests to verify 
the operability of the CRE boundary and implementing a program to 
assess and maintain CRE habitability ensure that the CRE emergency 
ventilation system is capable of adequately mitigating radiological 
consequences to CRE occupants during accident conditions, and that 
the CRE emergency ventilation system will perform as assumed in the 
consequence analyses of design basis accidents. Thus, the 
consequences of any accident previously evaluated are not increased. 
Therefore, the proposed change does not involve a significant 
increase in the probability or consequences of an accident 
previously evaluated.

Criterion 2--The Proposed Change Does Not Create the Possibility of a 
New or Different Kind of Accident From Any Accident Previously 
Evaluated

    The proposed change does not impact the accident analysis. The 
proposed change does not alter the required mitigation capability of 
the CRE emergency ventilation system, or its functioning during 
accident conditions as assumed in the licensing basis analyses of 
design basis accident radiological consequences to CRE occupants. No 
new or different accidents result from performing the new 
surveillance or following the new program. The proposed change does 
not involve a physical alteration of the plant (i.e., no new or 
different type of equipment will be installed) or a significant 
change in the methods governing normal plant operation. The proposed 
change does not alter any safety analysis assumptions and is 
consistent with current plant operating practice. Therefore, this 
change does not create the possibility of a new or different kind of 
accident from any accident previously evaluated.

Criterion 3--The Proposed Change Does Not Involve a Significant 
Reduction in the Margin of Safety

    The proposed change does not alter the manner in which safety 
limits, limiting safety system settings or limiting conditions for 
operation as determined. The proposed change does not affect safety 
analysis acceptance criteria. The proposed change will not result in 
plant operation in a configuration outside the design basis for an 
unacceptable period of time without compensatory measures. The 
proposed change does not adversely affect systems that respond to 
safely shut down the plant and to maintain the plant in a safe 
shutdown condition. Therefore, the proposed change does not involve 
a significant reduction in a margin of safety.

    The NRC staff has reviewed the licensee's analysis and, based on 
this review, it appears that the three standards of 10 CFR 50.92(c) are 
satisfied. Therefore, the NRC staff proposes to determine that the 
amendment request involves no significant hazards consideration.
    The Commission is seeking public comments on this proposed 
determination. Any comments received within 30 days after the date of 
publication of this notice will be considered in making any final 
determination.
    Normally, the Commission will not issue the amendment until the 
expiration of 60 days after the date of publication of this notice. The 
Commission may issue the license amendment before expiration of the 60-
day period provided that its final determination is that the amendment 
involves no significant hazards consideration. In addition, the 
Commission may issue the amendment prior to the expiration of the 30-
day comment period should circumstances change during the 30-day 
comment period such that failure to act in a timely way would result, 
for example, in derating or shutdown of the facility. Should the 
Commission take action prior to the expiration of either the comment 
period or the notice period, it

[[Page 51015]]

will publish in the Federal Register a notice of issuance. Should the 
Commission make a final No Significant Hazards Consideration 
Determination, any hearing will take place after issuance. The 
Commission expects that the need to take this action will occur very 
infrequently.
    Written comments may be submitted by mail to the Chief, Rulemaking, 
Directives and Editing Branch, Division of Administrative Services, 
Office of Administration, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001, and should cite the publication date and 
page number of this Federal Register notice. Written comments may also 
be delivered to Room 6D59, Two White Flint North, 11545 Rockville Pike, 
Rockville, Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. 
Documents may be examined, and/or copied for a fee, at the NRC's Public 
Document Room (PDR), located at One White Flint North, Public File Area 
O1F21, 11555 Rockville Pike (first floor), Rockville, Maryland.
    The filing of requests for hearing and petitions for leave to 
intervene is discussed below.
    Within 60 days after the date of publication of this notice, the 
person(s) may file a request for a hearing with respect to issuance of 
the amendment to the subject facility operating license and any 
person(s) whose interest may be affected by this proceeding and who 
wishes to participate as a party in the proceeding must file a written 
request via electronic submission through the NRC E-filing system for a 
hearing and a petition for leave to intervene. Requests for a hearing 
and a petition for leave to intervene shall be filed in accordance with 
the Commission's ``Rules of Practice for Domestic Licensing 
Proceedings'' in 10 CFR Part 2. Interested person(s) should consult a 
current copy of 10 CFR 2.309, which is available at the Commission's 
PDR, located at One White Flint North, Public File Area O1F21, 11555 
Rockville Pike (first floor), Rockville, Maryland. Publicly available 
records will be accessible from the Agencywide Documents Access and 
Management System's (ADAMS) Public Electronic Reading Room on the 
Internet at the NRC Web site, https://www.nrc.gov/reading-rm/doc-
collections/cfr/. If a request for a hearing or petition for leave to 
intervene is filed by the above date, the Commission or a presiding 
officer designated by the Commission or by the Chief Administrative 
Judge of the Atomic Safety and Licensing Board Panel, will rule on the 
request and/or petition; and the Secretary or the Chief Administrative 
Judge of the Atomic Safety and Licensing Board will issue a notice of a 
hearing or an appropriate order.
    As required by 10 CFR 2.309, a petition for leave to intervene 
shall set forth with particularity the interest of the petitioner in 
the proceeding, and how that interest may be affected by the results of 
the proceeding. The petition should specifically explain the reasons 
why intervention should be permitted with particular reference to the 
following general requirements: (1) The name, address and telephone 
number of the requestor or petitioner; (2) the nature of the 
requestor's/petitioner's right under the Act to be made a party to the 
proceeding; (3) the nature and extent of the requestor's/petitioner's 
property, financial, or other interest in the proceeding; and (4) the 
possible effect of any decision or order which may be entered in the 
proceeding on the requestor's/petitioner's interest. The petition must 
also identify the specific contentions which the petitioner/requestor 
seeks to have litigated at the proceeding.
    Each contention must consist of a specific statement of the issue 
of law or fact to be raised or controverted. In addition, the 
petitioner/requestor shall provide a brief explanation of the bases for 
the contention and a concise statement of the alleged facts or expert 
opinion which support the contention and on which the petitioner 
intends to rely in proving the contention at the hearing. The 
petitioner/requestor must also provide references to those specific 
sources and documents of which the petitioner is aware and on which the 
petitioner intends to rely to establish those facts or expert opinion. 
The petition must include sufficient information to show that a genuine 
dispute exists with the applicant on a material issue of law or fact. 
Contentions shall be limited to matters within the scope of the 
amendment under consideration. The contention must be one which, if 
proven, would entitle the petitioner to relief. A petitioner/requestor 
who fails to satisfy these requirements with respect to at least one 
contention will not be permitted to participate as a party.
    Those permitted to intervene become parties to the proceeding, 
subject to any limitations in the order granting leave to intervene, 
and have the opportunity to participate fully in the conduct of the 
hearing.
    If a hearing is requested, the Commission will make a final 
determination on the issue of no significant hazards consideration. The 
final determination will serve to decide when the hearing is held. If 
the final determination is that the amendment request involves no 
significant hazards consideration, the Commission may issue the 
amendment and make it immediately effective, notwithstanding the 
request for a hearing. Any hearing held would take place after issuance 
of the amendment. If the final determination is that the amendment 
request involves a significant hazards consideration, any hearing held 
would take place before the issuance of any amendment.
    A request for hearing or a petition for leave to intervene must be 
filed in accordance with the NRC E-Filing rule, which the NRC 
promulgated on August 28, 2007 (72 FR 49139). The E-Filing process 
requires participants to submit and serve documents over the internet 
or in some cases to mail copies on electronic storage media. 
Participants may not submit paper copies of their filings unless they 
seek a waiver in accordance with the procedures described below.
    To comply with the procedural requirements of E-Filing, at least 
ten (10) days prior to the filing deadline, the petitioner/requestor 
must contact the Office of the Secretary by e-mail at 
hearing.docket@nrc.gov, or by calling (301) 415-1677, to request (1) a 
digital ID certificate, which allows the participant (or its counsel or 
representative) to digitally sign documents and access the E-Submittal 
server for any proceeding in which it is participating; and/or (2) 
creation of an electronic docket for the proceeding (even in instances 
in which the petitioner/requestor (or its counsel or representative) 
already holds an NRC-issued digital ID certificate). Each petitioner/
requestor will need to download the Workplace Forms Viewer 
TM to access the Electronic Information Exchange (EIE), a 
component of the E-Filing system. The Workplace Forms Viewer 
TM is free and is available at https://www.nrc.gov/site-help/
e-submittals/install-viewer.html. Information about applying for a 
digital ID certificate is available on NRC's public Web site at https://
www.nrc.gov/site-help/e-submittals/apply-certificates.html.
    Once a petitioner/requestor has obtained a digital ID certificate, 
had a docket created, and downloaded the EIE viewer, it can then submit 
a request for hearing or petition for leave to intervene. Submissions 
should be in Portable Document Format (PDF) in accordance with NRC 
guidance available on the NRC public Web site at https://www.nrc.gov/
site-help/e-submittals.html. A filing is considered complete at the 
time the filer submits its

[[Page 51016]]

documents through EIE. To be timely, an electronic filing must be 
submitted to the EIE system no later than 11:59 p.m. Eastern Time on 
the due date. Upon receipt of a transmission, the E-Filing system time-
stamps the document and sends the submitter an e-mail notice confirming 
receipt of the document. The EIE system also distributes an e-mail 
notice that provides access to the document to the NRC Office of the 
General Counsel and any others who have advised the Office of the 
Secretary that they wish to participate in the proceeding, so that the 
filer need not serve the documents on those participants separately. 
Therefore, applicants and other participants (or their counsel or 
representative) must apply for and receive a digital ID certificate 
before a hearing request/petition to intervene is filed so that they 
can obtain access to the document via the E-Filing system.
    A person filing electronically may seek assistance through the 
``Contact Us'' link located on the NRC Web site at https://www.nrc.gov/
site-help/e-submittals.html or by calling the NRC technical help line, 
which is available between 8:30 a.m. and 4:15 p.m., Eastern Time, 
Monday through Friday. The help line number is (800) 397-4209 or 
locally, (301) 415-4737.
    Participants who believe that they have a good cause for not 
submitting documents electronically must file a motion, in accordance 
with 10 CFR 2.302(g), with their initial paper filing requesting 
authorization to continue to submit documents in paper format. Such 
filings must be submitted by: (1) First class mail addressed to the 
Office of the Secretary of the Commission, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, Attention: Rulemaking and 
Adjudications Staff; or (2) courier, express mail, or expedited 
delivery service to the Office of the Secretary, Sixteenth Floor, One 
White Flint North, 11555 Rockville, Pike, Rockville, Maryland, 20852, 
Attention: Rulemaking and Adjudications Staff. Participants filing a 
document in this manner are responsible for serving the document on all 
other participants. Filing is considered complete by first-class mail 
as of the time of deposit in the mail, or by courier, express mail, or 
expedited delivery service upon depositing the document with the 
provider of the service.
    Non-timely requests and/or petitions and contentions will not be 
entertained absent a determination by the Commission, the presiding 
officer, or the Atomic Safety and Licensing Board that the petition 
and/or request should be granted and/or the contentions should be 
admitted, based on a balancing of the factors specified in 10 CFR 
2.309(c)(1)(i)-(viii). To be timely, filings must be submitted no later 
than 11:59 p.m. Eastern Time on the due date.
    Documents submitted in adjudicatory proceedings will appear in 
NRC's electronic hearing docket which is available to the public at 
https://ehd.nrc.gov/ehd_proceeding/home.asp, unless excluded pursuant 
to an order of the Commission, an Atomic Safety and Licensing Board, or 
a Presiding Officer. Participants are requested not to include personal 
privacy information, such as social security numbers, home addresses, 
or home phone numbers in their filings. With respect to copyrighted 
works, except for limited excerpts that serve the purpose of the 
adjudicatory filings and would constitute a Fair Use application, 
Participants are requested not to include copyrighted materials in 
their submissions.
    For further details with respect to this license amendment 
application, see the application for amendment dated October 26, 2007, 
which is available for public inspection at the Commission's PDR, 
located at One White Flint North, File Public Area O1 F21, 11555 
Rockville Pike (first floor), Rockville, Maryland. Publicly available 
records will be accessible electronically from the Agencywide Documents 
Access and Management System's (ADAMS) Public Electronic Reading Room 
on the Internet at the NRC Web site, https://www.nrc.gov/reading-rm/
adams.html. Persons who do not have access to ADAMS or who encounter 
problems in accessing the documents located in ADAMS, should contact 
the NRC PDR Reference staff by telephone at 1-800-397-4209, 301-415-
4737, or by e-mail to pdr.resource@nrc.gov.

    Dated at Rockville, Maryland, this 25th day of August 2008.

    For the Nuclear Regulatory Commission.
Patrick D. Milano,
Senior Project Manager, Watts Bar Special Projects Branch, Division of 
Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. E8-20118 Filed 8-28-08; 8:45 am]
BILLING CODE 7590-01-P