Texas Gas Transmission, LLC; Notice of Application, 50956-50957 [E8-20053]
Download as PDF
50956
Federal Register / Vol. 73, No. 169 / Friday, August 29, 2008 / Notices
copies should be mailed to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. For
more information on how to submit
these types of filings please go to the
Commission’s Web site located at http:
//www.ferc.gov/filing-comments.asp.
More information about this project can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at http:
//www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13173) in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3372.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–20049 Filed 8–28–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No.: 2801–027]
Littleville Power Company, Inc.; Notice
Soliciting Scoping Comments
mstockstill on PROD1PC66 with NOTICES
August 22, 2008.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: P–2801–027.
c. Date filed: October 31, 2007.
d. Applicant: Littleville Power
Company, Inc.
e. Name of Project: Glendale
Hydroelectric Project.
f. Location: On the Housatonic River
in the Town of Stockbridge, Berkshire
County. The project does not affect
federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Kevin M. Webb,
Environmental Affairs Coordinator,
Littleville Power Company, Inc., One
Tech Drive, Suite 220, Andover, MA
01810, (978) 681–1900 ext. 809,
kevin.webb@northamerica.enel.it.
i. FERC Contact: Kristen Murphy,
(202) 502–6236 or
kristen.murphy@ferc.gov.
j. Deadline for filing scoping
comments: September 22, 2008.
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
k. This application has been accepted,
but is not ready for environmental
analysis at this time.
VerDate Aug<31>2005
17:32 Aug 28, 2008
Jkt 214001
l. As licensed, the existing Glendale
Project consists of: (1) A 250-foot long,
30-foot high concrete gravity dam with
a 182-foot-long spillway; (2) a 23-acre
reservoir; (3) two manually operated 10
by 10-foot intake gates; (4) a 1,500-foot
long, 40-foot wide intake canal; (5) a
forebay structure and a 250-foot long,
12-foot diameter steel penstock; (6) a
powerhouse with four turbines with a
combined installed capacity of 1,140kilowatts; (7) a 300-foot long tailrace
channel; (8) a step-up transformer and
an 83-foot-long 13.8 kilovolt
transmission line; and (9) appurtenant
facilities. The Housatonic River reach
that is bypassed by the project
(measured from the gatehouse to the
tailrace channel) is about 2,500 feet
long.
The proposed project would include a
new 165-kW turbine unit in the waste
gate slot located at the gatehouse
adjacent to the project dam. This unit
would operate off of a proposed
minimum bypassed reach flow of 90
cubic feet per second (cfs) or inflow. In
addition, the proposed project would
provide additional recreational access
through formal canoe portage facilities
and parking.
The applicant estimates that the total
average annual generation, with the
proposed additional turbine, would be
5,800 megawatt-hours. The applicant
proposes to continue to operate the
project in run-of-river mode with an
increase in minimum flow in the bypass
reach from 10 cfs to 90 cfs or inflow,
whichever is less. The purpose of the
project is to produce electrical power for
sale.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at FERCOnlineSupport
@ferc.gov or toll-free at 1–866–208–
3676, or for TTY, (202) 502–8659. A
copy is also available for inspection and
reproduction at the address in item h
above.
n. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Scoping Process
The Commission staff intends to
prepare a single environmental
assessment (EA) for the Glendale
Hydroelectric Project in accordance
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
with the National Environmental Policy
Act. The EA will consider both sitespecific and cumulative environmental
impacts and reasonable alternatives to
the proposed action.
Commission staff does not propose to
conduct any on-site scoping meetings at
this time. Instead, we are soliciting
comments, recommendations, and
information, on the scoping document
issued on August 22, 2008.
Copies of the scoping document
outlining the subject areas to be
addressed in the EA were distributed to
the parties on the Commission’s mailing
list and the applicant’s distribution list.
Copies of the scoping document may be
viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, call 1–866–208–3676 or for
TTY, (202) 502–8659.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–20047 Filed 8–28–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP07–417–002]
Texas Gas Transmission, LLC; Notice
of Application
August 22, 2008.
Take notice that on August 22, 2008,
Texas Gas Transmission, LLC (Texas
Gas), 3800 Frederica Street, Owensboro,
Kentucky 42301, filed in the above
referenced docket an application
pursuant to section 7(c) of the Natural
Gas Act (NGA), and section 157 of the
Commission’s regulations to amend the
certificate of public convenience and
necessity issued on May 2, 2008, in
Docket No. CP07–417–000. Specifically,
Texas Gas requests authorization to
increase in the maximum design
capability of the Fayetteville Lateral,
located in Arkansas and Mississippi,
from 841,000 MMBtu per day to 967,000
MMBtu/d, all as more fully set forth in
the application which is on file with the
Commission and open to public
inspection. The filing may also be
viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or toll
E:\FR\FM\29AUN1.SGM
29AUN1
mstockstill on PROD1PC66 with NOTICES
Federal Register / Vol. 73, No. 169 / Friday, August 29, 2008 / Notices
free at (866) 208–3676, or TTY, contact
(202) 502–8659.
Any questions concerning this
application may be directed to Kathy D.
Fort, Manager, Certificates and Tariffs,
Texas Gas Transmission, LLC, 3800
Frederica Street, Owensboro, Kentucky
42301 at (270) 688–6825.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
VerDate Aug<31>2005
17:32 Aug 28, 2008
Jkt 214001
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 14 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: August 29, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–20053 Filed 8–28–08; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. ER07–501–010; ER08–649–
005; ER06–739–014; ER06–738–014]
Birchwood Power Partners, L.P., EFS
Parlin Holdings LLC, Linden Holding
L.L.C., Technologies Linden Venture
L.P.; Notice of Filing
August 22, 2008.
Take notice that on June 27, 2008,
Birchwood Power Partners, L.P., EFS
Parlin Holdings LLC, Linden Holding
L.L.C. and Technologies Linden Venture
L.P. filed a triennial market power
analysis pursuant to the Commission’s
Order 697.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all the parties in this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on August 29, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–20052 Filed 8–28–08; 8:45 am]
BILLING CODE 6717–01–P
Frm 00033
Fmt 4703
50957
Sfmt 4703
E:\FR\FM\29AUN1.SGM
29AUN1
Agencies
[Federal Register Volume 73, Number 169 (Friday, August 29, 2008)]
[Notices]
[Pages 50956-50957]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-20053]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP07-417-002]
Texas Gas Transmission, LLC; Notice of Application
August 22, 2008.
Take notice that on August 22, 2008, Texas Gas Transmission, LLC
(Texas Gas), 3800 Frederica Street, Owensboro, Kentucky 42301, filed in
the above referenced docket an application pursuant to section 7(c) of
the Natural Gas Act (NGA), and section 157 of the Commission's
regulations to amend the certificate of public convenience and
necessity issued on May 2, 2008, in Docket No. CP07-417-000.
Specifically, Texas Gas requests authorization to increase in the
maximum design capability of the Fayetteville Lateral, located in
Arkansas and Mississippi, from 841,000 MMBtu per day to 967,000 MMBtu/
d, all as more fully set forth in the application which is on file with
the Commission and open to public inspection. The filing may also be
viewed on the Web at https://www.ferc.gov using the ``eLibrary'' link.
Enter the docket number excluding the last three digits in the docket
number field to access the document. For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll
[[Page 50957]]
free at (866) 208-3676, or TTY, contact (202) 502-8659.
Any questions concerning this application may be directed to Kathy
D. Fort, Manager, Certificates and Tariffs, Texas Gas Transmission,
LLC, 3800 Frederica Street, Owensboro, Kentucky 42301 at (270) 688-
6825.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 14 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commentors will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commentors will not be required to serve copies of filed
documents on all other parties. However, the non-party commentors will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and 14 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive e-mail
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: August 29, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-20053 Filed 8-28-08; 8:45 am]
BILLING CODE 6717-01-P